Detail Booklet StoTherm ci Mineral Wool - Sto Corp. · StoTherm®ci Mineral Wool General Notes...
Transcript of Detail Booklet StoTherm ci Mineral Wool - Sto Corp. · StoTherm®ci Mineral Wool General Notes...
Detail BookletStoTherm® ci Mineral WoolSeries 56s.xxSteel Frame ConstructionNovember 2018
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.comProperty of Sto Corp.All Rights Reserved.
3800 Camp Creek Pkwy. SWBldg. 1400 • Suite 120Atlanta, GA 30331Tel: (800) 221-2397Fax: (404) 346-3119helpdesk.stocorp.com
Sto Corp.
StoTherm®ci Mineral Wool General Notes
Detail No.: 56s.SGDate: November 2018Page 1 of 4
Structural - Wind and Axial Loads
1. Design for maximum allowable deflection normal to the plane of the wall of L/240.
2. Design for wind load in conformance with code requirements.
3. Frame Construction: space studs maximum 16 inches (406mm) on center using either 2x4 or 2x6 wood framing or minimum 18 gauge galvanized steel stud framing.
4. Maximum ultimate wind load resistance: positive 253 lb/ft2 (12.1 kPa), negative 126 lb/ft2 (-6.03 kPa). Refer to the Sto Design Guide for details of wind load resistance tested assemblies.
Fire
1. Insulation board is noncombustible as defined by NFPA 220 with 0 flame spread and 0 smoke development (ASTM E84).
2. Non-Combustible Construction: meets requirements for use on non-combustible construction without height limitation based on NFPA 285 and NFPA 268 engineering analyses.
3. Fire–Resistant Rated Construction: system maintains hourly fire resistance rating of concrete, concrete masonry, and non-load bearing steel frame wall assemblies.
Moisture Protection
1. Refer to Sto Tech Hotline No. 0403-BSc, Critical Detail Checklist for Wall Assemblies, and No. 0603-BSc Moisture Control Princples for Design and Construction of Wall Assemblies, for basic details and principles that must be employed in design and construction of wall assemblies to control moisture.
2. StoGuard functions as the air barrier and moisture barrier (AMB) in the system and conforms with the requirements of ASTM E2570, Standard Test Methods for Evaluating Water-Resistive Barrier (WRB) Coatings Used Under Exterior Insulation and Finish Systems (EIFS) or EIFS with Drainage. The moisture protection provided by StoGuard protects walls against moisture damage from rain during the construction process and in the event of a breach in the wall cladding while in service. Flashing must always be integrated with the AMB in the wall assembly to direct water to the exterior of the cladding, not into the wall assembly, particularly at potential leak sources such as windows.
3. The function of an air barrier should not be confused with that of a vapor retarder. A vapor retarder is placed in the wall to resist differential vapor pressures, whereas the air barrier is designed to resist the structural live loads induced by air pressure difference. (continued on next page)
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp.All Rights Reserved.
Moisture Protection (cont’d)
Generally a vapor retarder is placed on the warm side of the wall. Specifically, it is placed on the interior side of the insulation in cold climates and on the exterior side of the insulation in warm humid climates to minimize condensation within the wall assembly.
A vapor retarder may not be necessary depending on the wall components, the range of temperature/humidity conditions inside and outside, and the mechanical ventilation of the building. A vapor retarder should not be used on the interior side of walls in warm humid climates. Refer to applicable building codes for further guidance.
4. The system functions to resist water penetration based on testing in accordance with ASTM E331, (Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference) and also drains incidental water in the event of a breach of the outer facing (lamina). The system has a drainage efficiency greater than 90% based on testing in accordance with ASTM E2273, Standard Test Methods for Determining the Drainage Efficiency of Exterior Insulation and Finish Systems (EIFS) Clad Wall Assemblies.
5. The system is “vapor open” with vapor permeable air and moisture barrier, insulation board, and lamina components. If a vapor barrier is required refer to information on StoGuard VaporSeal.
6. Precautions must be taken to keep insulation board dry during construction and while in service. R-value, adhesion and other properties can be compromised if insulation stays wet. During construction protect with tenting, base coat, or other protection to maintain insulation board integrity and properties.
Thermal Insulation
1. The system employs noncombustible continuous exterior mineral wool insulation in compliance with ASTM C612, Standard Specifcation for Mineral Fiber Block and Board Thermal Insulation. The insulation comes in 2, 3, or 4 inch (51, 76, or 102mm) thicknesses with an R-value of 4.0 ft2•h•°F / Btu per inch (RSI-0.704 m2•K/W).
2. The system employs specially designed thermal dowels for attachment of the insulation to the supporting structure to minimize thermal bridging.
Impact Resistance
1. Heavy reinforcing mesh layer (11 oz/yd2 [373 g/m2]) is recommended for ground floors and other areas at risk of impacts or abuse. Alternative materials – stucco, stone, tile – may be more suitable in areas with heavy pedestrian traffic, vehicular traffic (e.g., porte cocherre), and industrial areas.
StoTherm®ci Mineral Wool General Notes
Detail No.: 56s.SGDate: November 2018Page 2 of 4
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp.All Rights Reserved.
Acoustics
1. Outdoor-Indoor Transmission Class has been measured and calculated at 45 in accordance with ASTM E1332, Standard Classification for Rating Outdoor-Indoor Sound Attenuation, and ASTM E413, Classification for Rating Sound Insulation.
Aesthetics
1. Slight surface irregularities may be apparent in the finished wall surface for brief periods during the day in critical light. Smooth or fine texture finishes are discouraged. Minimum 1.5 mm (Medium) or heavier textures are preferred to hide surface imperfections. On some occasions surface mount dowels may “read” through the finished wall surface as the building ages. This can be remedied by recoating (or prevented by using countersunk dowels).
Joints
1. System requires joints at: - Expansion, deflection, control, or cold joints in supporting construction - Changes in building height - Dissimilar construction or materials - Floor lines in multi-level wood frame construction
Regulatory Compliance
1. StoGuard Air and Moisture Barrier complies with IBC, IRC and IECC as an air barrier material and water-resistive barrier (WRB). Refer to ICC-ES ESR 1233 for listed products.
2. System conforms with 2018 IECC Section C402.2 prescriptive ci R-value requirements for above-grade walls.
3. System conforms with performance and drainage efficiency requirements of 2018 IBC Section 1407 and 2018 IRC Section R703.9.2.
4. System conforms with 2018 IBC Section 1402.5 for use on buildings of Types I, II, II, or IV construction without height limitation (other than height restrictions governed by wind pressure limits of the system).
StoTherm®ci Mineral Wool General Notes
Detail No.: 56s.SGDate: November 2018Page 3 of 4
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp.All Rights Reserved.
Sustainability
1. Insulation board is made of 70% recycled content.
2. StoGuard Air and Moisture Barrier, Sto adhesive, and Sto lamina components comply with VOC requirements of SCAQMD Rule 1113.
3. System has high potential for LEED and other sustainability program credits based on efficient and effective use of continuous exterior insulation and resulting reductions in greenhouse gas emissions
Other
1. Always construct a site built mock-up using materials and sub-trades associated with the project to verify installation, sequencing, detailing, and aesthetics, and test the performance of the window/wall assembly and other selected critical detail areas for air leakage, water infiltration, and structural adequacy in relation to design wind pressures. Correct any deficiencies shown by the mock-up and testing before commencing work.
2. Refer to Product Bulletins, StoTherm ci Mineral Design Guide, Installation Guide, and guide Specifications and Details, for additional information.
3. The final design of the project is the responsibility of the Design Professional. Sto accepts no liability for design, engineering, or workmanship of any project. The notes provided herein are in addition to Sto Guide Details, Guide Specifications, and other items available at www.stocorp.com
For Questions or Assistance:Sto Technical Services
Phone : +1 (800) 221-2397Help Desk: helpdesk.stocorp.com
Website: www.stocorp.com
StoTherm®ci Mineral Wool General Notes
Detail No.: 56s.SGDate: November 2018Page 4 of 4
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp.All Rights Reserved.
StoTherm®ci Mineral Wool Product Use Information
Detail No.: 56s.SGDate: November 2018Page 1 of 2
Sto Gold Coat® - Roller or spray applied vapor-permeable air & moisture barrier designed for use in StoTherm® ci Systems.
Sto AirSeal™ - Roller or spray applied, medium-to-high build, vapor-permeable air & moisture barrier for use behind siding, brick, stone, adhered veneer, StoTherm® ci Systems, and other claddings.
Sto Gold Coat® TA - Trowel applied vapor-permeable air & moisture barrier for use behind siding, brick, stone, adhered veneer, and StoTherm® ci Systems.
Sto VaporSeal™ - Roller or spray applied high build air barrier and Class 1 vapor retarder (< 0.1 perms). Provides superior protection against vapor diffusion, moisture intrustion, and air leakage.
Fluid Applied Air and Moisture Barrier Products
Detail Component Products
Sto Gold Fill® - Trowel applied joint treatment and air barrier material used to treat rough openings, corners, and sheathing joints with StoGuard® Mesh or Sto Detail Mesh.
Sto RapidGuard™ - One-component air barrier and waterproof material used to protect rough openings, sheathing joints, seams, cracks, penetrations, and other transitions in above grade wall construction.
StoGuard® Fabric - Non-woven cloth reinforcement to treat joints, inside and outside corners and rough openings when embedded in Sto Gold Coat, Sto Emerald Coat, Sto AirSeal or Sto VaporSeal.
StoGuard® Mesh - Glass fiber, self-adhesive mesh for use with Sto Gold Fill and Sto Gold Coat TA as part of the StoGuard assembly.
StoGuard® Transition Membrane - Flexible air barrier material used to make connections with adjoining construc-tion to achieve continuity of the air barrier assembly at dynamic joints and dissimilar materials.
StoGuard® Tape - A self-adhering membrane composed of spun bond polyester fabric laminated to rubberized asphalt adhesive for use as rough opening protection at windows and doors. StoGuard® Primer required.
®
StoTherm®ci Mineral Wool Product Use Chart
Detail No.: 56s.SGDate: November 2018Page 2 of 2
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, or for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp.All Rights Reserved.
StoGuard® Products for Transition Components, Joint Treatments and Rough Opening Protection
StoGuard® Fluid Applied Air & Moisture Barrier with
StoGuard® Fabric
Sheathing Jointsand Corners
Rough Opening Protection
Flashingand Penetration
Static Jointsand Seams
Dynamic Jointsand Seams
Sto Gold Coat® TA with StoGuard® Mesh embedded
Sto Gold Fill with StoGuard®
Mesh or StoGuard® Detail Mesh embedded
Sto RapidGuard™
StoGuard® Tape withStoGuard® Primer
StoGuard® Transition Membrane embedded with any StoGuard® Fluid Applied Air &
Moisture Barrier
1
Transition Components
StoGuard®
Product(s)
1
1
1 Contact Sto Tech Services for more information.
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Glass mat gypsum sheathing in compliance with ASTM C1177, exterior grade and Exposure 1 wood based sheathing, or cementitious sheathing in compliance with ASTM C1325.
3. StoTherm ci Mineral system components:- StoGuard Air and Moisture Barrier- Sto Adhesive- Mineral Wool Insulation Board- Mechanical Fasteners- Sto Base Coat- Sto Mesh- Sto primer (optional)- Sto Finish
4. Allow adhesive to dry before adding fasteners.
5. 2" insulation will use surface mounted fasteners, 3" and 4" insulation will use countersunk fasteners.
6. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
7. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
8. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
®
StoTherm® ci MineralSystem Components Detail No.: 56s.00
Date: November 2018
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier Sheathing Joint Treatment (See Note 1)
Sheathing(See Note 2)
Mineral WoolInsulation Board
Sto Base Coat (with Sto Mesh Embedded)and second layer (skim coat)
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Notes:
1. Additional framing may be needed to accommodate fastener spacing.
2. Allow adhesive to dry before adding fasteners.
3. 2" insulation will use surface mounted fasteners, 3" and 4" insulation will use countersunk fasteners.
4. Please refer to StoTherm ci Mineral Design Guide and StoTherm ci Mineral Install Guide for information on wind loads and fasteners
5. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
StoTherm® ci MineralMechanical Attachment Pattern and Components
Property of Sto Corp. All Rights Reserved.
A. 6-Fastener Configuration on Frame
B. 9-Fastener Configuration on Frame
16"(406mm)
24"
(610
mm
)48"
(1220mm)
6"(1
52m
m)
12"
(304
mm
)
6”(1
52m
m)
8"(203mm)
8"(203mm)
24"
(610
mm
)
48"(1220mm)
4"(1
02m
m)
8"(2
03m
m)
8"(2
03m
m)
4"(1
02m
m) 16"
(406mm)
8"(203mm)
8"(203mm)
Detail No.: 56s.01ADate: November 2018
Notes:
1. Allow adhesive to dry before adding fasteners.
2. 2" insulation will use surface mounted fasteners, 3" and 4" insulation will use countersunk fasteners.
3. Please refer to StoTherm ci Mineral Design Guide and StoTherm ci Mineral Install Guide for information on wind loads and fasteners
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
StoTherm® ci MineralMechanical Attachment Pattern and Components
Property of Sto Corp. All Rights Reserved.
С. 8-Fastener Configuration / Solid Substrate
24"
(610
mm
)
48”(1220mm)
18"(458mm)
18"(458mm)
6"(152mm)
6"(152mm)
12"
(304
mm
)
6"(1
52m
m)
18"(458mm)
6"(152mm)
15"(380mm)
15"(380mm)
6"(1
52m
m)
Detail No.: 56s.01BDate: November 2018
StoTherm® ci MineralTermination at Grade - Sheathing Flush with Foundation or Slab Edge
Detail No.: 56s.03ADate: November 2018
®
Notes:
1. Terminate system minimum 6" (15.2cm) above finished grade, higher for areas with heavy snow accumulations, or where required by code.
2. Ultra-high impact resistance recommended at all ground floors to a minimum height of 6'-0" (1.8m) above finished grade and other areas accesible to pedestrian traffic, abnormal stress or impact.
3. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Sheathing
Mineral WoolInsulation Board
Sto Base Coat(with Sto Mesh Embedded)and second layer(skim coat)
StoGuard® Transition Component Embedded in StoGuard® Air and Moisture Barrier(Protect with StoCoat Acryl Plus or Flashing)
StoGuard® Transition Component
Flashing, Sloped
Backer Rod & Sealant w/ Weep Holes
Terminate Assembly 6” (200 mm) Above Grade, min.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci Mineral at Grade - Sheathing Overlapping Slab or Foundation
Detail No.: 56s.03BDate: November 2018
®
Notes:
1. Terminate system minimum 6" (15.2cm) above finished grade, higher for areas with heavy snow accumulations, or where required by code.
2. Ultra-high impact resistance recommended at all ground floors to a minimum height of 6'-0" (1.8m) above finished grade and other areas accesible to pedestrian traffic, abnormal stress or impact.
3. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Sheathing
Mineral WoolInsulation Board
Terminate Assembly 6" (152 mm) Above Grade, min.
Sto Base Coat(with Sto Mesh embedded)
StoGuard® Transition Component Embedded in StoGuard® Air and Moisture Barrier (Protect with StoCoat Acryl Plus or Flashing)
StoGuard® Transition Component
Flashing, Sloped
Backer Rod & Sealant w/ Weep Holes
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralAesthetic Feature Band
Detail No.: 56s.04Date: November 2018
Notes:
1. Feature band attached with adhesive and thermal dowels/fasteners into supporting structure. Follow the same fastening pattern as for the base layer of insulation board
2. Slope top surface of feature band minimum 27 degrees. Increase slop for northern climates to prevent snow and ice accumulations
3. Limit thickness of build-out to reduce maintenance associated with projecting architectural features. Thickness of trim is limited by available fastener lengths.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
StoGuard® Air and Moisture Barrier
Sto Primer (Optional) Sheathing
Mineral WoolInsulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer(skim coat)
StoGuard® Air and Moisture Barrier
Sheathing
Mineral WoolInsulation Board
Sto Flexyl (with Sto Mesh or Sto Detail Mesh Embedded); Return Vertically 4" (102 mm) min. Above and Below Feature Band
Sto Finish
Sto Finish
Sto Primer (Required over Sto Flexyl and Sto Base Coat Above and Below)
Sto Adhesive
Sto Adhesive
Thin Build-Out
Thick Build-Out
Thick Build-Out, 2-4 in. (51-102 mm)
Thin Build-Out,
≤ 2 in. (51 mm)Light Gauge Steel Stud Framing
Light Gauge Steel Stud Framing
Sto Base Coat (with Sto Mesh Embedded) and second layer(skim coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralAesthetic Reveal
Detail No.: 56s.05Date: November 2018
®
Notes:
1. Slope bottom surface of reveal minimum 27 degrees. Increase slope for northern climates to prevent snow and ice accumulations.
2. Maintain minimum 1 1/2" (19mm) thickness of insulation board at base of reveal.
3. Note that locations of reveals in the system must be coordinated with fastener locations so that they do not cross each other. Reveals must be located 3" minimum from the dowel circumference.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Mineral WoolInsulation Board
Sto Base Coat (with Sto Detail Mesh Embedded)
1 1/2“ (38 mm) min.
2 1/2" (64 mm) min. Ovelap of Sto Detail Mesh w/ Sto Mesh @ Top and Bottom of Reveal
StoGuard® Air and Moisture Barrier
Sto Base Coat (with Sto Mesh Embedded) and second layer (skim coat)
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Mineral WoolInsulation Board
1 1/2“ (38mm) min.
StoGuard® Air and Moisture Barrier
Sheathing
Sheathing
Option 1 with Sto Detail Mesh
Option 2 with Continuous Sto Mesh
Light Gauge Steel Stud Framing
Light Gauge Steel Stud Framing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Base Coat (with Sto Mesh Embedded) and second layer (skim coat)
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents. Step 1 - Rough Opening Protection
StoTherm® ci MineralReceptor-Type Window Sill
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection Over Blocking
Blocking
StoGuard® Air and Moisture Barrier Rough Opening Protection
Detail No.: 56s.23A-1Date: November 2018
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
End Dam Set in Sealant
StoGuard® Air and Moisture Barrier Rough Opening Protection
Mineral Wool Insulation Board, Pre-Wrapped
Sto Adhesive (Fill Gap Between Mineral Wool Boards at Corner with Adhesive, Cut Flush with Surface and Rasp Smooth)
Mineral Wool Insulation Board, Pre-Wrapped around Rough Opening
Sill Receptor w/ Weep Holes (Sill Flashing Extender Not Shown for Clarity)
Sto Adhesive
Weep Holes
Angle (As Needed for Attachment of Sill Receptor and Support)
StoGuard® Air and Moisture Barrier Rough Opening Protection
Blocking
Step 2 - Receptor with End Dam
StoTherm® ci MineralReceptor-Type Window Sill
Detail No.: 56s.23A-2Date: November 2018
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents. Step 3 - Window and Sill Flashing, Cladding, and Perimeter Weather
and Air Seals
StoTherm® ci MineralReceptor-Type Window Sill
Detail No.: 56s.23A-3Date: November 2018
Sto Primer (Optional)
Sto Finish
Sto Base Coat (with Sto Mesh Embedded)and second layer(skim coat)
Backer Rod & Sealant (Entire Perimeter)
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection
Mineral Wool Insulation Board, Pre-Wrapped at Jamb
Mineral Wool Insulation Board, Pre-Wrapped around Rough Opening
Sill Receptor w/ Weep Holes
Sto Adhesive
Spray Polyurethane Foam Insulation
Jamb Receptor
Sill Extender w/ Continuous Bead of Sealant @ Bottom
Window Assembly
Air Seal, Backer Rod & Sealant (Air Seal Entire Perimeter)
Angle (As Needed for Attachment of Sill Receptor and Support)
StoGuard® Air and Moisture Barrier Rough Opening Protection
Blocking
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralReceptor-Type Window Head
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.23B-1Date: November 2018
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection
Flashing
StoGuard® Air and Moisture Barrier Rough Opening Protection
StoGuard® Air and Moisture Barrier
StoGuard® Air and Moisture Transition Component
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Step 1 - Rough Opening Protection, Head Flashing
Cement Board Filler or Other Trim
StoTherm® ci MineralReceptor-Type Window Head
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.23B-2Date: November 2018
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection
Mineral Wool Insulation Board
Minerall Wool Corner Board, Pre-Wrapped around Rough Opening
Window Assembly
Spray Polyurethane Foam Insulation
Head Receptor
Jamb Receptor
Cement Board Filler or Other TrimFlashing
StoGuard® Air and Moisture Barrier Rough Opening Protection
StoGuard® Air and Moisture Barrier
Sto Adhesive
Step 2 - Receptor and Window
Sto Adhesive
StoTherm® ci MineralReceptor-Type Window Head
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.23B-3Date: November 2018
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection
Mineral Wool Insulation Board
Mineral Wool Corner Board, Pre-Wrapped around Rough Opening
Window Assembly
Sto Adhesive
Sto Primer (Optional)
Sto Finish
(with Sto Mesh Embedded) and second layer(skim coat)
Sto Base Coat
Air Seal, Backer Rod and Sealant (Air Seal Entire Perimeter)
Head Receptor
Jamb Receptor Backer Rod & Sealant (Entire Perimeter, with Weeps at Head)
Cement Board Filler or Other Trim (Finish Cement Bd. w/ StoCoat Acryl Plus)
Flashing
StoGuard® Air and Moisture Barrier Rough Opening Protection
StoGuard® Air and Moisture Barrier
Spray Polyurethane Foam Insulation
Step 3 - Cladding and Perimeter Weather and Air Seals
Sto Adhesive
Pre-wrapped system termination(Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralFlanged Window-Sill
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
Step 1 - Rough Opening Protection, Sill Flashing
Detail No.: 56s.24A-1Date: November 2018
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
1/8" (3 mm) Thick Washers Behind Mounting Flange
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
StoGuard® Transition Component(See Note 1)
Flashingwith end dam (See Note 5)
Slope
StoTherm® ci MineralFlanged Window-Sill
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
Step 2 - Window and Trim
Detail No.: 56s.24A-2Date: November 2018
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Mineral Wool Insulation Board, Pre-Wrapped Around Opening (Cut Kerf in Back of Insulation and Slide over End Dam. Position insulation over Flashing with 1/4" [6 mm] Gap for Drainage)
Spray Polyurethane Foam Insulation
StoGuard® Air and Moisture Barrier Rough Opening Protection
Sealant Behind Mounting Flange (Jambs and Head Only)
Sto Adhesive
StoGuard® Transition Component(See Note 1)
Flashingwith end dam (See Note 5)
Slope
Window Assembly
1/8" (3 mm) Thick Washers Behind Mounting Flange
Spray Polyurethane Foam Insulation
StoTherm® ci MineralFlanged Window-Sill
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
®
Detail No.: 56s.24A-3Date: November 2018
Step 3 - Cladding and Perimeter Weather and Air Seals
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Primer (Optional)
Sto Finish
Sto Base Coat(with Sto MeshEmbedded) andsecond layer(skim coat)
Backer Rod & Sealant (Entire Perimeter)
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing(See note 2)
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Mineral Wool Insulation Board, Pre-Wrapped Around Opening
Mineral Wool Insulation Board
Spray Polyurethane Foam Insulation
Window Assembly
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Sto Adhesive
StoGuard® Transition Component(See Note 1)
Fillet Bead of Sealant (not shown) Between Underside of Flashing and Base Coat
1/8" (3 mm) Thick Washers Behind Mounting Flange
Sealant Behind Mounting Flange (Jambs and Head Only)
Air Seal, Backer Rod & Sealant (Air Seal Entire Perimeter)
Spray Polyurethane Foam Insulation
Backer Rod & Sealant with Weeps Between Trim and Flashing Leg
Flashing with end dam (See Note 5)
Air Seal, Backer Rod & Sealant (Air Seal Entire Perimeter)
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoTherm® ci MineralFlanged Window-Head
Detail No.: 56s.24B-1Date: November 2018
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Window Assembly
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
StoGuard® Transition Component(See Note 1)
Sealant Behind Mounting Flange (Jambs and Head Only)
Flashing
Sealant
Step 1 - Rough Opening Protection, Head Flashing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoTherm® ci MineralFlanged Window-Head
Detail No.: 56s.24B-2Date: November 2018
Step 2 - Window and Trim
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Mineral Wool Insulation Board, Pre-Wrapped Around Opening
Mineral WoolInsulation Board
Window Assembly
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Sto Adhesive
StoGuard® TransitionComponent(See Note 1)
Sealant Behind Mounting Flange (Jambs and Head Only)
Sealant
Spray Polyurethane Foam Insulation
Flashing
Backer Rod & Sealant Weather and Air Seals (Entire Perimeter with Weeps Between Underside of Trim & Flashing Leg)
Spray Polyurethane Foam Insulation
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Consult with window and sealant manufacturers to verify window installation and detailing and to assure no water leakage into the wall assembly. Consult with window manufacturer regarding window and/or flashing assembly thermal breaks to avoid condensation. Test the final assembly using materials and trades associated with the project to verify performance. Correct any deficiencies associated with excess air leakage, water infiltration into the wall assembly, or structural inadequacies.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoTherm® ci MineralFlanged Window-Head
Detail No.: 56s.24B-3Date: November 2018
Step 3 - Cladding and Perimeter Weather and Air Seals
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Primer (Optional)
Sto Finish
Sto Base Coat(With Sto Mesh Embedded)and second layer(Skim Coat)
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Mineral Wool Insulation Board, Pre-Wrapped Around Opening
Mineral WoolInsulation Board
StoGuard® Air and Moisture Barrier Rough Opening Protection(See Note 1)
Sto Adhesive
StoGuard® Transition Component(See Note 1)
Sealant Behind Mounting Flange (Jambs and Head Only)
Sealant
Spray Polyurethane Foam Insulation
Flashing
Spray Polyurethane Foam Insulation
Window Assembly
Backer Rod & Sealant Weather and Air Seals (Entire Perimeter with Weeps Between Underside of Trim & Flashing Leg)
StoTherm® ci MineralSoffit: Insulated and Unvented
Detail No.: 56s.30Date: November 2018
®
Notes:
1. Continue StoGuard air and moisture barrier onto dissimilar material or construction where required after verifying substrate material compatibility. Refer to Sto Detail 56s.53 for typical detailing of inside corner if substrate material or construction is dissimilar. Refer to Sto Detail 56s.54A if substrate material is similar at inside corner.
2. 4" (10cm) thick insulation board typically required for proper lap of accessory with mesh "tail". For thinner sections of insulation board pre-wrap insulation board with Sto base coat and mesh
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Nominal 1/4 inch (6 mm) Gap for Drainage
Sheathing
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
StoGuard® Joint Treatment(See Note 4)
Backer Rod and Sealant
Structure
Sto Drip Edge Profile
Sto Drip Edge Profile (See Drawing Below)
Dissimilar Material or Wall Construction
Light Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
StoGuard® Transition Component(See Note 4)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralSoffit: Uninsulated and Vented
Detail No.: 56s.31Date: November 2018
®
Notes:
1. Prevent "communication" of vented air space with conditioned interior air to reduce the likelihood of condensation on materials in the vented space.
2. Typical soffit board is gypsum sheathing in compliance with ASTM C 1177. Refer to Sto Specification No. F601S and Sto Detail Series 14.xx.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Nominal 1/4 inch (6 mm) Gap for Drainage
Sheathing
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
Backer Rod and Sealant
Structure
Sto Drip Edge Profile
Sto Drip Edge Profile (See Drawing Below)
Dissimilar Material or Wall Construction
Light Gauge Steel Stud FramingStoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
StoGuard® Joint Treatment(See Note 4)
Soffit Vent
Casing Bead
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralFloor Line Without Deflection
Detail No.: 56s.40Date: November 2018
®
Notes:
1. This detail is typically limited to low-rise construction where no floor line deflection is anticipated. Refer to Sto Details 53s.41A, and 53s.41B for a floor line condition with deflection.
2. Sheathing attachment is typically at 8" (20.3 cm) on center or less vertically. Add C-channels or other attachment means along slab edge if necessary to conform with required fastener spacing.
3. Provide fire stopping at floor line as needed.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
6. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
7. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Sheathing
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer(Skim Coat)
Sto Adhesive
StoGuard® Air and Moisture Barrier Sheathing Joint Treatment(See note 5)
Structure
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralFloor Line With Deflection - Concealed Flashing and Drainage at Floor Line
Detail No.: 56s.41ADate: November 2018
®
Notes:
1. Sheathing attachment is typically at 8" (20.3 cm) on center or less vertically. Add C-channels or other attachment means along slab edge if necessary to conform with required fastener spacing
2. provide fire stopping at floor line as needed
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Sheathing
Mineral Wool Insulation Board - Pre-Wrapped
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto AdhesiveStoGuard® Air and Moisture Barrier Sheathing Joint Treatment(See note 4)
StoGuard® Transition Membrane (See Note 4)
Horizontal Deflection Joint: Backer Rod & Sealant w/ Drainage Openings. Sealant Applied to Base Coat as per Sealant Manufacturer Instructions
Slotted Deflection Track
Backer Rod
Structure
Cant bead of Sto RapidGuard
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralFloor Line With Deflection - No Drainage at Floor Line
Detail No.: 56s.41BDate: November 2018
®
Notes:
1. Sheathing attachment istypically at 8" (20.3 cm) oncenter or less vertically. AddC-channels or otherattachment means alongslab edge if necessary toconform with requiredfastener spacing.
2. provide fire stopping at floor line as needed.
3. Provide drainage at floor line as deemed by design professional, typically no more then every third floor line. Refer to Sto Detail 56s.41A.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. See StoGuard Chart(56s.SG) for transition component, joint treatment and rough opening protection product options.
6. Mechanical Fasteners not shown. See Sto Detail56s.01 for mechanical attachment pattern and additional information.
7. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Sheathing
Mineral Wool Insulation Board, Pre-Wrapped @ Top and Bottom to Allow for Drainage
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto AdhesiveStoGuard® Air and Moisture Barrier Sheathing Joint Treatment (See note 5)
StoGuard® Transition Membrane (See Note 5)
Horizontal Deflection Joint: Backer Rod & Sealant. Sealant Applied to Base Coat as per Sealant Manufacturer Instructions
Slotted Deflection Track
Backer Rod
Structure
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralFloor Line With Deflection - Drainage at Floor Line
Detail No.: 56s.41CDate: November 2018
®
Notes:
1. Sheathing attachment istypically at 8" (20.3 cm) oncenter or less vertically. AddC-channels or otherattachment means alongslab edge if necessary toconform with requiredfastener spacing.
2. provide fire stopping at floor line as needed.
3. Provide drainage at floor line as deemed by design professional, typically no more then every third floor line. Refer to Sto Detail 56s.41A.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. See StoGuard Chart(56s.SG) for transition component, joint treatment and rough opening protection product options.
6. Mechanical Fasteners not shown. See Sto Detail56s.01 for mechanical attachment pattern and additional information.
7. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Sheathing
Mineral Wool Insulation Board - Pre-Wrapped
Sto Adhesive StoGuard® Air and Moisture Barrier Sheathing Joint Treatment (See note 5)
StoGuard® Transition Membrane (See note 5)
Horizontal Deflection Joint: Backer Rod & Sealant. Sealant Applied to Base Coat as per Sealant Manufacturer Instructions
Slotted Deflection Track
Backer Rod
Structure
Flashing
Sealant
StoGuard® Transition Component (See note 5)
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
®
Notes:
1. Detail applies to Balcony Protected by Balcony Ceiling Above.
2. Slope balcony to direct water away from wall.
3. Consider the use of high or ultra-high reinforcing meshes on balcony walls to supplement standard reinforcing mesh for added abuse and impact resistance.
4. Verify compatibility of StoGuard Air and Moisture Barrier with balcony waterproof membrane material where they interface or lap one another.
5. Counter flash balcony membrane on wall if not fluid applied.
6. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
7. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
8. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.42ADate: November 2018
StoTherm® ci MineralBalcony Floor/Wall
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Primer (Optional)
Sto Finish
(with Sto Mesh Embedded) and second layer(Skim Coat)
Sto Base Coat
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
Mineral Wool Insulation Board, Pre-Wrapped
Sto Adhesive
Balcony Slab Recess
Backer Rod & Sealant w/ Weeps
Balcony Waterproof Membrane and Finished Flooring
Balcony
Cant and Air Seal Transition Material
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
®
Notes:
1. Detail applies to Balcony Protected by Balcony Ceiling Above.
2. Underside of balcony may also be finished with Sto Finish or other Sto smooth or textured coatings.
3. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
6. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.42BDate: November 2018
StoTherm® ci MineralBalcony Ceiling/Wall
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier(See Note 3)
Sto Primer (Optional)
Sto Finish
Sto Adhesive
Sto Base Coat (with Sto Mesh Embedded)and second layer(Skim Coat)
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Sheathing
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Termination
Backer Rod
Backer Rod and Sealant
Balcony
Slotted Deflection Track
Skim Coat of Sto Base Coat
Sto Primer Smooth
StoCoat Acryl Plus
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralHorizontal Termination at Dissimilar Cladding
Detail No.: 56s.50Date: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer(Skim Coat)
Sto Adhesive
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
Backer Rod and Sealant with Weep Holes
Sheathing
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier (See Note 1)
Sealant
StoGuard® Transition Component (See Note 1)
Wood Blocking
Brick Cavity Wall
Masonry Sill
Flashing
StoGuard® Air and Moisture Barrier
StoGuard® Air and Moisture Barrier
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralVertical Termination at Dissimilar Cladding
Detail No.: 56s.51ADate: November 2018
®
Notes:
1. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
2. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
3. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Sheathing
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Vertical Termination
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto AdhesiveLight Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Masonry Veneer or Other Dissimilar Material
Sealant and Backer Rod
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralVertical Termination at Dissimilar Backup Wall Construction
Detail No.: 56s.51BDate: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier(See Note 1)
Sheathing
Light Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier (Minimum Two Coats on CMU Wall Surface)
CMU Backup
Masonry Veneer or Other Dissimilar Material
Sto Finish
Sealant and Backer Rod
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Primer (Optional)
Sto Adhesive
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Vertical Termination
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralVertical Expansion Joint in Back-Up Wall
Detail No.: 56s.52ADate: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Sheathing
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Vertical Termination
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto AdhesiveLight Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sealant and Backer Rod
Sto Finish
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier (See Note 1)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralVertical Expansion Joint in Back-Up Wall,StoTherm ci and Dissimilar Cladding
Detail No.: 56s.52BDate: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Vertical Termination
Masonry Veneer or Other Dissimilar Material
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier
StoGuard® Air and Moisture Barrier(See Note 1)
Sheathing
Sto Primer (Optional)
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Finish
Sealant and Backer Rod
Light Gauge Steel Stud Framing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralInside Corner with Dissimilar Backup Wall
Detail No.: 56s.53Date: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation Board, Back-Wrapped
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
StoGuard® Transition Membrane Embedded in StoGuard® Air and Moisture Barrier (See Note 1)
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
Sealant and Backer Rod
StoGuard® Air and Moisture Barrier (Minimum Two Coats on CMU Wall Surface)
CMU Backup
Sheathing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralInside and Outside Corner with Common Substrateand StoMesh Corner Bead Reinforcement
Detail No.: 56s.54ADate: November 2018
®
Notes:
1. Provide joint at interior corner if movement is anticipated. Refer to Sto Detail 56s.53.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral WoolInsulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
StoGuard® Joint Treatment(See note 2)
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
StoGuard® Air and Moisture Barrier
Sheathing
Sto-Mesh Corner Bead Standard (Embedded in Sto Base Coat)
Sto Mesh (Overlap StoMesh Corner Bead 4 in. ea. Side, min.)
Return Sto Mesh 6 in. (152mm) min. @ Inside Corner
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralInside and Outside Corner with Common Substrateand Sto Mesh Reinforcement
Detail No.: 56s.54BDate: November 2018
®
Notes:
1. Provide joint at interior corner if movement is anticipated. Refer to Sto Detail 56s.53.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
StoGuard® Joint Treatment(See Note 2)
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
StoGuard® Air and Moisture Barrier
Sheathing
Return Sto Mesh 6 in. (152mm) min. Around Corner
Return Sto Mesh 6 (152mm) in. min. @ Inside Corner
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralTermination at Parapet - Front
Detail No.: 56s.60ADate: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation Board, Back-Wrapped
Sto Base Coat (with Sto Mesh Embedded)and second layer(Skim Coat)
Sto Adhesive
Metal Coping
Light Gauge Steel Stud Framing
Sto Primer (Optional)
Sto Finish
StoGuard® Air and Moisture Barrier
Sheathing
Roof Structure
StoGuard® Transition Component Top Coated with StoGuard® Air and Moisture Barrrier (or Compatible Roofing Membrane)(See Note 1)
Wood Blocking
StoGuard® Transition Component (See Note 1)
Backer Rod & Sealant
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralTermination at Parapet - Back
Detail No.: 56s.60BDate: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Mineral Wool Insulation
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Adhesive
Metal Coping
Roof Membrane
Sto Primer (Optional)
Sto Finish
StoGuard® Transition Component (See Note 1)
Sheathing
Roof Structure
StoGuard® Transition Component Top Coated with StoGuard® Air and Moisture Barrrier (or Compatible Roofing Membrane)(See Note 1)Wood Blocking
Backer Rod and Sealant
StoGuard® Transition Component(See Note 1)
Termination Bar for Roof Membrane
Light Ga. Steel Stud Framing
Cover BoardRoof Insulation
StoGuard® Air and Moisture Barrier
Termination Bar for Roof Membrane
Mineral Wool Insulation Board
Wood Blocking
StoGuard® Transition Component(See Note 1)
Insulation
Z-Flashing
Roof Membrane
StoGuard® Air and Moisture Barrier
Sheathing
Backer Rod and Sealant with Weep Holes
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralParapet with Cornice Feature
Detail No.: 56s.61Date: November 2018
®
Notes:
1. Cornice feature limited to 12" (33 cm) maximum thickness, including base layer of insulation, for non-combustable type construction. Special analysis with regard to fire propagation may enable thicker sections. Thicker sections permitted within practical limits for combustible construction.
2. Cornice feature attached with Sto BTS Plus; also used as filler and rasped smooth at any gaps between feature band and base layer of insulation board.
3. Cornice feature may also be attached directly to StoGuard where applicable.
4. Supplemental mechanical attachment of feature band may be necessary in some cases. Verify installation method for adequate attachment before commencing work.
5. See StoGuard Chart(56s.SG) for transition component, joint treatment and rough opening protection product options.
6. Mechanical Fasteners not shown. See Sto Detail56s.01 for mechanical attachment pattern and additional information.
7. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
8. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.View of Pre-Wrapped CorniceView of Mesh Overlap
Sto Mesh Embedded in Base Coat Laps Sto Mesh on Cornice 2 1/2 in. (64 mm) min.
Sto EPS Insulation Cornice Feature
Cornice Feature Pre-Wrapped with Sto Base Coat (with Sto Mesh Embedded)
StoGuard® Transition Component Top Coated with StoGuard® Air and Moisture Barrrier (or Compatible Roofing Membrane, See Note 5)
Wood Construction as Required StoGuard® Air and Moisture Barrier Sheathing Joint Treatment Extends 2 in. (51 mm) min. at Vertical and Horizontal Surfaces (See Notes)
Mineral Wool Insulation Board, Back-Wrapped or Pre-Wrapped at Termination
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Metal Coping
Sto Primer (Optional)
Sto Finish
Sheathing
Backer Rod and Sealant
Light Gauge Steel Stud Framing
StoGuard® Air and Moisture Barrier
1/2 in. (13 mm) min. Gap Between Top Surface of Cornice Feature and Underside of Wood ConstructionPre-Wrapped
Cornice
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralDiverter Flashing at Roof/Wall Abutment
Detail No.: 56s.62Date: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Backer Rod and Sealant Around Vertical Leg of Diverter Flashing
Diverter Flashing
StoGuard® Air and Moisture Barrier
StoGuard® Transition Component(See Note 1)
Mineral Wool Insulation Board, Pre-Wrapped
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat) Sto Primer (Optional)
Sto Finish
Sheathing
Light Gauge Steel Stud Framing
Drip Edge Flashing
Gutter
StoGuard® Air and Moisture Barrier Sheathing Joint Treatment(See Note 1)
Sto Adhesive
Diverter Flashing
Terminate StoTherm ci 2 in. (51 mm) Above Finished Roof
Fascia
Drip Edge Flashing
Roof Structure
Step Flashing
Step Flashing
Sto Finish
Roof ShinglesRoof Underlayment
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralGravel Stop
Detail No.: 56s.63Date: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Mineral Wool Insulation Board
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Primer (Optional)
Sto Finish
Roof Air Barrier(Verify Compatibility)
Light Gauge Steel Stud Framing
Sto Adhesive
Gravel Roof Ballast
Continuous Cleat
Gravel Stop
Sheathing
1/4" (6 mm) Min. Gap Between Top of Mineral Wool Insulation Board and Wood Blocking
Wood Blocking
Roof Membrane
Roof Insulation
Roof Sheathing
Roof Structure
StoGuard® Air and Moisture Barrier Sheathing Joint Treatment (See note 1)
Backer Rod & Sealant
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralSaddle Flashing at Lower/Higher Wall Abutment
®
Notes:
1. Provide minimum 2" (51mm) gap between parapet cap flashing and StoTherm ci termination.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Sheathing
Detail No.: 56s.64-1Date: November 2018
StoGuard® Transition Component(See note 2)
StoGuard® Air and Moisture Barrier
Light Gauge Steel Stud Framing
Step 1 - Air and Moisture Barrier
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralSaddle Flashing at Lower/Higher Wall Abutment
®
Notes:
1. Provide minimum 2" (51mm) gap between parapet cap flashing and StoTherm ci termination.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.64-2Date: November 2018
A
BC
StoGuard® Air and Moisture Barrier
StoGuard® Air and Moisture Barrier
Assembled Saddle Flashing
Saddle Flashing Components
Step 2 - Saddle Flashing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
StoTherm® ci MineralSaddle Flashing at Lower/Higher Wall Abutment
®
Notes:
1. Provide minimum 2" (51mm) gap between parapet cap flashing and StoTherm ci termination.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Detail No.: 56s.64-3Date: November 2018
Parapet Cap Flashing Assembly Extends to Perpendicular Wall
Light Gauge Steel Stud Framing
StoGuard® Transition Component Top Coated with StoGuard® Air and Moisture Barrrier (or Compatible Roofing Membrane, See Note 2)
StoGuard® Transition Component
Wood Blocking
Saddle Flashing Assembly
Backer Rod & Sealant Between StoTherm ci and Saddle Flashing Assembly
StoGuard® Air and Moisture Barrier
Mineral Wool Insulation Board
StoTherm ci Assembly
Step 3 - Cladding, Coping, and Sealant
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralScupper Penetration
Detail No.: 56s.65Date: November 2018
®
Notes:
1. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Mineral Wool Insulation Board, Back-Wrapped Around Scupper Penetration
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat) Sto Primer (Optional)
Sto Finish
Light Gauge Steel Stud Framing
Sto Adhesive
Sheathing
Wood Blocking
Roof Membrane
Roof Insulation
Roof Structure
Backer Rod & Sealant
StoGuard® Transition Component(See Note 1)
Scupper Assembly
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
®
Notes:
1. Refer to Sto Detail 56s.70B where sheathing is "rough cut" around pipe or where gap around pipe exceeds allowable gap dimension for StoGuard Air and Moisture Barrier Detail Component.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Mineral Wool Insulation Board, Back-Wrapped Around Pipe Penetration
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Sto Primer (Optional)
Sto Finish
Light Gauge Steel Stud Framing
Sto Adhesive
Sheathing
Backer Rod & Sealant
StoGuard® Transition Component(See note 2)
Pipe
Detail No.: 56s.70ADate: November 2018
StoTherm® ci MineralPipe Penetration - Precision Cut Sheathing
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
®
Notes:
1. Appropriate spray foam is used to fill gaps in sheathing. Where sheathing fits snug around pipe refer to Sto Detail 56s.70A.
2. See StoGuard Chart (56s.SG) for transition component, joint treatment and rough opening protection product options.
3. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
4. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
5. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
Retrofit or Oversized Pipe Penetration Opening
Detail No.: 56s.70BDate: November 2018
StoTherm® ci MineralPipe Penetration - Rough Cut Sheathing
StoGuard® Air and Moisture Barrier
Mineral Wool Insulation Board, Back-Wrapped Around Pipe Penetration
Sto Primer (Optional)
Sto Finish
Light Gauge Steel Stud Framing
Sto Adhesive
Sheathing
Backer Rod & Sealant
Pipe
Spray Foam (to Fill Gaps, Shaved or Rasped Flush with Sheathing Surface)
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
StoGuard® Transition Component(See note 2)
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)
StoTherm® ci MineralSign Attachment
Detail No.: 56s.71Date: November 2018
®
Notes:
1. Blocking not required where solid substrate or wood-based sheathing is capable of supporting the sign (or other attached object). Use appropriate fasteners for attachment.
2. Mechanical Fasteners not shown. See Sto Detail 56s.01 for mechanical attachment pattern and additional information.
3. Refer to detail 56s.GN for general notes on the StoTherm ci Mineral system.
4. Components not identified as Sto are furnished by other manufacturers and are not necessarily installed by trades who install the Sto products. Refer to project specific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer(Optional)
Sto Finish
Light Gauge Steel Stud Framing
Sheathing
Wood Blocking
Hole Drilled in EIFS and Lined with Sealant
PVC or Stainless Steel Sleeve (Sleeve Extends From Finish Through Blocking, Shown Partial Length for Clarity)
Neutral Cure Sealant
Sign
Washer Behind Sign Set in Sealant
Mineral Wool Insulation Board
Sto Adhesive
Bolt w/ Washers at Each End
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
StoTherm® ci MineralFixture Attachment
Detail No.: 56s.73Date: November 2018
®
Notes:
1. Attach fixture to blockingor solid substrate. Whereattached to blocking seal theblocking with Sto DetailComponent.
2. See StoGuard Chart(56s.SG) for transitioncomponent, joint treatmentand rough openingprotection product options.
3. Mechanical Fasteners notshown. See Sto Detail56s.01 for mechanicalattachment pattern andadditional information.
4. Refer to detail 56s.GN forgeneral notes on theStoTherm ci Mineral system.
5. Components not identifiedas Sto are furnished by othermanufacturers and are notnecessarily installed bytrades who install the Stoproducts. Refer to projectspecific contract documents.
StoGuard® Air and Moisture Barrier
Sto Primer (Optional)
Sto Finish
Light Gauge Steel Stud Framing
Sto AdhesiveSheathing
Backer Rod & Sealant
StoGuard® Transition Component on Blocking; Extend onto Sheathing 2" (50mm) min.(See Note 2)
Exterior Electric Box for Fixture AttachmentBlocking
Mineral Wool Insulation Board, Back-Wrapped Around Electric Box Penetration
ATTENTION
Sto products are intended for use by qualified professional contractors, not consumers, as a component of a larger construction assembly as specified by a qualified design professional, general contractor or builder. They should be installed in accordance with those specifications and Sto’s instructions. Sto Corp. disclaims all, and assumes no, liability for on-site inspections, for its products applied improperly, or by unqualified persons or entities, or as part of an improperly designed or constructed building, for the nonperformance of adjacent building components or assemblies, of for other construction activities beyond Sto’s control. Improper use of Sto products or use as part of an improperly designed or constructed larger assembly or building may result in serious damage to Sto products, and to the structure of the building or its components.
STO CORP. DISCLAIMS ALL WARRANTIES EXPRESSED OR IMPLIED EXCEPT FOR EXPLICIT LIMITED WRITTEN WARRANTIES ISSUED TO AND ACCEPTED BY BUILDING OWNERS IN ACCORDANCE WITH STO’S WARRANTY PROGRAMS WHICH ARE SUBJECT TO CHANGE FROM TIME TO TIME. For the fullest, most current information on proper application, clean-up, mixing and other specifications and warranties, cautions and disclaimers, please refer to the Sto Corp. website, www.stocorp.com.
www.stocorp.com
Property of Sto Corp. All Rights Reserved.
Sto Base Coat (with Sto Mesh Embedded) and second layer (Skim Coat)
Pre-wrapped system termination (Sto detail mesh embedded in Sto Base Coat)