design a roof top based solar power station

57
1 A ROJECT REPORT ON DESIGN OF A ROOF TOP BASED SOLAR POWER STATION FOR SKYLINE INSTITUTE OF ENGINEERING &TECHNOLOGY GREATER NOIDA Submitted by SUMIT KUMAR SAROJ KUMAR SUDHANSHU KUMAR SUNNY KUMAR In partial fulfilment for the award of the degree Of BACHELOR OF TECHNOLOGY In ELECTRICAL & ELECTRONICS ENGINEERING Under the guidance of Dr. B.L. Kaul SKYLINE INSTITUTE OF ENGINEERING & TECHNOLOGY GREATER NOIDA 2015-2016

Transcript of design a roof top based solar power station

Page 1: design a roof top based solar power station

1

A ROJECT REPORT

ON

DESIGN OF A ROOF TOP BASED SOLAR POWER STATION

FOR SKYLINE INSTITUTE OF ENGINEERING

&TECHNOLOGY GREATER NOIDA

Submitted by

SUMIT KUMAR

SAROJ KUMAR

SUDHANSHU KUMAR

SUNNY KUMAR

In partial fulfilment for the award of the degree

Of

BACHELOR OF TECHNOLOGY

In

ELECTRICAL & ELECTRONICS ENGINEERING

Under the guidance of

Dr. B.L. Kaul

SKYLINE INSTITUTE OF ENGINEERING & TECHNOLOGY

GREATER NOIDA 2015-2016

Page 2: design a roof top based solar power station

2

CERTIFICATE

This is certify that

Sumit Kumar (1215321074)

Saroj Kumar (1215321065)

Sudhanshu Kumar (1215321073)

Sunny Kumar (1215321075)

Of B.Tech. (Electrical & Electronics Department), Semester VIII,

have satisfactorily completed the project on “DESIGN OF A ROOF

TOP BASED SOLAR POWER STATION FOR SIET GREATER

NOIDA” as a part of curriculum during the academic term 2015-

2016.

Date of submission: 28th, April, 2016

Guide: Dr. B.L. Kaul Head of Department: Mr. S.M Khan

Page 3: design a roof top based solar power station

3

ABSTRACT

The report presents the proposal of a novel design of ROOF TOP BASED

SOLAR POWER STATION FOR SKYLINE INSTITUTE OF

ENGINEERING & TECHNOLOGY.

Suitable roof areas of different blocks of the institute having proposed to

be utilised installation of PV module for generation of electric power

from sunlight as an alternative to electric power supply by NPCL

(NOIDA POWER CORPORATION LIMITED).

Page 4: design a roof top based solar power station

4

ACKNNOWLDGEMENTS

We would like to extend our heartfelt thanks to our Guide Dr. B.L. Kaul,

Who thought us worthy and kindly let us be a part of this project. We

thank him for his faith in us and for his encouragement, guidance and also

for his constant and avid interest in the project throughout its duration and

beyond. Sir, you are our guidance light.

We would also like to thank Mr. S.P. Singh for providing us electrical

load data of the institute for load study of the institute.

Page 5: design a roof top based solar power station

5

TABLE OF CONTENTS

Chapter no Contents Page no

1 Introduction. 6-14

2 Roof top based (SPV) system. 15-21

3 The load data of the institute. 22-27

4 The peak load of the institute (Existing). 28-31

5 Available roof top area of the institute. 32-44

6 Design and installation of the roof top based SPV

system.

45-46

7 Annual energy consumption of the institute. 47-51

8 Cost Estimation of the SPV power station. 52

9 Maintenance schedule. 53-55

10 Conclusion. 56

11 List of references. 57

Page 6: design a roof top based solar power station

6

CHAPTER 1

INTRODUCTION

1.1 SPV SYSTEMS

Solar photovoltaic (SPV) is a field of solar energy utilization by which

solar radiation is converted into electricity or electrical energy using a

device called photovoltaic (PV) cell or solar cell. A solar cell is made up

of a semiconductor material like silicon or other semiconductors material

like GaAs. When sunlight (in the form of photon) falls on these

semiconductor materials, electricity is generated. The amount of this

generated electricity is depends upon some factors like intensity of solar

radiation

A photovoltaic system, also solar PV power system, or PV system, is a

power system designed to supply usable solar power by means of

photovoltaic. It consists of an arrangement of several components,

including solar panels to absorb and convert sunlight into electricity, a

solar inverter to change the electric current from DC to AC, as well as

mounting, cabling and other electrical accessories to set up a working

system. It may also use a solar tracking system to improve the system's

overall performance and include an integrated battery solution, as prices

for storage devices are expected to decline. Strictly speaking, a solar array

only encompasses the ensemble of solar panels, the visible part of the PV

system, and does not include all the other hardware, often summarized as

balance of system (BOS). Moreover, PV systems convert light directly

Page 7: design a roof top based solar power station

7

into electricity and shouldn't be confused with other technologies, such as

concentrated solar power or solar thermal, used for heating and cooling.

PV systems range from small, rooftop-mounted or building-integrated

systems with capacities from a few to several tens of kilowatts, to large

utility-scale power stations of hundreds of megawatts. Nowadays, most

PV systems are grid-connected, while off-grid or stand-alone systems

only account for a small portion of the market.Operating silently and

without any moving parts or environmental emissions, PV systems have

developed from being niche market applications into a mature technology

used for mainstream electricity generation. A rooftop system recoups the

invested energy for its manufacturing and installation within 0.7 to 2

years and produces about 95 percent of net clean renewable energy over a

30-year service lifetime.

(Figure-1.1) Construction of PV module.

Page 8: design a roof top based solar power station

8

(Figure-1.2 ) SPV module.

Page 9: design a roof top based solar power station

9

1.2 PV CELL

A slab (or wafer) of pure silicon is used to make a PV cell. The top of the

slab is very thinly diffused with an “n” dopant such as phosphorous. On

the base of the slab a small amount of a “p” dopant, typically boron, is

diffused. The boron side of the slab is 1,000 times thicker than the

phosphorous side. Dopants are similar in atomic structure to the

primary material. The phosphorous has one more electron in its outer

shell than silicon, and the boron has one less. These dopants help create

the electric field that motivates the energetic electrons out of the cell

created when light strikes the PV cell.

Figure-1.3 Working principal of PV cell.

Page 10: design a roof top based solar power station

10

The phosphorous gives the wafer of silicon an excess of free electrons; it

has a negative character. This is called the n-type silicon (n = negative).

The n-type silicon is not charged—it has an equal number of protons and

electrons—but some of the electrons are not held tightly to the atoms.

They are free to move to different locations within the layer. The boron

gives the base of the silicon a positive character, because it has a

tendency to attract electrons. The base of the silicon is called p-type

silicon (p = positive).

The p-type silicon has an equal number of protons and electrons; it has a

positive character but not a positive charge. Where the n-type silicon and

p-type silicon meet, free electrons from the n-layer flow into the p-layer

for a split second, then form a barrier to prevent more electrons from

moving between the two sides.

Figure-1.4 Typical PV cell.

Page 11: design a roof top based solar power station

11

This point of contact and barrier is called the p-n junction. When both

sides of the silicon slab are doped, there is a negative charge in the p-type

section of the junction and a positive charge in the n-type section of the

junction due to movement of the electrons and “holes” at the junction of

the two types of materials. This imbalance in electrical charge at the p-n

junction produces an electric field between the p-type and n-type silicon.

the PV cell is placed in the sun, photons of light strike the electrons in the

p-n junction and energize them, knocking them free of their atoms. These

electrons are attracted to the positive charge in the n-type silicon and

repelled by the negative charge in the p-type silicon. Most photon-

electron collisions actually occur in the silicon base.

A conducting wire connects the p-type silicon to an electrical load, such

as a light or battery, and then back to the n-type silicon, forming a

complete circuit. As the free electrons are pushed into the n-type silicon

they repel each other because they are of like charge.

The wire provides a path for the electrons to move away from each other.

This flow of electrons is an electric current that travels through the circuit

from the n-type to the p-type silicon.

In addition to the semi-conducting materials, solar cells consist of a top

metallic grid or other electrical contact to collect electrons from the semi-

conductor and transfer them to the external load, and a back contact layer

to complete the electrical circuit.

Page 12: design a roof top based solar power station

12

1.2 ROOF TOP SPV SYSTEM

Several cities and towns in the country are experiencing a substantial

growth in their peak electricity demand. Municipal Corporations and the

electricity utilities are finding it difficult to cope with this rapid rise in

demand and as a result most of the cities/towns are facing severe

electricity shortages.

Various industries and commercial establishments e.g. Malls, Hotels,

Hospitals, Nursing homes etc housing complexes developed by the

builders and developers in cities and towns use diesel generators for

back-up power even during the day time. These generators capacities

vary from a few kilowatts to a couple of MWs. Generally, in a single

establishment more than one generators are installed; one to cater the

minimum load required for lighting and computer/ other emergency

operations during load shedding and the others for running

ACs and other operations such as lifts/ other power applications.

With an objective to reduce dependency on diesel gensets, a scheme to

replace them with SPV is being proposed. Further, in order to utilize the

existing roof space of buildings, the scheme proposes to promote roof-top

Page 13: design a roof top based solar power station

13

SPV systems on buildings to replace DG gensets installed for minimum

load requirement for operation during load shedding. These loads are

generally varying between 25 kW to 100 kW or so. A roof top SPV

system could be with or without grid interaction. In grid interaction

system, the DC power generated from SPV panels is converted to AC

power using power conditioning unit and is fed to the grid either of 11

KV three phase line or of 220 V single phase line depending on the

system installed at institution/commercial establishment or residential

complex. They generate power during the daytime which is utilized fully

by powering the captive loads and feeding excess power to the grid as

Page 14: design a roof top based solar power station

14

long as grid is available. In cases, where solar power is not sufficient due

to cloud cover etc. the captive loads are served by drawing power

from the grid. The grid- interactive roof-top SPV systems thus work on

net metering basis wherein the beneficiary pays to the utility on net meter

reading basis only. Ideally, grid interactive systems do not require

battery back up as the grid acts as the back-up for feeding excess solar

power and vice-versa. However, to enhance the performance

reliability of the overall systems, a minimum battery-back of one hr of

load capacity is strongly recommended. In grid interactive systems, it has

, however to be ensured that in case the grid fails, the solar power has to

be fully utilized or stopped immediately feeding to the grid (if any in

excess) so as to safe-guard any grid person/technician from getting shock

(electrocuted) while working on the grid for maintenance etc. This

feature is termed as ‘Islanding Protection’ Non-grid interactive systems

ideally require a full load capacity battery power back up system.

However, with the introduction of advanced load management and

power conditioning systems, and safety mechanisms, it is possible to

segregate the day-time loads to be served directly by solar power without

necessarily going through the battery back-up. As in the previous case of

grid-interactive systems, minimum one hour of battery back-up is,

however, strongly recommended for these systems also to enhance the

performance reliability of the systems. The non-grid interactive system

with minimum battery back are viable only at places where normal power

is not available during daytime. In case the SPV power is to be used after

sunshine hours, it would require full load capacity battery backup which

will increase the cost of system which may not be economically viable

even with support from Government.

Page 15: design a roof top based solar power station

15

CHAPTER 2

ROOF TOP BASED (SPV) SYSTEM

2.1 ABOUT ROOF TOP SPV

A rooftop photovoltaic power station, or rooftop PV system, is

a photovoltaic system that has its electricity-generating solar

panels mounted on the rooftop of a residential or commercial building or

structure. The various components of such a system include photovoltaic

modules, mounting systems, cables, solar inverters and other electrical

accessories.

Rooftop mounted systems are small compared to ground-

mounted photovoltaic power stations with capacities in the

megawatt range. Rooftop PV systems on residential buildings typically

feature a capacity of about 5 to 20 kilowatts (kW), while those mounted

on commercial buildings often reach 100 kilowatts or more.

The urban environment provides a large amount of empty rooftop spaces

and can inherently avoid the potential land use and environmental

concerns. Estimating rooftop solar insolation is a multi-faceted process,

as insolation values in rooftops are impacted by the following:

Time of the year

Latitude

Weather conditions

Roof slope

Roof aspect

Shading from adjacent buildings and vegetation

Page 16: design a roof top based solar power station

16

India’s solar market, especially solar photovoltaic, has seen significant

growth after the launch of the Jawaharlal Nehru National Solar Mission

in 2010, with an installed capacity of over 3 GW in just four years. The

Government of India is determined towards achieving 100 GW of grid

interactive solar power capacity by 2020, of which 40 GW would be

Deployed through decentralized and rooftop-scale solar projects.

Rooftop solar PV would play a prominent role in meeting energy

demands across segments. It has already achieved grid parity for

commercial and industrial consumers, and fast becoming attractive for

residential consumers as well. As a result, multiple state governments

have taken necessary steps to kick-start implementation of rooftop solar

PV projects.

2.2 TYPES OF ROOF TOP SPV SYSTEM

The rooftop SPV system can be installed in two configurations, namely

i. As A Standalone System

ii. As A Grid Interactive System

In urban areas the grid interactive systems are more feasible than the

standalone systems as almost all locations are connected by grid. These

grids act as storage for an intermittent source of generation. In this study

we are focusing on grid interactive rooftop SPV systems. In the grid

interactive systems, there are different grid interconnection configurations

Page 17: design a roof top based solar power station

17

depending on the reliability of electricity supply to the loads and the

consumer needs.

2.3 STAND ALONE ROOF TOP SPV SYSTEM

Solar Photovoltaic Technology is employed for directly converting solar

energy to electrical energy by the using “solar silicon cell”.

Non-grid interactive systems ideally require a full load capacity battery

power back up system. However, with the introduction of advanced load

management and power conditioning systems, and safety mechanisms, it

is possible to segregate the day-time loads to be served directly by solar

power without necessarily going through the battery back-up. As in the

previous case of grid-interactive systems, minimum one hour of battery

back-up is, however, strongly recommended for these systems also to

enhance the performance reliability of the systems. The non-grid

interactive system with minimum battery back are viable only at places

where normal power is not available during daytime. In case the SPV

power is to be used after sunshine hours, it would require full load

capacity battery backup which will increase the cost of system which may

not be economically viable even with support from Government.

There have been several initiatives from the Government of India to

promote solar PV applications. From time to time the Ministry has

implemented various schemes for demonstration and promotion of solar

energy devices.

Page 18: design a roof top based solar power station

18

2.4 GRID CONNECTED SPV SYSTEM

The grid- interactive rooftop SPV systems thus work on net metering

basis wherein the beneficiary pays to the utility on net meter reading basis

only. Ideally, grid interactive systems do not require battery backup as the

grid acts as the back-up for feeding excess solar power and vice versa.

However, to enhance the performance reliability of the overall systems, a

minimum battery-back of one hr of load capacity is strongly

recommended. In grid interactive systems, it has , however to be ensured

that in case the grid fails, the solar power has to be fully utilized or

stopped immediately feeding to the grid (if any in excess) so as to safe-

guard any grid person/technician from getting shock (electrocuted) while

working on the grid for maintenance etc. This feature is termed as

Islanding Protection.

Figure 2.1 Layout of grid connected SPV system.

Page 19: design a roof top based solar power station

19

Figure 2.2 A typical roof top SPV system.

Page 20: design a roof top based solar power station

20

Table 2.1 State wise installed roof top solar capacity.

State Current installed capacity in Mw

Punjab 19

Haryana 14

Rajasthan 21

Gujarat 25

Madhya Pradesh 10

Maharashtra 40

Karnataka 25

Kerala 8

Tamil Nadu 36

Andhra Pradesh 21

Odisha 14

Chhattisgarh 11

West Bengal 13

Uttar Pradesh 24

Bihar 5

Delhi 8

Uttarakhand 8

Page 21: design a roof top based solar power station

21

Jharkhand 1

Others 38

Total (all india) 350

*Approved in September 2015

Source BRIDGE TO INDIA

Page 22: design a roof top based solar power station

22

CHAPTER 3

THE LOAD DATA OF THE INSTITUTE

A measure of the electrical load of the institute has been recorded on the

hourly basis and the same is given as under.

The phase current are as record Ir, Iy, Ib, the average load has been

phase Iav

Table 3.1 The load data of the institute taken on 16th January 2016.

Time Ir Iy Ib Iav

09:00 AM 42.6 46.8 45.2 44.86

10:00 AM 51.2 48.6 49.8 49.86

11:00 AM 49.7 42.2 45.6 45.83

12:00 AM 54.3 49.8 42.6 48.9

01:00 PM 48.6 32.6 45.4 42.2

02:00 PM 45.4 47.6 45.3 46.1

03:00 PM 50.3 49.2 50.6 50.03

04:00 PM 35.8 29.2 39.6 34.86

05:00 PM 32.9 26.4 28.3 29.2

06:00 PM 45.4 40.6 58.0 48

07:00 PM 48.6 45.9 41.9 45.46

08:00 PM 46.9 44.6 40.9 44.13

09:00 PM 45.6 40.8 39.6 42

10:00 PM 46.3 40.2 38.5 41.66

11:00 PM 45.3 44.2 36.4 4196

12:00 PM 46.7 40.9 35.4 41

Page 23: design a roof top based solar power station

23

01:00 AM 36.2 36.4 30.3 34.3

02:00 AM 36.8 37.2 29.4 34.46

0

10

20

30

40

50

60

70

9:0

0 A

M

10

:00

AM

11

:00

AM

12

:00

AM

1:0

0 P

M

2:0

0 P

M

3:0

0 P

M

4:0

0 P

M

5:0

0 P

M

6:0

0 P

M

7:0

0 P

M

8:0

0 P

M

9:0

0 P

M

10

:00

PM

11

:00

PM

12

:00

PM

1:0

0 A

M

2:0

0 A

M

Cu

rre

nt

in A

mp

Time

I R I Y I B Average

Page 24: design a roof top based solar power station

24

2nd February load data

Table 3.2 The load data of the institute taken on 2nd February 2016.

TIME Ir Iy Ib Iav

9:00 AM 75 78.2 65.9 72.9

10:00 AM 77.4 69.4 65.2 70.6

11:00 AM 68.2 50.8 58.3 59.1

12:00 PM 65.1 62.8 62.4 63.3

1:00 PM 70.4 60.9 65.4 65.56

2:00 PM 63.8 52.8 56.2 56.4

3:00 PM 62.6 50.4 55.8 56.26

4:00 PM 69.9 61.3 71.6 67.6

5:00 PM 55.3 52.6 50.4 52.76

6:00 PM 64.7 60.2 50.2 58.36

7:00 PM 62.3 57.1 55.3 58.23

8:00 PM 63.6 55.7 56.4 58.56

9:00 PM 59.5 58.4 51.6 56.46

10:00 PM 61.2 61.3 52.3 58.26

11:00 PM 58.1 57.5 50.4 55.33

12:00 AM 55.4 55.2 49.5 53.36

1:00 AM 50 46.3 45.6 47.3

2:00 AM 41.6 41.5 35.2 38.45

Page 25: design a roof top based solar power station

25

0

10

20

30

40

50

60

70

80

90

Cu

rre

nt

in A

mp

Time

I R I Y I B Average

Page 26: design a roof top based solar power station

26

7th March, 2016 load data.

Table 3.3 The load data of the institute taken on 7th March, 2016.

TIME Ir Iy Ib Iav

9:00 AM 85 78.2 65.9 76.36

10:00 AM 90 69.4 65.2 74.86

11:00 AM 120 110 100 110

12:00 PM 100 90 105 98.33

1:00 PM 90 85 80 85.2

2:00 PM 70 65 75 70

3:00 PM 65 55 70 63.33

4:00 PM 70 60 75 68.3

5:00 PM 65 59 60 61.33

Page 27: design a roof top based solar power station

27

0

20

40

60

80

100

120

140

9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM

CU

RR

ENT

IN A

MP

TIME

Ir Iy Ib Iav

Page 28: design a roof top based solar power station

28

CHAPTER 4

PEAK LOAD OF THE INSTITUTE

PEAK LOAD

Peak demand, peak load or on-peak are terms used in energy demand

management describing a period in which electrical power is expected to

be provided for a sustained period at a significantly higher than average

supply level. Peak demand fluctuations may occur on daily, monthly,

seasonal and yearly cycles. For an electric utility company, the actual

point of peak demand is a single half-hour or hourly period which

represents the highest point of customer consumption of electricity.

The daily peak demand usually occurs around 9:00 AM at this time there

is a combination of office demand and all student and faculties are come

in the institute. The peak demand of the institute is in summer due to all

fans and AC is operating.

Page 29: design a roof top based solar power station

29

Minimum load of the institute

Minimum load of the institute is taken on march 2016.

Table 4.1 24 hour load data of 7th March, 2016.

TIME Ir Iy Ib Iav Total

9:00 AM 31.18 32.47 27.4 30.35 91.05

10:00

AM 32.18 28.85 27.11 29.38

88.14

11:00

AM 28.35 21.12 24.24 24.57

73.71

12:00 PM 27.06 26.11 25.94 26.37 89.11

1:00 PM 29.27 25.32 27.11 27.23 81.69

2:00 PM 26.52 21.95 23.32 23.93 71.79

3:00 PM 26.02 20.95 23.2 23.33 69.99

4:00 PM 28.73 27.98 29.68 28.79 86.37

5:00 PM 22.99 21.88 21.16 22.1 66.3

6:00 PM 26.9 25.03 20.99 24.03 72.04

7:00 PM 25.9 23.74 23.32 24.32 72.96

8:00 PM 26.44 23.16 21.45 23.68 70.89

9:00 PM 24.74 24.28 21.87 23.63 70.89

10:00 PM 20.83 21.28 17.83 19.98 59.94

11:00 PM 20.04 19.62 16.25 18.63 55.89

12:00

AM 18.75 18.69 13.51 16.98

51

1:00 AM 18.08 16.88 12.3 15.66 46.5

2:00 AM 16.67 14.71 10.6 13.80 41.4

3:00 AM 16 13.09 9.39 12.82 38.5

4:00 AM 16.04 12.51 8.89 12.48 37.44

5:00 AM 16.67 12.3 8.56 12.51 37.53

6:00 AM 17.13 14.96 10.02 14.09 42.27

7:00 AM 16.88 15.59 12.22 14.89 44.67

8:00 AM 20.95 19.45 14.63 18.34 55.2

9:00 AM 31.18 32.47 27.4 30.35 91.05

Page 30: design a roof top based solar power station

30

According to data curve:-

Total power consumed in 7th March 2016 is 1603.32 Kw in 24 hours.

Hence power consumed in 1 hour is 66.93 Kw

According to NPCL bill:-

The minimum load demand of our institute is taken on March 2016

according to our meter reading by NPCL bill.

Total consumed unit in March 2016 is 32054 Kwh.

Total power demand average per day is 44.51 Kw.

0

5

10

15

20

25

30

35

PO

WER

IN K

W

TIME

24 Hour load cycle of 2nd february, 2016

R PHASE Y PHASE B PHASE AVERAGE

Page 31: design a roof top based solar power station

31

Maximum load of the institute

Maximum load of the institute is taken on September 2015 according to

NPCL bill.

Total energy consumed in September 2015 is 69989 Kwh.

Total energy consumed per day in September 2015 is 2333 Kwh.

Hence power consumed in one hour is 97.20 Kw.

Hence maximum load of the institute approx. 100 Kw.

Table 4.2 Minimum and maximum load demand per hour of the institute

Month / Year Total energy

consumed (Kwh)

Power per hour

(Kw)

March, 2016 32054 44.51

September, 2015 69989 97.20

0

20

40

60

80

100

120

March, 2016 September, 2015

Kw

Month / Year

Power per hour

Power per hour

Page 32: design a roof top based solar power station

32

CHAPTER 5

ROOF TOP AREA AVAILABLE IN THE INSTITUTE

The objective of the project is to proposed a roof top based solar power

station for our institute skyline institute of engineering and technology.

And design the same roof top area of the different block of the institute

consider, one by one for the achievement of the result.

ROOF TOP AREA OF BLOCK A & B SIET GREATER

NOIDA

The roof top area of block A & B are used to be installing PV panel for

generating electricity as per efficiency of the panel. The roof top area of this

block have some obstacles and already utilised area such as for stair roof, water

tank and water pipes. The roof area and shading part is shown in figure below.

Table 6.1 Available roof top area of block A & B of the S.I.E.T

Total roof area 1420.45 m2

Covered area 68.41 m2

Shaded area 109.9 m2

Net area = TRA-(C+S) 1242.14 m2

*TRA =Total roof area, *C+S = covered +shaded

Page 33: design a roof top based solar power station

33

Table 6.1 Administration (A & B) block S.I.E.T Greater Noida.

Page 34: design a roof top based solar power station

34

Figure 6.2 Available roof area.

Figure 6.3

Page 35: design a roof top based solar power station

35

ROOF TOP AREA OF BLOCK C

SIET GREATER NOIDA

Table 6.2 Available roof top area of block C, S.I.E.T Greater Noida.

Total roof area 1551 m2

Covered area 229.8 m2

Shaded area 102.4 m2

Net area = TRA-(C+S) 1218.8 m2

Page 36: design a roof top based solar power station

36

Figure 6.4 Available roof top area of block C, S.I.E.T Greater Noida.

Page 37: design a roof top based solar power station

37

Figure 6.5 Water pipe and water tank on block C.

Page 38: design a roof top based solar power station

38

ROOF TOP AREA OF PGDM BLOCK

SIET GREATER NOIDA

Table 6.3 Available roof top area of PGDM block S.I.E.t Greater Noida.

Total roof area 1096.25 M^2

Covered area 120.53 M^2

Shaded area 153.9 M^2

Net area = TRA-(C+S) 822.47 M^2

Page 39: design a roof top based solar power station

39

Figure 6.6 Available rof top area of PGDM block S.I.E.T Greater Noida.

Page 40: design a roof top based solar power station

40

ROOF TOP AREA OF BLOCK D

SIET GREATER NOIDA

Figure 6.4 Available roof top area of block D, S.I.E.T Greater Noida.

Total roof area 1060.28 M^2

Covered area 160.62 M^2

Shaded area 167.70 M^2

Net area = TRA-(C+S) 731.96 M^2

Page 41: design a roof top based solar power station

41

Figure 6.7 Available roof top area of block D, S.I.E.T Greater Noida.

Page 42: design a roof top based solar power station

42

ROOF TOP AREA OF MBA BLOCK

SIET GREATER NOIDA

Table 6.5 Available roof top area of MBA block S.I.E.T Greater Noida.

Total roof area 1177.6 m2

Covered area 155.0 m2

Shaded area 49.6 m2

Net area = TRA-(C+S) 973.0 m2

Page 43: design a roof top based solar power station

43

Figure 6.8 Available roof top area of MBA block SIET.

Page 44: design a roof top based solar power station

44

Table 6.7 Total roof area available for installation of SPV power station.

Block

Name

Total Roof

Area

Available

area

Useful Area

AMF=Area Multiplying Factor

AMF=0.6 AMF=0.65 AMF=0.7

Block A 1420.42 1242.14 745.28 807.39 869.49

Block B/C 1551.01 1218.8 731.28 792.22 853.16

Block D 1060.28 731.96 439.17 475.77 512.37

PGDM 1096.25 973.0 583.80 632.45 681.10

MBA 1177.60 827.47 493.48 534.60 575.72

TOTAL 4993.37 2993.01 3242.43 3491.84

All area are in m2

AA= Available Area= TOTAL AREA – ALREADY UTILISED AREA

Page 45: design a roof top based solar power station

45

CHAPTER 6

DESIGNING AND INSTALLATION OF THE SPV

SYSTEM

Total available roof top area for designing and installation of the SPV system is

given below

Table 7.1 Total roof top area available in the institute.

Block Name Total Roof Area Available

area

Useful Area

AMF=Area Multiplying Factor

AMF=0.6 AMF=0.65 AMF=0.7

Block A 1420.42 1242.14 745.28 807.39 869.49

Block B/C 1551.01 1218.8 731.28 792.22 853.16

Block D 1060.28 731.96 439.17 475.77 512.37

PGDM 1096.25 973.0 583.80 632.45 681.10

MBA 1177.60 827.47 493.48 534.60 575.72

TOTAL 4993.37 2993.01 3242.43 3491.84

Page 46: design a roof top based solar power station

46

Total available roof top area of the institute cannot be taken to install SPV

system due to following reason.

Solar panel maintenance.

Movement of personnel from one corner to another corner.

Water pipe repairing.

So we take area multiply factor (A.M.F) 0.65 for the installation of SPV

system

ENERGY GENERATION FROM THE AVAILABLE ROOF TOP

AREA IS GIVEN BELOW

Table 7.2 Available area for energy generation at AMF=0.65.

Block Available area

(m2)

Available area for energy

generation (m2)

Block A & B 1242.14 807.39

Block C 1218.8 792.22

Block D 731.96 475.77

PGDM block 973.0 632.45

MBA block 827.47 534.60

TOTAL 4993.37 3242.43

ENERGY GENERATED 324.2 Kw

Since 10 m2 = 1 Kw.

Hence 3242 m2 = 324 Kw.

Thus total energy generation from the available roof top area is approx.

325 Kw

Page 47: design a roof top based solar power station

47

CHAPTER 7

Annual, Monthly Energy Consumption of Institute 2012-2016

This is the data which shows the annual monthly energy consumption of the

skyline institute of engineering and technology. This is given by NPCL to

the institute. It is the annually consume by the institute from the grid.

Table 5.1 Annual, Monthly Energy Consumption of Institute 2012-2016.

Month 2012 2013 2014 2015 2016

January 31732 35287 27520 32132 39557

February 42700 37937 31867 28937 37585

March 38142 39527 17367 23712 32054

April 54930 59260 65860 42805

May 57446 63580 45890 62427

June 47667 42222 53172 58787

July 35895 22057 37227 37910

August 42690 40967 53005 58475

September 57460 45792 56420 69989

October 51855 42730 39329 56460

November 31962 29255 36557 36255

December 45485 41230 41335 38032

TOTAL 537964 458614 505549 545921

Page 48: design a roof top based solar power station

48

0

10000

20000

30000

40000

50000

60000

70000

80000

Kw

h

Months

Graph of energy consumption 2012-2016.

2012 2013 2014 2015 2016

Page 49: design a roof top based solar power station

49

Table 5.2 Energy consumption of year 2015.

Month Unit Consume In (Kwh)

January 32132

February 28937

March 23712

April 42805

May 62427

June 58787

July 37910

August 58475

September 69989

October 56460

November 36255

December 38025

Page 50: design a roof top based solar power station

50

32132

28937

23712

42805

62427

58787

37910

58475

69989

56460

3625538025

0

10000

20000

30000

40000

50000

60000

70000

80000U

nit

in K

wh

Month

Unit Consume In 2015 (Kwh)

Page 51: design a roof top based solar power station

51

Energy consumption of year 2016

Table 5.3 Energy consumption of year 2016.

Month Unit Consume In (Kwh)

January 39557

February 37585

March 32054

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

Un

its

in K

wh

Month

Unit Consume In 2016 (Kwh)

Page 52: design a roof top based solar power station

52

CHAPTER 8

COST ESTIMATION OF THE POWER STATION

Table 8.1 Cost estimation for the installation of SPV power station.

Capacity (Kw) Estimated cost

300 2.10 Cr

350 2.45 Cr

400 2.80 Cr

450 3.10 Cr

0

0.5

1

1.5

2

2.5

3

3.5

300 350 400 450

RU

PEE

S IN

CR

OR

E

INSTALLED CAPACITY IN KW

Estimated cost

Estimated cost

Page 53: design a roof top based solar power station

53

CHAPTER 9

System Maintenance

In last 15 year it has been found that the biggest factor attributing to the

inconsistent performance of the system is poor maintenance .the dos and

don’ts for the maintenance of spv module and associated system are:

Do’s

1. Ensure that the SPV panels are at the right direction receiving

maximum sunlight without obstruction throughout the day and

SPV and should not be

2. Moved or shift from the original position of installation

3. Never be kept under any form of shadow or shad and should be

located in a place where it receives unobstructed sunlight from sun

rise to sun set.

4. Ensure the (SPV) is kept very clean and free from any dust and

foreign material.

5. Ensure that the condition of the cables connected to the system and

battery are not physically abused and are always in good condition.

6. Clean the glass core of the module regularly at last once a week if

we clarify, This will also located .in general It should be cleaned

once in two days .A solar based system has 100% dependency on

sunlight Is and not cleaning the system will definitely affected its

performance.

7. Always insure that the DM water (battery water) is always full

inside the battery and its cells pour through expansion bottle .If the

water is not full this will affect the backup time and will not give

the desired illumination period

Page 54: design a roof top based solar power station

54

8. Ensure the battery is always kept clean and terminal should be

clean and smeared with Vaseline to avoid oxidation regularly.

9. Ensure only recommended luminaries is use for lighting which is

provided with the system.

10. Ensure the external cabling does not exceed 7mtrs/20feet. If

external cabling exceeds the recommended length. The system

output will be reduced an account of cable/ current losses in the

cable line.

11. When the ambient temperature falls below 35deg centigrade

(especially during winters) always keep the battery in good charged

condition, as this will enable the system to perform well at its

optimum best.

12. During the cloudy and overshadow sky and also during rainy

season the backup will vary hence this should be kept on mind that

being solar system the illumination of lamp period/duration may

vary.

13. The lamp should not flicker continuously and should be intimated

to the supplier to replace immediately at company charges.

Don’ts

1. Do not cover the collectors.

2. Do not erect any structure which can cast shadow on the

collectors.

3. Do not draw electricity more than required.

4. Do not connect more than one luminary per system per panel

supplied in series.

5. Do not keep the battery and the SPV panel near dirty place and

hot area.

Page 55: design a roof top based solar power station

55

6. Do not flaunt norms laid by the manufactures you will never

benefit its advantage.

7. Do not have dense foliage around the panels which can cast

shadow over it in the entire day, kindly prune the tree regularly.

8. Do not allow any person or agency/person other than the company

or company authorized service personal to inspect or service the

system as this may cease the warranty/guarantee of the system

immediately.

9 .For replacement of unserviceable parts contact authorized company

service centre.

Page 56: design a roof top based solar power station

56

CHAPTER 10

CONCLUSION

Modern societies require increasing amounts of energy for domestics,

Industrial, Commercial, Agricultural and transport uses .Because of High

Cost of conventional Energy used, we need to switch over to systematic

Approach for development of Non-Conventional Energy resources,

preferably

Solar energy.

Total area available in the institute for the installation of solar

power plant is equal to 3243.43 m2.

We can generate 325 Kw power from the available area.

The peak demand of the institute is 100 Kw hourly in September

2015 according to NPCL bill of our institute.

The minimum peak demand of the institute is 44.54 Kw hourly in

March 2016.

So we are able to fulfilment the demand of power of the institute by

the installation of 325 Kw solar power station.

If we require more power demand in future then available roof top

area should be increase by including the roof top areas of Girl’s

hostel, Boy’s hostel and Workshop block.

Page 57: design a roof top based solar power station

57

CHAPTER 11

REFERANCE’S

We have assimilated the data, concepts and information required during

the course of the project from various books, websites and research

papers apart from going to our mentor Dr. B.L. Kaul whenever the need

arose.

Our sources include:

www.solarpanelslus.com

www.powerflimsolar.com

www.xantrex.com

www.solarking.com

www.wikkipeadia.com

www.phocos.com