Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.
-
Upload
brooke-banks -
Category
Documents
-
view
212 -
download
0
Transcript of Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.
![Page 1: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/1.jpg)
Dep
artm
en
t of P
ub
lic Works
Winter 2009-2010Great Highway Emergency Case Study
![Page 2: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/2.jpg)
Assessment of El Nino Type Storm
Winter 2010 Events
~ 7-ft tides~ 22-ft swells
![Page 3: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/3.jpg)
footer
Strom Damage Impact to Pubic Access
Identified 3 impact areas
North Sloat Parking Lot Exit
South Sloat Parking Lot Exit
Great Highway southbound travel lanes that provides public access and has over 9000 vehicle trips per day.
![Page 4: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/4.jpg)
Timeline of Events
footer
December 2009 DPW closes lane of Great Highway due to storm damage to bluff, road and parking lots
and engages GGNRA/NPS
January 2010 After more bluff is lost, DPW closes southbound lanes of GH at Sloat and engages
engineering firms to prepare emergency repair options Governor, Mayor, Director of Public Works declare storm-related emergencies.
February 2010 Field reviews with all necessary federal and state agencies and permits attained Emergency Repair selected to stabilize toe and repairs begin City and Caltrans evaluate roadway City requests state funding for emergency repairs to reopen road and long term funding
for permanent repairs.
March 2010 DPW selects firm to design Emergency Roadway Opening project DPW meets with Caltrans and FHA to review site/assess federal involvement
Timeline
![Page 5: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/5.jpg)
footer
Evaluation of Emergency Response
Agency Immediate Long Term
Staffing Operations
Technical Support Initial for immediate assessment Design
Equipment Assess equipment needs that can fit into normal operations .
Duration 3-5 days Up to 6 months
Documentation From day one all labor and materials should be identified in a cost center for potential reimbursement
Reporting Local, regional and state agencies
Permit requirements
Funding Federal Highway Administration Emergency Relief fundingCalifornia Emergency Management Agency funding
Federal Highway Administration Emergency Relief fundingCalifornia Emergency Management Agency funding
![Page 6: Department of Public Works Winter 2009-2010 Great Highway Emergency Case Study.](https://reader036.fdocuments.us/reader036/viewer/2022083004/56649f005503460f94c1607a/html5/thumbnails/6.jpg)
footer
Reports, Data Gathering , and Design Developed technical report on storm damage assessment
Permitting and Regulatory Approvals California Coastal Commission Department of Fish and Game Army Corps of Engineers National Park Service monitoring and alternatives report Needed to prepare post construction technical report for each of the
regulatory agencies
Regulatory Obligations