Delhi Metro A Project Management Bench Mark

26
Delhi Metro A Project Management Bench Mark Presentation By Kumar Keshav Director (Project &Planning), DMRC 23 rd June, 2011

description

Delhi Metro A Project Management Bench Mark. Presentation By Kumar Keshav Director (Project &Planning), DMRC 23 rd June , 2011. Delhi Metro Rail Corporation (DMRC). Set up in May’95 under the Indian Companies Act. - PowerPoint PPT Presentation

Transcript of Delhi Metro A Project Management Bench Mark

Page 1: Delhi Metro A Project Management Bench Mark

Delhi Metro A Project Management Bench Mark

Presentation By

Kumar KeshavDirector (Project &Planning), DMRC

23rd June, 2011

Page 2: Delhi Metro A Project Management Bench Mark

Delhi Metro Rail Corporation (DMRC)

• Set up in May’95 under the Indian Companies Act.

• A joint venture between the Federal Government of India and the Provincial Government of Delhi State, with equal equity.

• DMRC has the responsibility for construction and operation of Delhi Metro.

2

Page 3: Delhi Metro A Project Management Bench Mark

Delhi Metro Rail Corporation (DMRC)

• A Master Plan had been drawn up for Delhi Metro expansion, consisting of 12 lines, covering 420 kms. to be completed by 2021 in four Phases.

• Works started on Phase I on 1st October, 1998 and completed in December, 2005.

• Phase-I – 65 kms. Cost US $ 2.5 billion. Completed in 7 years and 3 months (2 years & 9 months ahead of schedule)

3

Page 4: Delhi Metro A Project Management Bench Mark

• Phase-II covers 124 kms. This also includes a high speed Metro connection from centre of the city to the new airport in 18 minutes.

Phase-II works commenced in January 2006 and completed in October, 2010 – 5 months ahead of schedule.

• Phase-III will consist of about 104 km at a cost of US $ 8.6 billion. The first contract for Phase-III has since been awarded.

4

Delhi Metro Rail Corporation (DMRC)

Page 5: Delhi Metro A Project Management Bench Mark

Funding of the Metro

– 20% of the cost is borne by the Federal Government.

– 20% of the cost is borne by the State Government.

– About 50 – 60% of the cost through JICA Loan.

– 5% of the cost by DMRC through Property

Development.

5

Page 6: Delhi Metro A Project Management Bench Mark

• 2500 train trips with 200 train sets on 6 lines. • Each train used to consist of 4 coaches. Trains

progressively being lengthened to 6 coaches and finally to 8 coaches.

• Average daily ridership - About 16.5 lakh passengers with average lead of 14 kms.

• Frequency during peak hours – 2 m 30 sec.• System fully Barrier Free for Physically

challenged.• DMRC has introduced feeder bus short loop services

• Punctuality measured with a least count of 60 Sec. and average punctuality percentage is above 99%.

Operation Highlights

6

Page 7: Delhi Metro A Project Management Bench Mark

• Fare : From Rs. 8/- (17 cents) to Rs. 30/- (65 cents) - fare structure lowest in the world except Kolkata.

• The system making operational profit from Day-1.• Delhi Metro receives no subsidy from the two

Governments.• We are able to meet the operating and maintenance

expenditure fully.• In addition we are servicing and repaying the loans

taken from JICA.• 20% of DMRC’s revenue is from Non-operational

sources – mainly real estate development and advertisements.

Financial Success of Delhi Metro

7

Page 8: Delhi Metro A Project Management Bench Mark

Challenges in Implementation • Delhi Metro Project is the biggest urban intervention

since Independence.

• Project is to be executed in very difficult urban environment.

• Being in the capital city all actions under close scrutiny of VVIPs.

• Project approved on completion cost.

• The Project implementation period extremely compressed and strict completion targets.

• Metro being constructed to world class standards with frontline technologies.

Page 9: Delhi Metro A Project Management Bench Mark

Challenges

• The sensitivities of the city to be respected during construction – No hardship or inconvenience to the public – Calcutta Experience.

• Each day’s delay in completion of project costs DMRC Rs. 2.3 Cr (Rs. 1.4 Cr by way of escalation and Rs.90 lakh by loss of revenues).

Page 10: Delhi Metro A Project Management Bench Mark

• Large scale land acquisition in the city

• Tree cutting permission- Substantial No. of trees are transplanted.

- For every tree cut, compulsory afforestation of 10 trees is undertaken.

• Utility diversions for Telecom, Electrical, Sewerage & Water pipe lines

• Special permissions such as for Ridge (Reserve Forest) Land, from Archaeological Survey of India , National Monument Authority

Constraints in Project Implementation

Page 11: Delhi Metro A Project Management Bench Mark

How Challenges have been met

Page 12: Delhi Metro A Project Management Bench Mark

Work Culture & Organizational Values of DMRC

1. Punctuality.

2. Integrity – highest premium

3. Professional Competence.

4. Physical Fitness.

5. Quick Decision Making

6. High Discipline and loyalty to the Organization.

7. Prompt response to the needs of the Public and Contractors.

Page 13: Delhi Metro A Project Management Bench Mark

Dynamic Management Style• Corporate Mission and Corporate Culture• A slim but effective organization - No ineffective

layers such as clerks, peons• Reverse Time clocks.• Democracy in management – Weekly HOD

meetings and Monthly Dy. HOD meetings.• Discourage paper oriented work – replies to

outsiders within 10 days.• Predominant use of information systems.• High premium for integrity in the organisation

Page 14: Delhi Metro A Project Management Bench Mark

Dynamic Management Style

• Ample delegation of powers – accountability with delegation

• Redefined the role of Finance – Finance equally accountable with executive.

• Officers encouraged to take decisions on the spot.• The fear of Audit and Vigilance not allowed to cramp

the style.• Leading from the front and not pushing from the rear.

- Top Management readily available for decisions.

Management based on trust

Page 15: Delhi Metro A Project Management Bench Mark

Project Monitoring at all Stages

Page 16: Delhi Metro A Project Management Bench Mark

Tendering & Award of work• General philosophy – success of the project depends

upon success of the contractors.• Tenders from Pre-qualified list of bidders• A unique filtering criterion evolved for prequalification

covering vital items of technical & financial capabilities of the tenderers

• Objective evaluation criteria based on ‘scoring system’ • The tender conditions finalized keeping in view the JBIC

Procurement guidelines, FIDIC document and Indian Contract Act .

• Full powers for dealing with the tenders within organization

• Tenders are decided fast – so that no lobbying is possible.

Page 17: Delhi Metro A Project Management Bench Mark

Monitoring during execution• Contractors prepare detailed Base – line work

schedule for execution including duration of activities and identification of critical activities/path

• Close monitoring of work schedule, mobilization of ‘Manpower’, ‘Machinery & Plant’ and ‘Materials’

• Weakly meetings with Contractors for planning the work and solving their problems.

• Practical approach to solve the genuine problems of contractors.

• Failing contractors are enabled to perform by timely assistance.

• Streamlined prompt payment procedure and quick decision-making.

Page 18: Delhi Metro A Project Management Bench Mark

Monitoring during execution

• Stringent penalties for failures to deliver.• Prompt resolution of claims.• Round the clock supervision guaranteed

• Strict independent quality & safety audit.

• Monthly progress presentations by the contractors

• DMRC directly handles works pertaining to other Government and Civic Departments to speed up.

Have been able to establish that we are different than the normal executing agencies and mean business.

Page 19: Delhi Metro A Project Management Bench Mark

Interface Management

• Interface Management - “Access dates” and “Key dates” listed in contract document itself.

•The important items which require interface with other contractors are clearly identified and indicated in contracts.

•Other contractors with whom the contractor has to interface are also clearly defined.

Page 20: Delhi Metro A Project Management Bench Mark

Monitoring during Testing & Commissioning

• Each activity of testing identified and duration of all these activities pre-determined

• Trials conducted as per schedule pre-determined jointly by System Contracts

• Service trial schedules also laid out in advance

• Sufficient time provided before actual commissioning

Page 21: Delhi Metro A Project Management Bench Mark

Training and motivation of employees

– A rigid screening process for inducting staff and officers.

– Training and exposure in the appropriate areas. – Management objectives and philosophy clearly

shared with executives and staff.– Chief Executive and Top Managers themselves set

an examples.– Immediate appreciation and reward for good work

done but no castigation for failures. – No witch hunting for genuine mistakes.Officers encouraged to take quick decisions . Tendency to

push decisions to higher levels curbed.

Page 22: Delhi Metro A Project Management Bench Mark

Public relations initiative– Works planned and managed with the least

inconvenience to the public. – Press regularly briefed on the progress and

programmes.– Community interaction at difficult work sites.– Proper barricading and good house keeping.– Proper signages, security men to guide traffic.– Special measures taken to protect the environment.

• Control on noise levels and vibrations during work.

• Washing tyres of vehicles. Performance is our best publicity. Have

been able to establish credibility with the public by delivery on time.

Page 23: Delhi Metro A Project Management Bench Mark

Benefits of Delhi Metro

• A study by CRRI has brought out benefits of Delhi Metro Phase-I and worked out EIRR = 19.96%.

Thus the entire cost of Phase-I recovered by the city of Delhi in 5yrs by 2010.

Page 24: Delhi Metro A Project Management Bench Mark

DMRC: An organisation with a difference…..

Page 25: Delhi Metro A Project Management Bench Mark

Thanks

DMRC Ltd.Metro Bhawan,Fire Brigade Lane,Barakhamba Road, New Delhi - 110 001.

Page 26: Delhi Metro A Project Management Bench Mark

R K ASHRAM

JHANDEWALA

KAROL BAGH

RAJE

NDRA

PL

PATE

L NAG

AR

SHAD

IPU

R

KIRT

I NAG

AR

MO

TI N

AGAR

RAM

ESH

NAG

AR

RAJO

URI

GAR

DEN

TAG

ORE

GAR

DEN

DW

ARKA

MO

R

NAW

ADA

UTT

AM N

AGAR

WES

T

UTT

AM N

AGAR

EAS

TJA

NAK

PURI

WES

TJA

NAK

PURI

EAS

TTI

LAK

NAG

AR

SUBH

AS N

AGAR

DWARKA

DWARKA SEC-14

DWARKA SEC-13

DWARKA SEC-12

DWARKA SEC-11

DWARKA SEC-10

DWARKA SEC-9

INDRAPRASTHA

B K RD

MANDI HOUSE

PRAG MN

SHAH

DAR

A

WELCOME

SEEL

AMPU

R

SHAS

TRI P

ARK

KASHMERE GATE

TIS

HAZA

RI

PULB

ANG

ASH

PRAT

AP N

AGAR

SHAS

TRI N

AGAR

INDER

LOKKANHAIYA NGR

KESHAV PRMN S

PLA

CE

KOHA

T ENC

LAVE

PITA

MPU

RA

ROHI

NI EA

ST

ROHI

NI W

EST

RITH

ALA

CHANDNI CHOWKCHAWRI BAZAR

RAJIV CHOWKPATEL CHOWK

Central SECTT

CIVIL LINESVIDHAN SABHAVISWAVIDYALAYA

NDLS

LAXM

I NAG

AR

YAM

UN

A BA

NK

NIR

MAN

VIH

AR

PREE

T VI

HAR

KARK

AR D

UM

A

ANAND VIHAR ISBT

KAUSHAMBI

VAISHALI

HAUZ KHAS

UDYOG BHAWAN

RACE COURSE

JOR BAGH

AIIMS

GREEN PARK

MALVIYA NAGAR

SAKET

QUTAB MINAR

CHHATARPUR

SULTANPUR

GHITORNI

ARJAN GARH

INA

HUDA CITY CENTRE

IFFCO CHOWK

GU

RU D

RON

ACHA

RYA

SIKA

NDA

RPU

R

M G

RO

AD

AKSHARDHAM

MAYUR VIHAR I

MAYU

R VIHAR EX

T.

NEW ASHOK NGR

NOIDA SECTOR 15

NOIDA SECTOR 18

BOTANICAL GARDEN

GOLF COURSE

NOIDA CITY CENTRENOIDA SECTOR 16

KHAN MARKET

JLN STADIUM

JANGPURA

LAJPAT NAGAR

MOOLCHAND

KAILASH COLONY

NEHRU PLACE

KALKAJI MANDIR

GOVIND PURI

OKHLA

SARITA

VIHAR

MOHAN ESTATE

TUGHLAKABAD

BADARPUR

JASOLA

MAN

SARO

VAR

PARK

JHIL

MIL

DIL

SHAD

GAR

DENGTB NAGAR

MODEL TOWN

AZADPUR

ADAR

SH N

AGAR

JAHANGIR

PURI

SHIVAJI STADIUM

DHAULA KUAN

DELHI AEROCITY

AIRPO

RT

DWARKA SEC 8

DWARKA SEC 21

PUNJABI BAGH

SRS MARG

ASHOKPARKSH

IVAJ

I PAR

K

MAD

IPUR

PASC

HIM

VIH

AR E

PASC

HIM

VIH

AR W

PEER

AGAR

HI

UDYO

G NA

GAR

SURA

JMAL

STAD

IUM

NANG

LOI

NANG

LOI R

LY. S

TN

RAJD

HANI

PAR

K

MUN

DKA

ASH

RAM

MAYUR VIHAR ph-1TRILOKPURI

VINOD NAGAR

IP EXTN N

SRIN

IVAS

PURI

DHAULA KUAN

JAGATPURI

ARJUN NAGAR

BHOLANATH NAGAR

MAUJPUR

YAMUNA VIHAR

JAFFRABAD

DELHI C

ANTT

NARAINA 1

NARAINA 2

MAYAPURI`

`

ESI HOSPITAL

SHAKURPUR

SHALIMAR BAGH S

MUKUNDPUR

MOTI

BAGHBHIKA

JI KAM

A

PLACE

SARO

JINI N

AGAR

SOUT

H

EXTN

HAZARAT NIZAMUDDIN

AMITY NOIDA

KALINDI KUNJ

JASO

LA V

IHAR

JOKH

ALA

VIHA

R

JAM

IA

NAGA

R

ISHW

AR N

AGAR

JOKH

ALA

PH-II

I

NEH

RU P

LACE

G. K

. EN

CLAV

E

CHIR

AG D

ELH

I

PAN

CHSH

EEL

PARKI.I.T

.

R. K.

PURA

M

VASA

NT V

IHAR

MUNIR

KA

I.G.D

. AI

RPOR

TPALAM

DHSRATH PURI

DABRI MOR

JANAKPURI C-2B

JANAKPURI WEST

BOTANICAL GARDEN

ROHINI S

EC. 1

8SH

ALIMAR P

LACE

BADLI

JAHANGIR

PURI

ITO

JANAPATH

DELHI GATE

JAMA MASJID

LAL QUILA

KASHMERE GATE

Central SECTT