Death Spiral of a Building Case Study of the Natural History ......Death Spiral of a Building Case...
Transcript of Death Spiral of a Building Case Study of the Natural History ......Death Spiral of a Building Case...
-
Death Spiral of a BuildingCase Study of the Natural History Museum Bldg.
Sarah Boll - DFCM UtahSanjiv “Sunny” Devnani, P.E. - kW Engineering
-
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
2
-
Learning Objectives
Commissioning or Retro-Commissioning
3
1. Whole Building Approach2. Systems are interactive and interdependent3. Scope must be all encompassing4. Problem solving at the Fundamental Level
http://www.aia.org/education/
-
NHMU
4
-
NHMU Layout
5
-
Simplified Layout
Can
yon
South
North
-
Building Pressurization Basics
Can
yon
South
North
150 CFM100 CFM
25 CFM25 CFM
-
8
UnitOA
(CFM)RA
(CFM)SA
(CFM)Exhaust (CFM)
Pressure (CFM)
Air Handling Unit 1 100 1,000 1,100 - 100 Air Handling Unit 2 50 500 550 - 50 Subtotal 150
Exhaust Exhaust 1 100 (100) Subtotal (100)
Total 150 1,500 1,650 100 50
Air Balance Chart - OUTPUT
-
• Complex Design• 3X Energy usage and spend • Maintenance:
• Routine occupant complaints• Filters changed every 3 weeks ($1,700/week)
• Collection Rooms Humidity & Temp Control • >10% deviation• Tracking with ambient
Issues Plaguing Building Operation
9
-
-0.07 in. wc
-
Simultaneous Dehumidification and Humidification
12
0
20
40
60
80
100
Perc
ent O
n [%
]
Dehumidification
0102030405060708090
100
Perc
ent O
n [%
]
Humidification
-
NHMU Air Balance
13
Unit
Outside Air/ Fresh Air
(CFM)
Return Air
(CFM)Supply Air (AHU CFM)
Exhaust (CFM)
Pressure (CFM)
AHU-1 - - 16,000 - (16,000) AHU-2 15,000 18,667 3,000 - 30,667 AHU-3 In Override 40,000 8,000 40,000 35,000 (27,000) AHU-4 20,000 20,000 4,000 - 36,000 AHU-5 875 17,500 3,500 - 14,875 AHU-6 10,000 - 2,000 - 8,000 Subtotal 85,875 64,167 68,500 35,000 46,542
Exhaust Toilets 0 - Kitchen 36990 (36,990) Paint Booth 18000 (18,000) Subtotal 54990 (54,990)
Total Pressurization 85,875 64,167 68,500 89,990 (8,448)
Air Balance Chart - OUTPUT
Current Conditions & Test Case
Current ConditionsCheck Values
AHUSupply Fan SizeReturn Fan SizeRelief Fan SizeSupply Fan VFD Return Fan VFDRelief Fan VFDRelief DamperSupply Fan VFD Return Fan VFDRelief Fan VFDOA DamperOA CFMSupply Air FlowReturn Air FlowExhaust Air FlowOA LimitDDH
IDCFMCFMCFMHzHzHz%%%%%CFMCFMCFMCFMCFM
AHU-180,000- 060,00053.0- 025.250%88%0%42%0%- 070,666.67- 012,600030,000
AHU-215,00020,000- 0- 050.4- 00%0%84%0%0%- 0- 016,800- 0150000
AHU-340,0008,00035,00048.0- 0- 00%80%0%0%10%4,00032,000.00- 0- 0400000
TravelAHU-420,00020,000- 054.030.0- 00%90%50%0%5%1,00018,000.0010,000- 0200007,500
collAHU-517,50017,500- 060.048.0- 00%100%80%0%7%1,22517,500.0014,000- 09002,180
AHU-610,000- 0- 048.0- 0- 00%80%0%
Sanjiv Devnani: Sanjiv Devnani:This is a dummy value. There is no Return Fan. The supply air is just dumped into the space and becomes part of the overall RA in the bldg.0%100%10,0008,000.00- 0- 0100000
Day?Yes
BoothNo- 0
Toilets/HoodYes36,990
16,225146,16740,80049,59085,90039,680
OA + RASF + EX
57,025195,757
CFM(138,732)-243%
FPM100
Opening Area(1,387.32)ft2
Any Condition - Test Case - Select OA Damper Position between above settings for Day/NightCheck Values
AHUSupply Fan SizeReturn Fan SizeRelief Fan SizeSupply Fan VFD Return Fan VFDRelief Fan VFDRelief DamperSupply Fan VFD Return Fan VFDRelief Fan VFDOA DamperOA CFMSupply Air FlowReturn Air FlowExhaust Air FlowVFD OffsetOA LimitDDHModeling Notes
IDCFMCFMCFMHzHzHz%%%%%CFMCFMCFMCFMCFM(Limits for Modulation are described below)
AHU-180,000- 060,00012.0- 0- 050%20%0%0%0%- 016,000- 0- 00030,000OA= 0% as it is fed by AHU-2. SF VFD min of 20% speed with Delta of 18 hz or 30% with RF. RF can max out at 100%.
AHU-215,00020,000- 012.056.0- 00%20%93%0%100%15,0003,00018,667- 044150000Day: Max OA% = 75%, Min = 50%. During Night = 5%. SF min/max = 16 hz/60 hz. RF min = 12 hz, RF max (SF Hz-Offset hz))
AHU-3 In Override40,0008,00035,00012.060.0- 00%100%100%100%100%40,00040,000.008,00035,000.0048400000Day: Max OA% = 55% when Pt Booth is off. 100% when Booth on. During Night = 5%. SF min/max = 12 hz/60 hz. RF min (SF Hz+Offset hz),RF Max = 60 hz)
TravelAHU-420,00020,000- 012.060.0- 00%20%100%0%100%20,0004,00020,000- 048200007,500Day: Max OA% = 75%, Min = 50%. During Night = 5%. SF min/max = 12 hz/60 hz. RF min = 12 hz, RF max (SF Hz-Offset hz))
collAHU-517,50017,500- 012.060.0- 00%20%100%0%5%8753,50017,500- 0489002,180OA=5% fixed. SF min/max = 12 hz/60 hz. RF min = 12 hz, RF max (SF Hz-Offset hz))
AHU-610,000- 0- 012.0- 0- 00%20%0%
Sanjiv Devnani: Sanjiv Devnani:This is a dummy value. There is no Return Fan. The supply air is just dumped into the space and becomes part of the overall RA in the bldg.0%100%10,0002,000- 0- 00100000OA=0-100%. SF min/max = 12 hz/60 hz. No Return Fan Present)
Day?YesSelect Yes or No
BoothYes18,000Select Yes or No
Toilets/HoodYes36,990Select Yes or No
85,87568,50064,16789,99085,90039,680
OA + RASF + EX
150,042158,490- 0
CFM(8,448)-6%
FPM100
Opening Area(84.48)ft2
Air Balance Output
Consultant Name
Project Name
Project Location (City)
Air Balance Chart - OUTPUT
UnitOutside Air/ Fresh Air (CFM)Return Air (CFM)Supply Air (AHU CFM)Exhaust (CFM)Pressure (CFM)
AHU-1- 0- 016,000- 0(16,000)
AHU-215,00018,6673,000- 030,667
AHU-3 In Override40,0008,00040,00035,000(27,000)
AHU-420,00020,0004,000- 036,000
AHU-587517,5003,500- 014,875
AHU-610,000- 02,000- 08,000
Subtotal85,87564,16768,50035,00046,542
Exhaust
Toilets0- 0
Kitchen36990(36,990)
Paint Booth18000(18,000)
Subtotal54990(54,990)
Total Pressurization85,87564,16768,50089,990(8,448)
% Pressurization-6%
Schedule
AHU SUMMARY
Flow (cfm)Flow (cfm)
AHU-1100,000OSA Range0-15,000
AHU-215,000OSA Range-
AHU-340,000OSA Range0-40,000
AHU-420,000OSA Range300-20,000
AHU-517,500Min. OSA900
AHU-610,000Min. OSA0RELIEF FANS (RF)
Flow (cfm)(hp)(bhp)VFD #
SUPPLY FANS (SF)AHU 1 & 2
Flow (cfm)(hp)VFD #RF-260,0003025.515
AHU 1RF-520,00054.5428
SF-1a25,0003010AHU 3
SF-1b25,0003011RF-3a17,50032.9918Exhaust CFM
SF-1c25,0003012RF-3b17,50032.99192200
SF-1d25,0003013RF-68,00021.53302500
AHU 2AHU 45170
SF-215,0001514RF-120,00054.05225170
AHU 3AHU 53500
SF-3a20,0002516RF-417,50054.07251000
SF-3b20,00025173000
AHU 4DESICCANT DEHUMIDFIER (DDH)Booth18000
SF-4a10,00010Proces Flow (cfm)kW600
SF-4b10,00010AHU 1900
AHU 5DDH-130,00059.051700
SF-5a8,7507.5AHU 4950
SF-5b8,7507.5DDH-27,50013.45100
AHU 6AHU 5125
SF-610,0007.5DDH-34901900
AHU 7DDH-4490100
SF-78,5001DDH-51,200100
625
1850
AHU #ScheduleDayLocationZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 72900
124/7M-S3rd flr SLife SouthFirst PeopleLife NorthThe LandPast WorldsLakeNative Voices600
2n/aM-S3rd flr S1700
324/7M-S3rd flr NRM 4142RM 4159RM 4102RM 4112300
424/7M-S3rd flr N2 Exhibits?Total 54990
524/7M-S6th flrRM 4100RM 3103RM 4109Total w/o Booth36990
66 am - 6 pmM-S1st flrSnowmelt/??
724/7M-S2nd flr??Display Case
AHU #HTG SPCLG SP
16870
2
3
470
56666
680-88
77272
Sheet1
NameAgreementRate ScheduleService NoService DescService Address Line 1Service Address Line 2Rvn YearmonthReading DtReading CycleElapsed DaysKwOffkwOnkwKwhOffkwhOnkwhShkwhDSM ChargeTotal Invoice
UNIVERSITY OF UTAH1848199607500208NMT06135674211593004NEW MUSEUM NMS SOLAR 333 KW301 S WAKARA WAYSALT LAKE CITY UT 841082013011/22/131533559 287700 514.0419728.73
2013022/20/131529488 238500 436.1716749.86PeriodReading DateDaykWhkWMonthly Cost$/kWhkWh/day% Diff (16 vs 15)
2013033/21/131529481 202500 364.6915257.13Pre/Baseline1/22/1333287,700559$ 19,729$ 0.06868,718
2013044/19/131529518 235500 394.617081.331/22/1433301,500532$ 20,508$ 0.06809,136
2013055/20/131531469 220500 401.0817361.281/22/1531294,000514$ 20,248$ 0.06899,484
2013066/19/131530477 211800 417.1418053.64Trial1/22/1631238,800434$ 16,859$ 0.07067,70381%
2013077/19/131530536 243300 473.9220502.22
2013088/20/131532571 264600 510.0422059.723%
2013099/19/131530571 267600 546.2222548.77
20131010/18/131529515 231300 548.3318476.48
20131111/19/131532507 269700 558.7918827.73
20131212/20/131531524 290400 591.9919942.39
2014011/22/141533532 301500 608.8320507.96
2014022/20/141529518 262500 556.4318748.52
2014033/21/141529557 264300 577.2919448.79
2014044/21/141531580 292200 621.0220917.05
2014055/20/141529580 277200 669.6622550.14
2014066/19/141530568 266100 679.9522895.62
2014077/21/141532530 297300 697.923498.29
2014088/20/141530564 247200 654.4722040.31
2014099/19/141530502 261900 638.2621496.07
20141010/20/141531507 278400 606.4120426.65
20141111/19/141530497 267000 559.1918841.2
20141212/22/141533531 297900 614.0720683.85
2015011/22/151531514 294000 601.1220247.923134400241563
2015022/20/151529511 249600 595.4318476.910.30.0770683384
2015033/23/151531499 265500 632.0218939.62940320$ 72,468.90
2015044/21/151529515 251700 622.3318650.27
2015055/20/151529526 269700 723.3721667.91
2015066/19/151530520 270000 752.0822525.07
2015077/21/151532543 282300 786.1923543.79
2015088/20/151530513 260700 73421985.31
2015099/21/151532485 250800 704.4821103.55
20151010/20/151529492 241800 631.8418934.44
20151111/19/151530491 245700 603.6118091.34
20151212/22/151533436 252600 580.3717397.15
2016011/22/161531434 238800 603.0416859.29
-
OA Dampers Closed
-
VAV w/RH
78°F 68°F72°F
OAT/RH = 60°F
SAT = 55°F
RH Valve Open
>90°F
-
• Thermostat senses that space is cold• Reheat valve opens• Boiler comes on, HHW pumps comes on. • Dehumidification system comes on• The occupants in the space are uncomfortable• Adjust thermostat to lower setting• Supply air to the VAV box• Chiller plant is turned on (CT/Pumps etc)• Reheat valve & VAV box damper opens more as the SAT is now
colder • Duct pressure reduces. • VFD on AHU ramps• Simultaneous heating and cooling
Death Spiral of a Building
-
Change in Building Pressure – Immediate Results
-
VAV w/RH
72°F 72°F72°F
SAT = 60°F
RH Valve Closed/Modulating OAT/RH = 60°F
-
AHU Fan Speed
-
Annual Electric Costs
20
$-
$5,000
$10,000
$15,000
$20,000
$25,000
$/M
onth
Natural History Museum of Utah
2015-162016-17
-
• HVAC operations can be counter-intuitive• A single VAV Box can impact Whole Building• Complex problems can be broken down to basics• Stress test the interactive effects of systems• If it doesn’t work on paper it will not work in reality. • HVAC Lighting nexus is only going to complicate operations further
Key Points
21
-
Sanjiv “Sunny” [email protected]
Sarah [email protected]
mailto:[email protected]:[email protected]
Death Spiral of a Building�Case Study of the Natural History Museum Bldg. Slide Number 2Slide Number 3NHMUNHMU LayoutSimplified LayoutBuilding Pressurization BasicsSlide Number 8Issues Plaguing Building OperationSlide Number 10Slide Number 11Simultaneous Dehumidification and HumidificationNHMU Air BalanceOA Dampers ClosedSlide Number 15Death Spiral of a BuildingChange in Building Pressure – Immediate ResultsSlide Number 18AHU Fan SpeedAnnual Electric CostsKey PointsSanjiv “Sunny” Devnani�[email protected]�801.599.2388��Sarah Boll�[email protected]�801.538.3017