Data Rates-P & M Works-4

download Data Rates-P & M Works-4

of 21

Transcript of Data Rates-P & M Works-4

  • 8/13/2019 Data Rates-P & M Works-4

    1/21

    DATA RATES- P AND M WORKS

    In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.54 cum

    Number of buckets per load ( 4.54 / 0.53 ) say : 8 buckets

    Cycle time for loading 8 buckets ( 8 x 20 / 60 ) say : 2.70 min

    Round trip cycle time for tipper:

    Ideal cycle time of shovel for digging and loading : 2.70 min

    Time for 1km haulage under load ( 60 / 15 ) : 4.00 min

    Time for turning and un-loading : 2.00 min

    Time for 1 km return trip ( 60 / 20 ) : 3.00 min

    Time for turning and spotting : 0.50 min

    Total : 12.20 min

    As the movement of tippers will be slow in breached portion due limited area 1 minute extra time

    may be considered for the round trip cycle time of tippers.

    Corrected round trip cycle time for tipper ( 12.20 + 1.00 ) : 13.20 min

    No.of tippers to match corrected cycle time of tipper ( 13.20 / 2.70 ) say : 5 Nos

    Output of tipper / hr with 50 min working / hr ( 50 x 4.54 / 13.2 ) : 17.20 cum

    Output for 5 tippers per day ( 5 x 17.20 x 8 ) say : 688 cumThe in-situ dry density of soil in borrow area will be generally less than dry density of compacted

    embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

    area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

    of embankment. For 95 % density control of embankment in breached portion a shrinkage factor

    of 5 % may be assumed for use of borrow area soil.

    Further, as the insitu density of soil in dump area will be less compared to natural ground due

    to bulkage of soil during excavation for applying the shrinkage foctor it is necessary to convert

    the insitu dump area quantity to equivalent borrow area quantity by applying bulkage factor.

    Equivalent borrow area quantity for 10% bulkage ( 688 / 1.1 ) : 625 cum

    Qty of compacted embankment for 5 % shrinkage ( 625 x 0.95 ) : 594 cum

    Qty of soil for computing royalty charges @ 1.6 t /cum ( 594 x 1.6 ) : 950 tonnes

    1. Stripping of borrow area :

    Since soil is from dump area no stripping is involved.

    However, use of dozer is necessary for forming rampways and for trimming the old embankment

    on either side of breached portion to required slope for abutting the fresh embankment layers.

    Assume use of dozer for 0.5 hour daily for this purpose.

    Deploy dozer for forming ramps / slopes for 1 day work : 0.5 hour

    2. Collection of soil for embankment:

    Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.

    Deploy 5 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

    3. Spreading soil in 250 to 300 mm layer:

    Quantity of loose soil to be spread ( 688 / 1.10 ) : 757 cum

    Output of dozer for levelling per hour : 200 cum

    Time required for levelling 757 cum say : 4.00 hours

    4. Watering;

    Generally soil in the dump area will be in moist condition. In the beginning of the season nowatering may be necessary. However, in summer months as the loose soil looses moisture at

    faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain

    the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5

    to 6 percent watering by weight, requirement of water for 594 cum of embankment will be about

    7 tanker loads of 8000 ltrs each.

    Deploy 8000 ltr capacity water tanker for 7 hours for watering before rolling.

    Deploy 5 hp pump for 3.5 hours.

    60

  • 8/13/2019 Data Rates-P & M Works-4

    2/21

    DATA RATES- P AND M WORKS

    5. Compaction:

    Soil collected for embankment layer gets compacted to some extent during levelling by dozer.

    Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

    control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining

    adjacent to breached portion a combination of 8 to 10 passes of road roller followed by 2 to 4

    passes of dozer is considered for compaction and roughening top surface for laying next layer.

    Effective length of roller drum : 1.50 m

    Speed of roller per hour : 3.0 km

    Thickness of layer : 0.3 m

    Number of roller passes : 9 Nos

    Output of road roller / hr with 50 min / hr working and 70 % effinciancy:

    ( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 say : 88 cum

    Time for rolling 757 cum soil in embankment layer say : 8.5 hours

    Effective width of dozer track : 1.00 m

    Speed of dozer per hour : 4.0 km

    Thickness of layer : 0.3 m

    Number of dozer passes : 3 NosOutput of dozer / hr with 50 min / hr working and 70 % effinciancy:

    ( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 say : 230 cum

    Time for compacting 757 cum soil in embankment layer say : 3.50 hours

    Deploy road roller for 8.5 hours and dozer for 3.5 hours for compaction.

    6. Sorting out / sectioning / labour for testing etc :

    Assume 2 heavy and 2 light mazdoors.

    RATE ANALYSIS UNIT : 594.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Add Royalty charges on 950 t soil @ Rs: 10.00 / tonne Rs: 9500.00

    Total cost of Materials : Rs: 9500.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Angle dozer Hour 8.00 1154.00 9232.00

    Fuel / Energy charges Hour 8.00 423.00 3384.00

    2 Shovel 0.50 cum capacity Hour 8.00 725.00 5800.00Fuel / Energy charges Hour 8.00 330.00 2640.00

    3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 271.00 10840.00

    Fuel / Energy charges Hour 40.00 208.00 8320.00

    4 Pump 5 hp ( diesel ) Hour 3.50 7.00 24.50

    Fuel / Energy charges Hour 3.50 55.00 192.50

    Contd

    Description Quantity Rate

    Quantity Rate

    in Rs.

    Perticulars

    in Rs.

    61

  • 8/13/2019 Data Rates-P & M Works-4

    3/21

    DATA RATES- P AND M WORKS

    B. MACHINERY ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    5 Water tanker 8000 ltr Hour 7.00 268.00 1876.00

    Fuel / Energy charges Hour 7.00 208.00 1456.00

    6 Road roller 10 tonne ( diesel ) Hour 8.50 228.00 1938.00

    Fuel / Energy charges Hour 8.50 495.00 4207.50

    7 Sundries LS 2.00 30.00 60.00

    Total Rs: 49970.50

    Add for small Tools and Plants @ 1% Rs: 499.71

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 2026.00

    Add for Contractor's Overheads @ 5% Rs: 2498.53

    Total hire charges of Machinery : Rs: 54994.73

    C. LABOUR:

    Sl No Unit Amount

    in Rs.1 Crew for Dozer Hour 8.00 77.50 620.00

    2 Crew for Shovel Hour 8.00 77.50 620.00

    3 Crew for Tipper Hour 40.00 56.70 2268.00

    4 Crew for Pump Hour 3.50 35.80 125.30

    5 Crew for Water tanker Hour 7.00 56.70 396.90

    6 Crew for Roller Hour 8.50 72.00 612.00

    7 Maistry Day 2.00 141.50 283.00

    8 Heavy mazdoor Day 2.00 132.00 264.00

    9 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 5450.20

    Add for small Tools and Plants @ 1% Rs: 54.50

    Add for Contractor's Profit @ 10% Rs: 545.02

    Add for hidden cost on Labour @ 15% Rs: 817.53

    Add for Contractor's Overheads @ 5% Rs: 272.51

    Total cost of Labour : Rs: 7139.76

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 9500.00

    B. Hire charges of Machinery Rs: 54994.73

    C. Cost of Labour Rs: 7139.76

    TOTAL Rs: 71634.49

    Add for enabling works @ 1.00% Rs: 716.34

    Total cost for 594.00 cum Rs: 72350.84

    Rate per cum Rs: 122.00

    Rate approved per cum Rs: 122.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 25

    ITEM: Providingpervious / semi-pervious casing for breached /damaged portion of embankment

    with soil from approved dump areas in layers of 250 to 300 mm before compaction

    including cost of all materials, machinery, labour, all operations such as collection of soil,

    sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering,

    Description

    Description

    Quantity Rate

    in Rs.

    in Rs.

    Quantity Rate

    62

  • 8/13/2019 Data Rates-P & M Works-4

    4/21

    DATA RATES- P AND M WORKS

    compacting each layer to density control of not less than 95 percent or as stipulated by using

    combination of road roller and dozer etc., complete with initial lead upto 1 km and all lifts.

    DATA:Capacity of shovel bucket : 0.50 cum

    Capacity of shovel bucket under heaped condition : 0.58 cum

    Insitu quantity of soil per bucket considering 10 % bulkage : 0.53 cum

    Capacity of tipper : 5.00 cum

    Lead for conveyance of soil : Upto 1 km

    Speed for loaded tipper under haul road condition : 15 km / hr

    Speed for empty tipper under haul road condition : 20 km / hr

    Turning and unloading time : 2.00 min

    Same digging and loading cycle as considered for borrow area may be assumed for use of soil

    from spoil bank formed during construction of canal in view of partial settlement of soil.

    Shovel digging and loading cycle per bucket : 25 sec

    In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.54 cum

    Number of buckets per load ( 4.54 / 0.53 ) say : 8 buckets

    Cycle time for loading 8 buckets ( 8 x 25 / 60 ) say : 3.50 min

    Round trip cycle time for tipper:

    Ideal cycle time of shovel for digging and loading : 3.50 minTime for 1km haulage under load ( 60 / 15 ) : 4.00 min

    Time for turning and un-loading : 2.00 min

    Time for 1 km return trip ( 60 / 20 ) : 3.00 min

    Time for turning and spotting : 0.50 min

    Total : 13.00 min

    As the movement of tippers will be slow in breached portion due limited area 1 minute extra time

    may be considered for the round trip cycle time of tippers.

    Corrected round trip cycle time for tipper ( 13.00 + 1.00 ) : 14.00 min

    No.of tippers to match corrected cycle time of tipper (14.00 / 3.5.00) : 4 Nos

    Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 14.00 ) : 14.30 cum

    Output for 3 tippers per day ( 4 x 14.30 x 8 ) say : 458 cum

    The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

    embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

    area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

    of embankment. For 95 % density control of embankment in breached portion a shrinkage factor

    of 5 % may be assumed.

    Quantity of embankment considering 5 %shrinkage ( 458 x 0.95 ) say : 435 cum

    Qty of soil for computing royalty charges @ 1.6 t /cum ( 435 x 1.6 ) : 696 tonnes

    1. Stripping of borrow area :

    Since the soil is from dump area no stripping is involved.

    Further, use of dozer is necessary for forming rampways and for trimming the old embankment

    on either side of breached portion to required slope for abutting the fresh embankment layers.

    Assume use of dozer for 0.5 hour daily for this purpose.

    Deploy dozer for forming ramps / slopes for 1 day work : 0.5 hour

    2. Collection of soil for embankment:

    Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

    3. Spreading soil in 250 to 300 mm layer:

    Quantity of loose soil to be spread ( 458 x 1.1 ) : 504 cum

    Output of dozer for levelling per hour : 200 cum

    63

  • 8/13/2019 Data Rates-P & M Works-4

    5/21

    DATA RATES- P AND M WORKS

    Time required for levelling 504 cum say : 2.50 hours

    4. Watering;

    Generally soil in the dump area will be in moist condition. In the beginning of the season no

    watering may be necessary. However, in summer months as the loose soil looses moisture at

    faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain

    the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5

    to 6 percent watering by weight, requirement of water for 435 cum of embankment will be about

    about 5 tanker loads of 8000 ltrs each.

    Deploy 8000 ltr capacity water tanker for 5 hours for watering before rolling.

    Deploy 5 hp pump for 2.5 hours.

    5. Compaction:

    Soil collected for embankment layer gets compacted to some extent during levelling by dozer.

    Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

    control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining

    adjacent to the breached portion a combination of 8 to 10 passes of road roller followed by

    2 to 4 passes of dozer is considered for compaction and roughening the top surface for laying

    next layer.

    Effective length of roller drum : 1.50 mSpeed of roller per hour : 3.0 km

    Thickness of layer : 0.3 m

    Number of roller passes : 9 Nos

    Output of road roller / hr with 50 min / hr working and 70 % effinciancy:

    ( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 say : 88 cum

    Time for rolling 504 cum soil in embankment layer say : 6 hours

    Effective width of dozer track : 1.00 m

    Speed of dozer per hour : 4.0 km

    Thickness of layer : 0.3 m

    Number of dozer passes : 3 Nos

    Output of dozer / hr with 50 min / hr working and 70 % effinciancy:

    ( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 say : 230 cum

    Time for rolling 504 cum soil in embankment layer say : 2 hours

    Deploy road roller for 6 hours and dozer for 2 hours for compaction.

    6. Sorting out / sectioning / labour for testing etc :

    Assume 2 heavy and 2 light mazdoors.

    RATE ANALYSIS UNIT : 435.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00Add for Contractor's Overheads @ 5% Rs: 0.00

    Add Royalty charges on 696 t soil @ Rs: 10.00 / tonne Rs: 6960.00

    Total cost of Materials : Rs: 6960.00

    Perticulars Quantity Rate

    in Rs.

    64

  • 8/13/2019 Data Rates-P & M Works-4

    6/21

    DATA RATES- P AND M WORKS

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Angle dozer 90 hp Hour 5.00 1154.00 5770.00

    Fuel / Energy charges Hour 5.00 423.00 2115.00

    2 Shovel 0.50 cum capacity Hour 8.00 725.00 5800.00

    Fuel / Energy charges Hour 8.00 330.00 2640.00

    3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 271.00 8672.00

    Fuel / Energy charges Hour 32.00 208.00 6656.00

    4 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

    Fuel / Energy charges Hour 2.50 55.00 137.50

    5 Water tanker 8000 ltr Hour 5.00 268.00 1340.00

    Fuel / Energy charges Hour 5.00 208.00 1040.00

    6 Road roller 10 tonne ( diesel ) Hour 6.00 228.00 1368.00

    Fuel / Energy charges Hour 6.00 495.00 2970.00

    7 Sundries LS 2.00 30.00 60.00

    Total Rs: 38586.00

    Add for small Tools and Plants @ 1% Rs: 385.86

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 1561.85

    Add for Contractor's Overheads @ 5% Rs: 1929.30

    Total hire charges of Machinery : Rs: 42463.01

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Dozer Hour 5.00 77.50 387.50

    2 Crew for Shovel Hour 8.00 77.50 620.00

    3 Crew for Tipper Hour 32.00 56.70 1814.40

    4 Crew for Pump Hour 2.50 35.80 89.50

    5 Crew for Water tanker Hour 5.00 56.70 283.50

    6 Crew for Roller Hour 6.00 72.00 432.00

    7 Maistry Day 2.00 141.50 283.00

    8 Heavy mazdoor Day 2.00 132.00 264.00

    9 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 4434.90

    Add for small Tools and Plants @ 1% Rs: 44.35

    Add for Contractor's Profit @ 10% Rs: 443.49

    Add for hidden cost on Labour @ 15% Rs: 665.24

    Add for Contractor's Overheads @ 5% Rs: 221.75

    Total cost of Labour : Rs: 5809.72

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 6960.00

    B. Hire charges of Machinery Rs: 42463.01

    C. Cost of Labour Rs: 5809.72

    TOTAL Rs: 55232.73

    Add for enabling works @ 1.00% Rs: 552.33

    Total cost for 435.00 cum Rs: 55785.06Rate per cum Rs: 128.00

    Rate approved per cum Rs: 128.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 26

    Quantity Rate

    in Rs.

    Quantity Rate

    in Rs.

    Description

    Description

    65

  • 8/13/2019 Data Rates-P & M Works-4

    7/21

    DATA RATES- P AND M WORKS

    ITEM: Repairing rain cuts/ resectioning canal slopes to required lines and grades as directed using

    available soil including dressing, clod breaking, packing, tamping etc., complete with all leads

    and lifts.

    DATA:1heavy and 1 light mazdoor assumed for repairing rain cuts in 250 sqm canal slope per day.

    Consider 1000 sqm canal slope for maintanance for rate analysis.

    1. Requirement of materials:

    Available soil from canal side.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Maistry : 1 No.

    Heavy mazdoor : 4 Nos.

    Light mazdoor : 4 Nos.

    RATE ANALYSIS UNIT : 1000.00 sqm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total cost of Materials : Rs: 0.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 4.00 132.00 528.00

    3 Light mazdoor Day 4.00 130.50 522.00

    Total Rs: 1191.50

    Add for small Tools and Plants @ 1% Rs: 11.92Contd

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    Perticulars

    Description

    Description

    Description

    in Rs.

    in Rs.

    Quantity Rate

    Quantity Rate

    Quantity Rate

    in Rs.

    Quantity Rate

    66

  • 8/13/2019 Data Rates-P & M Works-4

    8/21

    DATA RATES- P AND M WORKS

    in Rs.

    Contd

    Add for Contractor's Profit @ 10% Rs: 119.15

    Add for hidden cost on Labour @ 15% Rs: 178.73

    Add for Contractor's Overheads @ 5% Rs: 59.58

    Total cost of Labour : Rs: 1560.87

    ABSTRACT:

    A. Cost of Materials Rs: 0.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1560.87

    TOTAL Rs: 1560.87

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 1000.00 sqm Rs: 1560.87

    Rate per sqm Rs: 1.55

    Rate approved per sqm Rs: 1.55

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 27

    ITEM: Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing

    including chiselling and removing leached lime deposit and disposing off all the waste materialout side adits in specified location etc., complete with all leads and lifts.

    DATA:Consider 100 Rm of gallery for cleaning:

    1. Requirement of materials:

    Wire brush : 5 Nos

    Coir brush : 10 Nos.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Chiseller Cl II : 2 Nos.

    Heavy mazdoor : 4 Nos.

    Light mazdoors : 2 Nos.

    RATE ANALYSIS UNIT : 100.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Wire brush Each 5.00 30.00 150.00

    2 Coir brush Each 10.00 20.00 200.00

    3 Sundries ( brooms, gloves etc ) LS 2.00 30.00 60.00

    Total Rs: 410.00

    Add for small Tools and Plants @ 1% Rs: 4.10

    Add for Contractor's Profit @ 10% Rs: 41.00

    Add for Contractor's Overheads @ 5% Rs: 20.50

    Total cost of Materials : Rs: 475.60

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    in Rs.

    Perticulars

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Description

    67

  • 8/13/2019 Data Rates-P & M Works-4

    9/21

    DATA RATES- P AND M WORKS

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Chiseller Cl II Day 2.00 146.00 292.00

    2 Heavy mazdoor Day 4.00 132.00 528.00

    3 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 1081.00

    Add for small Tools and Plants @ 1% Rs: 10.81

    Add for Contractor's Profit @ 10% Rs: 108.10

    Add for hidden cost on Labour @ 15% Rs: 162.15

    Add for Contractor's Overheads @ 5% Rs: 54.05

    Total cost of Labour : Rs: 1416.11

    ABSTRACT:

    A. Cost of Materials Rs: 475.60

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1416.11

    TOTAL Rs: 1891.71

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 Rm Rs: 1891.71

    Rate per Rm Rs: 19.00

    Rate approved per Rm Rs: 19.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 28

    ITEM: Cleaning dam parapetinner face and top using oxalic acid and water by scrubbing / brushing

    and washing to remove all surface coatings etc., complete .

    DATA:Consider 100 Rm of parapet for cleaning:

    Area to be cleaned considering 1.25 sqm per Rm length : 125 sqm

    1. Requirement of materials:

    Oxalic acid @ 25 sqm / ltr : 5 ltr

    Wire brush : 5 Nos

    Coir brush : 10 Nos.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Heavy mazdoor : 5 Nos.

    Light mazdoors : 1 No.

    RATE ANALYSIS UNIT : 100.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.in Rs.

    Quantity Rate

    in Rs.

    Quantity Rate

    Description

    Perticulars

    68

  • 8/13/2019 Data Rates-P & M Works-4

    10/21

    DATA RATES- P AND M WORKS

    1 Oxalic acid ltr 5.00 60.00 300.00

    2 Wire brush Each 5.00 30.00 150.00

    3 Coir brush Each 10.00 20.00 200.00

    4 Sundries ( brooms, gloves etc ) LS 2.00 30.00 60.00

    Total Rs: 710.00

    Add for small Tools and Plants @ 1% Rs: 7.10

    Add for Contractor's Profit @ 10% Rs: 71.00

    Add for Contractor's Overheads @ 5% Rs: 35.50

    Total cost of Materials : Rs: 823.60

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Heavy mazdoor Day 5.00 132.00 660.00

    2 Light mazdoor Day 1.00 130.50 130.50

    Total Rs: 790.50

    Add for small Tools and Plants @ 1% Rs: 7.91

    Add for Contractor's Profit @ 10% Rs: 79.05

    Add for hidden cost on Labour @ 15% Rs: 118.58

    Add for Contractor's Overheads @ 5% Rs: 39.53

    Total cost of Labour : Rs: 1035.56

    ABSTRACT:

    A. Cost of Materials Rs: 823.60

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1035.56

    TOTAL Rs: 1859.16

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 Rm Rs: 1859.16

    Rate per Rm Rs: 19.00

    Rate approved per Rm Rs: 19.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 29

    ITEM: Cleaning gates / hoists / embedded partsfor re-painting by removing rust, old paint, grease

    etc., by using wire brush,scrubber, rust remover and applying a coat of rust inhibitive

    compound etc., complete.

    DATA:Consider 100 sqm area for cleaning:

    Description

    Description

    in Rs.

    Quantity Rate

    Quantity Rate

    in Rs.

    69

  • 8/13/2019 Data Rates-P & M Works-4

    11/21

    DATA RATES- P AND M WORKS

    1. Requirement of materials:

    Wire brush : 10 Nos

    Rust remover / Inhibiter : 2 ltrs

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Painter Class-II : 5 Nos.

    Heavy mazdoor : 6 Nos.

    RATE ANALYSIS UNIT : 100.00 sqm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Wire brush Each 10.00 30.00 300.00

    2 Rust cleaner / inhibitor ltr 2.00 240.00 480.00

    3 Sundries ( sand papers etc ) LS 4.00 30.00 120.00

    Total Rs: 900.00

    Add for small Tools and Plants @ 1% Rs: 9.00

    Add for Contractor's Profit @ 10% Rs: 90.00

    Add for Contractor's Overheads @ 5% Rs: 45.00

    Add for scaffolding / ladder etc @ 10% Rs: 90.00Total cost of Materials : Rs: 1134.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Painter Class-II Day 5.00 141.50 707.50

    2 Heavy mazdoor Day 6.00 132.00 792.00

    Total Rs: 1499.50

    Add for small Tools and Plants @ 1% Rs: 15.00

    Add for Contractor's Profit @ 10% Rs: 149.95

    Add for hidden cost on Labour @ 15% Rs: 224.93

    Add for Contractor's Overheads @ 5% Rs: 74.98

    Total cost of Labour : Rs: 1964.35

    ABSTRACT:

    A. Cost of Materials Rs: 1134.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1964.35

    TOTAL Rs: 3098.35

    Add for enabling works @ 0.00% Rs: 0.00

    Perticulars

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Quantity Rate

    in Rs.

    Description

    Description

    70

  • 8/13/2019 Data Rates-P & M Works-4

    12/21

    DATA RATES- P AND M WORKS

    Total cost for 100.00 sqm Rs: 3098.35

    Rate per sqm Rs: 31.00

    Rate approved per sqm Rs: 31.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 30

    ITEM: Cleaning gates / hoists / embedded parts to expose fresh metal surface for repainting by

    sand blastingmethod as per specifications including cost of all materials, labour, machinery,

    scaffolding, applying a coat of rust inhibitive etc., complete with initial lead for sand upto

    1 km and all lifts.

    DATA:Consider 100 sqm area for cleaning:

    1. Requirement of materials :

    Sand of gradation 2mm to 1mm @ 0.10 cum / sqm

    Approximately 2 cum natural river sand yeilds 1 cum of sand blasting grade sand after seiving

    in 2mm and 1 mm sieves.

    Allowing 50 % extra for projections, the actual area of sand blasting : 150 sqm

    Requirement of processed sand ( 150 x 0.10 ) : 15.00 cum

    Requirement of natural river sand ( 15.00 x 2 ) : 30.00 cum

    2. Requirement of machinery :

    Output of sand blasting per hour : 20 to 25 sqm

    Considering 50 minutes per hour working,

    Requirement of 7 cmm compressor ( 150 x 60 / 50 / 22.5 ) : 8 hours

    Requirement of sand blasting equipment : 8 hours

    3. Requirement of workforce ( Other than machinery crew ) :

    Heavy mazdoor:

    For seiving sand : 6 Nos.

    For loading sand blast drum : 2 Nos.

    For assisting sand blaster : 1 No.

    Light mazdoor:

    For seiving sand : 4 Nos.

    For cleaning / collection of rebound sand and other works : 2 Nos.

    4. Use rate of materials :

    Cost of 25 mm dia 50 m air hose @ Rs: 150.00 / Rm Rs: 7500.00

    Life of air hose : 800 hours

    Use rate of air hose per hour ( cost / life ) Rs: 9.38

    Cost of sand blast gun nozzle @ Rs: 312.00 / Each Rs: 312.00

    Life of sand blast gun nozzle : 200 hours

    Use rate of sand blast gun nozzle per hour ( cost / life ) : 1.56

    RATE ANALYSIS UNIT : 100.00 sqm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Natural river sand ( unscreened ) cum 30.00 154.00 4620.00

    2 Use rate of air hose Hour 8.00 9.38 75.00

    3 Use rate of sand blast gun nozzle Hour 8.00 1.56 12.48

    Perticulars

    in Rs.

    Quantity Rate

    71

  • 8/13/2019 Data Rates-P & M Works-4

    13/21

    DATA RATES- P AND M WORKS

    4 Sundries( Rust inhibitive, Seive etc ) LS 5.00 30.00 150.00

    Total Rs: 4857.48

    Add for small Tools and Plants @ 1% Rs: 48.57

    Add for Contractor's Profit @ 10% Rs: 485.75

    Add for Contractor's Overheads @ 5% Rs: 242.87

    Add for scaffolding / ladder etc @ 10% Rs: 485.75

    Total cost of Materials : Rs: 6120.42

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Air compressor 7 cmm diesel Hour 8.00 166.00 1328.00

    Fuel / Energy charges Hour 8.00 495.00 3960.00

    2 Sand blasting equipment Hour 8.00 84.00 672.00

    Fuel / Energy charges Hour 8.00 9.00 72.00

    Total Rs: 6032.00

    Add for small Tools and Plants @ 1% Rs: 60.32

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 403.20

    Add for Contractor's Overheads @ 5% Rs: 301.60

    Total hire charges of Machinery : Rs: 6797.12

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Air compressor Hour 8.00 72.10 576.80

    2 Crew for Sand blasting equipment Hour 8.00 74.40 595.20

    3 Heavy mazdoor Day 9.00 132.00 1188.00

    4 Light mazdoor Day 6.00 130.50 783.00

    Total Rs: 3143.00

    Add for small Tools and Plants @ 1% Rs: 31.43

    Add for Contractor's Profit @ 10% Rs: 314.30

    Add for hidden cost on Labour @ 15% Rs: 471.45

    Add for Contractor's Overheads @ 5% Rs: 157.15

    Total cost of Labour : Rs: 4117.33

    ABSTRACT:

    A. Cost of Materials Rs: 6120.42

    B. Hire charges of Machinery Rs: 6797.12

    C. Cost of Labour Rs: 4117.33

    TOTAL Rs: 17034.87

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 sqm Rs: 17034.87

    Rate per sqm Rs: 170.00

    Rate approved per sqm Rs: 170.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 31

    ITEM: Providing two coats of painting to hoist supporting structures / hoists / moving gantry

    cranes / railings etc., with zinc chromate alluminium primer paint of approved quality

    including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc.,

    complete withall leads and all lifts.

    DATA:Consider 100 sqm area for painting:

    Description

    Description

    in Rs.

    Quantity Rate

    Quantity Rate

    in Rs.

    72

  • 8/13/2019 Data Rates-P & M Works-4

    14/21

    DATA RATES- P AND M WORKS

    1. Requirement of materials :

    Coverage of paints for each coat : 12 sqm / ltr

    Qty of paint 2 coats 100 sqm with 2 % wastage( 100x2x1.02/ 12 ) : 17 ltrs

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.

    Painter Class-II for painting @ 15 sqm / day : 7 Nos.

    Heavy mazdoor for assisting painter for cleaning and painting : 5 Nos.

    RATE ANALYSIS UNIT : 100.00 sqm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Zinc chromate, alluminium primer ltr 17.00 140.00 2380.00

    2 Sundries LS 2.00 30.00 60.00

    Total Rs: 2440.00

    Add for small Tools and Plants @ 1% Rs: 24.40

    Add for Contractor's Profit @ 10% Rs: 244.00

    Add for Contractor's Overheads @ 5% Rs: 122.00

    Add for scaffolding / ladder etc @ 2% Rs: 48.80Total cost of Materials : Rs: 2879.20

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Painter Class-II Day 10.00 141.50 1415.00

    2 Heavy mazdoor Day 5.00 132.00 660.00

    Total Rs: 2075.00

    Add for small Tools and Plants @ 1% Rs: 20.75

    Contd

    C. LABOUR ( Contd ) :Sl No Unit Amount

    in Rs.

    Contd

    Add for Contractor's Profit @ 10% Rs: 207.50

    Add for hidden cost on Labour @ 15% Rs: 311.25

    Add for Contractor's Overheads @ 5% Rs: 103.75

    Total cost of Labour : Rs: 2718.25

    Description Quantity Rate

    in Rs.

    Perticulars

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Quantity Rate

    in Rs.

    Description

    Description

    73

  • 8/13/2019 Data Rates-P & M Works-4

    15/21

    DATA RATES- P AND M WORKS

    ABSTRACT:

    A. Cost of Materials Rs: 2879.20

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 2718.25

    TOTAL Rs: 5597.45

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 sqm Rs: 5597.45

    Rate per sqm Rs: 56.00

    Rate approved per sqm Rs: 56.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 32

    ITEM: Providing two coats of painting100 micron dry film thickness each coat to embedded parts

    / gates with cold appliedcoal tar epoxy paint of approved quality including removing rust,

    cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and

    all lifts.

    DATA:Consider 100 sqm area for painting:

    1. Requirement of materials :

    Coverage of paints for each coat : 6 sqm / ltr Qty of paint 100 sqm 2 coats with 2 % wastage(100 x 2 x 1.02 / 6) : 34.00 ltrs

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.

    Painter Class-II for painting @ 10 sqm / day : 10 Nos.

    Heavy mazdoor for assisting painter for cleaning and painting : 6 Nos.

    RATE ANALYSIS UNIT : 100.00 sqm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Coal tar epoxy paint ltr 34.00 208.00 7072.00

    2 Sundries ( rust remover / brush etc ) LS 4.00 30.00 120.00

    Total Rs: 7192.00

    Add for small Tools and Plants @ 1% Rs: 71.92

    Add for Contractor's Profit @ 10% Rs: 719.20

    Add for Contractor's Overheads @ 5% Rs: 359.60

    Add for scaffolding / ladder etc @ 5% Rs: 359.60

    Total cost of Materials : Rs: 8702.32

    B. MACHINERY:

    Sl No Unit Amountin Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    Description

    in Rs.

    in Rs.Quantity Rate

    Quantity RatePerticulars

    74

  • 8/13/2019 Data Rates-P & M Works-4

    16/21

    DATA RATES- P AND M WORKS

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Painter Class-II Day 13.00 141.50 1839.50

    2 Heavy mazdoor Day 6.00 132.00 792.00

    Total Rs: 2631.50

    Add for small Tools and Plants @ 1% Rs: 26.32

    Add for Contractor's Profit @ 10% Rs: 263.15

    Add for hidden cost on Labour @ 15% Rs: 394.73

    Add for Contractor's Overheads @ 5% Rs: 131.58

    Total cost of Labour : Rs: 3447.27

    ABSTRACT:

    A. Cost of Materials Rs: 8702.32

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 3447.27

    TOTAL Rs: 12149.59

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 sqm Rs: 12149.59

    Rate per sqm Rs: 121.00Rate approved per sqm Rs: 121.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 33

    ITEM: Providing two coats of painting to hoist supporting structures / hoists / moving gantry

    cranes / railings etc., with first quality synthetic enemel paint of approved colour

    including cleaning surface, cost of all materials, labour, scaffolding etc., complete with

    all leads and all lifts.

    DATA:Consider 100 sqm area for painting:

    1. Requirement of materials :

    Coverage of paints for each coat : 12 sqm / ltr

    Qty of paint 2 coats 100 sqm with 2 % wastage( 100x 2x1.02 /12 ) : 17 ltrs

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.

    Painter Class-II for painting @ 15 sqm / day : 7 Nos.

    Heavy mazdoor for assisting painter for cleaning and painting : 5 Nos.

    RATE ANALYSIS UNIT : 100.00 sqm

    A. MATERIALS:

    Sl No Unit Amountin Rs.

    1 Synthetic enamel paint ( 1st quality ) ltr 17.00 176.00 2992.00

    2 Sundries LS 2.00 30.00 60.00

    Total Rs: 3052.00

    Add for small Tools and Plants @ 1% Rs: 30.52

    Add for Contractor's Profit @ 10% Rs: 305.20

    Add for Contractor's Overheads @ 5% Rs: 152.60

    Add for scaffolding / ladder etc @ 2% Rs: 61.04

    Perticulars

    Description Quantity Rate

    in Rs.

    Quantity Ratein Rs.

    75

  • 8/13/2019 Data Rates-P & M Works-4

    17/21

    DATA RATES- P AND M WORKS

    Total cost of Materials : Rs: 3601.36

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Painter Class-II Day 10.00 141.50 1415.00

    2 Heavy mazdoor Day 5.00 132.00 660.00

    Total Rs: 2075.00

    Add for small Tools and Plants @ 1% Rs: 20.75

    Add for Contractor's Profit @ 10% Rs: 207.50Add for hidden cost on Labour @ 15% Rs: 311.25

    Add for Contractor's Overheads @ 5% Rs: 103.75

    Total cost of Labour : Rs: 2718.25

    ABSTRACT:

    A. Cost of Materials Rs: 3601.36

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 2718.25

    TOTAL Rs: 6319.61

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 sqm Rs: 6319.61

    Rate per sqm Rs: 63.00

    Rate approved per sqm Rs: 63.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 34

    ITEM: Excavation and removal of silt and silt mixed with sand from canal bed in dry condition

    including disposing off the same in spoil bank or on the canal embankment in layers as

    directed etc., complete with initiallead upto 50 m and all lifts.

    DATA:1 heavy and 1 light mazdoor assumed for removing 5 cum dry silt per day.

    Consider removal of 10 cum dry silt for rate analysis.1. Requirement of materials :

    No materials required.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Heavy mazdoor : 2 Nos.

    Light mazdoor : 2 Nos.

    Quantity Rate

    in Rs.

    Quantity Rate

    in Rs.

    Description

    Description

    76

  • 8/13/2019 Data Rates-P & M Works-4

    18/21

    DATA RATES- P AND M WORKS

    RATE ANALYSIS UNIT : 10.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total cost of Materials : Rs: 0.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Heavy mazdoor Day 2.00 132.00 264.00

    2 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 525.00

    Add for small Tools and Plants @ 1% Rs: 5.25

    Add for Contractor's Profit @ 10% Rs: 52.50

    Add for hidden cost on Labour @ 15% Rs: 78.75

    Add for Contractor's Overheads @ 5% Rs: 26.25

    Total cost of Labour : Rs: 687.75

    ABSTRACT:

    A. Cost of Materials Rs: 0.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 687.75

    TOTAL Rs: 687.75

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 10.00 cum Rs: 687.75

    Rate per cum Rs: 69.00Rate approved per cum Rs: 69.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 35

    ITEM: Excavation and removal of siltor silt mixed with sand inslussy condition from canal bed

    including disposing off the same in spoil bank or on the canal embankment in layers as

    directed etc., complete with initial lead upto 50 m and all lifts.

    Perticulars

    Description

    Description

    in Rs.

    Rate

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Quantity

    77

  • 8/13/2019 Data Rates-P & M Works-4

    19/21

    DATA RATES- P AND M WORKS

    DATA:Excavated silt in slussy condition can be disposed off in single operation without heaping silt in

    mortar pans or by collecting and rehandling after draining out water.

    Output of 1 heavy and 2 light mazdoor assumed at 6 cum per day.

    Consider removal of 12 cum silt in slussy condition for rate analysis.

    1. Requirement of materials :

    No materials required.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Heavy mazdoor : 2 Nos.

    Light mazdoor : 4 Nos.

    RATE ANALYSIS UNIT : 12.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total cost of Materials : Rs: 0.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Heavy mazdoor Day 2.00 132.00 264.00

    2 Light mazdoor Day 4.00 130.50 522.00

    Total Rs: 786.00Add for small Tools and Plants @ 1% Rs: 7.86

    Add for Contractor's Profit @ 10% Rs: 78.60

    Add for hidden cost on Labour @ 15% Rs: 117.90

    Add for Contractor's Overheads @ 5% Rs: 39.30

    Total cost of Labour : Rs: 1029.66

    ABSTRACT:

    A. Cost of Materials Rs: 0.00

    Description

    Perticulars

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Quantity Rate

    in Rs.

    Description

    78

  • 8/13/2019 Data Rates-P & M Works-4

    20/21

    DATA RATES- P AND M WORKS

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1029.66

    TOTAL Rs: 1029.66

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 12.00 cum Rs: 1029.66

    Rate per cum Rs: 86.00

    Rate approved per cum Rs: 86.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 36.a

    ITEM: Removing and hauling all kinds of soil / soft rock including boulders upto 0.6 m diameter

    slipped due to natural causes and disposing off the same in specified dump area or as

    directed including cost of all materials, machinery, labour, rampways and all other ancillary

    operations etc., complete with initial lead upto 50 m and lift upto 1.5 m.

    Note: The rate under this item is for unit quantity of soil / soft rock in slipped condition.

    The rate under this item shall be adopted where the material can be disposed off within 50 m

    lead or where the slipped zone is inaccessible for disposal of material by mechanical mode.

    The wieghted average rate applicable to entire quantity based on rates provided under items

    36.a and 37.a may be considered where the slipped material consists of mixture of soil / soft

    rock and hard rock.

    DATA:Consider removal of 100 cum slipped soil / soft rock for rate analysis.

    The quantity assumed for analysis is the volume of soil / soft rock in slipped condition.

    Therefore, the measurement for soil / soft rock shall be for the volume in slipped condition and

    not for the original in-situ condition.

    Average output of 1 heavy and 1 light mazdoor assumed at 6 cum / day for removing muck.

    1. Requirement of materials :

    No materials required.

    2. Requirement of machinery :

    No machinery proposed for the work.

    3. Requirement of workforce :

    Maistry : 0.5 No.

    Heavy mazdoor : 17 Nos.

    Light mazdoor : 17 Nos.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total cost of Materials : Rs: 0.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    Description

    Rate

    in Rs.

    in Rs.

    Quantity Rate

    QuantityPerticulars

    79

  • 8/13/2019 Data Rates-P & M Works-4

    21/21

    DATA RATES- P AND M WORKS

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 0.50 141.50 70.75

    2 Heavy mazdoor Day 17.00 132.00 2244.00

    3 Light mazdoor Day 17.00 130.50 2218.50

    Total Rs: 4533.25

    Add for small Tools and Plants @ 1% Rs: 45.33

    Add for Contractor's Profit @ 10% Rs: 453.33

    Add for hidden cost on Labour @ 15% Rs: 679.99

    Add for Contractor's Overheads @ 5% Rs: 226.66

    Total cost of Labour : Rs: 5938.56

    ABSTRACT:

    A. Cost of Materials Rs: 0.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 5938.56

    TOTAL Rs: 5938.56

    Add for enabling works @ 0.00% Rs: 0.00

    Total cost for 100.00 cum Rs: 5938.56

    Rate per cum Rs: 59.00

    Rate approved per cum Rs: 59.00

    SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 36.b

    ITEM: Removing and hauling all kinds of soil / soft rock including boulders upto 0.6 m diameter

    slipped due to natural geological causes and disposing off the same in specified dump

    area or as directed including costof all materials, machinery, labour, rampways and all other

    ancillary operations etc., complete with initial lead upto 1 km and all lifts.

    Note: The rate under this item is for unit quantity of soil / soft rock in slipped condition.

    The wieghted average rate applicable to entire quantity based on rates provided under items

    36.b and 37.b may be considered where the slipped material consists of mixture of soil / soft

    rock and hard rock.

    DATA:The quantity assumed for analysis is the volume of soil / soft rock in slipped condition.For soil / soft rock in slipped condition 10 % bulkage is assumed and further bulkage of another

    10 % is asssumed on digging / loading the slipped soil / soft rock mass for disposal.

    Therefore, the measurement for soil / soft rock shall be for the volume in slipped condition and

    not for the original in-situ condition.

    Consider 95 % quantity with 1 km lead for disposal by shovel and tipper combination.

    Consider 5 % quantity ( residual muck at bed ) with 50 m lead for disposal by work force.

    Capacity of shovel bucket : 0.50 cum

    Capacity of shovel bucket under heaped condition : 0.58 cum

    Quantity Rate

    in Rs.

    Description