Data Rates-P & M Works-4
-
Upload
vpmohammed -
Category
Documents
-
view
219 -
download
0
Transcript of Data Rates-P & M Works-4
-
8/13/2019 Data Rates-P & M Works-4
1/21
DATA RATES- P AND M WORKS
In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.54 cum
Number of buckets per load ( 4.54 / 0.53 ) say : 8 buckets
Cycle time for loading 8 buckets ( 8 x 20 / 60 ) say : 2.70 min
Round trip cycle time for tipper:
Ideal cycle time of shovel for digging and loading : 2.70 min
Time for 1km haulage under load ( 60 / 15 ) : 4.00 min
Time for turning and un-loading : 2.00 min
Time for 1 km return trip ( 60 / 20 ) : 3.00 min
Time for turning and spotting : 0.50 min
Total : 12.20 min
As the movement of tippers will be slow in breached portion due limited area 1 minute extra time
may be considered for the round trip cycle time of tippers.
Corrected round trip cycle time for tipper ( 12.20 + 1.00 ) : 13.20 min
No.of tippers to match corrected cycle time of tipper ( 13.20 / 2.70 ) say : 5 Nos
Output of tipper / hr with 50 min working / hr ( 50 x 4.54 / 13.2 ) : 17.20 cum
Output for 5 tippers per day ( 5 x 17.20 x 8 ) say : 688 cumThe in-situ dry density of soil in borrow area will be generally less than dry density of compacted
embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow
area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction
of embankment. For 95 % density control of embankment in breached portion a shrinkage factor
of 5 % may be assumed for use of borrow area soil.
Further, as the insitu density of soil in dump area will be less compared to natural ground due
to bulkage of soil during excavation for applying the shrinkage foctor it is necessary to convert
the insitu dump area quantity to equivalent borrow area quantity by applying bulkage factor.
Equivalent borrow area quantity for 10% bulkage ( 688 / 1.1 ) : 625 cum
Qty of compacted embankment for 5 % shrinkage ( 625 x 0.95 ) : 594 cum
Qty of soil for computing royalty charges @ 1.6 t /cum ( 594 x 1.6 ) : 950 tonnes
1. Stripping of borrow area :
Since soil is from dump area no stripping is involved.
However, use of dozer is necessary for forming rampways and for trimming the old embankment
on either side of breached portion to required slope for abutting the fresh embankment layers.
Assume use of dozer for 0.5 hour daily for this purpose.
Deploy dozer for forming ramps / slopes for 1 day work : 0.5 hour
2. Collection of soil for embankment:
Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.
Deploy 5 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.
3. Spreading soil in 250 to 300 mm layer:
Quantity of loose soil to be spread ( 688 / 1.10 ) : 757 cum
Output of dozer for levelling per hour : 200 cum
Time required for levelling 757 cum say : 4.00 hours
4. Watering;
Generally soil in the dump area will be in moist condition. In the beginning of the season nowatering may be necessary. However, in summer months as the loose soil looses moisture at
faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain
the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5
to 6 percent watering by weight, requirement of water for 594 cum of embankment will be about
7 tanker loads of 8000 ltrs each.
Deploy 8000 ltr capacity water tanker for 7 hours for watering before rolling.
Deploy 5 hp pump for 3.5 hours.
60
-
8/13/2019 Data Rates-P & M Works-4
2/21
DATA RATES- P AND M WORKS
5. Compaction:
Soil collected for embankment layer gets compacted to some extent during levelling by dozer.
Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density
control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining
adjacent to breached portion a combination of 8 to 10 passes of road roller followed by 2 to 4
passes of dozer is considered for compaction and roughening top surface for laying next layer.
Effective length of roller drum : 1.50 m
Speed of roller per hour : 3.0 km
Thickness of layer : 0.3 m
Number of roller passes : 9 Nos
Output of road roller / hr with 50 min / hr working and 70 % effinciancy:
( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 say : 88 cum
Time for rolling 757 cum soil in embankment layer say : 8.5 hours
Effective width of dozer track : 1.00 m
Speed of dozer per hour : 4.0 km
Thickness of layer : 0.3 m
Number of dozer passes : 3 NosOutput of dozer / hr with 50 min / hr working and 70 % effinciancy:
( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 say : 230 cum
Time for compacting 757 cum soil in embankment layer say : 3.50 hours
Deploy road roller for 8.5 hours and dozer for 3.5 hours for compaction.
6. Sorting out / sectioning / labour for testing etc :
Assume 2 heavy and 2 light mazdoors.
RATE ANALYSIS UNIT : 594.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Add Royalty charges on 950 t soil @ Rs: 10.00 / tonne Rs: 9500.00
Total cost of Materials : Rs: 9500.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Angle dozer Hour 8.00 1154.00 9232.00
Fuel / Energy charges Hour 8.00 423.00 3384.00
2 Shovel 0.50 cum capacity Hour 8.00 725.00 5800.00Fuel / Energy charges Hour 8.00 330.00 2640.00
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 271.00 10840.00
Fuel / Energy charges Hour 40.00 208.00 8320.00
4 Pump 5 hp ( diesel ) Hour 3.50 7.00 24.50
Fuel / Energy charges Hour 3.50 55.00 192.50
Contd
Description Quantity Rate
Quantity Rate
in Rs.
Perticulars
in Rs.
61
-
8/13/2019 Data Rates-P & M Works-4
3/21
DATA RATES- P AND M WORKS
B. MACHINERY ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
5 Water tanker 8000 ltr Hour 7.00 268.00 1876.00
Fuel / Energy charges Hour 7.00 208.00 1456.00
6 Road roller 10 tonne ( diesel ) Hour 8.50 228.00 1938.00
Fuel / Energy charges Hour 8.50 495.00 4207.50
7 Sundries LS 2.00 30.00 60.00
Total Rs: 49970.50
Add for small Tools and Plants @ 1% Rs: 499.71
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 2026.00
Add for Contractor's Overheads @ 5% Rs: 2498.53
Total hire charges of Machinery : Rs: 54994.73
C. LABOUR:
Sl No Unit Amount
in Rs.1 Crew for Dozer Hour 8.00 77.50 620.00
2 Crew for Shovel Hour 8.00 77.50 620.00
3 Crew for Tipper Hour 40.00 56.70 2268.00
4 Crew for Pump Hour 3.50 35.80 125.30
5 Crew for Water tanker Hour 7.00 56.70 396.90
6 Crew for Roller Hour 8.50 72.00 612.00
7 Maistry Day 2.00 141.50 283.00
8 Heavy mazdoor Day 2.00 132.00 264.00
9 Light mazdoor Day 2.00 130.50 261.00
Total Rs: 5450.20
Add for small Tools and Plants @ 1% Rs: 54.50
Add for Contractor's Profit @ 10% Rs: 545.02
Add for hidden cost on Labour @ 15% Rs: 817.53
Add for Contractor's Overheads @ 5% Rs: 272.51
Total cost of Labour : Rs: 7139.76
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 9500.00
B. Hire charges of Machinery Rs: 54994.73
C. Cost of Labour Rs: 7139.76
TOTAL Rs: 71634.49
Add for enabling works @ 1.00% Rs: 716.34
Total cost for 594.00 cum Rs: 72350.84
Rate per cum Rs: 122.00
Rate approved per cum Rs: 122.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 25
ITEM: Providingpervious / semi-pervious casing for breached /damaged portion of embankment
with soil from approved dump areas in layers of 250 to 300 mm before compaction
including cost of all materials, machinery, labour, all operations such as collection of soil,
sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering,
Description
Description
Quantity Rate
in Rs.
in Rs.
Quantity Rate
62
-
8/13/2019 Data Rates-P & M Works-4
4/21
DATA RATES- P AND M WORKS
compacting each layer to density control of not less than 95 percent or as stipulated by using
combination of road roller and dozer etc., complete with initial lead upto 1 km and all lifts.
DATA:Capacity of shovel bucket : 0.50 cum
Capacity of shovel bucket under heaped condition : 0.58 cum
Insitu quantity of soil per bucket considering 10 % bulkage : 0.53 cum
Capacity of tipper : 5.00 cum
Lead for conveyance of soil : Upto 1 km
Speed for loaded tipper under haul road condition : 15 km / hr
Speed for empty tipper under haul road condition : 20 km / hr
Turning and unloading time : 2.00 min
Same digging and loading cycle as considered for borrow area may be assumed for use of soil
from spoil bank formed during construction of canal in view of partial settlement of soil.
Shovel digging and loading cycle per bucket : 25 sec
In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.54 cum
Number of buckets per load ( 4.54 / 0.53 ) say : 8 buckets
Cycle time for loading 8 buckets ( 8 x 25 / 60 ) say : 3.50 min
Round trip cycle time for tipper:
Ideal cycle time of shovel for digging and loading : 3.50 minTime for 1km haulage under load ( 60 / 15 ) : 4.00 min
Time for turning and un-loading : 2.00 min
Time for 1 km return trip ( 60 / 20 ) : 3.00 min
Time for turning and spotting : 0.50 min
Total : 13.00 min
As the movement of tippers will be slow in breached portion due limited area 1 minute extra time
may be considered for the round trip cycle time of tippers.
Corrected round trip cycle time for tipper ( 13.00 + 1.00 ) : 14.00 min
No.of tippers to match corrected cycle time of tipper (14.00 / 3.5.00) : 4 Nos
Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 14.00 ) : 14.30 cum
Output for 3 tippers per day ( 4 x 14.30 x 8 ) say : 458 cum
The in-situ dry density of soil in borrow area will be generally less than dry density of compacted
embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow
area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction
of embankment. For 95 % density control of embankment in breached portion a shrinkage factor
of 5 % may be assumed.
Quantity of embankment considering 5 %shrinkage ( 458 x 0.95 ) say : 435 cum
Qty of soil for computing royalty charges @ 1.6 t /cum ( 435 x 1.6 ) : 696 tonnes
1. Stripping of borrow area :
Since the soil is from dump area no stripping is involved.
Further, use of dozer is necessary for forming rampways and for trimming the old embankment
on either side of breached portion to required slope for abutting the fresh embankment layers.
Assume use of dozer for 0.5 hour daily for this purpose.
Deploy dozer for forming ramps / slopes for 1 day work : 0.5 hour
2. Collection of soil for embankment:
Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.
3. Spreading soil in 250 to 300 mm layer:
Quantity of loose soil to be spread ( 458 x 1.1 ) : 504 cum
Output of dozer for levelling per hour : 200 cum
63
-
8/13/2019 Data Rates-P & M Works-4
5/21
DATA RATES- P AND M WORKS
Time required for levelling 504 cum say : 2.50 hours
4. Watering;
Generally soil in the dump area will be in moist condition. In the beginning of the season no
watering may be necessary. However, in summer months as the loose soil looses moisture at
faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain
the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5
to 6 percent watering by weight, requirement of water for 435 cum of embankment will be about
about 5 tanker loads of 8000 ltrs each.
Deploy 8000 ltr capacity water tanker for 5 hours for watering before rolling.
Deploy 5 hp pump for 2.5 hours.
5. Compaction:
Soil collected for embankment layer gets compacted to some extent during levelling by dozer.
Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density
control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining
adjacent to the breached portion a combination of 8 to 10 passes of road roller followed by
2 to 4 passes of dozer is considered for compaction and roughening the top surface for laying
next layer.
Effective length of roller drum : 1.50 mSpeed of roller per hour : 3.0 km
Thickness of layer : 0.3 m
Number of roller passes : 9 Nos
Output of road roller / hr with 50 min / hr working and 70 % effinciancy:
( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 say : 88 cum
Time for rolling 504 cum soil in embankment layer say : 6 hours
Effective width of dozer track : 1.00 m
Speed of dozer per hour : 4.0 km
Thickness of layer : 0.3 m
Number of dozer passes : 3 Nos
Output of dozer / hr with 50 min / hr working and 70 % effinciancy:
( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 say : 230 cum
Time for rolling 504 cum soil in embankment layer say : 2 hours
Deploy road roller for 6 hours and dozer for 2 hours for compaction.
6. Sorting out / sectioning / labour for testing etc :
Assume 2 heavy and 2 light mazdoors.
RATE ANALYSIS UNIT : 435.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00Add for Contractor's Overheads @ 5% Rs: 0.00
Add Royalty charges on 696 t soil @ Rs: 10.00 / tonne Rs: 6960.00
Total cost of Materials : Rs: 6960.00
Perticulars Quantity Rate
in Rs.
64
-
8/13/2019 Data Rates-P & M Works-4
6/21
DATA RATES- P AND M WORKS
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Angle dozer 90 hp Hour 5.00 1154.00 5770.00
Fuel / Energy charges Hour 5.00 423.00 2115.00
2 Shovel 0.50 cum capacity Hour 8.00 725.00 5800.00
Fuel / Energy charges Hour 8.00 330.00 2640.00
3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 271.00 8672.00
Fuel / Energy charges Hour 32.00 208.00 6656.00
4 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50
Fuel / Energy charges Hour 2.50 55.00 137.50
5 Water tanker 8000 ltr Hour 5.00 268.00 1340.00
Fuel / Energy charges Hour 5.00 208.00 1040.00
6 Road roller 10 tonne ( diesel ) Hour 6.00 228.00 1368.00
Fuel / Energy charges Hour 6.00 495.00 2970.00
7 Sundries LS 2.00 30.00 60.00
Total Rs: 38586.00
Add for small Tools and Plants @ 1% Rs: 385.86
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 1561.85
Add for Contractor's Overheads @ 5% Rs: 1929.30
Total hire charges of Machinery : Rs: 42463.01
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Dozer Hour 5.00 77.50 387.50
2 Crew for Shovel Hour 8.00 77.50 620.00
3 Crew for Tipper Hour 32.00 56.70 1814.40
4 Crew for Pump Hour 2.50 35.80 89.50
5 Crew for Water tanker Hour 5.00 56.70 283.50
6 Crew for Roller Hour 6.00 72.00 432.00
7 Maistry Day 2.00 141.50 283.00
8 Heavy mazdoor Day 2.00 132.00 264.00
9 Light mazdoor Day 2.00 130.50 261.00
Total Rs: 4434.90
Add for small Tools and Plants @ 1% Rs: 44.35
Add for Contractor's Profit @ 10% Rs: 443.49
Add for hidden cost on Labour @ 15% Rs: 665.24
Add for Contractor's Overheads @ 5% Rs: 221.75
Total cost of Labour : Rs: 5809.72
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 6960.00
B. Hire charges of Machinery Rs: 42463.01
C. Cost of Labour Rs: 5809.72
TOTAL Rs: 55232.73
Add for enabling works @ 1.00% Rs: 552.33
Total cost for 435.00 cum Rs: 55785.06Rate per cum Rs: 128.00
Rate approved per cum Rs: 128.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 26
Quantity Rate
in Rs.
Quantity Rate
in Rs.
Description
Description
65
-
8/13/2019 Data Rates-P & M Works-4
7/21
DATA RATES- P AND M WORKS
ITEM: Repairing rain cuts/ resectioning canal slopes to required lines and grades as directed using
available soil including dressing, clod breaking, packing, tamping etc., complete with all leads
and lifts.
DATA:1heavy and 1 light mazdoor assumed for repairing rain cuts in 250 sqm canal slope per day.
Consider 1000 sqm canal slope for maintanance for rate analysis.
1. Requirement of materials:
Available soil from canal side.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Maistry : 1 No.
Heavy mazdoor : 4 Nos.
Light mazdoor : 4 Nos.
RATE ANALYSIS UNIT : 1000.00 sqm
A. MATERIALS:
Sl No Unit Amount
in Rs.1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total cost of Materials : Rs: 0.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Maistry Day 1.00 141.50 141.50
2 Heavy mazdoor Day 4.00 132.00 528.00
3 Light mazdoor Day 4.00 130.50 522.00
Total Rs: 1191.50
Add for small Tools and Plants @ 1% Rs: 11.92Contd
C. LABOUR ( Contd ) :
Sl No Unit Amount
Perticulars
Description
Description
Description
in Rs.
in Rs.
Quantity Rate
Quantity Rate
Quantity Rate
in Rs.
Quantity Rate
66
-
8/13/2019 Data Rates-P & M Works-4
8/21
DATA RATES- P AND M WORKS
in Rs.
Contd
Add for Contractor's Profit @ 10% Rs: 119.15
Add for hidden cost on Labour @ 15% Rs: 178.73
Add for Contractor's Overheads @ 5% Rs: 59.58
Total cost of Labour : Rs: 1560.87
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1560.87
TOTAL Rs: 1560.87
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 1000.00 sqm Rs: 1560.87
Rate per sqm Rs: 1.55
Rate approved per sqm Rs: 1.55
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 27
ITEM: Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing
including chiselling and removing leached lime deposit and disposing off all the waste materialout side adits in specified location etc., complete with all leads and lifts.
DATA:Consider 100 Rm of gallery for cleaning:
1. Requirement of materials:
Wire brush : 5 Nos
Coir brush : 10 Nos.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Chiseller Cl II : 2 Nos.
Heavy mazdoor : 4 Nos.
Light mazdoors : 2 Nos.
RATE ANALYSIS UNIT : 100.00 Rm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Wire brush Each 5.00 30.00 150.00
2 Coir brush Each 10.00 20.00 200.00
3 Sundries ( brooms, gloves etc ) LS 2.00 30.00 60.00
Total Rs: 410.00
Add for small Tools and Plants @ 1% Rs: 4.10
Add for Contractor's Profit @ 10% Rs: 41.00
Add for Contractor's Overheads @ 5% Rs: 20.50
Total cost of Materials : Rs: 475.60
B. MACHINERY:
Sl No Unit Amount
in Rs.
in Rs.
Perticulars
Quantity Rate
Quantity Rate
in Rs.
in Rs.
Description
67
-
8/13/2019 Data Rates-P & M Works-4
9/21
DATA RATES- P AND M WORKS
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Chiseller Cl II Day 2.00 146.00 292.00
2 Heavy mazdoor Day 4.00 132.00 528.00
3 Light mazdoor Day 2.00 130.50 261.00
Total Rs: 1081.00
Add for small Tools and Plants @ 1% Rs: 10.81
Add for Contractor's Profit @ 10% Rs: 108.10
Add for hidden cost on Labour @ 15% Rs: 162.15
Add for Contractor's Overheads @ 5% Rs: 54.05
Total cost of Labour : Rs: 1416.11
ABSTRACT:
A. Cost of Materials Rs: 475.60
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1416.11
TOTAL Rs: 1891.71
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 Rm Rs: 1891.71
Rate per Rm Rs: 19.00
Rate approved per Rm Rs: 19.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 28
ITEM: Cleaning dam parapetinner face and top using oxalic acid and water by scrubbing / brushing
and washing to remove all surface coatings etc., complete .
DATA:Consider 100 Rm of parapet for cleaning:
Area to be cleaned considering 1.25 sqm per Rm length : 125 sqm
1. Requirement of materials:
Oxalic acid @ 25 sqm / ltr : 5 ltr
Wire brush : 5 Nos
Coir brush : 10 Nos.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Heavy mazdoor : 5 Nos.
Light mazdoors : 1 No.
RATE ANALYSIS UNIT : 100.00 Rm
A. MATERIALS:
Sl No Unit Amount
in Rs.in Rs.
Quantity Rate
in Rs.
Quantity Rate
Description
Perticulars
68
-
8/13/2019 Data Rates-P & M Works-4
10/21
DATA RATES- P AND M WORKS
1 Oxalic acid ltr 5.00 60.00 300.00
2 Wire brush Each 5.00 30.00 150.00
3 Coir brush Each 10.00 20.00 200.00
4 Sundries ( brooms, gloves etc ) LS 2.00 30.00 60.00
Total Rs: 710.00
Add for small Tools and Plants @ 1% Rs: 7.10
Add for Contractor's Profit @ 10% Rs: 71.00
Add for Contractor's Overheads @ 5% Rs: 35.50
Total cost of Materials : Rs: 823.60
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Heavy mazdoor Day 5.00 132.00 660.00
2 Light mazdoor Day 1.00 130.50 130.50
Total Rs: 790.50
Add for small Tools and Plants @ 1% Rs: 7.91
Add for Contractor's Profit @ 10% Rs: 79.05
Add for hidden cost on Labour @ 15% Rs: 118.58
Add for Contractor's Overheads @ 5% Rs: 39.53
Total cost of Labour : Rs: 1035.56
ABSTRACT:
A. Cost of Materials Rs: 823.60
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1035.56
TOTAL Rs: 1859.16
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 Rm Rs: 1859.16
Rate per Rm Rs: 19.00
Rate approved per Rm Rs: 19.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 29
ITEM: Cleaning gates / hoists / embedded partsfor re-painting by removing rust, old paint, grease
etc., by using wire brush,scrubber, rust remover and applying a coat of rust inhibitive
compound etc., complete.
DATA:Consider 100 sqm area for cleaning:
Description
Description
in Rs.
Quantity Rate
Quantity Rate
in Rs.
69
-
8/13/2019 Data Rates-P & M Works-4
11/21
DATA RATES- P AND M WORKS
1. Requirement of materials:
Wire brush : 10 Nos
Rust remover / Inhibiter : 2 ltrs
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Painter Class-II : 5 Nos.
Heavy mazdoor : 6 Nos.
RATE ANALYSIS UNIT : 100.00 sqm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Wire brush Each 10.00 30.00 300.00
2 Rust cleaner / inhibitor ltr 2.00 240.00 480.00
3 Sundries ( sand papers etc ) LS 4.00 30.00 120.00
Total Rs: 900.00
Add for small Tools and Plants @ 1% Rs: 9.00
Add for Contractor's Profit @ 10% Rs: 90.00
Add for Contractor's Overheads @ 5% Rs: 45.00
Add for scaffolding / ladder etc @ 10% Rs: 90.00Total cost of Materials : Rs: 1134.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Painter Class-II Day 5.00 141.50 707.50
2 Heavy mazdoor Day 6.00 132.00 792.00
Total Rs: 1499.50
Add for small Tools and Plants @ 1% Rs: 15.00
Add for Contractor's Profit @ 10% Rs: 149.95
Add for hidden cost on Labour @ 15% Rs: 224.93
Add for Contractor's Overheads @ 5% Rs: 74.98
Total cost of Labour : Rs: 1964.35
ABSTRACT:
A. Cost of Materials Rs: 1134.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1964.35
TOTAL Rs: 3098.35
Add for enabling works @ 0.00% Rs: 0.00
Perticulars
Quantity Rate
Quantity Rate
in Rs.
in Rs.
Quantity Rate
in Rs.
Description
Description
70
-
8/13/2019 Data Rates-P & M Works-4
12/21
DATA RATES- P AND M WORKS
Total cost for 100.00 sqm Rs: 3098.35
Rate per sqm Rs: 31.00
Rate approved per sqm Rs: 31.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 30
ITEM: Cleaning gates / hoists / embedded parts to expose fresh metal surface for repainting by
sand blastingmethod as per specifications including cost of all materials, labour, machinery,
scaffolding, applying a coat of rust inhibitive etc., complete with initial lead for sand upto
1 km and all lifts.
DATA:Consider 100 sqm area for cleaning:
1. Requirement of materials :
Sand of gradation 2mm to 1mm @ 0.10 cum / sqm
Approximately 2 cum natural river sand yeilds 1 cum of sand blasting grade sand after seiving
in 2mm and 1 mm sieves.
Allowing 50 % extra for projections, the actual area of sand blasting : 150 sqm
Requirement of processed sand ( 150 x 0.10 ) : 15.00 cum
Requirement of natural river sand ( 15.00 x 2 ) : 30.00 cum
2. Requirement of machinery :
Output of sand blasting per hour : 20 to 25 sqm
Considering 50 minutes per hour working,
Requirement of 7 cmm compressor ( 150 x 60 / 50 / 22.5 ) : 8 hours
Requirement of sand blasting equipment : 8 hours
3. Requirement of workforce ( Other than machinery crew ) :
Heavy mazdoor:
For seiving sand : 6 Nos.
For loading sand blast drum : 2 Nos.
For assisting sand blaster : 1 No.
Light mazdoor:
For seiving sand : 4 Nos.
For cleaning / collection of rebound sand and other works : 2 Nos.
4. Use rate of materials :
Cost of 25 mm dia 50 m air hose @ Rs: 150.00 / Rm Rs: 7500.00
Life of air hose : 800 hours
Use rate of air hose per hour ( cost / life ) Rs: 9.38
Cost of sand blast gun nozzle @ Rs: 312.00 / Each Rs: 312.00
Life of sand blast gun nozzle : 200 hours
Use rate of sand blast gun nozzle per hour ( cost / life ) : 1.56
RATE ANALYSIS UNIT : 100.00 sqm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Natural river sand ( unscreened ) cum 30.00 154.00 4620.00
2 Use rate of air hose Hour 8.00 9.38 75.00
3 Use rate of sand blast gun nozzle Hour 8.00 1.56 12.48
Perticulars
in Rs.
Quantity Rate
71
-
8/13/2019 Data Rates-P & M Works-4
13/21
DATA RATES- P AND M WORKS
4 Sundries( Rust inhibitive, Seive etc ) LS 5.00 30.00 150.00
Total Rs: 4857.48
Add for small Tools and Plants @ 1% Rs: 48.57
Add for Contractor's Profit @ 10% Rs: 485.75
Add for Contractor's Overheads @ 5% Rs: 242.87
Add for scaffolding / ladder etc @ 10% Rs: 485.75
Total cost of Materials : Rs: 6120.42
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Air compressor 7 cmm diesel Hour 8.00 166.00 1328.00
Fuel / Energy charges Hour 8.00 495.00 3960.00
2 Sand blasting equipment Hour 8.00 84.00 672.00
Fuel / Energy charges Hour 8.00 9.00 72.00
Total Rs: 6032.00
Add for small Tools and Plants @ 1% Rs: 60.32
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 403.20
Add for Contractor's Overheads @ 5% Rs: 301.60
Total hire charges of Machinery : Rs: 6797.12
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Air compressor Hour 8.00 72.10 576.80
2 Crew for Sand blasting equipment Hour 8.00 74.40 595.20
3 Heavy mazdoor Day 9.00 132.00 1188.00
4 Light mazdoor Day 6.00 130.50 783.00
Total Rs: 3143.00
Add for small Tools and Plants @ 1% Rs: 31.43
Add for Contractor's Profit @ 10% Rs: 314.30
Add for hidden cost on Labour @ 15% Rs: 471.45
Add for Contractor's Overheads @ 5% Rs: 157.15
Total cost of Labour : Rs: 4117.33
ABSTRACT:
A. Cost of Materials Rs: 6120.42
B. Hire charges of Machinery Rs: 6797.12
C. Cost of Labour Rs: 4117.33
TOTAL Rs: 17034.87
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 sqm Rs: 17034.87
Rate per sqm Rs: 170.00
Rate approved per sqm Rs: 170.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 31
ITEM: Providing two coats of painting to hoist supporting structures / hoists / moving gantry
cranes / railings etc., with zinc chromate alluminium primer paint of approved quality
including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc.,
complete withall leads and all lifts.
DATA:Consider 100 sqm area for painting:
Description
Description
in Rs.
Quantity Rate
Quantity Rate
in Rs.
72
-
8/13/2019 Data Rates-P & M Works-4
14/21
DATA RATES- P AND M WORKS
1. Requirement of materials :
Coverage of paints for each coat : 12 sqm / ltr
Qty of paint 2 coats 100 sqm with 2 % wastage( 100x2x1.02/ 12 ) : 17 ltrs
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.
Painter Class-II for painting @ 15 sqm / day : 7 Nos.
Heavy mazdoor for assisting painter for cleaning and painting : 5 Nos.
RATE ANALYSIS UNIT : 100.00 sqm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Zinc chromate, alluminium primer ltr 17.00 140.00 2380.00
2 Sundries LS 2.00 30.00 60.00
Total Rs: 2440.00
Add for small Tools and Plants @ 1% Rs: 24.40
Add for Contractor's Profit @ 10% Rs: 244.00
Add for Contractor's Overheads @ 5% Rs: 122.00
Add for scaffolding / ladder etc @ 2% Rs: 48.80Total cost of Materials : Rs: 2879.20
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Painter Class-II Day 10.00 141.50 1415.00
2 Heavy mazdoor Day 5.00 132.00 660.00
Total Rs: 2075.00
Add for small Tools and Plants @ 1% Rs: 20.75
Contd
C. LABOUR ( Contd ) :Sl No Unit Amount
in Rs.
Contd
Add for Contractor's Profit @ 10% Rs: 207.50
Add for hidden cost on Labour @ 15% Rs: 311.25
Add for Contractor's Overheads @ 5% Rs: 103.75
Total cost of Labour : Rs: 2718.25
Description Quantity Rate
in Rs.
Perticulars
Quantity Rate
Quantity Rate
in Rs.
in Rs.
Quantity Rate
in Rs.
Description
Description
73
-
8/13/2019 Data Rates-P & M Works-4
15/21
DATA RATES- P AND M WORKS
ABSTRACT:
A. Cost of Materials Rs: 2879.20
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2718.25
TOTAL Rs: 5597.45
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 sqm Rs: 5597.45
Rate per sqm Rs: 56.00
Rate approved per sqm Rs: 56.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 32
ITEM: Providing two coats of painting100 micron dry film thickness each coat to embedded parts
/ gates with cold appliedcoal tar epoxy paint of approved quality including removing rust,
cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts.
DATA:Consider 100 sqm area for painting:
1. Requirement of materials :
Coverage of paints for each coat : 6 sqm / ltr Qty of paint 100 sqm 2 coats with 2 % wastage(100 x 2 x 1.02 / 6) : 34.00 ltrs
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.
Painter Class-II for painting @ 10 sqm / day : 10 Nos.
Heavy mazdoor for assisting painter for cleaning and painting : 6 Nos.
RATE ANALYSIS UNIT : 100.00 sqm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Coal tar epoxy paint ltr 34.00 208.00 7072.00
2 Sundries ( rust remover / brush etc ) LS 4.00 30.00 120.00
Total Rs: 7192.00
Add for small Tools and Plants @ 1% Rs: 71.92
Add for Contractor's Profit @ 10% Rs: 719.20
Add for Contractor's Overheads @ 5% Rs: 359.60
Add for scaffolding / ladder etc @ 5% Rs: 359.60
Total cost of Materials : Rs: 8702.32
B. MACHINERY:
Sl No Unit Amountin Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
Description
in Rs.
in Rs.Quantity Rate
Quantity RatePerticulars
74
-
8/13/2019 Data Rates-P & M Works-4
16/21
DATA RATES- P AND M WORKS
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Painter Class-II Day 13.00 141.50 1839.50
2 Heavy mazdoor Day 6.00 132.00 792.00
Total Rs: 2631.50
Add for small Tools and Plants @ 1% Rs: 26.32
Add for Contractor's Profit @ 10% Rs: 263.15
Add for hidden cost on Labour @ 15% Rs: 394.73
Add for Contractor's Overheads @ 5% Rs: 131.58
Total cost of Labour : Rs: 3447.27
ABSTRACT:
A. Cost of Materials Rs: 8702.32
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3447.27
TOTAL Rs: 12149.59
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 sqm Rs: 12149.59
Rate per sqm Rs: 121.00Rate approved per sqm Rs: 121.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 33
ITEM: Providing two coats of painting to hoist supporting structures / hoists / moving gantry
cranes / railings etc., with first quality synthetic enemel paint of approved colour
including cleaning surface, cost of all materials, labour, scaffolding etc., complete with
all leads and all lifts.
DATA:Consider 100 sqm area for painting:
1. Requirement of materials :
Coverage of paints for each coat : 12 sqm / ltr
Qty of paint 2 coats 100 sqm with 2 % wastage( 100x 2x1.02 /12 ) : 17 ltrs
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Painter Class-II for preparing surface @ 30 to 40 sqm / day : 3 Nos.
Painter Class-II for painting @ 15 sqm / day : 7 Nos.
Heavy mazdoor for assisting painter for cleaning and painting : 5 Nos.
RATE ANALYSIS UNIT : 100.00 sqm
A. MATERIALS:
Sl No Unit Amountin Rs.
1 Synthetic enamel paint ( 1st quality ) ltr 17.00 176.00 2992.00
2 Sundries LS 2.00 30.00 60.00
Total Rs: 3052.00
Add for small Tools and Plants @ 1% Rs: 30.52
Add for Contractor's Profit @ 10% Rs: 305.20
Add for Contractor's Overheads @ 5% Rs: 152.60
Add for scaffolding / ladder etc @ 2% Rs: 61.04
Perticulars
Description Quantity Rate
in Rs.
Quantity Ratein Rs.
75
-
8/13/2019 Data Rates-P & M Works-4
17/21
DATA RATES- P AND M WORKS
Total cost of Materials : Rs: 3601.36
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Painter Class-II Day 10.00 141.50 1415.00
2 Heavy mazdoor Day 5.00 132.00 660.00
Total Rs: 2075.00
Add for small Tools and Plants @ 1% Rs: 20.75
Add for Contractor's Profit @ 10% Rs: 207.50Add for hidden cost on Labour @ 15% Rs: 311.25
Add for Contractor's Overheads @ 5% Rs: 103.75
Total cost of Labour : Rs: 2718.25
ABSTRACT:
A. Cost of Materials Rs: 3601.36
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2718.25
TOTAL Rs: 6319.61
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 sqm Rs: 6319.61
Rate per sqm Rs: 63.00
Rate approved per sqm Rs: 63.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 34
ITEM: Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initiallead upto 50 m and all lifts.
DATA:1 heavy and 1 light mazdoor assumed for removing 5 cum dry silt per day.
Consider removal of 10 cum dry silt for rate analysis.1. Requirement of materials :
No materials required.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Heavy mazdoor : 2 Nos.
Light mazdoor : 2 Nos.
Quantity Rate
in Rs.
Quantity Rate
in Rs.
Description
Description
76
-
8/13/2019 Data Rates-P & M Works-4
18/21
DATA RATES- P AND M WORKS
RATE ANALYSIS UNIT : 10.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total cost of Materials : Rs: 0.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Heavy mazdoor Day 2.00 132.00 264.00
2 Light mazdoor Day 2.00 130.50 261.00
Total Rs: 525.00
Add for small Tools and Plants @ 1% Rs: 5.25
Add for Contractor's Profit @ 10% Rs: 52.50
Add for hidden cost on Labour @ 15% Rs: 78.75
Add for Contractor's Overheads @ 5% Rs: 26.25
Total cost of Labour : Rs: 687.75
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 687.75
TOTAL Rs: 687.75
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 10.00 cum Rs: 687.75
Rate per cum Rs: 69.00Rate approved per cum Rs: 69.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 35
ITEM: Excavation and removal of siltor silt mixed with sand inslussy condition from canal bed
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
Perticulars
Description
Description
in Rs.
Rate
Quantity Rate
Quantity Rate
in Rs.
in Rs.
Quantity
77
-
8/13/2019 Data Rates-P & M Works-4
19/21
DATA RATES- P AND M WORKS
DATA:Excavated silt in slussy condition can be disposed off in single operation without heaping silt in
mortar pans or by collecting and rehandling after draining out water.
Output of 1 heavy and 2 light mazdoor assumed at 6 cum per day.
Consider removal of 12 cum silt in slussy condition for rate analysis.
1. Requirement of materials :
No materials required.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Heavy mazdoor : 2 Nos.
Light mazdoor : 4 Nos.
RATE ANALYSIS UNIT : 12.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total cost of Materials : Rs: 0.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Heavy mazdoor Day 2.00 132.00 264.00
2 Light mazdoor Day 4.00 130.50 522.00
Total Rs: 786.00Add for small Tools and Plants @ 1% Rs: 7.86
Add for Contractor's Profit @ 10% Rs: 78.60
Add for hidden cost on Labour @ 15% Rs: 117.90
Add for Contractor's Overheads @ 5% Rs: 39.30
Total cost of Labour : Rs: 1029.66
ABSTRACT:
A. Cost of Materials Rs: 0.00
Description
Perticulars
Quantity Rate
Quantity Rate
in Rs.
in Rs.
Quantity Rate
in Rs.
Description
78
-
8/13/2019 Data Rates-P & M Works-4
20/21
DATA RATES- P AND M WORKS
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1029.66
TOTAL Rs: 1029.66
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 12.00 cum Rs: 1029.66
Rate per cum Rs: 86.00
Rate approved per cum Rs: 86.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 36.a
ITEM: Removing and hauling all kinds of soil / soft rock including boulders upto 0.6 m diameter
slipped due to natural causes and disposing off the same in specified dump area or as
directed including cost of all materials, machinery, labour, rampways and all other ancillary
operations etc., complete with initial lead upto 50 m and lift upto 1.5 m.
Note: The rate under this item is for unit quantity of soil / soft rock in slipped condition.
The rate under this item shall be adopted where the material can be disposed off within 50 m
lead or where the slipped zone is inaccessible for disposal of material by mechanical mode.
The wieghted average rate applicable to entire quantity based on rates provided under items
36.a and 37.a may be considered where the slipped material consists of mixture of soil / soft
rock and hard rock.
DATA:Consider removal of 100 cum slipped soil / soft rock for rate analysis.
The quantity assumed for analysis is the volume of soil / soft rock in slipped condition.
Therefore, the measurement for soil / soft rock shall be for the volume in slipped condition and
not for the original in-situ condition.
Average output of 1 heavy and 1 light mazdoor assumed at 6 cum / day for removing muck.
1. Requirement of materials :
No materials required.
2. Requirement of machinery :
No machinery proposed for the work.
3. Requirement of workforce :
Maistry : 0.5 No.
Heavy mazdoor : 17 Nos.
Light mazdoor : 17 Nos.
RATE ANALYSIS UNIT : 100.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total cost of Materials : Rs: 0.00
B. MACHINERY:
Sl No Unit Amount
in Rs.
Description
Rate
in Rs.
in Rs.
Quantity Rate
QuantityPerticulars
79
-
8/13/2019 Data Rates-P & M Works-4
21/21
DATA RATES- P AND M WORKS
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total Rs: 0.00
Add for small Tools and Plants @ 1% Rs: 0.00
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00
Add for Contractor's Overheads @ 5% Rs: 0.00
Total hire charges of Machinery : Rs: 0.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Maistry Day 0.50 141.50 70.75
2 Heavy mazdoor Day 17.00 132.00 2244.00
3 Light mazdoor Day 17.00 130.50 2218.50
Total Rs: 4533.25
Add for small Tools and Plants @ 1% Rs: 45.33
Add for Contractor's Profit @ 10% Rs: 453.33
Add for hidden cost on Labour @ 15% Rs: 679.99
Add for Contractor's Overheads @ 5% Rs: 226.66
Total cost of Labour : Rs: 5938.56
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 5938.56
TOTAL Rs: 5938.56
Add for enabling works @ 0.00% Rs: 0.00
Total cost for 100.00 cum Rs: 5938.56
Rate per cum Rs: 59.00
Rate approved per cum Rs: 59.00
SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 36.b
ITEM: Removing and hauling all kinds of soil / soft rock including boulders upto 0.6 m diameter
slipped due to natural geological causes and disposing off the same in specified dump
area or as directed including costof all materials, machinery, labour, rampways and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.
Note: The rate under this item is for unit quantity of soil / soft rock in slipped condition.
The wieghted average rate applicable to entire quantity based on rates provided under items
36.b and 37.b may be considered where the slipped material consists of mixture of soil / soft
rock and hard rock.
DATA:The quantity assumed for analysis is the volume of soil / soft rock in slipped condition.For soil / soft rock in slipped condition 10 % bulkage is assumed and further bulkage of another
10 % is asssumed on digging / loading the slipped soil / soft rock mass for disposal.
Therefore, the measurement for soil / soft rock shall be for the volume in slipped condition and
not for the original in-situ condition.
Consider 95 % quantity with 1 km lead for disposal by shovel and tipper combination.
Consider 5 % quantity ( residual muck at bed ) with 50 m lead for disposal by work force.
Capacity of shovel bucket : 0.50 cum
Capacity of shovel bucket under heaped condition : 0.58 cum
Quantity Rate
in Rs.
Description