    DAM ALLIED WORKS

    DATA:For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20

    Fine aggregate : 0.40 cum. Cement : 247 kg Super plasticizer : 0.75 ltr

    For 1 cum plum CC :- Coarse aggregates : 0.765 cum Blending ratio : 50 :30 : 20

    Fine aggregate : 0.34 cum. Super plasticizer : 0.65 ltr

    Cement : 210 kg.

    Plums of size 150 to 80 mm : 0.24 cum

    Wastage : 1 % for cement and 2 % for coarse / fine aggregates & plums.

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 40-20 mm CA ( 0.091 ) cum : 3.50 min

    Batching 20-10 mm & 10 mm below CA parellel activity : ---

    Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 minMixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 5.00 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 5 ) : 80 mixes

    Output of CC for 80 mixes ( 80 x 50 / 247 ) say : 16.20 cum

    Quantity of plum concrete for sinking 15 % plums ( 16.20 / 0.85 ) : 19.00 cum

    Qty of plums ( solid volume ) in plum concrete ( 19.00 x 0.15 ) : 2.85 cum

    Consider 19.00 cum plum concrete for rate analysis.

    1. Requirement of materials:

    Cement for mix with 1 % wastage ( 19 x 210 x 1.01 ) : 4030 kg

    Cement for incidental works @ 3 kg / cum ( 19 x 3 ) : 57 kg

    Coarse aggregate 40-20 mm size range ( 19 x 0.765 x 0.5 x 1.02 ) : 7.45 cum

    Coarse aggregate 20-10 mm size range ( 19 x 0.765 x 0.3 x 1.02 ) : 4.45 cum

    Coarse aggregate 10-4.75 mm size ( 19 x 0.765 x 0.2 x 1.02 ) : 2.95 cum

    Qty of plums ( loose volume) with 2 % wastage ( 19 x 0.24 x 1.02 ) : 4.65 cum

    Fine aggregate ( 19 x 0.34 x 1.02 ) : 6.60 cum

    Super plasticiser ( 19 x 0.65 x 1.02 ) : 12.6 ltrs

    2. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    3. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Requirement of shuttering for plain concrete works is assumed at 1 sqm / cum of concrete.

    Shuttering @ 1.00 sqm per cum of concrete ( 19 x 1 ) : 19.00 sqm

    Scaffolding / supports etc @ 15 percent of cost of shuttering.

    4. Requirement of workforce ( other than machinery crew ) :Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 40-20 mm CA Heavy mazdoors : 3 Nos.

    Batching 20-10 mm & 10 mm below CA Heavy mazdoors : 3 Nos.

    Batching fine aggregate Heavy mazdoors : 3 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 4 Nos.

    Light mazdoors : 16 Nos.

    Conveying plums Heavy mazdoors : 1 Nos.

    60

  • 8/13/2019 Data Rates-Dam Works-Part 4

    2/21

    DAM ALLIED WORKS

    Light mazdoors : 2 Nos.

    Laying concrete and plums Mason : 1 No.

    Heavy mazdoors : 4 Nos.

    Washing / cleaning / curing etc Light mazdoors : 1 No.

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.

    5. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    6. Use rate of materials :

    Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07

    RATE ANALYSIS UNIT : 19.00 cum

    A. MATERIALS:Sl No Unit Amount

    in Rs.

    1 Cement for mix with 1 % wastage kg 4030.00 4.00 16120.00

    Cement for incidentals @ 3 kg/cum PC kg 57.00 4.00 228.00

    2 Coarse aggregate 40-20 mm cum 7.45 381.00 2838.45

    Coarse aggregate 20-10 mm cum 4.45 520.00 2314.00

    Coarse aggregate 10 mm below cum 2.95 669.00 1973.55

    3 Plums of size 150 to 80 mm cum 4.65 240.00 1116.00

    4 Fine aggregate ( screened ) cum 6.60 199.00 1313.40

    5 Super Plasticizer ltr 12.60 75.00 945.00

    6 Use rate of shuttering for 40 uses sqm 19.00 151.07 2870.24

    7 Scaffolding @ 15 % of shuttering 430.54

    Total Rs: 30149.18

    Add for small Tools and Plants @ 1% Rs: 301.49

    Add for Contractor's Profit @ 10% Rs: 3014.92

    Add for Contractor's Overheads @ 5% Rs: 1507.46

    Add Royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add Royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 34973.04

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 10 hp pump ( ele ) Hour 1.00 5.00 5.00

    Fuel / Energy charges Hour 1.00 50.00 50.003 Needle vibrator 60 mm dia ( ele ) Hour 8.00 8.00 64.00

    Fuel / Energy charges Hour 8.00 8.00 64.00

    4 Sundries LS 1.00 30.00 30.00

    Total Rs: 717.00

    Add for small Tools and Plants @ 1% Rs: 7.17

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 34.40

    Add for Contractor's Overheads @ 5% Rs: 35.85

    Total hire charges of Machinery : Rs: 794.42

    Perticulars

    Description Quantity Rate

    Quantity

    in Rs.

    Rate

    in Rs.

    61

  • 8/13/2019 Data Rates-Dam Works-Part 4

    3/21

    DAM ALLIED WORKS

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 1.00 26.90 26.90

    3 Crew for Needle vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 1.00 159.00 159.00

    5 Maistry Day 1.00 141.50 141.50

    6 Heavy mazdoor

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 9.00 132.00 1188.00

    for loading mortar pans Day 4.00 132.00 528.00

    for loading plums Day 1.00 132.00 132.00

    for laying concrete and plums Day 4.00 132.00 528.00

    7 Light mazdoorfor conveying concrete Day 16.00 130.50 2088.00

    for conveying plums Day 2.00 130.50 261.00

    for cleaning / washing / curing Day 1.00 130.50 130.50

    8 Labour for shuttering sqm 19.00 33.17 630.14

    Labour for scaffolding @ 15 % 189.04

    Total Rs: 7297.28

    Add for small Tools and Plants @ 1% Rs: 72.97

    Add for Contractor's Profit @ 10% Rs: 729.73

    Add for hidden cost on Labour @ 15% Rs: 1094.59

    Add for additional hidden cost on Labour @ 5% Rs: 364.86

    Add for Contractor's Overheads @ 5% Rs: 364.86

    Total cost of Labour : Rs: 9924.29

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 34973.04

    B. Hire charges of Machinery Rs: 794.42

    C. Cost of Labour Rs: 9924.29

    Total Rs: 45691.76

    Add for enabling works @ 1.40% Rs: 639.68

    46331.44

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 4087 kg @ Rs: 129.10 / tonne Rs: 527.63

    C A and plums 19.5 cum @ Rs: 121.90 / cum Rs: 2377.05

    Fine aggregates 6.6 cum @ Rs: 84.90 / cum Rs: 560.34

    Total cost for 19.00 cum Rs: 49796.46

    Rate per cum Rs: 2621.00

    Rate approved per cum Rs: 2621.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 18

    ITEM: Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than

    10 N / sq mm ) grade cement concrete using 40 mm down sizeapproved, clean, hard, graded

    aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,

    cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete

    Description Quantity Rate

    in Rs.

    TOTAL Rs:

    62

  • 8/13/2019 Data Rates-Dam Works-Part 4

    4/21

    DAM ALLIED WORKS

    for plain concreteworks with initial lead upto 1 km and all lifts. ( Cement content 220 kg /

    cum with use of super plasticiser )

    DATA:For 1 cum CC :- Coarse aggregates : 0.90 cum. Blending ratio : 50 :30 : 20

    Fine aggregate : 0.40 cum. Cement : 220 kg Super plasticizer : 0.70 ltr

    Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 40-20 mm CA ( 0.102 cum ) : 4.00 min

    Batching 20-10 mm & 10 mm below CA parellel activity : ---

    Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 minCycle time for batching / mixing / unloading 1 mix : 5.50 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) : 73 mixes

    Output of CC for 73 mixes ( 73 x 50 / 220 ) say : 16.60 cum

    Consider 16.60 cum concrete for rate analysis.

    1. Requirement of materials:

    Cement for mix with 1 % wastage ( 16.6 x 220 x 1.01 ) : 3689 kg

    Cement for incidental works @ 3 kg / cum ( 16.6 x 3 ) : 50 kg

    Coarse aggregate 40-20 mm size range ( 16.6 x 0.9 x 0.5 x 1.02 ) : 7.60 cum

    Coarse aggregate 20-10 mm size range ( 16.6 x 0.9 x 0.3 x 1.02 ) : 4.55 cum

    Coarse aggregate 10-4.75 mm size ( 16.6 x 0.9 x 0.2 x 1.02 ) : 3.05 cum

    Fine aggregate ( 16.6 x 0.4 x 1.02 ) : 6.75 cum

    Super plasticiser ( 16.6 x 0.7 x 1.02 ) : 11.90 ltrs

    2. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    3. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Requirement of shuttering for concrete works is assumed at 1 sqm / cum of concrete.

    Shuttering @ 1.00 sqm per cum of concrete ( 16.6 x 1 ) : 16.60 sqm

    Scaffolding / supports etc @ 15 percent of cost of shuttering.

    4. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 40-20 mm CA Heavy mazdoors : 3 Nos.

    Batching 20-10 mm & 10 mm below CA Heavy mazdoors : 3 Nos.

    Batching fine aggregate Heavy mazdoors : 3 Nos.

    Batching cement Heavy mazdoors : 2 Nos.Remixing and conveying concrete Heavy mazdoors : 4 Nos.

    Light mazdoors : 17 Nos.

    Laying concrete Mason : 1 No.

    Heavy mazdoors : 3 Nos.

    Washing / cleaning / curing etc Light mazdoors : 1 No.

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.

    63

  • 8/13/2019 Data Rates-Dam Works-Part 4

    5/21

    DAM ALLIED WORKS

    5. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    6. Use rate of materials :

    Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07

    RATE ANALYSIS UNIT : 16.60 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement for mix with 1% wastage kg 3689.00 4.00 14756.00

    Cement for incidentals @ 3 kg/ cum kg 50.00 4.00 200.00

    2 Coarse aggregate 40-20 mm cum 7.60 381.00 2895.60

    Coarse aggregate 20-10 mm cum 4.55 520.00 2366.00

    Coarse aggregate 10 mm below cum 3.05 669.00 2040.45

    3 Fine aggregate ( screened ) cum 6.75 199.00 1343.25

    4 Super plasticizer ltr 11.90 75.00 892.50

    5 Use rate of shuttering sqm 16.60 151.07 2507.68 6 Use rate of scaffolding @ 15 % 376.15

    Total Rs: 27377.64

    Add for small Tools and Plants @ 1% Rs: 273.78

    Add for Contractor's Profit @ 10% Rs: 2737.76

    Add for Contractor's Overheads @ 5% Rs: 1368.88

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 31758.06

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 10 hp pump ( ele ) Hour 1.00 5.00 5.00

    Fuel / Energy charges Hour 1.00 50.00 50.00

    3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00

    Fuel / Energy charges Hour 8.00 5.00 40.00

    Total Rs: 655.00

    Add for small Tools and Plants @ 1% Rs: 6.55

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00

    Add for Contractor's Overheads @ 5% Rs: 32.75

    Total hire charges of Machinery : Rs: 723.30

    C. LABOUR:

    Sl No Unit Amount

    in Rs.1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 1.00 26.90 26.90

    3 Crew for Needle vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 1.00 159.00 159.00

    Contd

    Description

    Description

    Perticulars

    in Rs.

    Quantity Rate

    in Rs.

    Quantity Rate

    Quantity Rate

    in Rs.

    64

  • 8/13/2019 Data Rates-Dam Works-Part 4

    6/21

    DAM ALLIED WORKS

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    5 Heavy mazdoor

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 9.00 132.00 1188.00

    for loading mortar pans Day 4.00 132.00 528.00

    for laying Day 3.00 132.00 396.00

    6 Light mazdoor

    for conveying concrete Day 17.00 130.50 2218.50

    for cleaning / washing / curing Day 1.00 130.50 130.50

    7 Labour cost of shuttering sqm 16.60 33.17 550.54

    8 Labour cost of scaffolding @ 15 % 82.58

    Total Rs: 6575.22

    Add for small Tools and Plants @ 1% Rs: 65.75

    Add for Contractor's Profit @ 10% Rs: 657.52

    Add for hidden cost on Labour @ 15% Rs: 986.28Add for additional hidden cost on labour @ 5% Rs: 328.76

    Add for Contractor's Overheads @ 5% Rs: 328.76

    Total cost of Labour : Rs: 8942.30

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 31758.06

    B. Hire charges of Machinery Rs: 723.30

    C. Cost of Labour Rs: 8942.30

    Total Rs: 41423.66

    Add for enabling works @ 1.40% Rs: 579.93

    42003.59

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 3739 kg @ Rs: 129.10 / tonne Rs: 482.70

    Coarse aggregates 15.2 cum @ Rs: 121.90 / cum Rs: 1852.88Fine aggregates 6.75 cum @ Rs: 84.90 / cum Rs: 573.08

    Total cost for 16.60 cum Rs: 44912.25

    Rate per cum Rs: 2706.00

    Rate approved per cum Rs: 2706.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 19

    ITEM: Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than

    15 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded

    aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,

    cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete

    for plain concreteworks with initiallead upto 1 km and all lifts. ( Cement content : 290 kg /

    cum with use of super plasticiser )

    DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35

    Fine aggregate : 0.45 cum. Super plasticizer : 0.90 ltr

    Cement : 290 kg.

    Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

    Description Quantity Rate

    in Rs.

    TOTAL Rs:

    65

  • 8/13/2019 Data Rates-Dam Works-Part 4

    7/21

    DAM ALLIED WORKS

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 20-10 mm CA ( 0.089 cum ) : 3.50 min

    Batching 10 mm below CA parellel activity : ---

    Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 5.00 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 5 ) : 80 mixes

    Output of CC for 80 mixes ( 80 x 50 / 290 ) say : 13.80 cum

    Consider 13.80 cum concrete for rate analysis.

    1. Requirement of materials:

    Cement for mix with 1 % wastage ( 13.8 x 290 x 1.01 ) : 4042 kg

    Cement for incidental works @ 3 kg / cum ( 13.8 x 3 ) : 42 kg

    Coarse aggregate 20-10 mm size range ( 13.8 x 0.8 x 0.65 x 1.02 ) : 7.30 cum

    Coarse aggregate 10-4.75 mm size ( 13.8 x 0.8 x 0.35 x 1.02 ) : 3.95 cumFine aggregate ( 13.8 x 0.45 x 1.02 ) : 6.35 cum

    Super plasticiser ( 13.8 x 0.9 x 1.02 ) : 12.70 ltrs

    2. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    3. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Requirement of shuttering for concrete works is assumed at 1 sqm / cum of concrete.

    Shuttering @ 1.00 sqm per cum of concrete ( 13.8 x 1 ) : 13.80 sqm

    Scaffolding / supports etc @ 15 percent of cost of shuttering.

    4. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 20-10 mm CA Heavy mazdoors : 3 Nos.

    Batching 10 mm below CA Heavy mazdoors : 2 Nos.

    Batching fine aggregate Heavy mazdoors : 3 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 4 Nos.

    Light mazdoors : 14 Nos.

    Laying concrete Mason : 1 No.

    Heavy mazdoors : 3 Nos.

    Washing / cleaning / curing etc Light mazdoors : 1 No.

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.

    5. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.6. Use rate of materials :

    Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07

    66

  • 8/13/2019 Data Rates-Dam Works-Part 4

    8/21

    DAM ALLIED WORKS

    RATE ANALYSIS UNIT : 13.80 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement for mix with 1% wastage kg 4042.00 4.00 16168.00

    Cement for incidentals @ 3 kg/ cum kg 42.00 4.00 168.00

    2 Coarse aggregate 20-10 mm cum 7.30 520.00 3796.00

    Coarse aggregate 10 mm below cum 3.95 669.00 2642.55

    3 Fine aggregate ( screened ) cum 6.35 199.00 1263.65

    4 Super plasticiser ltr 12.70 75.00 952.50

    5 Use rate of shuttering sqm 13.80 151.07 2084.70

    6 Use rate of scaffolding @ 15 % 312.71

    Total Rs: 27388.11

    Add for small Tools and Plants @ 1% Rs: 273.88

    Add for Contractor's Profit @ 10% Rs: 2738.81

    Add for Contractor's Overheads @ 5% Rs: 1369.41

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 31770.20

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 10 hp pump ( ele ) Hour 1.00 5.00 5.00

    Fuel / Energy charges Hour 1.00 50.00 50.00

    3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00

    Fuel / Energy charges Hour 8.00 5.00 40.00

    Total Rs: 655.00

    Add for small Tools and Plants @ 1% Rs: 6.55

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00

    Add for Contractor's Overheads @ 5% Rs: 32.75

    Total hire charges of Machinery : Rs: 723.30

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 1.00 26.90 26.90

    3 Crew for Needle vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 1.00 159.00 159.00

    5 Heavy mazdoor

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 8.00 132.00 1056.00

    for loading mortar pans Day 4.00 132.00 528.00

    for laying Day 3.00 132.00 396.006 Light mazdoor

    for conveying concrete Day 14.00 130.50 1827.00

    Contd

    Description

    Perticulars

    Description Quantity Rate

    Quantity

    in Rs.

    Quantity Rate

    in Rs.

    Rate

    in Rs.

    67

  • 8/13/2019 Data Rates-Dam Works-Part 4

    9/21

    DAM ALLIED WORKS

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    for cleaning / washing / curing Day 1.00 130.50 130.50

    7 Labour cost of shuttering sqm 13.80 33.17 457.68

    8 Labour cost of scaffolding @ 15 % 68.65

    Total Rs: 5944.93

    Add for small Tools and Plants @ 1% Rs: 59.45

    Add for Contractor's Profit @ 10% Rs: 594.49

    Add for hidden cost on Labour @ 15% Rs: 891.74

    Add for additional hidden cost on labour @ 5% Rs: 297.25

    Add for Contractor's Overheads @ 5% Rs: 297.25

    Total cost of Labour : Rs: 8085.10

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 31770.20

    B. Hire charges of Machinery Rs: 723.30

    C. Cost of Labour Rs: 8085.10

    TOTAL Rs: 40578.60

    Add for enabling works @ 1.40% Rs: 568.10Total Rs: 41146.71

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 4084 kg @ Rs: 129.10 / tonne Rs: 527.24

    Coarse aggregates 10.95 cum @ Rs: 121.90 / cum Rs: 1334.81

    Fine aggregates 6.35 cum @ Rs: 84.90 / cum Rs: 539.12

    Total cost for 13.80 cum Rs: 43547.87

    Rate per cum Rs: 3156.00

    Rate approved per cum Rs: 3156.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 20

    ITEM: Providing and laying insitu vibrated M-20( 28 days cube compressive strength not less than

    20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded

    aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,

    cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete

    for RCC works of spillway bridge, blockout concretingand such other similar structures with

    conjested reinforcement areas with initial lead upto 1 km and all lifts. ( Cement content :

    330 kg / cum with use of super plasticiser ).

    DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35

    Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticizer : 1.00 ltr

    Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min

    Batching 10 mm below CA parellel activity : ---Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Description Quantity Rate

    in Rs.

    68

  • 8/13/2019 Data Rates-Dam Works-Part 4

    10/21

    DAM ALLIED WORKS

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 4.50 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 4.5 ) : 89 mixes

    Output of CC for 89 mixes ( 89 x 50 / 330 ) say : 13.50 cum

    Consider 13.50 cum concrete for rate analysis.

    1. Requirement of materials:

    Cement for mix with 1 % wastage ( 13.5 x 330 x 1.01 ) : 4500 kg

    Cement for incidental works @ 3 kg / cum ( 13.8 x 3 ) : 41 kg

    Coarse aggregate 20-10 mm size range ( 13.5 x 0.8 x 0.65 x 1.02 ) : 7.15 cum

    Coarse aggregate 10-4.75 mm size ( 13.5 x 0.8 x 0.35 x 1.02 ) : 3.85 cum

    Fine aggregate ( 13.5 x 0.45 x 1.02 ) : 6.20 cum

    Super plasticiser ( 13.5 x 1.0 x 1.02 ) : 13.80 ltrs

    2. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    3. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Requirement of shuttering for bridge concrete works is assumed at 4 sqm / cum of concrete.

    Shuttering @ 4 sqm per cum of concrete ( 13.5 x 4 ) : 54 sqmScaffolding / supports etc @ 100 percent of cost of shuttering.

    4. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 20-10 mm CA Heavy mazdoors : 3 Nos.

    Batching 10 mm below CA Heavy mazdoors : 2 Nos.

    Batching fine aggregate Heavy mazdoors : 3 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 4 Nos.

    Light mazdoors : 14 Nos.

    Laying concrete Mason : 1 No.

    Heavy mazdoors : 3 Nos.

    Washing / cleaning / curing etc Light mazdoors : 1 No.

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 100 % of cost labour for shuttering.

    5. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    6. Use rate of materials :

    Use rate of normal shutter per sqm for 30 uses ( Annexure-A Item : 13 ) Rs: 186.42

    RATE ANALYSIS UNIT : 13.50 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement for mix with 1% wastage kg 4500.00 4.00 18000.00

    Cement for incidentals @ 3 kg/ cum kg 41.00 4.00 164.00

    2 Coarse aggregate 20-10 mm cum 7.15 520.00 3718.00

    Coarse aggregate 10 mm below cum 3.85 669.00 2575.65Contd

    A. MATERIALS ( Contd ) :

    Sl No Unit Amount

    Perticulars Quantity Rate

    in Rs.

    Perticulars Quantity Rate

    69

  • 8/13/2019 Data Rates-Dam Works-Part 4

    11/21

    DAM ALLIED WORKS

    in Rs.

    Contd

    3 Fine aggregate ( screened ) cum 6.20 199.00 1233.80

    4 Super plasticiser ltr 13.80 75.00 1035.00

    5 Use rate of shuttering sqm 54.00 186.42 10066.70

    6 Scaffolding @ 100 % of shuttering 10066.70

    Total Rs: 46859.84

    Add for small Tools and Plants @ 1% Rs: 468.60

    Add for Contractor's Profit @ 10% Rs: 4685.98

    Add for Contractor's Overheads @ 5% Rs: 2342.99

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 54357.42

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 10 hp pump ( ele ) Hour 1.00 5.00 5.00

    Fuel / Energy charges Hour 1.00 50.00 50.003 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00

    Fuel / Energy charges Hour 8.00 5.00 40.00

    Total Rs: 655.00

    Add for small Tools and Plants @ 1% Rs: 6.55

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00

    Add for Contractor's Overheads @ 5% Rs: 32.75

    Total hire charges of Machinery : Rs: 723.30

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 1.00 26.90 26.90

    3 Crew for Needle vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 1.00 159.00 159.00

    5 Heavy mazdoor

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 8.00 132.00 1056.00

    for loading mortar pans Day 4.00 132.00 528.00

    for laying Day 3.00 132.00 396.00

    6 Light mazdoor

    for conveying concrete Day 14.00 130.50 1827.00

    for cleaning/ washing/ curing Day 1.00 130.50 130.50

    7 Labour cost of shuttering sqm 54.00 33.17 1790.91

    8 Labour cost of scaffolding @ 100 % 1790.91

    Total Rs: 9000.42

    Contd

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Description

    Description Quantity Rate

    in Rs.

    Quantity Rate

    in Rs.

    in Rs.

    Description Quantity Rate

    in Rs.

    70

  • 8/13/2019 Data Rates-Dam Works-Part 4

    12/21

    DAM ALLIED WORKS

    Contd

    Add for small Tools and Plants @ 1% Rs: 90.00

    Add for Contractor's Profit @ 10% Rs: 900.04

    Add for hidden cost on Labour @ 15% Rs: 1350.06

    Add for additional hidden cost on labour @ 5% Rs: 450.02

    Add for Contractor's Overheads @ 5% Rs: 450.02

    Total cost of Labour : Rs: 12240.57

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 54357.42

    B. Hire charges of Machinery Rs: 723.30

    C. Cost of Labour Rs: 12240.57

    TOTAL Rs: 67321.29

    Add for enabling works @ 1.40% Rs: 942.50

    Total Rs: 68263.79

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 4541 kg @ Rs: 129.10 / tonne Rs: 586.24

    Coarse aggregates 11.0 cum @ Rs: 121.90 / cum Rs: 1340.90

    Fine aggregates 6.2 cum @ Rs: 84.90 / cum Rs: 526.38

    Total cost for 13.50 cum Rs: 70717.31

    Rate per cum Rs: 5238.00Rate approved per cum Rs: 5238.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 21

    ITEM: Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23 cm diameter

    central hole using cement and 20 mm downapproved, clean, hard, graded coarse aggregates

    in 1 : 3.50 proportion by volume including cost of all materials, machinery, labour, formwork,

    curing etc., complete with initial lead upto 1 km and all lifts.

    DATA:Area of concrete for body drain ( 0.685 x 0.685 - 0.7857 x 0.23 x 0.23 ) : 0.428 sqm

    For 1 cum porous CC : Coarse aggregate : 1.00 cum Blending ratio : 65 : 35

    Cement : 408 kg.

    Wastage : 1 % for cement and 2 % for aggregate.

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 20-10 mm CA ( 0.080 cum ) : 3.00 min

    Batching 10 mm below CA parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 4.50 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 4.5 ) : 89 mixes

    Output of CC for 89 mixes ( 89 x 50 / 408 ) say : 10.90 cum

    Generally, body drain is formed by casting porous concrete blocks of convenient height in the

    casting yard and the blocks after curing are shifted to body drain location as concrete / masonry

    work progresses for the dam block.

    Assuming 2 % wastage of CC during casting of blocks the quantity of concrete required per

    metre height of body drain will be ( 0.428 x 1.02 ) : 0.436 cum

    71

  • 8/13/2019 Data Rates-Dam Works-Part 4

    13/21

    DAM ALLIED WORKS

    Length of body drain for 1 day output of mixer ( 10.9 / 0.436 ) : 25.00 m

    Consider 25 m porous concrete body drain for analysis.

    1. Requirement of materials:

    Cement for mix with 1 % wastage ( 10.9 x 408 x 1.01 ) : 4492 kg

    Coarse aggregate 20-10 mm size range ( 10.9 x 1.0 x 0.65 x 1.02 ) : 7.20 cum

    Coarse aggregate 10-4.75 mm size ( 10.9 x 1.0 x 0.35 x 1.02 ) : 3.90 cum

    2. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of porous concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    3. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in moulds.

    Requirement of shuttering for 1 m height ( 4 x 0.685 + 3.14 x 0.23 ) say : 3.46 sqm

    Shuttering for 25 m height of drain ( 25 x 3.5 ) : 86.50 sqm

    4. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 20-10 mm CA Heavy mazdoors : 3 Nos.

    Batching 10 mm below CA Heavy mazdoors : 2 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 4 Nos.

    Light mazdoors : 11 Nos.

    Shuttering for blocks Fitter shuttering : 1 No.Laying concrete for blocks Mason : 1 No.

    Heavy mazdoors : 1 No.

    Washing / cleaning / curing etc Light mazdoors : 1 No.

    Conveying blocks to body drain location Heavy mazdoors : 2 Nos.

    5. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    6. Use rate of materials :

    Consider 100 uses of moulds.

    Cost of shuttering per sqm as per data in Item-13 @ Rs: 3535.51

    Use rate of shutter per sqm for 100 uses 3535.51 / 100 Rs: 35.36

    Add for shutter oil 0.2 ltr / sqm @ Rs: 25.00 / ltr Rs: 5.00

    Use rate of shutter per sqm for 100 uses Rs: 40.36

    RATE ANALYSIS UNIT : 25.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement with 1% wastage kg 4492.00 4.00 17968.00

    2 Coarse aggregate 20-10 mm cum 7.20 520.00 3744.00

    3 Coarse aggregate 10-4.75 mm cum 3.90 669.00 2609.10

    4 Use rate of shuttering sqm 86.50 40.36 3490.71

    Total Rs: 27811.81

    Add for small Tools and Plants @ 1% Rs: 278.12

    Add for Contractor's Profit @ 10% Rs: 2781.18

    Contd

    A. MATERIALS ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    Add for Contractor's Overheads @ 5% Rs: 1390.59

    Quantity Rate

    in Rs.

    Perticulars

    Perticulars

    Quantity Rate

    in Rs.

    72

  • 8/13/2019 Data Rates-Dam Works-Part 4

    14/21

    DAM ALLIED WORKS

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 32261.70

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 10 hp pump ( ele ) Hour 1.00 5.00 5.00

    Fuel / Energy charges Hour 1.00 50.00 50.00

    Total Rs: 559.00

    Add for small Tools and Plants @ 1% Rs: 5.59

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 25.00

    Add for Contractor's Overheads @ 5% Rs: 27.95

    Total hire charges of Machinery : Rs: 617.54

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.802 Crew for Pump Hour 1.00 26.90 26.90

    3 Mason Class-I Day 1.00 159.00 159.00

    4 Heavy mazdoor

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 5.00 132.00 660.00

    for loading mortar pans Day 2.00 132.00 264.00

    for laying & packing concrete Day 3.00 132.00 396.00

    for shifting blocks to site Day 2.00 132.00 264.00

    5 Light mazdoor

    for conveying concrete Day 11.00 130.50 1435.50

    6 Fitter shuttering Day 1.00 148.50 148.50

    Total Rs: 4222.70

    Add for small Tools and Plants @ 1% Rs: 42.23

    Add for Contractor's Profit @ 10% Rs: 422.27

    Add for hidden cost on Labour @ 15% Rs: 633.41

    Add for additional hidden cost on labour @ 5% Rs: 211.14

    Add for Contractor's Overheads @ 5% Rs: 211.14

    Total cost of Labour : Rs: 5742.87

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 32261.70

    B. Hire charges of Machinery Rs: 617.54

    C. Cost of Labour Rs: 5742.87

    TOTAL Rs: 38622.12

    Add for enabling works @ 1.40% Rs: 540.71

    Total Rs: 39162.83

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 4492 kg @ Rs: 129.10 / tonne Rs: 579.92

    Coarse aggregates11.10 cum @ Rs: 121.90 / cum Rs: 1353.09

    Total cost for 25.00 Rm Rs: 41095.83

    Description

    Description

    in Rs.

    Quantity Rate

    in Rs.

    Quantity Rate

    73

  • 8/13/2019 Data Rates-Dam Works-Part 4

    15/21

    DAM ALLIED WORKS

    Rate per Rm Rs: 1644.00

    Rate approved per Rm Rs: 1644.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 22.a

    ITEM: Providing and laying insitu vibrated M-20( 28 days cube compressive strength not less than

    20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded

    aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,

    cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete

    for RCC solid parapetconsisting of 350 x 200 mm kerb, 350 x 350 x 1000 mm pillars spaced

    approximately at 3.35 m c / c, 125 mm thick wall 800 mm height with 125 mm thick and 350

    mm wide coping slab for wall and 125 mm thick 400 x 400 mm coping for pillars with top edges

    of kerb and coping chamferred / rounded as directed etc., complete ( excluding cost of providing

    and placing reinforcement steel and gate ) with initiallead upto 1 km and all lifts. ( Cement

    content 330 kg / cum with use of super plasticiser )

    DATA:Consider one spillway bridge span of 18 m.

    Consider solid parapet for rate analysis for one span.

    Consider 0.9 wide opening for approach to pier top hoist platform on d / s side.

    0.35 mGate 3.00 m 0.125 m

    0.8 m

    0.20 m

    SKETCH SHOWING COMPONENTS OF RCC SOLID PARAPET

    Length of kerb on u /s and d / s ( 18.00 + 18.00 ) : 36.00 m

    Length of parapet ( 18.00 + 18.00 - 0.90 ) : 35.10 m

    Number of pillars for 3.35 m c / c spacing : 12 Nos

    Number of wall panels of size 3.00 x 0.80 x 0.125 m : 10 Nos

    Number of wall panels of size 0.45 x 0.80 x 0.125 m (on u/s only) : 2 Nos

    Length of coping for wall panels ( 3 x 10 + 2 x 0.45 ) : 30.90 m

    Number of coping slabs for pillers : 12 Nos

    For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35

    Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticiser : 1.00 ltr.

    Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

    1. Quantity of concrete per span :

    For kerb ( 36 x 0.35 x 0.20 ) : 2.52 cum

    For pillars ( 12 x 1 x 0.35 x 0.35 ) : 1.47 cum

    For wall panels ( 10 x 3 x 0.80 x 0.125 + 2 x 0.45 x 0.80 x 0.125 ) : 3.09 cum

    For wall coping ( 10 x 3 x 0.35 x 0.125 + 2 x 0.45 x 0.35 x 0.125 ) : 1.35 cum

    For pillar coping ( 12 x 0.40 x 0.40 x 0.125 ) : 0.24 cum

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

    74

  • 8/13/2019 Data Rates-Dam Works-Part 4

    16/21

    DAM ALLIED WORKS

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min

    Batching 10 mm below CA parellel activity : ---

    Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 4.50 min

    Construction of parapet involves laying of concrete in three stages namely ( i ) kerb, ( ii ) pillars

    and wall panels and ( iii ) coping. While concrete laying cycle can be matched with production

    cycle for kerb and coping, the laying cycle will be very slow for pillars and wall panels in view of

    thin sections with reinforcement. Considering the laying time for pillars and wall panels at twice

    the production time the average cycle time will be about 1.5 times the production cycle time.

    Average cycle time for laying concrete ( 4.50 x 1.5 ) : 6.75 min

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 6.75 ) : 59 mixes

    Output of CC for 59 mixes ( 59 x 50 / 330 ) : 8.9 cum

    As the computed daily output of 8.9 cum is close to one span quantity of 8.7 cum consider the

    daily output at 8.7 cum for rate analysis.

    2. Requirement of materials:Cement for mix with 1 % wastage ( 8.7 x 330 x 1.01 ) : 2900 kg

    Cement for incidental works @ 5 kg / cum ( 8.7 x 5 ) : 43.5 kg

    Coarse aggregate 20-10 mm size range ( 8.7 x 0.8 x 0.65 x 1.02 ) : 4.60 cum

    Coarse aggregate 10-4.75 mm size ( 8.7 x 0.8 x 0.35 x 1.02 ) : 2.50 cum

    Fine aggregate ( 8.7 x 0.45 x 1.02 ) : 4.00 cum

    Super plasticiser ( 8.7 x 1.0 x 1.02 ) : 8.90 ltrs

    3. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    4. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Shuttering for kerb x 18 x 0.20 + 4 x 0.35 x 0.20 ) : 14.68 sqm

    For pillars x 2 x 0.55 x 1 + 2 x 0.15 x 1 ) : 13.50 sqm

    For wall panels ( 10x2x3x0.80 + 2x2x0.45x0.80 + 2x0.15x0.80 ) : 49.68 sqm

    For wall coping( 0.45 x 3 x 10 + 0.45 x 0.45 x 2 + 2 x 0.35 x 0.15 ) : 14.01 sqm

    For pillar coping ( 12 x 4 x 0.35 x 0.15 ) : 2.52 sqm

    Total ( say ) : 95.00 sqm

    Scaffolding / supports assumed at 15 percent of cost of shuttering.

    5. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 20-10 mm CA Heavy mazdoors : 2 Nos.

    Batching 10 mm below CA Heavy mazdoors : 2 Nos.

    Batching fine aggregate Heavy mazdoors : 2 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 2 Nos.

    Light mazdoors : 9 Nos.

    Laying concrete Mason Class-I : 2 Nos.

    Heavy mazdoors : 2 Nos.

    Washing / cleaning / curing etc Light mazdoors : 2 Nos.

    75

  • 8/13/2019 Data Rates-Dam Works-Part 4

    17/21

    DAM ALLIED WORKS

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.

    6. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    7. Use rate of materials :

    Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07

    RATE ANALYSIS UNIT : 36.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement with 1% wastage for mix kg 2900.00 4.00 11600.00

    Cenent for incidentals @ 5 kg / cum kg 43.50 4.00 174.00

    2 Coarse aggregate 20-10 mm cum 4.60 520.00 2392.00

    Coarse aggregate 10-4.75 mm cum 2.50 669.00 1672.50

    3 Fine aggregate ( screened ) cum 4.00 199.00 796.00

    4 Super plasticiser ltr 8.90 75.00 667.50

    5 Use rate of shuttering sqm 95.00 151.07 14351.20

    6 Scaffolding @ 15 % of shuttering 2152.68

    7 Sundries LS 2.00 30.00 60.00

    Total Rs: 33865.88Add for small Tools and Plants @ 1% Rs: 338.66

    Add for Contractor's Profit @ 10% Rs: 3386.59

    Add for Contractor's Overheads @ 5% Rs: 1693.29

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 39284.42

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 Needle vibrator 40 mm ( ele ) Hour 8.00 7.00 56.00

    Fuel / Energy charges Hour 8.00 5.00 40.00

    3 10 hp pump ( ele ) Hour 0.50 5.00 2.50

    Fuel / Energy charges Hour 0.50 50.00 25.00

    Total Rs: 627.50

    Add for small Tools and Plants @ 1% Rs: 6.28

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 26.50

    Add for Contractor's Overheads @ 5% Rs: 31.38

    Total hire charges of Machinery : Rs: 691.65

    C. LABOUR:Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 0.50 26.90 13.45

    3 Crew for Vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 2.00 159.00 318.00

    5 Maistry Day 1.00 141.50 141.50

    6 Heavy mazdoor

    Description

    Description

    Perticulars

    in Rs.

    Quantity Rate

    in Rs.

    Quantity Rate

    Quantity Rate

    in Rs.

    76

  • 8/13/2019 Data Rates-Dam Works-Part 4

    18/21

    DAM ALLIED WORKS

    for batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 6.00 132.00 792.00

    for loading mortar pans Day 2.00 132.00 264.00

    for laying & packing concrete Day 2.00 132.00 264.00

    7 Light mazdoor

    for conveying concrete Day 9.00 130.50 1174.50

    for curing & miscellaneous Day 2.00 130.50 261.00

    8 Labour for shuttering sqm 95.00 33.17 3150.68

    9 Labour for scaffolding @ 15 % 472.60

    Total Rs: 8146.93

    Add for small Tools and Plants @ 1% Rs: 81.47

    Add for Contractor's Profit @ 10% Rs: 814.69

    Add for hidden cost on Labour @ 15% Rs: 1222.04

    Add for additional hidden cost on labour @ 5% Rs: 407.35

    Add for Contractor's Overheads @ 5% Rs: 407.35

    Total cost of Labour : Rs: 11079.82

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 39284.42

    B. Hire charges of Machinery Rs: 691.65

    C. Cost of Labour Rs: 11079.82TOTAL Rs: 51055.89

    Add for enabling works @ 1.40% Rs: 714.78

    Total Rs: 51770.67

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 2943.5 kg @ Rs: 129.10 / tonne Rs: 380.01

    Coarse aggregates 7.10 cum @ Rs: 121.90 / cum Rs: 865.49

    Fine aggregate 4.00 cum @ Rs: 84.90 / cum Rs: 339.60

    Total cost for 36.00 Rm Rs: 53016.17

    Rate per Rm Rs: 1473.00

    Rate approved per Rm Rs: 1473.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 22.b

    ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

    20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded

    aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,

    cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete

    for RCC ornamental parapetconsisting of 350 x 200 mm kerb, 350 x 350 x 1000 mm pillars

    spaced approximately at 3.5 m apart, 150 x 125 mm posts 600 mm height approximately 316

    mm c/c with 125 mm thick and 350 mm wide coping slab for posts and pillars with top edges of

    kerb and coping chamferred or rounded as directed etc., complete ( excluding cost of providing

    and placing reinforcement steel and gate ) with initial lead upto 1 km and all lifts. ( Cementcontent : 330 kg / cum with use of super plasticiser )

    DATA:Consider one spillway bridge span of 18 m.

    Consider ornamental parapet for rate analysis for one span.

    Consider 0.9 wide opening for approach to pier top hoist platform on d / s side.

    0.35 m

    Gate 3.00 m 0.125 m

    77

  • 8/13/2019 Data Rates-Dam Works-Part 4

    19/21

    DAM ALLIED WORKS

    0.8 m

    0.20 m

    SKETCH SHOWING COMPONENTS OF RCC ORNAMENTAL PARAPET

    Length of kerb on u / s and d / s ( 18.00 + 18.00 ) : 36.00 m

    Length of parapet ( 18.00 + 18.00 - 0.90 ) : 35.10 m

    Number of pillars for 3.35 m c / c spacing : 12 Nos

    Number of wall panels of size 3.00 x 0.80 x 0.125 m : 10 Nos

    Number of wall panels of size 0.45 x 0.80 x 0.125 m ( on u/s only ) : 2 Nos

    Length of coping for wall panels ( 3 x 10 + 2 x 0.45 ) : 30.90 m

    Number of coping slabs for pillers : 12 Nos

    For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35

    Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticiser : 1.00 ltr Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

    1. Quantity of concrete per span :

    For kerb ( 36 x 0.35 x 0.20 ) : 2.52 cum

    For pillars ( 12 x 1 x 0.35 x 0.35 ) : 1.47 cum

    For wall panels ( 10 x 3 x 0.80 x 0.125 + 2 x 0.45 x 0.80 x 0.125 ) : 3.09 cum

    For wall coping ( 10 x 3 x 0.35 x 0.125 + 2 x 0.45 x 0.35 x 0.125 ) : 1.35 cum

    For pillar coping ( 12 x 0.40 x 0.40 x 0.125 ) : 0.24 cum

    Total : 8.70 cum

    Less openings in wall panels ( 10x 9x 0.60x 0.166x 0.125) : 1.12 cum

    Total ( say ) : 7.60 cum

    Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

    Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA

    Cycle time for batching / mixing / unloading 1 mix :

    Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min

    Batching 10 mm below CA parellel activity : ---

    Batching fine aggregate parellel activity : ---

    Batching cement parellel activity : ---

    Loading mixer drum & miscellaneous : 1.00 min

    Mixing and unloading parellel activity : ---

    Add for possible delays in any of the activity : 0.50 min

    Cycle time for batching / mixing / unloading 1 mix : 4.50 minConstruction of parapet involves laying of concrete in three stages namely ( i ) kerb, ( ii ) pillars

    and wall panels and ( iii ) coping. While concrete laying cycle can be matched with production

    cycle for kerb and coping, the laying cycle will be very slow for pillars and wall panels in view of

    thin sections with reinforcement. For ornamental parapet the laying cycle time will be more than

    solid parapet in view of openings in wall panels. Considering the laying cycle time for pillars and

    wall panels with openings 3 times the production cycle time the average cycle time will be about

    1.8 times the production cycle time.

    Average cycle time for laying concrete ( 4.50 x 1.8 ) : 8.10 min

    78

  • 8/13/2019 Data Rates-Dam Works-Part 4

    20/21

    DAM ALLIED WORKS

    No. of mixes per day with 50 min / hr working ( 50 x 8 / 8.1 ) say : 50 mixes

    Output of CC for 50 mixes ( 50 x 50 / 330 ) : 7.6 cum

    As the computed daily output of 7.60 cum also matches with the one span parapet quantity of

    7.60 cum consider the daily output at 7.60 cum for rate analysis.

    2. Requirement of materials:

    Cement for mix with 1 % wastage ( 7.6 x 330 x 1.01 ) : 2533 kg

    Cement for incidental works @ 5 kg / cum ( 7.6 x 5 ) : 38 kg

    Coarse aggregate 20-10 mm size range ( 7.6 x 0.8 x 0.65 x 1.02 ) : 4.05 cum

    Coarse aggregate 10-4.75 mm size ( 7.6 x 0.8 x 0.35 x 1.02 ) : 2.20 cum

    Fine aggregate ( 7.6 x 0.45 x 1.02 ) : 3.50 cum

    Super plasticiser ( 7.6 x 1.0 x 1.02 ) : 7.75 ltrs

    3. Requirement of machinery :

    Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.

    Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

    Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.

    4. Formwork & scaffolding :

    Consider normal shuttering as concrete is laid in smaller lifts.

    Shuttering for kerb x 18 x 0.20 + 4 x 0.35 x 0.20 ) : 14.68 sqm

    For pillars (12x 2x 0.55x1 + 2x 0.15x1) : 13.50 sqm

    For wall panels ( 10x2x3x0.80 + 2x2x0.45x0.80 + 2x0.15x0.80 ) : 49.68 sqm

    For openings ( 10x 2x 2 x 9 x 0.125 x 0.6 ) : 20.00 sqmFor wall coping( 0.45 x 3 x 10 + 0.45 x 0.45 x 2 + 2 x 0.35 x 0.15 ) : 14.01 sqm

    For pillar coping ( 12 x 4 x 0.35 x 0.15 ) : 2.52 sqm

    Total ( say ) : 115.00 sqm

    Scaffolding / supports assumed at 15 percent of cost of shuttering.

    5. Requirement of workforce ( other than machinery crew ) :

    Consider batching of materials and conveyance & laying of concrete by manual labour.

    Batching 20-10 mm CA Heavy mazdoors : 2 Nos.

    Batching 10 mm below CA Heavy mazdoors : 2 Nos.

    Batching fine aggregate Heavy mazdoors : 2 Nos.

    Batching cement Heavy mazdoors : 2 Nos.

    Remixing and conveying concrete Heavy mazdoors : 2 Nos.

    Light mazdoors : 8 Nos.

    Laying concrete Mason Class-I : 2 Nos.

    Heavy mazdoors : 2 Nos.

    Washing / cleaning / curing etc Light mazdoors : 2 Nos.

    Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17

    Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.

    6. Rehandling / Initial lead for materials:

    1 km rehandling lead for cement and 1 km initial lead for other materials considered.

    7. Use rate of materials :

    Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07

    RATE ANALYSIS UNIT : 36.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement with 1% wastage for mix kg 2533.00 4.00 10132.00

    Cenent for incidentals @ 5 kg / cum kg 38.00 4.00 152.00

    2 Coarse aggregate 20-10 mm cum 4.05 520.00 2106.00

    Perticulars Quantity Rate

    in Rs.

    79

  • 8/13/2019 Data Rates-Dam Works-Part 4

    21/21

    DAM ALLIED WORKS

    Coarse aggregate 10-4.75 mm cum 2.20 669.00 1471.80

    3 Fine aggregate ( screened ) cum 3.50 199.00 696.50

    4 Super plasticiser ltr 7.75 75.00 581.25

    5 Use rate of shuttering sqm 115.00 151.07 17372.50

    6 Scaffolding @ 15 % of shuttering 2605.88

    7 Sundries LS 2.50 30.00 75.00

    Total Rs: 35192.93

    Add for small Tools and Plants @ 1% Rs: 351.93

    Add for Contractor's Profit @ 10% Rs: 3519.29

    Add for Contractor's Overheads @ 5% Rs: 1759.65

    Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00

    Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00

    Total cost of Materials : Rs: 40823.80

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00

    Fuel / Energy charges Hour 8.00 25.00 200.00

    2 Needle vibrator 40 mm ( ele ) Hour 8.00 7.00 56.00

    Fuel / Energy charges Hour 8.00 5.00 40.003 10 hp pump ( ele ) Hour 0.50 5.00 2.50

    Fuel / Energy charges Hour 0.50 50.00 25.00

    Total Rs: 627.50

    Add for small Tools and Plants @ 1% Rs: 6.28

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 26.50

    Add for Contractor's Overheads @ 5% Rs: 31.38

    Total hire charges of Machinery : Rs: 691.65

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Concrete mixer Hour 8.00 75.10 600.80

    2 Crew for Pump Hour 0.50 26.90 13.45

    3 Crew for Vibrator Hour 8.00 53.30 426.40

    4 Mason Class-I Day 2.00 159.00 318.00

    5 Maistry Day 1.00 141.50 141.50

    Contd

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    6 Heavy mazdoorfor batching cement ( cement handling ) Day 2.00 134.00 268.00

    for batching other materials Day 6.00 132.00 792.00

    for loading mortar pans Day 2.00 132.00 264.00

    for laying & packing concrete Day 2.00 132.00 264.00

    7 Light mazdoor

    for conveying concrete Day 8.00 130.50 1044.00

    for curing & miscellaneous Day 2.00 130.50 261.00

    8 Labour for shuttering sqm 115.00 33.17 3813.98

    in Rs.

    in Rs.

    Description

    Description

    Description

    Quantity Rate

    in Rs.

    Quantity Rate

    Quantity Rate