cww-introduction-2006.pdf

download cww-introduction-2006.pdf

of 11

Transcript of cww-introduction-2006.pdf

  • 8/11/2019 cww-introduction-2006.pdf

    1/11

    CAPWAP

    CAPWAP

    IntroductionIntroduction

    0.0 1000.0 2000.0 3000.0 4000.00.00

    Load(kN) PileTopBottom

    20062006--20112011 -- GRL Engineers, Inc.GRL Engineers, Inc. -- Pile Dynamics, Inc.Pile Dynamics, Inc.

    5.00

    10.00

    15.00

    20.00

    Ru = 3425.2 kNRs = 1458.6 kN

    Rb = 1966.6 kNDy = 18.8 mm

    Dx= 18.8 mm

    CAPWAPCAse Pile Wave Analysis Programsince 1969

    Automatic (Univac) until 1974

    Interactive (Varian, Minc, Early PCs)

    Automatic and interactive since 1988

    CAPWAP is aSignal Matching Program

    (System Identification Analysis or Reverse Analysis)

    CAPWAP is aSignal Matching Program

    (System Identification Analysis or Reverse Analysis)

    We know the Load (i.e. the measured force)

    We know the Movement under the Load (i.e. the

    displacement from the measured acceleration)

    But we do not know the System

    We know the Load (i.e. the measured force)

    We know the Movement under the Load (i.e. the

    displacement from the measured acceleration)

    But we do not know the System

    ys emys em ovemenovemenoaoa

    The System Consists of

    Pile and Soil

    The System Consists of

    Pile and Soil

    Normally all pile parameters are known! Therefore

    only soil parameters must be calculated.

    Normally all pile parameters are known! Therefore

    only soil parameters must be calculated.

    CAPWAP has to determine soil parameters. Input

    into CAPWAP program are:

    Pile top force and velocity

    Pile properties

    CAPWAP has to determine soil parameters. Input

    into CAPWAP program are:

    Pile top force and velocity

    Pile properties

    Why all that calculation?Why all that calculation?

    Why not plot

    Measured Force vs Measured Displacement?

    Why not plot

    Measured Force vs Measured Displacement?

    . Because Measured Force Includes:

    Impact and wave effects

    Static resistance effects

    Dynamic resistance effects

    . Because Measured Force Includes:

    Impact and wave effects

    Static resistance effects

    Dynamic resistance effects

    1500

    0

    250

    500

    750

    1000

    1250

    0 5 10 15 20 25

    Pile top displacement in mm

    Piletop

    forcein

    kN

  • 8/11/2019 cww-introduction-2006.pdf

    2/11

    The CAPWAP ProcedureThe CAPWAP Procedure

    CAPWAP solves the rocess in anCAPWAP solves the rocess in an

    iterative procedure

    iterative procedure

    CAPWAP METHODCAPWAP METHODCAPWAP METHODCAPWAP METHOD

    1 Set up pile model and1 Set up pile model and

    assume Rassume Rshaftshaft and Rand Rtoetoe

    2 A l one measured curve2 A l one measured curve vvmm

    vvmm FFccFFmm

    RRshaftshaft

    RRtoetoe5 Go to Step 25 Go to Step 2

    4 Adjust R4 Adjust Rshaftshaft and Rand Rtoetoe

    3 Compare3 Compare FFcc with measuredwith measured FFmm

    Calculate complementaryCalculate complementary FFcc

    Repeat until matchRepeat until match

    is satisfactoryis satisfactory

    Final match (good)

    First try (poor)

    ustments

    CAPWAP is an iterative process

    The Pile ModelThe Pile ModelThe Pile ModelThe Pile Model

    ZZii--11LLiiLLii

    The Pile is divided in NThe Pile is divided in Nppuniform pile segmentsuniform pile segmentsof approx. 1 m length.of approx. 1 m length.

    The Pile is divided in NThe Pile is divided in Nppuniform pile segmentsuniform pile segmentsof approx. 1 m length.of approx. 1 m length.

    ZZi+1i+1

    ZZii

    t =t =

    LLii/c/cii

    The Wave travel time,The Wave travel time,

    t, ist, is the same in allthe same in allsegments (.2 to .25 ms)segments (.2 to .25 ms)

    The Wave travel time,The Wave travel time,

    t, ist, is the same in allthe same in allsegments (.2 to .25 ms)segments (.2 to .25 ms)

    ac segmen asac segmen as

    impedance Zimpedance Zii = E= EiiAAii/c/ciiand wave speed cand wave speed cii

    ac segmen asac segmen as

    impedance Zimpedance Zii = E= EiiAAii/c/ciiand wave speed cand wave speed cii

    The Combined Pile and Soil ModelThe Combined Pile and Soil ModelThe Combined Pile and Soil ModelThe Combined Pile and Soil Model

    Soil segment lengthSoil segment lengthSoil segment lengthSoil segment length

    Mass density,Mass density,

    Modulus, EModulus, E

    Mass density,Mass density,

    Modulus, EModulus, E

    Spring (static resistance)Spring (static resistance)Spring (static resistance)Spring (static resistance)

    WavespeedWavespeed

    c =c =

    (E/(E/

    ))

    WavespeedWavespeed

    c =c =

    (E/(E/

    ))

    t

    t

    t

    Pile segment lengthPile segment lengthPile segment lengthPile segment length

    as po ynam c res s anceas po ynam c res s anceas po ynam c res s anceas po ynam c res s ance

    Travel timeTravel time

    t =t = L/cL/c

    Travel timeTravel time

    t =t = L/cL/c

    t

    t

    t

    XX--secn area, Asecn area, AXX--secn area, Asecn area, A

    PilePile

    Impedance,Impedance,

    Z = EA/cZ = EA/c

    PilePile

    Impedance,Impedance,

    Z = EA/cZ = EA/c

    RRuiui, q, qii JJ ii

    RRNsNs

    RRNsNs--11

    TheThe

    CAPWAPCAPWAP

    SoilSoil

    ResistanceResistance

    ModelModel

    TheThe

    CAPWAPCAPWAP

    SoilSoil

    ResistanceResistance

    ModelModel

    RRtt, q, q ttJJTT

    mmPLPL

    Shaft Resistance,Shaft Resistance,

    Ns timesNs timesttGG

  • 8/11/2019 cww-introduction-2006.pdf

    3/11

    RRu,su,s

    RRssquake, qquake, qss

    Static Shaft Resistance ModelStatic Shaft Resistance Model

    uuss

    RRu,nu,n

    UN =UN = --RRu,nu,n/R/Ru,su,s

    Unloading quake,Unloading quake,

    qqss ccss

    ss

    RRss

    RRu,tu,t

    RRtt

    Static Toe Resistance ModelStatic Toe Resistance Model

    uuttquake, qquake, qtt

    unloadingunloading

    quake, qquake, qtt cctt

    Toe gap: tToe gap: tgg

    Damping Resistance: RDamping Resistance: Rdd = J= Jvv vv

    RRdd = J= JCaseCase Z vZ v = J= JSmithSmith RRuu vv

    PilePile

    SegmentSegment

    Velocity,Velocity,

    vv

    Damping ConstantDamping Constant

    Conversions:Conversions:

    JJSmithSmith = J= Jvv /R/RuuJJCaseCase = J= Jvv /Z/Z

    JJSmithSmith = J= JCaseCase Z / RZ / Ruu

    Damping ConstantDamping Constant

    Conversions:Conversions:

    JJSmithSmith = J= Jvv /R/RuuJJCaseCase = J= Jvv /Z/Z

    JJSmithSmith = J= JCaseCase Z / RZ / Ruu

    NormalNormal--Viscous (Option=0)Viscous (Option=0)

    RRdd = J= JCC Z v =Z v = RRUU JJSS vv

    NormalNormal--Viscous(Option=0)Viscous (Option=0)

    RRdd = J= JCC Z v =Z v = RRUU JJSS vv

    velocityvelocity

    vv

    PilePile

    JJss = J= Jcc Z/RZ/RUUJJss = J= Jcc Z/RZ/RUU

    CAPWAP Damping ModelCAPWAP Damping ModelCAPWAP Damping ModelCAPWAP Damping Model

    SmithSmith--Combined (Option=2)Combined (Option=2)

    RRdd = R= RSS JJSS vv

    True Smith unti l RTrue Smith unti l RSS = R= RUUthen true viscousthen true viscous

    SmithSmith--Combined (Option=2)Combined (Option=2)

    RRdd = R= RSS JJSS vv

    True Smith unti l RTrue Smith unti l RSS = R= RUUthen true viscousthen true viscous

    Smith (Option=1)Smith (Option=1)

    RRdd = R= RSS JJSS vv

    Smith (Option=1)Smith (Option=1)

    RRdd = R= RSS JJSS vv

    RRuiui, q, qii JJii

    mmss

    RRNsNs--11

    TheThe

    CAPWAPCAPWAP

    SoilSoil

    ResistanceResistance

    ModelModel

    TheThe

    CAPWAPCAPWAP

    SoilSoil

    ResistanceResistance

    ModelModel RRNsNs

    mmtt

    RRtt, q, qttJJTT

    SKSK

    JJBTBT

    mmPLPL

    ttGG

    Not usedNot used

    Shaft Resistance,Shaft Resistance,

    Ns timesNs times

    Mass related to circumferenceMass related to circumference

    Damper related to soil strengthDamper related to soil strength

    Radiation Damping Model Radiation Damping Model

    Standard CAPWAP UnknownsStandard CAPWAP Unknowns

    Main Parameters

    Rui: NS values at shaft +1 value at toe

    Ji: 1 value at shaft +1 value at toe

    qi: Loading - 1 value at shaft +1 value at toe

    Main Parameters

    Rui: NS values at shaft +1 value at toe

    Ji: 1 value at shaft +1 value at toe

    qi: Loading - 1 value at shaft +1 value at toe

    Major Trimming Parameters

    Unloading quake - 1 value at shaft +1 value at toe

    + 1 shaft unloading level

    Major Trimming Parameters

    Unloading quake - 1 value at shaft +1 value at toe

    + 1 shaft unloading level

    Total NS + 8 unknownsTotal NS + 8 unknowns

    For 20 m pile penetration: 18 unknownsFor 20 m pile penetration: 18 unknowns

  • 8/11/2019 cww-introduction-2006.pdf

    4/11

    CAPWAP Match QualityCAPWAP Match Quality

    Match Quality isMatch Quality is

    The sum of absolute values of differences between computedThe sum of absolute values of differences between computed

    and measured values divided by maximum forceand measured values divided by maximum forcePlus blow count penalty (> 0)Plus blow count penalty (> 0)

    MQ =MQ = PeriodPeriodtimetime[F[FMM --FFCC]/F]/FXX ++

    Computed Final SetComputed Final Set Measured Final SetMeasured Final Set 1 mm1 mm

    Toe res. begins, total capacity developsToe res. begins, total capacity develops

    CAPWAP Record DivisionsCAPWAP Record DivisionsCAPWAP Record DivisionsCAPWAP Record Divisions

    Shaft resistance begins to developShaft resistance begins to develop

    FxFx

    Unloading period beginsUnloading period begins

    trtr

    CAPWAP Match QualityCAPWAP Match Quality

    2L/c2L/c

    Period IPeriod I

    tr+3tr+3

    msms

    IIII IIIIII

    tr+5mstr+5ms

    25ms25ms

    IVIV

    trtr

    Match QuantityMatch QuantityMatch QuantityMatch Quantity

    Traditionally we have used measured velocity,

    vm, as an input and calculated force, Fc, and

    compared with measured force, Fm.

    s o en e er o use wave own, d,m, as an

    input, calculate wave up, FU,C and compare it

    with Fu,m. WHY?

    Remember FU,m = (Fm - Zvm)

    and Fd,m = (Fm + Zvm)

    Remember FU,m = (Fm - Zvm)

    and Fd,m = (Fm + Zvm)

    150

    -2000.00

    0.00

    2000.00

    4000.00

    ms

    kipsForceMsd

    ForceCptFORCE MATCHINGFORCE MATCHING

    WAVE MATCHINGWAVE MATCHING

    150

    -500.00

    0.00

    500.00

    1000.00

    ms

    kips

    5 L/c

    WupMsd

    WupCpt

    Recommended CAPWAP ProcedureRecommended CAPWAP Procedure

    1. Data input: select the proper record

    1. Data adjustment (normally automatic)

    2. Build pile model (normally automatic)

    1. Improve resistance distribution

    1. Check quake (particularly toe effect)

    1. Data input: select the proper record

    1. Data adjustment (normally automatic)

    2. Build pile model (normally automatic)

    1. Improve resistance distribution

    1. Check quake (particularly toe effect)

    . ec amp ng e ec s

    3. Check unloading effects

    2. Repeat

    3. Repeat and find absolutely best match quality

    2. Produce output

    . ec amp ng e ec s

    3. Check unloading effects

    2. Repeat

    3. Repeat and find absolutely best match quality

    2. Produce output

  • 8/11/2019 cww-introduction-2006.pdf

    5/11

    Record Selection - QualityRecord Selection - Quality

    Use record of good quality Good proportionality

    No electronic or mechanical noise

    Force returns to zero

    Short rise time

    Record SelectionRecord SelectionWe cannot completely control the test!We cannot completely control the test!

    1.1. For high resistance (set < 3 mm/blow; > 8 BPI)

    find high energy/high force record

    1.1. For high resistance (set < 3 mm/blow; > 8 BPI)

    find high energy/high force record

    . or ow res s ance se > mm ow; < ,

    find blow with low energy/low force

    or reduce energy input to pile

    . or ow res s ance se > mm ow; < ,

    find blow with low energy/low force

    or reduce energy input to pile

    Unit friction < 4Unit friction < 4 ksfksf(200(200 kPakPa )) for most soilsfor most soils

    QT (+TG)QT (+TG) 1.0 if gap is usedCT can be > 1.0 if gap is used

    Match set / blowMatch set / blow (has penalty if set difference > 1 mm)(has penalty if set difference > 1 mm)

    use SK for low set / blow, drilled oruse SK for low set / blow, drilled or augeredaugered pilespiles

    do NOT use SK in high set / blow ( > 8 mm / blow; < 3 BPI )do NOT use SK in high set / blow ( > 8 mm / blow; < 3 BPI )

    Build Pile ModelBui ld Pile ModelBui ld Pile ModelBui ld Pile Model

    1.1. Use 1 m pile segments in most cases

    2. For records with very high frequency content,

    use shorter pile segments - no point using less

    than .25 m se ment len th )t = .05 to .06 ms

    1.1. Use 1 m pile segments in most cases

    2. For records with very high frequency content,

    use shorter pile segments - no point using less

    than .25 m se ment len th )t = .05 to .06 ms

    3. Use 2 m soil segments in most cases

    4. Use 1m soil segments where shallow

    penetrations would yield less than 4 soil

    segments (CAPWAP default)

    3. Use 2 m soil segments in most cases

    4. Use 1m soil segments where shallow

    penetrations would yield less than 4 soil

    segments (CAPWAP default)

    CAPWAPCAPWAP

    Lets have a look at the interactive demo

    that is part of the CAPWAP package.

    CAPWAP Interactive Demo

    Record Adjustment: Use PDARecord Adjustment: Use PDA--W/CWW/CW

    Proportionality and IntegrationProportionality and Integration

    Record Adjustment: Use PDARecord Adjustment: Use PDA--W/CWW/CW

    Proportionality and IntegrationProportionality and Integration

  • 8/11/2019 cww-introduction-2006.pdf

    6/11

    First Trial Analysis: RFirst Trial Analysis: Ruu = RX5;= RX5;

    J=0.16/0.5 s/m; qJ=0.16/0.5 s/m; qss=2.5 mm; q=2.5 mm; qtt=D/120; R=D/120; Rii automaticautomatic

    Force MatchingForce Matching

    First Trial Analysis: RFirst Trial Analysis: Ruu = RX5;= RX5;

    J=0.16/0.5 s/m; qJ=0.16/0.5 s/m; qss=2.5 mm; q=2.5 mm; qtt=D/120; R=D/120; Rii automaticautomatic

    Force MatchingForce Matching

    Wave matchingWave matching -- preferredpreferredWave matchingWave matching -- preferredpreferred

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    2. Determine resistance distribution from difference2. Determine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    2. Determine resistance distribution from difference2. Determine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    ChangedChanged

    1: 59 to 101: 59 to 10

    2: 110 to 102: 110 to 10

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    ChangedChanged

    3: 163 to 1003: 163 to 100

    4: 218 to 1004: 218 to 100

    5: 273 to 1005: 273 to 100

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Used AFUsed AF

  • 8/11/2019 cww-introduction-2006.pdf

    7/11

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Determine resistance distribution from differenceDetermine resistance distribution from difference

    between calculated and measured wavebetween calculated and measured wave--upup

    Used FurtherUsed Further

    ManualManual

    ImprovementsImprovements

    Adjust CAPWAP variablesAdjust CAPWAP variablesAdjust CAPWAP variablesAdjust CAPWAP variables

    Used AQUsed AQ

    adjustingadjusting

    damping,damping,

    quakes, toe andquakes, toe and

    unloadingunloading

    parametersparameters

    Iterate for total capacity, CAPWAP Variables,Iterate for total capacity, CAPWAP Variables,

    damping mode, toe resistance magnitudedamping mode, toe resistance magnitude

    Iterate for total capacity, CAPWAP Variables,Iterate for total capacity, CAPWAP Variables,

    damping mode, toe resistance magnitudedamping mode, toe resistance magnitude

    Check totalCheck total

    capacity (ARD),capacity (ARD),

    Recheck AQRecheck AQ

    Check toe SmithCheck toe Smith

    damping anddamping andresistanceresistance

    Toe quakeToe quake

    sensitivitysensitivity

    Toe quakeToe quake

    sensitivitysensitivity

    QQtt: 0.2: 0.2 0.710.71

    (inch)(inch)

    QQtt: 0.2: 0.2 0.710.71

    (inch)(inch)

    Shaft damping sensitivityShaft damping sensitivityShaft damping sensitivityShaft damping sensitivity

  • 8/11/2019 cww-introduction-2006.pdf

    8/11

    Js: 0.336Js: 0.336 0.200 (s/ft)0.200 (s/ft)Js: 0.336Js: 0.336 0.200 (s/ft)0.200 (s/ft) Toe damping sensitivityToe damping sensitivityToe damping sensitivityToe damping sensitivity

    JJtt: 0.027: 0.027 0.15 (s/ft)0.15 (s/ft)JJtt: 0.027: 0.027 0.15 (s/ft)0.15 (s/ft) Check damping parameters

    1. Higher than recommended at shaft and toe?Low resistance soil? May be OK

    High resistance soil? Consider higher resistance or radiation

    damping (Use RD)

    No experience in these soils? Maybe OK?

    .Switch static resistance or damping from shaft to toe or vice

    versa

    3. Lower than .1 s/m at shaft or toe?Reduce capacity (RD)

    Switch static resistance or damping from shaft to toe or vice

    versa

    OutputOutputOutputOutputOutput Tables:Output Tables:

    Calculated SoilCalculated Soil

    ModelModel

    Output Tables:Output Tables:

    Calculated SoilCalculated Soil

    ModelModel

    CAPWAP FINAL RESULTS

    Total CAPWAP Capacity: 804.4; along Shaft 96.4; at Toe 708.0 kips

    Soil Dist. Depth Ru Force Sum Unit Unit Smith Quake

    Sgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor

    ft ft kips kips kips k ips/ft ksf s/ft in

    804.4

    1 79.4 5.8 16.9 787.5 16.9 2.55 0.27 0.243 0.100

    2 86.0 12.4 9.5 778.0 26.4 1.44 0.15 0.243 0.1003 92.6 19.0 1.9 776.1 28.3 0.29 0.03 0.243 0.100

    4 99.2 25.7 0.0 776.1 28.3 0.00 0.00 0.000 0.100

    5 105.8 32.3 0.0 776.1 28.3 0.00 0.00 0.000 0.1006 112.5 38.9 0.0 776.1 28.3 0.00 0.00 0.000 0.100

    7 119.1 45.5 6.5 769.6 34.8 0.98 0.10 0.243 0.100

    8 125.7 52.1 11.3 758.3 46.1 1.71 0.18 0.243 0.1009 132.3 58.7 11.3 747.0 57.4 1.71 0.18 0.243 0.100

    10 138.9 65.3 6.5 740.5 63.9 0.98 0.10 0.243 0.100

    11 145.5 72.0 6.5 734.0 70.4 0.98 0.10 0.243 0.100

    12 152.2 78.6 6.5 727.5 76.9 0.98 0.10 0.243 0.10013 158 8 85 2 6 5 721 0 83 4 0 98 0 10 0 243 0 100 ii,, ii,, ii ,, ii ii,,

    JJii,, qqii

    ++

    Soil Model ExtensionsSoil Model Extensions

    ii,, ii,, ii ,, ii ii,,

    JJii,, qqii

    ++

    Soil Model ExtensionsSoil Model Extensions

    1 1 . . . 1 . . . .1 . .1

    14 165.4 91.8 6.5 714.5 89.9 0.98 0.10 0.243 0.100

    15 172.0 98.4 6.5 708.0 96.4 0.98 0.10 0.243 0.100

    Avg. Skin 6.4 0.98 0.10 0.243 0.100

    Toe 708.0 100.16 0.092 0.830

    Soil Model Parameters/Extensions Skin Toe

    Case Damping Factor 0.111 0 .309 Smith Type

    Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 75

    R es is ta nc e G ap ( in cl ud ed i n T oe Q ua ke ) ( in ) 0 .0 30

    CAPWAP match quality: 3.96(Wave Up Match)

    Observed: final set = 0.197 in; blow count = 61 b/ftComputed: final set = 0.121 in; blow count = 100 b/ft

  • 8/11/2019 cww-introduction-2006.pdf

    9/11

    Output Tables:Output Tables:

    Extrema,Extrema,

    Case MethodCase Method

    Output Tables:Output Tables:

    Extrema,Extrema,

    Case MethodCase Method

    EXTREMA TABLE

    Pile Dist. max. min. max. max. max. max. max.

    Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy

    ft kips kips ksi ksi kip-ft ft/s in

    1 3.3 1419.4 -559.9 2.914 -1.150 69.27 6.7 1.301

    2 6.6 1419.4 -566.2 2.914 -1.163 69.21 6.7 1.2965 16.5 1420.0 -551.5 2.915 -1.132 69.00 6.7 1.277

    8 26.5 1419.5 -518.3 2.914 -1.064 68.68 6.7 1.25311 36.4 1418.3 -476.7 2.912 -0.979 68.25 6.7 1.22514 46.3 1419.8 -434.1 2.915 -0.891 67.67 6.7 1.195

    17 56.2 1431.7 -394.7 2.939 -0.810 66.93 6.7 1.161

    20 66.2 1440.1 -353.3 2.957 -0.725 65.98 6.6 1.12623 76.1 1442.1 -297.7 2.961 -0.611 64.73 6.6 1.106

    26 86.0 1401.1 -267.7 2.877 -0.550 60.86 6.6 1.091

    29 95.9 1378.0 -196.0 2.829 -0.402 57.21 6.5 1.074

    32 105.8 1393.5 -118.1 2.861 -0.242 55.58 6.7 1.05435 115.8 1404.9 -117.0 2.884 -0.240 55.11 7.2 1.033

    38 125.7 1397.5 -107.4 2.869 -0.221 53.35 8.0 1.01041 135.6 1253.0 -82.1 2.572 -0.169 48.50 8.5 0.985

    44 145.5 1079.6 -74.0 2.217 -0.152 46.60 9.6 0.96047 155.5 954.6 -57.3 1.960 -0.118 43.37 9.8 0.932

    48 158.8 873.8 -57.2 1.794 -0.117 43.10 9.2 0.92349 162.1 843.2 -51.8 1.731 -0.106 41.59 8.8 0.913

    50 165 4 790 2 -53 2 1 622 -0 109 41 30 9 0 0 903 . . . . . . . .51 168.7 813.5 -49.6 1.670 -0.102 39.80 9.1 0.89352 172.0 865.3 -54.5 1.777 -0.112 39.52 9.0 0.883

    Absolute 79.4 2.963 (T = 30.8 ms) 6.6 -1.163 (T = 47.4 ms)

    CASE METHOD

    J = 0 .0 0 .1 0 .2 0 . 3 0 . 4 0 .5 0 .6 0 .7 0 .8 0 .9

    R S1 6 66 .8 49 3. 6 3 20 .5 1 47 .3 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0

    RMX 1060.4 974.9 948.5 922.0 897.9 880.5 874.2 873.5 872.7 871.9R SU 6 66 .8 49 3. 6 3 20 .5 1 47 .3 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0

    RAU= 864.6 (kips); RA2= 891.2 (kips)

    Current CAPWAP Ru= 804.4 (kips); Corresponding J(Rs)= 0.00; J(Rx)=1.00

    VMX VFN VT1*Z FT1 FMX DMX DFN EMX RLT

    ft/s ft/s kips kips kips in in kip-ft kips 6 .8 6 0 .0 0 12 21. 9 1 17 6. 6 1 4 20 .4 1. 313 0 .1 97 6 9. 5 1 10 4. 1

    Output Tables:Output Tables:

    AnnotationsAnnotations

    To review complexTo review complex

    Output Tables:Output Tables:

    AnnotationsAnnotations

    To review complexTo review complex

    Demo; Pile: p66-rst - H-pile Test: 26-Apr-2006 08:01:

    HP14*89; Blow: 4 CAPWAP(R) 2006

    GRL Engineers, Inc. OP: jiu

    CAPWAP ANNOTATIONS

    QS UN CS LS JS SS OSP SK MS PS

    2.520 0.200 0.707 1.000 2.641 0.652 0 0.000 0.000 0.000

    QT TG CT LT JT ST OP BT MT PL

    2.848 0.445 0.300 1.000 0.134 0.080 2 0.000 0.000 1.853

    RSA PI

    0 0.010

    TV AC T1 T2 A12 T3 T4 A34

    20.5 0.08 0.0 20.5 0.05 20.5 24.5 -3.86

    Replay Factor 1 2 Avg.

    Force 0.990 0.990 0.990

    Veloctiy 1.000 1.010 1.005

    Since the data was adjusted through PDA-W,

    no other data adjustment parameters available.

    PE M_BLct C_BLct CI BT MQ FR J_Rx J_Rs

    20. 5 1049.9 744.6 1.422 0.126 1.50 50 00 0. 72 0 .71

    Models, AdjustmentsModels, AdjustmentsModels, AdjustmentsModels, Adjustments

    Page 1 Analysis: 03-Aug-2006

    Added E-Modulus Cut-off Toe Quake and Uplift Frictn

    Quake Multipl ier Damping Optn Reduct. Factr

    0.00 0.00 1.00 0 0.80

    Added Impedance

    13

    87.56

    Added Damping

    None

    Damping Multipliers

    All ones

    Capac ity Reduction Factors

    All ones

    Check calculated final set (blow count)Check calculated final set (blow count)Check calculated final set (blow count)Check calculated final set (blow count)

    How is final set (blow count) calculated?

    Average of final set of all segments

    How does calculated final set (blow count) affect match

    quality?

    MQ penalty: difference of final set in mm - 1

    Calculated final set de ends on and can becorrected b :

    How is final set (blow count) calculated?

    Average of final set of all segments

    How does calculated final set (blow count) affect match

    quality?

    MQ penalty: difference of final set in mm - 1

    Calculated final set de ends on and can becorrected b :

    acceleration adjustment

    total resistance change (static and dynamic)

    quakes

    unloading parameters

    rechecking measured final set

    acceleration adjustment

    total resistance change (static and dynamic)

    quakes

    unloading parameters

    rechecking measured final set

    Find best MQFind best MQ

    Adjust individual segment resistances to improve match

    automatic feature may smoothen distribution too much

    1. See how shifting resistance from shaft to toe and vice

    versa with appropriate quake and damping adjustments

    can improve match

    Adjust individual segment resistances to improve match

    automatic feature may smoothen distribution too much

    1. See how shifting resistance from shaft to toe and vice

    versa with appropriate quake and damping adjustments

    can improve match

    2. Use ARD (or ARDQ) to vary capacity and check RU

    3. Use AQ (Automatic Quantity improvement) on individual

    quantities or groups of CAPWAP variables

    4. Do not spend excessive effort on late record portion

    unless it does affect the capacity/distribution results

    2. Use ARD (or ARDQ) to vary capacity and check RU

    3. Use AQ (Automatic Quantity improvement) on individual

    quantities or groups of CAPWAP variables

    4. Do not spend excessive effort on late record portion

    unless it does affect the capacity/distribution results

    CAPWAP Automatic Features

    AC Automatic CAPWAP (after user initialization)

    AF Calculate shaft resistance parameters

    AQ Select and change CW quantities for BM

    AQ Change current CW quantity for BM

    AQ-Std Change CW standard quantities* for BM

    AC Automatic CAPWAP (after user initialization)

    AF Calculate shaft resistance parameters

    AQ Select and change CW quantities for BM

    AQ Change current CW quantity for BM

    AQ-Std Change CW standard quantities* for BM

    a cu a e a se o oe parame ers

    ARD Static/dynamic resistance exchange for with

    user interaction for BM

    ARDQ Quick Static/dynamic resistance exchange

    *CW standard quantities: SS, ST, QS, QT, TG, UN, CS, CT

    a cu a e a se o oe parame ers

    ARD Static/dynamic resistance exchange for with

    user interaction for BM

    ARDQ Quick Static/dynamic resistance exchange

    *CW standard quantities: SS, ST, QS, QT, TG, UN, CS, CT

    CAPWAP Help FeaturesCAPWAP Help FeaturesCAPWAP Help FeaturesCAPWAP Help Features

    HCHC CAPWAP Variable HelpCAPWAP Variable HelpHCHC CAPWAP Variable HelpCAPWAP Variable Help

    HRHR CAPWAP ResistanceCAPWAP Resistance

    vs Displacement Helpvs Displacement Help

    HMHM CAPWAP Match suggestionsCAPWAP Match suggestions

    HRHR CAPWAP ResistanceCAPWAP Resistance

    vs Displacement Helpvs Displacement Help

    HMHM CAPWAP Match suggestionsCAPWAP Match suggestions

  • 8/11/2019 cww-introduction-2006.pdf

    10/11

    CAPWAP Static Analysis OptionsCAPWAP Static Analysis OptionsCAPWAP Static Analysis OptionsCAPWAP Static Analysis Options

    Extrapolation

    SmootingUser Capacity

    Extrapolation

    SmootingUser Capacity

    0.0 300.0 600.0 900.0 1200.0 1500.00.00

    0.30

    0.60

    Load(kips)PileTop

    Bottom

    PileTop*

    Bottom*

    Ru = 1105.4 kips

    Rs = 780.0 kips

    Rb = 325.4 kips

    Dy = 0.79in

    Dx = 1.41in

    *

    0.90

    1.20

    1.50

    xrap.

    The PEBWAP Result

    (Pile End Bearing Wave Analysis Program)

    0.0 225.0 450.0 675.0 900.0

    0.00

    0 05

    Load (kips)Pile Top

    Stat R. J = 0.7

    RR--TotalTotal

    FFbb(T) = F(T) = F(T) + F(T) + F (T+2L/c)(T+2L/c)

    VVbb(T) = v(T) + v (T+2L/c)(T) = v(T) + v (T+2L/c).

    0.10

    0.15

    0.20

    Set(inch)

    Set(inch)

    = { F(T)= { F(T) F (T+2L/c) } / ZF (T+2L/c) } / Z

    DDbb(T) =(T) = Vb(T)Vb(T) dtdt

    Now plotNow plot Fb(T)Fb(T) vs.vs. Db(T)Db(T)

    PEBWAP AnalysisPEBWAP AnalysisPEBWAP AnalysisPEBWAP AnalysisPile End Bearing Wave Analysis ProgramPile End Bearing Wave Analysis Program

    Load = Case MethodLoad = Case Method

    Displacement =Displacement = vvtoetoe dt;dt; vvtoetoe = (2*WD1= (2*WD1 RTL)/ZRTL)/Z

    Helps find RHelps find Rshaftshaft, q, qtoetoe, J, Jtoetoe

    Pile End Bearing Wave Analysis ProgramPile End Bearing Wave Analysis Program

    Load = Case MethodLoad = Case Method

    Displacement =Displacement = vvtoetoe dt;dt; vvtoetoe = (2*WD1= (2*WD1 RTL)/ZRTL)/Z

    Helps find RHelps find Rshaftshaft, q, qtoetoe, J, Jtoetoe

    CAPWAP Summary and

    Recommendations

    CAPWAP Summary and

    Recommendations

    Signal matching, primarily using resistance

    distribution and damping quantities to obtain

    static bearing capacity and load-set curve

    Engineer has to carefully review result and

    Signal matching, primarily using resistance

    distribution and damping quantities to obtain

    static bearing capacity and load-set curve

    Engineer has to carefully review result and

    com ne w t ot er now e ge a out so to

    get reliable answers

    Automatic methods are tools and cannot be used

    without the discriminating review of the

    CAPWAP engineer

    com ne w t ot er now e ge a out so to

    get reliable answers

    Automatic methods are tools and cannot be used

    without the discriminating review of the

    CAPWAP engineer

    Introducing iCAP

    Signal matching program, working in background,

    which allows immediate analysis during data

    collection

    PAX sends data of blows that meat the user

    defined criteria to iCAP, without user intervention

    per orms an au oma c s gna ma c

    iCAP sends the results back to the PAX program

    when it finishes the analysis

    iCAP results are not available for every blow

    PAX displays last available iCAP results, plus

    currently collected data.

    Introducing iCAP

    Also works with the PDA-W program, for immediate

    signal match capacity determination in remote mode

    (SiteLink).

    Can be performed during replay of previously saved

    data.

  • 8/11/2019 cww-introduction-2006.pdf

    11/11

    Introducing iCAP

    iCAP results:Numeric

    Total iCAP capacity (RU)

    Skin Friction (SF)

    End Bearing (EB)

    MQ match quality number (allows the user to evaluate

    the validity of the iCAP result)

    JC Case Method damping factor (allows the user to fine

    tune the CASE method results for the blows that were not

    analyzed during the test)

    Maximum compression stress (CSC)

    Maximum tension stress (TSC)

    Graphic

    Load-displacement curve

    Force in pile versus depth

    Wave-up measured versus Wave-up calculated

    Introducing iCAP

    iCAP limitations:

    Devised primarily for driven piles of moderate

    length (say less than 30 or 40 m), with known

    uniform pile cross sectional properties, and setper blow between 2.5 and 10 mm

    Not all situations et successful or ossible

    (non-uniform piles, piles with cracks, variable

    conditions)

    Absolutely best match may not be achieved

    Analyst will have to use engineering judgment to

    decide whether iCAP will be sufficient, or whether

    regular CAPWAP Analysis is needed

    Quick iCAP CAPWAP

    Ru 493 kips 506 kips

    CSC 3.15 ksi 3.17 ksi

    TSC 0.22 ksi 0.17 ksi

    MQ 2.12 MQ1.48