Current and Future trends in the High Voltage Direct
Current (HVDC) Market
Current and Future trends in the High Voltage Direct
Current (HVDC) Market
Current and Future Development in the High
Voltage Direct Current (HVDC) Business
Ir. Terklin Sinulingga MM
Senior Bid Manager Alstom HVDC, Stafford - England
USU Medan, 15/05/2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
2/32
HVDC Market
Teknik Elektro USU, 15 May 2013
Market assessment
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
3/32
Market Trends since 2010 till 2020 and onwards
Teknik Elektro USU, 15 May 2013
1. Many HVDC projects in the execution stages, numerous projects in pipeline :
HVDC LCC : Trend on EHVDC : 800 KV >> India, China, Brazil
HVDC-VSC : More projects coming : Norbalt, EstLink, South West Link, Dolwin 3
Offshore wind : Existing market in Germany, potential market in UK, North America
2. Many new outsiders willing to enter the game : Chinese, Japanese, Korean, GE
3. Global price trend : the demand higher than delivered capacity, a positive
effect on higher end markets.
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
4/32
Market assessmentHVDC
Assumption 1 EURO = Rp. 12 000
Potential market HVDC = Rp. 600 Billion, Equi = 60 Billion/year.
APBN Indonesia 2013 = Rp. 1 700 Billion >> 3x potential market HVDC
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
5/32
HVDC Market Evolution
Teknik Elektro USU, 15 May 2013
0
1
2
3
4
5
6
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
Market (
B)
Market (m)
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
6/32
Market Growths
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
7/32Teknik Elektro USU, 15 May 2013
UHVDC Prospects 600kV-800kV
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
8/32
HVDC Market Situation
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
9/32
Current : Traditional Customers
Transmission System Operators (TSO)
- SGCC, CSG - China, project : 3 GeorgesShanghai 500 kV, 3000 MW
- FurnasBrazil, project : Rio Madeira 600 KV, 3150 MW
Government owned
- KEPCO - Korea, project : JejuHainam 180 KV, 400 MW
- Svenska KraftnatDenmark, project : Konti Skan 380 KV, 400 MW
- UTEUruguay, project : Melo 80 KV, 500 MW
- PLN (Future), project : JavaSumatera 500 KV, 3000 MW
De-regulated privately owned- National Grid - UK, project : Western Link 600KV, 2200 MW
- Scottish Power Large companies, UK
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
10/32
Future : Potential Customers
Merchant :
- Tres Amigas, AWT in USA
Large Company :
- Gorgon - Australia, Free port - Indonesia
Significant engineering capability
Manitoba Hydro/TeshmontCanada
Confirmed source of finance
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
11/32
Government owned : HVDC BtB project
MeloUruguay
- Interconnects
500kV 50Hz Uruguay 525kV 60Hz Brazil
- 500MW pole
- 80kV
- 3125A DC current
- Turn-key project - 31 months
Rivera 80MW BtB project
Teknik Elektro USU, 15 May 2013
MontevideoBuenosAires
Rivera
URUGUAY
Melo
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
12/32
Government owned : Submarine Cable Project
Teknik Elektro USU, 15 May 2013
400 MW submarine cable scheme
- 250kV
- 105km submarine cable
- 17km underground cable
- Metallic return
- Bi-directional power flow
- Turn-key project (excluding cables)
Seoul
S. KOREA
Jeju
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
13/32
TSO : Brazilian Model
Customer is a consortium of TSOs
I E Madeira = Furnas + Chesf + ISA/CTEP
Multiple packages ,e.g. stations, lines, switchyards,
Pre-qualification of bidders
Internet auction for contract award
Build Own Operate concept
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
14/32
TSO : Rio Madeira Project - Brazil
Teknik Elektro USU, 15 May 2013
Rio Madeira, Brazil
- 2 x 3150MW bi-poles
BP1: ABB BP2: Alstom
- 600kV
- 2635A DC current
- 2375km OHL
- Worlds longest DC line
- 2 x BtB (ABB)
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
15/32
Chinese Model
Only 2 TSO customers
State Grid Corporation of China (SGCC), China SouthGrid (CSG)
Equipment supply only
Technology transfer to local partners is mandatory
Customer integrates the project
Design Institute is heavily involved
Teknik Elektro USU, 15 May 2013Knowledge Club, 11 May 2012
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
16/32
HVDC Valves : China Main Market features
1. HVDC market in China is not turnkey projects market
2. HVDC scheme is split in various packages by Customers.
3. Market more dominated by the three Chinese players :
XD, XUJI and CEPRI. Both XUJI and CEPRI, owned by SGCC
XUJI based on a technology similar to Siemens technology for 50% of
the sending end, other 50 % is based XUJI/ABB technology.
CEPRI based on their own technology for 25% of the receiving end.
4. Most of the coming 5 years projects in China will be 800 kV or above.
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
17/32
TSO, China : OHL Transmission Projects
Teknik Elektro USU, 15 May 2013Knowledge Club, 11 May 2012
Ningdong Shandong
4000MW
660kV
1335km OHL
3030A DC current
3 Gorges - Shanghai
3000MW
500kV
970km OHL
3000A DC current
ALSTOM + CEPRI partners in thyristor valve order
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
18/32
Teknik Elektro USU, 15 May 2013
Ningdong-Shandong 660kV scheme
2
Ningdong-Shandong HVDC Scheme,
Northern China
Worlds first 660kV HVDC system
All converter equipment supplied by Alstom
Worlds largest single power electronicconverter (2000MW)
660kV1 5 9
7 11 3
12 4 8
6 10 2
12m tall
3000A
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
19/32
Merchant Schemes
Private developments for economic gain
Small companies (
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
20/32
Tres Amigas Project, USA
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
21/32
Atlantic Wind Connection, USA
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
22/32
Off-shore Wind Farms - UK Round 3
Off-shore Transmission Operators (OFTO)
Can not be the GB system operator (National Grid)
Consortia of groups have won the rights
EAOW = Iberdrola + Scottish Power + Vatenfall Hornsea = Mainstream Renewable + Siemens + Hotchtief Dogger Bank = SSE Renewables + RWE Renewables + Statoil/Statkraft Firth of Forth = SSE Renewables + Fluor
Generators can build the transmission scheme, but must sell the asset
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
23/32
North Sea HVDC projects
Teknik Elektro USU, 15 May 2013
Firth of
Forth
Dogger Bank
Hornsea
East Anglia
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
24/32
HVDC Connections - incl. Off-shore Wind Farms
Teknik Elektro USU, 15 May 2013
DC cable
Q1 Q2P
VSC VSC
Station 1 Station 2
UC1 UC2
IC1
Network
1
Network
2
Off-shore
wind farm
HVAC
platform
HVDC
platform
On-shore
HVDC station
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
25/32
Off-shore Wind Farm Connection
Teknik Elektro USU, 15 May 2013
AC/AC AC/DC DC/AC
Wind
turbines
MV
cablearray
AC
platform
HV
cable
HVDC
platform
DC cable HVDC
station
Generator Transmission operator
HVAC/HVDC manuf.
Scope
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
26/32
Potential market : Refurbishment ConverterStation
The last mercury arc and first generation thyristor HVDC scheme need
equipment replacement
Complete station replacementKonti-Skan, Denmark
Valve and control replacementCross Channel, France - England
Controls replacementMcNeil, Canada
Many more schemes need refurbishment/replacement
Pacific intertieCelilo and Sylmar, USA
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
27/32
Example Refurbishment : Cross Channel (IFA2000)
Teknik Elektro USU, 15 May 2013
Sellindge (UK)
Air-cooled Valves, H200 type : old
2 x 3.6kV, 56mm
Thyristor Valves , H400 type: new
8.5 kV, 125 mm Thyristor
Les Mandarins (Fr)
Air-cooled Valves, H200 type : old
2 x 4kV, 75mm
Thyristor Valves, H400 type : new
8.5 kV, 125 mm Thyristor
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
28/32
Potential market : Multi-terminal DC Schemes(MTDC)
There are only 2 such (LCC) schemes in the world
SCAOI : Sardinia - CorsicaItaly QuebecNew England
LCC scheme in construction
NERAGRA in India
VSC technology opens up the market for many moreMTDC schemes
South West Link, Sweden Eastern Link, UK Atlantic Wind, USA Ultimately the European Super grid
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
29/32
Teknik Elektro USU, 15 May 2013
Example MTDC : Sweden - South West
Power: 2 x 720MW
Voltage DC: +/-300kVdcVoltage AC: 420kVac
Client: Svenska Kraftnt
Contract award : Dec 2011
Phase 1 in-service : 2014/15
Phase 2 in service : 2018
Phase 1: South West Link
-4 x VSC Converter Stations
-2 x 720MV links, +/- 300kV DC,
-OHL and Cables (by others)
-Multi-terminal control system
Phase 2:
- 2 x VSC Converter Stations in Norway
- Connection of Barkeryds converter
stations to Norway
- Operation in multi-terminal mode
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
30/32
PriorityElectricity Corridors
Northern Seas
North Sea Irish Sea Baltic Sea English Channel
NorthSouth
Western Europe
North- South
Central Europe Eastern Europe
Baltic states
Teknik Elektro USU, 15 May 2013
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
31/32
HVDC Trend Markets Conclusions
1. HVDC is a multi-Billion Euro per year market
2. The customer base is increasing but changing
3. Traditional TSOs are being joined by new players, such as generators,
construction companies, oil & gas companies, etc
4. Merchant schemes are now being developed
5. VSC Multi-terminal systems are coming and will need new technologies
6. HVDC scope of supply is increasing
Teknik Elektro USU, 15 May 2013
O f C
-
5/22/2018 Current and Future Customers in HVDC Market USU 15 May 2013 Final
32/32
Opportunity for Collaboration Industry andUniversity
More and more Collaboration between Industry & University :
- Development Thyristor Valves H400 : Alstom with Manchester University, England
- Development VSC Generation 1 & 2 : Alstom with Nottingham University andImperial College London
- Development Software engineering study : Alstom with Manitoba University Canada