Given: 1. At start of project, each of three separate activities A B, & C may begin and progress concurrently. 2. D may begin until A is completed 3. E may also begin only upon completion of A 4. F follows Activity B 5. G cannot be started until both E and F are completed. 6. Completion of both G and H allow J to start. 7. H is dependent upon completion of C for its start. 8. The start of J is further restrained by a notice of completion of D. 9. K follows D and culminates with event J. Required: a. Draw the network diagram for the above project and prepare a table for ES, EF, LS, LF, TF, and FF. b. Determine also the critical activities. c. Prepare a bar chart for the above project.

description

construction planning

Transcript of cpm

Given:1. At start of project, each of three separate activities A B, & C may begin and progress concurrently.2. D may begin until A is completed3. E may also begin only upon completion of A4. F follows Activity B5. G cannot be started until both E and F are completed.6. Completion of both G and H allow J to start.7. H is dependent upon completion of C for its start.8. The start of J is further restrained by a notice of completion of D.9. K follows D and culminates with event J.

Required:a. Draw the network diagram for the above project and prepare a table for ES, EF, LS, LF, TF, and FF.b. Determine also the critical activities.c. Prepare a bar chart for the above project.