Department of Public Works and Environmental Services Planning & Design Division 12000 Government Center Parkway, Suite 449 Fairfax, VA 22035-0052 Phone: 703-324-5800, TTY: 1-800-828-1120, Fax: 703-324-4365 www.fairfaxcounty.gov/dpwes County of Fairfax, Virginia M E M O R A N D U M DATE: June 19, 2008 TO: Jimmie D. Jenkins, Director Department of Public Works and Environmental Services FROM: Ronald N. Kirkpatrick Planning and Design Division SUBJECT: Planning and Design Division Monthly Projects Status Report Attached is a copy of the May 2008 Monthly Projects Status Report. This report provides a status summary for capital projects managed within the Planning and Design Division (P&DD). A separate report will be issued by the Stormwater Planning Division for drainage related capital projects. If you have any questions, please call at 703-324-5800. RNK/ml/1257m Attachment: As Stated PUBLIC WORKS AND ENVIRONMENTAL SERVICES DISTRIBUTION Howard J. Guba, Deputy Director, Department of Public Works and Environmental Services Shahram Mohsenin, Director, Wastewater Planning and Monitoring Division Gilbert Osei-Kwadwo, Branch Chief, Wastewater Planning and Monitoring Division Edgar R. Jones, Chief, Financial Management & Financial Planning Branch, Wastewater Planning & Monitoring Division Randy Bartlett, Director, Stormwater Management, DPWES Scott R. St.Clair, Director, Maintenance and Stormwater Management Division Steve Aitcheson, Stormwater Management Craig Carinci, Director, Stormwater Planning Division (SWPD) Don Demetrius, Chief, Watershed Projects Evaluation Branch (WPEB), SWPD Chad Crawford, Chief, Watershed Projects Implementation Branch (WPIB), SWPD Scott Ramsey, MA III, SWPD, DPWES Dale Glines, Engineering Technician III, MSMD, DPWES Nat Atapoor, Director, Construction Management Division Vickie McEntire, County Surveyor, CMD Bruce Goudarzi, Chief, Utilities Construction Branch, CMD Robin W. Patton, Director, Land Acquisition Division James Ratliff, Project Manager, Land Acquisition Division John Honnick, Senior Right-of-Way Agent, Land Acquisition Division Keith Wilson, Senior Right-of-Way Agent, Land Acquisition Division Walter T. Wozniak, Chief, Utilities Design Branch, P&DD Larry Ichter, Deputy Director, Transportation Design, P&DD Carey F. Needham, Deputy Director, Building Design, P&DD Jeff Kent, Chief, Administrative Support Branch, CAP Natalie Colley, Engineering Technician III, TDB, P&DD Anna Carlen, Administrative Support Branch, CAP OUTSIDE AGENCY DISTRIBUTION Carol Bondurant, VDOT, 14685 Avion Parkway, Chantilly, VA 20151 w/attachment Fund 304, 314, 315, HCD, & Misc.; [email protected] Dorothy Purvis, VDOT, 14685 Avion Parkway, Chantilly, VA 20151; [email protected] Rick A. Miller, VDOT, [email protected] Jan Vaughan, VDOT, [email protected]

Transcript of County of Fairfax, Virginia · County of Fairfax, Virginia M E M O R A N D U M ... Carey F....

Department of Public Works and Environmental ServicesPlanning & Design Division

12000 Government Center Parkway, Suite 449Fairfax, VA 22035-0052

Phone: 703-324-5800, TTY: 1-800-828-1120, Fax: 703-324-4365www.fairfaxcounty.gov/dpwes

C o u n t y o f F a i r f a x , V i r g i n i a

M E M O R A N D U M

DATE: June 19, 2008 TO: Jimmie D. Jenkins, Director

Department of Public Works and Environmental Services

FROM: Ronald N. Kirkpatrick Planning and Design Division SUBJECT: Planning and Design Division Monthly Projects Status Report Attached is a copy of the May 2008 Monthly Projects Status Report. This report provides a status summary for capital projects managed within the Planning and Design Division (P&DD). A separate report will be issued by the Stormwater Planning Division for drainage related capital projects. If you have any questions, please call at 703-324-5800. RNK/ml/1257m Attachment: As Stated PUBLIC WORKS AND ENVIRONMENTAL SERVICES DISTRIBUTIONHoward J. Guba, Deputy Director, Department of Public Works and Environmental Services Shahram Mohsenin, Director, Wastewater Planning and Monitoring Division Gilbert Osei-Kwadwo, Branch Chief, Wastewater Planning and Monitoring Division Edgar R. Jones, Chief, Financial Management & Financial Planning Branch, Wastewater Planning & Monitoring Division Randy Bartlett, Director, Stormwater Management, DPWES Scott R. St.Clair, Director, Maintenance and Stormwater Management Division Steve Aitcheson, Stormwater Management Craig Carinci, Director, Stormwater Planning Division (SWPD) Don Demetrius, Chief, Watershed Projects Evaluation Branch (WPEB), SWPD Chad Crawford, Chief, Watershed Projects Implementation Branch (WPIB), SWPD Scott Ramsey, MA III, SWPD, DPWES Dale Glines, Engineering Technician III, MSMD, DPWES Nat Atapoor, Director, Construction Management Division Vickie McEntire, County Surveyor, CMD Bruce Goudarzi, Chief, Utilities Construction Branch, CMD Robin W. Patton, Director, Land Acquisition Division James Ratliff, Project Manager, Land Acquisition Division John Honnick, Senior Right-of-Way Agent, Land Acquisition Division Keith Wilson, Senior Right-of-Way Agent, Land Acquisition Division Walter T. Wozniak, Chief, Utilities Design Branch, P&DD Larry Ichter, Deputy Director, Transportation Design, P&DD Carey F. Needham, Deputy Director, Building Design, P&DD Jeff Kent, Chief, Administrative Support Branch, CAP Natalie Colley, Engineering Technician III, TDB, P&DD Anna Carlen, Administrative Support Branch, CAP OUTSIDE AGENCY DISTRIBUTION Carol Bondurant, VDOT, 14685 Avion Parkway, Chantilly, VA 20151 w/attachment Fund 304, 314, 315, HCD, & Misc.; [email protected] Dorothy Purvis, VDOT, 14685 Avion Parkway, Chantilly, VA 20151; [email protected] A. Miller, VDOT, [email protected] Jan Vaughan, VDOT, [email protected]

Jimmie D. Jenkins Planning and Design Division Monthly Projects Status Report Page 2 of 2

Charlene Whitfield, DVP, Manager Regional Projects, 171 Elden St., Herndon, Va. 20170; [email protected] John W. Dargle, Director, Fairfax County Park Authority Mike Lake, Department of Transportation w/attachment Fund 304, 305, & Misc. Katharine Ichter, Director, Department of Transportation Charlie Strunk, Department of Transportation Ellen Gallagher, Department of Transportation Karyn Moreland, Department of Transportation Chris Wells, Department of Transportation Tom Biesiadny, Department of Transportation Paul Mounier, Bus Stop Coordinator, Department of Transportation Jeffrey Hermann, Department of Transportation David B. Marshall, Assistant Director, Planning Division, Department of Planning and Zoning Paula C. Sampson, Director, Housing and Community Development (HCD), w/attachment 314 and 315 Harry Swanson, Director of Revitalization & Real Estate, HCD, w/attachment Fund 315 Barbara Byron, Director, Zoning Evaluation Division, Department of Planning and Zoning Sheng Leu, Department of Planning and Zoning Dave Guerra, Fairfax County Water Authority; [email protected] Jeannie Swim, Fairfax County Water Authority; [email protected] Scott, Fairfax County Water Authority; [email protected] Milgrim, Environmental Health Supervisor, Fairfax County Health Department Susanne Sotirchos, HCD, w/attachment Fund 308, 314, 315, HCD & Misc. Mark Canale, Department of Transportation Bill Harrell, Department of Transportation, [email protected] Todd Lawson, Verizon, 2980 Fairview Park Dr., 7th Floor, Falls Church, VA. 22042; [email protected] David A. Guillaudeu, Engineering Assistant, Verizon Communications, david.a.guillaudeu@verizon,com Jo Anne Sorenson, VDOT, 14685 Avion Parkway, Chantilly VA 20151, w/attachment Fund 308, 304, 305, 314, 315, HCD & Misc.; [email protected] William V. Johnson Jr. 14685 Avion Pkwy, Chantilly, VA 20151; [email protected] Burke, VDOT, [email protected] Charlotte E. Miller, VDOT, [email protected] Donald Ostrander, Traffic Engineering Section, VDOT Northern Va. District, [email protected] Melliza, Washington Gas; [email protected] Mullins, VDOT, [email protected] Javier Baldivieso, [email protected] Love, [email protected]

PLANNING & DESIGN DIVISION MONTHLY PROJECT STATUS REPORT

May 2008

TABLE OF CONTENTS PAGE . UTILITIES DESIGN BRANCH

FUND 102 - FEDERAL & STATE GRANT (BUS SHELTERS) 1 - 5 FUND 303 - COUNTY CONSTRUCTION 6 - 33 FUND 307 - SIDEWALK CONSTRUCTION 33 - 44 FUND 402 - SANITARY SEWER CONSTRUCTION 44 - 48

TRANSPORTATION DESIGN BRANCH

FUND 102 - FEDERAL & STATE GRANTS 1 - 2 FUND 301 - CONTRIBUTED ROADWAY IMPROVEMENT FUNDS 2 - 3 FUND 303 - COUNTY CONSTRUCTION 3 FUND 304 - PRIMARY & SECONDARY ROAD BOND CONSTRUCTION 3 - 27 FUND 307 - SIDEWALK CONSTRUCTION 28 FUND 312 - PUBLIC SAFETY CONSTRUCTION 29 FUND 315 - COMMERCIAL REVITALIZATION PROGRAM 28 - 29 FUND 340 - HOUSING ASSISTANCE PROGRAM 29

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

26002G

Bus Shelters-CMAQ02407

South Van Dorn St @Crown Royal Dr NB

$19,000

Installation of bus shelter Survey, utility designation, and design complete; NEPA document approved; environmental clearance to start land acquisition obtained; utility conflicts with Verizon and FCWA resolved; land acquisition in progress (authorization to begin negotiations issued 5/03); property owner concerned that shelter plans conflict with rezoning and development plan; coordinated with Supervisor's office; DOT coordinating with proposed rezoning application to obtain a proffer commitment to install the proposed bus shelter (development plan currently going through rezoning process); project on-hold pending the completion of this coordination (follow up memorandum to DOT 3/19/08 for a status update).

Lee Guarino, MichaelGlass, Lisa

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

04/04102 On-Hold

26002G

Bus Shelters-CMAQ02409

Franconia Rd @ Westchester St EB

$15,000

Installation of bench Survey, utility designation, and design complete; NEPA document approved; environmental clearance to start land acquisition obtained; additional property research revealed that land acquisition is required; land acquisition in progress (authorization to prepare VDOT Basic Acquisition Report and begin negotiations issued 10/1/03); property owner non-responsive - finally able to contact; property owner's revisions to easement language reviewed by County Attorney's office and forwarded back to property owner; subsequent negotiations unsuccessful; memo to DOT 9/26/06, recommending deletion of project; DOT coordinating with Supervisor's office (follow up memorandum to DOT 3/19/08 for a status update).

Lee Guarino, MichaelColeman, Michael

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/06TBDNA TBDTBD09/05

Monthly RemarksProject Description

04/06102 On-Hold

26002G

Bus Shelters-CMAQ02602

Ft Hunt Rd @ Belle View Blvd WB (N Side)

$19,000$0

Installation of bus shelter Survey, utility designation, and design complete; stop moved from location in initial federal environmental clearance - new NEPA document approved; environmental clearance to start land acquisition obtained; utility coordination in progress; land acquisition required (authorization to begin land acquisition issued 11/03); property owner requested changes in easement language made but subsequent negotiations unsuccessful; memo to DOT 9/26/06, recommending deletion of project; DOT coordinating with Supervisor's office and on 7/24/07 advised that Supervisor supports condemnation to acquire outstanding land rights (VDOT does not have any restrictiions for the use of grant funds for condemnation); LAD coordinating with District Supevisor's office.

Mount Vernon Guarino, MichaelColeman, Michael

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/10 01/06 08/1006/10NA 09/05

Monthly RemarksProject Description

04/06102 Land Acquisition

Thursday, June 19, 2008 Page 1 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

26002G

Bus Shelters-CMAQ02719

Arlington Boulevard EB @ Prosperity Ave

$45,000$0

Installation of bus shelter CMD authorized 5/2/08 to proceed with construction via the annual contractor; NTP issued 6/2/08 (scheduled completion 7/17/08).

Providence Royse, AndyColeman, MichaelFarsad, NahidMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0704/07 04/07 04/08 07/0805/0811/07

Monthly RemarksProject Description

102 Construction

26002G

Bus Shelter-CMAQ07001

BS#01730 Alban Road EB @ Springfield Oaks Drive

$30,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey, utility designation, and preliminary site layout complete; negotiations in progress with the environmental consultant to obtain NEPA clearance (final comments being addressed); schedule to be determined once environmental contract is executed.

Lee Gallo, Michael

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

26002G

Bus Shelter-CMAQ07002

BS#01248 Hinson Farm WB @ Tis Well

$30,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey, utility designation, and preliminary site layout complete; negotiations in progress with the environmental consultant to obtain NEPA clearance (final comments being addressed); schedule to be determined once environmental contract is executed.

Mount Vernon Gallo, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

Thursday, June 19, 2008 Page 2 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

26002G

Bus Shelter-CMAQ07003

BS#03020 Leesburg Pike EB @ Nevius Street

$35,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey complete; ran preliminary sight distance calculations which may impact final shelter location; negotiations in progress with the environmental consultant to obtain NEPA clearance (final comments being addressed); schedule to be determined once survey complete and environmental contract executed.

Mason Gallo, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

26002G

Bus Shelter-CMAQ07004

BS#03129 Old Keene Mill EB @ Ainsworth Avenue

$30,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey complete; sight distance requirements may prevent installation of shelter - coordination with VDOT required to resolve issue; coordination with DOT on overall project scope; negotiations in progress with the environmental consultant to obtain NEPA clearance (final comments being addressed); schedule to be determined once environmental contract is executed.

Springfield Gallo, Michael

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

26002G

Bus Shelter-CMAQ07005

BS#04042 Braddock Road EB @ Carriagepark Drive

$35,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey, utility designation, and preliminary site layout complete; negotiations in progress with the environmental consultant to obtain NEPA clearance (final comments being addressed); schedule to be determined once survey complete and environmental contract executed.

Braddock Gallo, Michael

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

Thursday, June 19, 2008 Page 3 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

26002G

Bus Shelter-CMAQ07006

BS#04050 Braddock Road EB @ Nash Drive

$35,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey, utility designation, and preliminary site layout complete; negotiations with the environmental consultant in progress to obtain NEPA clearance (final comments being addressed); schedule to be determined once environmental contract executed.

Braddock Gallo, Michael

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

26002G

Bus Shelter-CMAQ07007

BS#05343 McClearen Road EB @ Towerview Road

$30,000$0

Installation of bus shelter Project funded with federal (CMAQ) dollars; field survey, utility designation, and preliminary site layout complete; negotiations with the environmental consultant in progress to obtain NEPA clearance (final comments being addressed); schedule to be determined once environmental contract executed.

Sully Gallo, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

102 Pre-Design

26006G

Richmond Hwy Public Transport Initiative: Intersections Phase 4

06004

Route 1 SB: Sacramento Drive: Southbound REX Bus Stop

$65,000

Installation of REX Bus Shelter and Bus Stop Improvements

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; CMD authorized 12/13/06 to proceed with construction via the annual contractor (NTP issued 1/3/07); construction 100% complete (reset of trash can so display can be opened in progress); material for solar lights received and installed; lighted sign pole solar light installation outstanding (P&DD coordinating with new manufacturer); trash can location to be changed.

Mount Vernon Zahirieh, Shahla

Minnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/06 12/06 02/07 01/0612/06NANA

Monthly RemarksProject Description

102 Post-Construction

Thursday, June 19, 2008 Page 4 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

26007G

Seven Corners Transit Center06000

$1,000,000$0

Design and construction of a transit center on the Seven Corners Shopping Center parking lot site

CMAQ funds approved for project; VDOT Project Agreement approved and VDOT authorization to initiate the Preliminary Engineering phase received; survey and design by Rinker Design Associates (task order NTP issued 1/31/07); preliminary design plans and submitted 3/24/08 to LDS for review; 60% design plans and final environmental documents submitted 4/8/08 to County and VDOT; AE is addressing comments (90% complete design plan submission scheduled for 8/08); current indications are that no land acquisition will be required.

Mason Adams, Shanna

Farsad, NahidHousley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/08 01/09 06/09 10/0903/09NANA

Monthly RemarksProject Description

102 Planning and Design

26008G

Countywide Trails07001

Soapstone Drive Walkway

$1,500,000$0

3,300 LF of walkway Project Agreement with VDOT approved; VDOT authorization to proceed with Preliminary Engineering received 11/26/07 (full length of project); feasibility study to be prepared and citizen coordination conducted to define scope of walkway improvements prior to initiating design; selection process for a consulting engineer complete and Request for a Proposal sent 6/4/08; contract negotiations in progress; completion schedule to be prepared after contract for the feasibility study is approved.

Hunter Mill Adams, ShannaPM PDD:PM LAD:PM CMDE:PM CMDS:

NATBD TBD TBDTBDNA

Monthly RemarksProject Description

102 Pre-Design

26008G

Countywide Trails07002

Columbia Pike Phase II Walkway

$500,000$0

600 LF of 8-foot wide walkway and installation of a bus shelter, eastbound lane Columbia Pike at Powell Lane

All necessary land rights for the project acquired 10/6/06; trail project to provide for the construction of the proposed bus shelter; additional CMAQ funds approved for the construction of the Phase II section of trail; Project Agreement with VDOT approved; DOT coordinating with VDOT to issue authorization to proceed (completion schedule to be prepared after VDOT issues a NTP).

Mason Guarino, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

NATBD TBD TBD TBDTBDNA

Monthly RemarksProject Description

11/07102 On-Hold

Thursday, June 19, 2008 Page 5 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

009471

Lee District Capital ProjectsWT002

Governor's Hill Drive Walkway

$240,000$0

750 LF of 5-foot wide concrete walkway along the south side of Franconia Road between Governor's Hill Road and Telegraph Road

Lee District Capital Project funds reassigned 7/17/06; survey and design by annual consultant (task order cost proposal approved 10/18/06); survey complete and design in progress (A/E is addressing pre-final plan review comments); citizen meeting conducted 3/1/07; LAD authorized 8/1/07 to acquire easements from HOA property (point of contact established and negotiations in progress ~ LAD coordinating with District Supervisor on difficult negotiations with the HOA and possible project deletion); LAD schedule adjustment 3/27/08.

Lee Royse, AndyBarnes, Dianne

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0806/07 08/07 10/08 02/0909/0805/08

Monthly RemarksProject Description

303 Land Acquisition

009472

Mason District Capital ProjectsWT002

Columbia Pike: Govnmnt Ctr to Dowing St

$570,000$0

500 LF of 5-foot wide concrete sidewalk

Project is part of the Second Four-Year Transportation Program and was approved by the BOS on 10/15/07; design complete and all land rights obtained; retaining wall design by annual consultant complete (application for a building permit submitted); VDOT final review complete and land use permit obtained; construction bid package prepared and will be processed for final authorization after receipt of building permit; additional funding required for construction included in the approved Fall 2007 Transportation Bond Referendum.

Mason Flowers, RandallBuckley, BethFarsad, NahidJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0602/07 11/07 12/08 12/0807/0702/07

Monthly RemarksProject Description

303 Planning and Design

009473

Mt. Vernon District Capital Projects

WT002

David Site Wayside Signage

$10,000$0

Installation of signage at historic site

District Supervisor 8/27/07 reassigned funds to project; sign graphics complete; coordination on going with citizen group and FCPA on scope of improvements.

Mount Vernon Flowers, RandallPM PDD:PM LAD:PM CMDE:PM CMDS:

NANA NA TBD TBDTBDNA

Monthly RemarksProject Description

303 Pre-Design

Thursday, June 19, 2008 Page 6 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

009474

Providence District Capital Projects

WT003

Allan Avenue Walkway

$7,000$0

Engineering survey to determine Allan Avenue right-of-way

Funds reassigned 11/30/06 from Providence Contingency to stake out Allen Avenue right of way to determine impact of proposed walkway on adjacent properties; survey work complete and citizen meeting conducted 4/26/07; coordination in progress between the District Supervisors office and the HOA for a determination on obtaining citizen support to proceed with design (anticipated resolution 7/08).

Providence Rayyan, Ahmed

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

NANA NA NA NANANA

Monthly RemarksProject Description

12/07303 On-Hold

009475

Springfield District Capital Projects

WT002

Tuttle Road

$441,200$175,000

2,100 LF of 5-foot wide asphalt walkway

Survey and design by Rinker Detwiller via a task order to an annual contract; field survey complete; design complete including addressing final review comments; final plans resubmitted 5/30/07 to VDOT for approval; LAD acquired land rights (easements and FCSB permit) 2/12/07); coordination on going with Verizon for pole adjustments; additional funds for construction requested at the FY 2007 Third Quarter Budget Review submission but not approved (to be resubmitted for consideration with the FY 2008 Carryover Budget Review); project on hold pending identification of addditonal funds to complete.

Springfield Flowers, RandallZore, Tasneem

Jozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0703/06 04/06 05/07 TBDTBD09/06

Monthly RemarksProject Description

10/07303 On-Hold

V00003

Road Viewer ProjectsRVP34

I-Street

$36,000

180 LF road improvements Preliminary punch list developed with VDOT; design phase behind schedule (approved due date 12/05); VDOT has verbally advised that they will accept prior BOS resolution for incorporation of this road into the State Secondary System; coordination with VDOT ongoing to finalize this understanding.

Mount Vernon Wozniak, WalterPM PDD:PM LAD:PM CMDE:PM CMDS:

12/06 06/08 NA NA NANANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 7 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

V00003

Road Viewer ProjectsRVP35

Woodburn Access Rd

$250,300

850 LF road improvements Negotiations between County and INOVA in progress on Woodburn Center for Community Mental Health site which may delete the need to proceed with the access road project; Building Design Branch to included access road issue with briefing of County Executive (deletion of road improvements deferred ~ project to remain on hold).

Providence Wozniak, WalterColeman, MichaelFarsad, NahidMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

NATBD TBD TBD TBDTBDNA

Monthly RemarksProject Description

04/03303 On-Hold

V00004

Road Maintenance ProgramRM101

Tilbury Road

$70,000$0

Acquisition of existing roadway right-of-way and minor maintenance of existing alley

Funds approved at the FY 2007 Third Quarter Budget Review to address the ownership of Tilbury Road right-of-way and to provide emergency access by the Fire Department; property and topographic survey complete; citizen meeting conducted 3/12/08; LAD authorized 3/20/08 to acquire the existing right-of-way via condemnation of an "owner unknown" (Administration Item scheduled 6/30/08 and public hearing scheduled 7/21/08);

Lee Schmidt, NatashaZore, Tasneem

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0804/08 04/08 10/08NANA08/08

Monthly RemarksProject Description

303 Land Acquisition

V00004

Road Maintenance ProgramRM185

Allen Street

$577,000

780 LF road improvements Construction 100% complete (addressing punch list items: Dominion Power removed guy wire; obtaining proposal from Verizon to raise overhead cable); administrative processing for acceptance of road by VDOT in progress (submitted paperwork to VDOT utility checklist approved and final package for VDOT; final site inspection approval obtained 10/18/06); additional field tests on asphalt (density and thickness) performed by the contractor (test result summary received 5/25/07 ~ passed); VDOT administrataive process continuing.

Providence Schmidt, NatashaColeman, MichaelMinnix, Wesley

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/04 09/0403/04NA

Monthly RemarksProject Description

303 Post-Construction

Thursday, June 19, 2008 Page 8 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

V00004

Road Maintenance ProgramRM188

Abbott Lane

$65,000$0

380 LF road improvements Design in progress; updated survey in progress; coordination with VDOT in progress to conduct a joint site inspection to define scope of corrective work; ECS geotechnical engineering of existing pavement structure completed 12/9/05; no land acquisition is anticipated; construction contingent upon availability of possible BORV funds that may be approved during FY 2006/FY 2007; project completion schedule to be approved after a funding source for construction is identified.

Providence Flowers, RandallPM PDD:PM LAD:PM CMDE:PM CMDS:

02/06 06/06NATBD TBDTBDNA

Monthly RemarksProject Description

303 Planning and Design

V00004

Road Maintenance ProgramRM190

Silverleaf Drive

$75,000$0

700 LF road improvements VDOT punch-list items obtained, geotechnical investigation complete, and preliminary VDOT comments on pavement design received; project in design; coordination with VDOT in progress to conduct a joint site inspection to define scope of corrective work; ECS conducting soil borings to determine existing pavement structure; updated survey complete; land acquisition may be required; construction contingent upon availability of FCRMIP funds after the completion of the project design; project completion schedule to be approved after a funding source for construction is identified.

Springfield Flowers, RandallPM PDD:PM LAD:PM CMDE:PM CMDS:

04/06 NATBD TBD TBDTBDNA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

01063

WB Little River Tnpk and Pinecrest Vista Dr

$24,000$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 9 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

01125

SB Fort Hunt Road near Gahant Road

$21,200$0

Loading pad Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review; land acquisition required (preparing schedule adjustment due to required easements).

Mount Vernon Utterback, BrianBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0803/08 06/08 07/08 03/0912/0811/08

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

01185

NB Fort Hunt Road and Gahant Road

$21,400$0

Loading pad, 35 LF trail, retaining wall, and pedestrian ramp

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 60% design plans received 4/4/08 and under review; test hole to locate a water line complete - no conflict; land acquisition required (preparing schedule adjustment due to required easements).

Mount Vernon Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

12/0803/08 07/08 07/08 04/0901/0912/08

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

01600

WB Arlington Dr near Windbreak Dr

$15,700$0

Loading pad and accesss improvements

Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Mount Vernon Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 10 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

01904

SB Colts Neck Road & Hunter Square Court

$29,000$0

Loading pad, sidewalk, and pedestrian ramp

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08; survey (by County) and utility designation complete; design in progress; easement required.

Hunter Mill Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0908/08 08/08 06/09 06/0902/0901/09

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

01906

NB Reston Parkway and South Lakes Dr

$19,900$0

Loading pad and curb and gutter extension

Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); relocation of existing stop required; survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

02022

SB Telegraph Road and Highland Meadows Ct

$29,200$0

Loading pad, 100' curb and gutter and concrete sidewalk, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review; land acquisition and VDOT plan review required (preparing schedule adjustment due to required easements and VDOT review).

Lee Utterback, BrianBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0903/08 09/08 07/08 06/0903/0902/09

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 11 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

02420

WB Arlington Boulevard Near Graham Road

$28,700$0

Loading pad, bus shelter, lighting, 20 LF sidewalk, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review; VDOT plan review required (preparing schedule adjustment due to required VDOT review).

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 08/08 07/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

02421

WB Arlington Boulevard and Allen St

$28,700$0

Loading pad, improved access, and curb cut ramp from frontage road.

Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress; expanding scope to improve accessibility per 4/15/08 meeting with DOT.

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

02465

SB Fairview Park Dr and Yancey Dr

$15,700$0

Loading pad Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 12 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

02471

NB Fairfview Park Dr and New Providence Dr

$20,000$0

Loading pad and bench Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 08/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03082

WB Old Keene Mill Road and Ainsworth Avenue

$33,000$0

Loading pad, sidewalk and curb and gutter improvements

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08; survey (by County) and utility designation complete; design in progress; easement required.

Springfield Utterback, Brian

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0908/08 08/08 06/09 06/0902/0901/09

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03083

WB Old Keene Mill Rd and Carrleigh Pkwy

Loading pad, 50' concrete sidewalk, 2 pedestrian ramps, 2 cross walks, and 6 pedestrian signals

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; NTP for traffic signal design issued 3/1/08; A/E preparing 60% design plans; land acquisition and VDOT plan review required (preparing schedule adjustment due to required easements, VDOT review, and signal design; preparing new TPE to incorporate signal work).

Springfield Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

05/0903/08 11/08 07/08 03/1010/0905/09

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 13 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03125

EB Old Keene Mill Rd @ Millwood Dr

$16,500$0

Loading Pad Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; project scope revised from a shelter to a loading pad due to field conditions; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Springfield Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03128

EB Old Keene Mill Rd and Carrleigh Pkwy

Loading pad, 175' asphalt trail, and pedestrian signals

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; NTP for traffic signal design issued 3/1/08; A/E preparing 60% design plans; land acquisition and VDOT plan review required (preparing schedule adjustment due to required easements, VDOT review, and signal design; preparing new TPE to incorporate signal work).

Springfield Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

05/0903/08 11/08 07/08 03/1010/0905/09

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03130

EB Old Keene Mill Road at Bardu Avenue

$42,500$0

Loading pad, 125' sidewalk, 125' culvert, & 125' retaining wall

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08; survey (by County) complete; project on hold pending further direction from DOT (may relocate stop and revise scope).

Springfield Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

303 On-Hold

Thursday, June 19, 2008 Page 14 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03131

EB Old Keene Mill Road and Jansen Drive

$33,000$0

Loading pad, sidewalk, curb and gutter, pedestrian ramp, and storm drainage improvements

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; design in progress; may require easements based on preliminary design.

Springfield Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03168

NB Frontier Dr near Franconia Rd

$39,400$0

Bus shelter Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Lee Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03173

EB Franconia Rd and Grovedale Dr

TBD Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; DOT following up on citizen request to define scope of work (bus shelter will require stop relocation); project on hold pending further direction from DOT.

Lee Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

12/07303 On-Hold

Thursday, June 19, 2008 Page 15 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03265

EB Edsall Road and Industrial Drive

$86,500$0

Loading pad, asphalt walkway, pedestrian ramps, crosswalk, and pedestrian signals

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; design in progress.

Mason Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03266

WB Edsall Road and Cherokee Avenue

$16,000$0

Loading pad Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; design in progress.

Mason Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03565

NB Industrial Road near Edsall Road

$28,000$0

Loading pad, sidewalk, and pedestrian ramp

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08; survey (by County) and utility designation complete; design in progress; easement required.

Mason Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0908/08 08/08 06/09 06/0902/0901/09

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 16 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03566

SB Industrial Road near Edsall Road

$16,000$0

Loading pad Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; design in progress.

Mason Utterback, BrianZore, Tasneem

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03673

EB Little River Turnpike and Elizabeth Drive

$23,400$0

Loading pad, drainage culvert, and cross walk

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 60% design plans received 4/4/08 and under review.

Braddock Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 06/08 07/08 10/0807/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03691

EB Little River Turnpike and Logsdon Dr

$20,900$0

Loading pad and sidewalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 17 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03692

EB Little River Turnpike and Conwell Dr

$20,000$0

loading pad and sidewalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03693

EB Little River Turnpike and Columbia Pike

$21,900$0

Loading pad, sidewalk connection, and relocate crosswalk

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03694

EB Little River Turnpike and Willow Run Dr

$19,000$0

Loading pad and sidewalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 18 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

03702

EB Lee Jackson Memorial Hwy and Galesbury Ln

$25,600$0

Loading pad, 15' retaining wall, 10' concrete sidewalk, pedestrian ramp, and cross walk

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; A/E preparing 60% design plans (extensive site improvements proposed; design delayed due to extra coordination on final scope; preparing schedule adjustment).

Sully Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 07/08 07/08 11/0808/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

03721

WB Lee Jackson Memorial Hwy near Galesbury Ln

$15,700$0

Loading pad Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; CMD authorized 5/1/08 to proceed with construction via the annual construction contract; construction NTP 6/9/08 (scheduled completion 7/7/08).

Sully Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 04/08 07/08 07/0805/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

04024

WB Braddock Rd and Redfox Dr

$26,300$0

Loading pad, 10 LF sidewalk, and drainage inlet

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review; VDOT plan review required (preparing schedule adjustment due to required VDOT review).

Braddock Utterback, BrianBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 08/08 07/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 19 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

04077

WB Little River Turnpike and Old Columbia Pike

$24,900$0

Loading pad, retaining wall, and sidewalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

04078

WB Little River Turnpike and Pinecrest Heights Dr

$21,000$0

Loading pad and sidwalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

04079

WB Little River Turnpike and Pinecrest Parkway

$20,200$0

Loading pad and sidewalk connection

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 20 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

04080

WB Little River Tnpk and Roberts Ave

$23,200$0

Loading pad, 15-foot wide asphalt trail, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review (redesigning due to safety concerns per 4/15/08 meeting with DOT; preparing schedule adjustment due to redesign).

Mason Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 06/08 07/08 10/0807/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

04099

WB Little River Turnpike and Glenbrook Road

$20,900$0

Ramps, cross walks and pedestrian signals

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; CMD authorized 5/1/08 to proceed with construction via the annual contruction contract; construction NTP 6/9/08 (scheduled completion 7/7/08). .

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 04/08 07/08 07/0805/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

04127

NB Pimmit Dr and Leesburg Pike

$25,600$0

Loading pad, trash can, and improved access

Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08; survey and utility designation in progress; relocation of stop location may be required to avoid conflicts with overhead utilities; easements required.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

12/0807/08 07/08 04/09 04/0902/0912/08

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 21 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

04157

WB Leesburg Pk and Idylwood Rd

$16,700$0

Loading pad and bench Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; CMD authorized 5/1/08 to proceed with construction via the annual contruction contract; construction NTP 6/9/08 (scheduled completion 7/7/08). .

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 04/08 07/08 07/0805/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

04323

SB Magarity Rd near Lusby Pl

$26,500$0

4 pedestrian ramps and 2 crosswalks

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; CMD authorized 5/1/08 to proceed with construction via the annual contruction contract; construction NTP 6/9/08 (scheduled completion 7/7/08). .

Providence Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 04/08 07/08 07/0805/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

04329

NB Magarity Rd and Lusby Pl

$20,400$0

20' concrete sidewalk, loading pad, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; CMD authorized 5/1/08 to proceed with construction via the annual contruction contract; construction NTP 6/9/08 (scheduled completion 7/7/08). .

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 04/08 07/08 07/0805/08NANA

Monthly RemarksProject Description

303 Construction

Thursday, June 19, 2008 Page 22 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

04378

SB Chain Bridge Rd near McLean Commons Ct

$15,200$0

Concrete pad Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

04379

SB Chain Bridge Rd and Montcalm Dr

$15,200$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

04380

NB Chain Bridge Rd and Hunting Avenue

$18,500$0

Loading pad, sidewalk connection, and drainage ditch regrading

Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 23 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05061

WB South Lakes Dr near Chestnut Burr Ct

$17,500$0

Loading pad, 2-pedestrian ramps, and cross walk

Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; addressing final review comments and preparing construction task order authorization package.

Hunter Mill Utterback, Brian

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05062

WB South Lakes Dr & Pine Cone Ct

$15,400$0

Loading pad Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; CMD authorized 6/11/08 to construct the project via the annual contractor.

Hunter Mill Utterback, Brian

Farsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

05063

WB South Lakes Drive & Soaptone Dr

$15,400$0

Loading pad Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; CMD authorized 6/11/08 to construct the project via the annual contractor.

Hunter Mill Utterback, Brian

Farsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Construction

Thursday, June 19, 2008 Page 24 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05064

WB South Lakes Dr & Green Watch Way

$15,800$0

1-pedestrian ramp Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; CMD authorized 6/11/08 to construct the project via the annual contractor.

Hunter Mill Utterback, Brian

Farsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

05072

NB Glade Dr and Cocquina Dr

$16,200$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05073

WB Sunrise Valley Dr and Glade Dr

$21,800$0

Bench Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 25 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05078

EB Sunset Hills Rd near Town Center Parkway

$19,900$0

Loading pad and bench Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/08 11/08 11/0809/08TBDTBD

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05082

EB Glade Drive near Breton Court

$22,000$0

Loading pad, sidewalk, and pedestrian ramp

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; 60% design plans received 4/15/08 and under review.

Hunter Mill Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05120

NB Soapstone and Hearthstone Ct

$20,200$0

20' concrete sidewalk, loading pad, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 60% design plan comments returned 3/19/08 (redesigning due to safety concerns per 4/15/08 meeting with DOT; preparing schedule adjustment due to redesign).

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 06/08 07/08 10/0807/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 26 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05137

SB Soapstone Dr near Hearthstone Ct

$15,400$0

Loading pad Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 60% design plan comments returned 3/19/08 (redesigning due to safety concerns per 4/15/08 meeting with DOT; preparing schedule adjustment due to redesign).

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 06/08 07/08 10/0807/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05144

WB Glade Drive & Breton Court

$15,000$0

Loading pad Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; 60% design plans received 4/15/08 and under review.

Hunter Mill Utterback, BrianFinnell, Richard

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05148

NB Colts Neck Road & Steeplechase Drive

$15,000$0

Loading pad Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; 60% design plans received 4/10/08 and under review.

Hunter Mill Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 27 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05149

NB Colts Neck Road near Insha Court

$15,000$0

Loading pad Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08 (completion schedule assumes no easement required); survey (by County) and utility designation complete; 60% design plans received 4/10/08 and under review.

Hunter Mill Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05165

EB South Lakes Dr & Springwood Dr

$15,400$0

Loading pad Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; CMD authorized 6/11/08 to construct the project via the annual contractor.

Hunter Mill Utterback, Brian

Farsad, Nahid

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Construction

Z00032

Safety Improvements at Bus Shelters/Stops

05167

EB South Lakes Dr & Soapstone Dr

$15,400$0

Loading pad Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; CMD authorized 6/11/08 to construct the project via the annual contractor.

Hunter Mill Utterback, Brian

Farsad, Nahid

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Construction

Thursday, June 19, 2008 Page 28 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05168

EB South Lakes Dr & Chestnut Burr Ct

$16,900$0

Loading pad and 30 LF sidewalk Group 2; part of the Safety Enhancements @ Bus Shelters/Stops project; survey and (by County) and utility designation complete; addressing final review comments and preparing construction task order authorization package.

Hunter Mill Utterback, BrianFinnell, Richard

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/08 06/08 06/08 08/0806/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05216

EB Sunrise Valley Dr and Glade Dr

$16,200$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05217

SB Glade Dr and Cocquina Dr

$16,200$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 29 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05224

WB Sunrise Valley and South Lakes Dr

$16,200$0

load pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05226

EB Sunrise Valley Dr near Glade Dr

$16,400$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05227

EB Sunrise Valley Dr and South Lakes Dr

$18,300$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 30 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05536

NB Reston Parkway & Glade Drive

$30,000$0

Loading pad, sidewalk, and curb and gutter

Group 3; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 10/11/07; design task order approved and NTP issued 1/11/08; survey (by County) and utility designation complete; design in progress; easement required.

Hunter Mill Utterback, Brian

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0908/08 08/08 06/09 06/0902/0901/09

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05631

EB Great Falls Street and Aynsley Ln

$16,000$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

05632

WB Great Falls Street and Eldorado Ct

$16,200$0

Loading pad Group 5; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/12/07; survey and design task order approved and NTP issued 3/7/08 (completion schedule assumes no easements required); survey and utility designation in progress.

Dranesville Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 08/08 12/08 12/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Thursday, June 19, 2008 Page 31 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

05873

SB Telegragh Rd and Roxann Rd

$24,300$0

Loading pad, 10' retaining wall, and drainage culvert

Group 1; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 4/27/07; survey and design task order approved and NTP issued 8/2/07; survey and utility designation complete; 90% design plans received 4/4/08 and under review; land acquisition required (preparing schedule adjustment due to required easements).

Lee Utterback, BrianBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0803/08 06/08 07/08 03/0912/0811/08

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Enhancements - Bus Shelters/Stop

06013

SB Town Center Pkwy at Market St

$15,900$0

Loading pad Group 4; part of the Safety Enhancements @ Bus Shelters/Stops project; joint field review conducted 12/4/07; survey and design task order approved and NTP issued 2/21/08 (completion schedule assumes no easement required); survey and utility designation in progress.

Hunter Mill Utterback, BrianPM PDD:PM LAD:PM CMDE:PM CMDS:

07/08 07/02 11/08 11/0809/08NANA

Monthly RemarksProject Description

303 Planning and Design

Z00032

Safety Improvements at Bus Shelters/Stops

06037

SB Griffith Rd & Burfoot St

$20,500$0

Loading pad and 40' sidewalk DOT 8/10/07 requested Capital Facilities to relocate an existing bus stop; design complete (no land acquisition required); CMD authorized 3/31/08 to proceed with construction via the annual construction contract; constrution NTP 6/2/08 issued after addressing citizen opposition from the adjacent property owner (scheduled completion 7/7/08).

Dranesville Gallo, Michael

Farsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

03/08 03/08 05/08 07/0804/08NANA

Monthly RemarksProject Description

303 Construction

Thursday, June 19, 2008 Page 32 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

Z00032

Safety Improvements at Bus Shelters/Stops

06058

Janna Lee Ave & Tamarind St

$33,500$0

Bus shelter and walkway connections

Expedited project requested by DOT 6/21/07 based on coordination with the FCPD and the Lee District Supervisor; design complete and required land rights obtained; CMD authorized 6/10/08 to proceed with construction via the annual contractor (construction NTP will be issued upon receipt of the state building permit).

Lee Gallo, MichaelZore, TasneemFarsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0802/08 02/08 11/08 07/0806/0808/08

Monthly RemarksProject Description

303 Construction

D00448

Plaza America Pedestrian Improvements

PA02B

Sunset Hills Road: Reston Center to Town Center Parkway

$170,000$0

600 LF 8' wide asphalt trail100 LF 6' wide concrete walkway

Funding provided by Plaza America cash proffer contribution; field property and topographic survey complete; design complete; LAD directed 3/24/06 to acquire easements for 2-properties (titles and appraisals complete and offer letters sent); LAD second schedule extension approved 7/19/07; updated utility designation complete & coordination ongoing to address extensive utilities on-site; project scope has been changed by District Supervisor to an 8-foot wide trial based on citizen's and property owner's request; proceeding with redesign for 8-foot trail; test hole data received (utility coordination in progress); new fiber optic lines found on site - revising alignment to avoid costly relocation (schedule adjustment approved 6/2/08 due to additional redesign).

Hunter Mill Zahirieh, ShahlaBarnes, DianneGharavi, MoHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/0806/08 06/08 01/09 01/0911/0809/08

Monthly RemarksProject Description

307 Planning and Design

D00448

Plaza America Pedestrian Improvements

PA050

Sunset Hills Rd Trail: Rstn Pkwy-Wiehle

$195,000$0

350 LF 8' asphalt trail from Sunset Hills Road to W&OD Trail

Partial funding provided by Plaza America proffer contribution and funds from the Old Reston Avenue roadway improvement project; survey and utility designation complete; scope reduced to asphalt trail connection to W&OD trail; land acquisition authorized 4/25/08 to acquire easements; obtaining permit from NVRPA for connection to W&OD Trail (design revised based on NVRPA comments); building permit required for proposed retaining wall.

Hunter Mill Zahirieh, ShahlaBuckley, BethTopper, WilliamHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0804/06 04/08 09/07 06/0911/0801/07

Monthly RemarksProject Description

307 Land Acquisition

Thursday, June 19, 2008 Page 33 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

D00448

Plaza America Pedestrian Improvements

PA060J

Sunset Hills Road @ Target EB Bus Stop Improvements

$30,000

Installation of a bus shelter Funding provided by Plaza America proffer contribution; design complete; Land Acquisition authorized 10/13/05 to acquire land rights; negotiations (Reston legal council) unsuccessful; LAD recommended 1/3/07 that project be deleted (memorandum to DOT 1/11/07 recommending deletion ~ followup memorandum to DOT 4/9/08); proposed development may provide bus stop improvements and relocation of stop - DOT following up.

Hunter Mill Flowers, RandallBuckley, BethFarsad, NahidMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/05 10/05 10/06TBD TBDTBD06/06

Monthly RemarksProject Description

01/07307 On-Hold

D00448

Plaza America Pedestrian Improvements

PA060O

Sunset Hills Road @ WO&D Trail WB Bus Stop Improvements

$30,000

Installation of a bus shelter Partial funding provided by Plaza America proffer contribution; original design complete and land acquisition authorized 1/06 to acquire easement from NVRPA; NVRPA denied permit for bus shelter due to sight distance issues with trail users and is opposed to a possible scope change to a pad and bench facility only; LAD initiated discussions with the adjacent property (Postal Services) for a stop relocation, who requested more information on impact to property; completed utility designation, prepared preliminary design, and coordinated with property owner's representative; owner still undecided about granting easement; plat prepared and LAD authorized 1/17/08 to initiate formal easement negotiations; LAD 5/2/08 recommended that project be cancelled; project on hold pending resolution.

Hunter Mill Gallo, MichaelBuckley, BethFarsad, Nahid

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/08 01/08 12/08TBD TBDTBD08/08

Monthly RemarksProject Description

05/08307 On-Hold

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4D

RS211

Route 1 SB: South of Dogue Creek to Mobile Home Sales Park

300 LF 8' Asphalt Trail and Pedestrian Bridge over Dogue Creek

Project is part of the Four-Year Transportation Program approved by the BOS on 10/15/07; part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; design funded through a revenue sharing agreement with VDOT (additional county, state, and federal monies to be used); survey and utility designation complete; developing design scope for project; design to be performed by consultant; schedule to be determined once contract executed with design consultant; land acquisition required.

Mount Vernon Zahirieh, ShahlaPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Pre-Design

Thursday, June 19, 2008 Page 34 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4D

RS212

Route 1 SB: Mobile Home Sales Park to Sacramento Center

$40,000$0

300 LF of 5-foot wide concrete sidewalk

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; targeted project for expedited completion; design funded through a $700k revenue sharing agreement with VDOT (county funds identified for construction); CMD authorized 5/4/07 to proceed with construction (NTP 5/21/07); Fairfax Water relocated fire hydrant; Verizon and Dominion Virginia Power completed pedestrian guy wire installations; construction 100% complete 7/7/07 (pavement markings redone and awaiting VDOT permit release).

Mount Vernon Zahirieh, Shahla

Minnix, W. ToddTBD, To be Deter

PM PDD:PM LAD:PM CMDE:PM CMDS:

03/07 05/07 04/07 07/0705/07NANA

Monthly RemarksProject Description

307 Post-Construction

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4D

RS213

Route 1 SB: Sacramento Drive to Engleside Plaza (North of Woodlawn Court)

$350,000$0

1400 LF of 5' Concrete Sidewalk Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaKresge, Carol

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4D

RS214

Route 1 SB: South of Sky View Drive

$42,500$0

170 LF 5' Concrete Sidewalk and Bus Stop Pad

Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaKresge, Carol

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

Thursday, June 19, 2008 Page 35 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4E

RS221

Route 1 NB: North of Reddick Avenue/Russell Road (towards Janna Lee Avenue)

$125,000$0

500 LF of 5' Concrete Sidewalk Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaKresge, Carol

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4E

RS222

Route 1 NB: South of Janna Lee Avenue to Buckman Road/Mt. Vernon Highway

$302,500$0

1210 LF of 5' Concrete Sidewalk Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaKresge, Carol

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4E

RS223

Route 1 NB: Mt. Vernon Highway/Buckman Road to North of Napper Road

$125,000$0

Pedestrian Crossing at Mt. Vernon Hwy. and 500 LF 5' Concrete Sidewalk

Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaKresge, Carol

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

Thursday, June 19, 2008 Page 36 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4F

RS232

Route 1 NB: South of Kings Village Road

$37,500$0

150 LF of 5' Concrete Sidewalk Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaBuckley, Beth

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4F

RS233

Route 1 NB: South of Fordson Road to Woodlawn Trail

$410,000$0

1640 LF of 5' Concrete Sidewalk Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4G

RS241

Route 1 NB: Dart Drive to Grand View Drive - Phase 1

$150,000$0

1,200 LF of 5-foot wide concrete sidewalk

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; targeted project for expedited completion; design funded through a $700k revenue sharing agreement with VDOT (County funds identified for construction); CMD authorized 11/17/06 to proceed with construction via the annual contractor (NTP issued for 2/12/07); construction 100% complete 6/25/07 (punch list items addressed and awaiting a VDOT permit release).

Mount Vernon Zahirieh, ShahlaBarnes, DianneMinnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/06 11/06 01/07 06/0702/07NANA

Monthly RemarksProject Description

307 Post-Construction

Thursday, June 19, 2008 Page 37 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4G

RS242

Route 1 NB: Dart Drive to Grand View Drive - Phase 2

$30,000$0

Curb Ramps and Short Sections of 5' Concrete Sidewalk at Bus Stop at Route 1 NB @ Fordson Road/Holly Hill Road (Cherry Arms Apartments)

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; design funded through a revenue sharing agreement with VDOT (County funds identified for construction); survey, utility designation, and design complete; apartment complex signed letter of permission for construction in lieu of easements and agreed to maintain proposed facilities on their property; obtained VDOT approval to add on to Phase 1 of project - Project No. K00447 (RS241), and CMD authorized to proceed with construction as part of Phase 1 construction contract (construction to coincide with punch list items on Phase 1, but was delayed due to issue with VDOT utility vault); construction 99% complete (awaiting a VDOT permit release).

Mount Vernon Zahirieh, ShahlaBarnes, DianneMinnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/08 01/08NANA NA NANA

Monthly RemarksProject Description

307 Post-Construction

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4H

RS251

Route 1 NB: Quander Road - Phase 1

$60,000$0

275 LF of 5-foot wide concrete sidewalk north of Quander and 200 LF of 5-foot wide concrete sidewalk south of Quander

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; targeted project for expedited completion; design funded through a $700k revenue sharing agreement with VDOT (County funds identified for construction); Dominion Virginia Power complete pedestrian guy wire installation; CMD authorized 11/2/06 to proceed with constuction via the annual contractor; construction 100% complete 12/15/06 (awaiting a VDOT permit release).

Mount Vernon Zahirieh, Shahla

Minnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/06 11/06 01/07 12/0611/06NANA

Monthly RemarksProject Description

307 Post-Construction

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4H

RS252

Route 1 NB: Quander Road - Phase 2

$112,500$0

450 LF of 5' Concrete Sidewalk South of Quander

Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaBuckley, Beth

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

Thursday, June 19, 2008 Page 38 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4H

RS253

Route 1 SB: Belle Haven Towers - Phase 1

$110,000$0

850 LF of 5-foot wide concrete sidewalk

Part of a multi-phased project along the Route 1 Corridor (Fort Belvoir to Huntington Metro) with an overall TPE of $55 million; targeted project for expedited completion; design funded through a $700k revenue sharing agreement with VDOT (County funds identified for construction); survey, utility designation, and design complete; Dominion Virginia Power completed installation of conduit on existing electric lines; Cox Communications completed relocation of cable; does not require land acquisition (section that required easement removed from Phase I of project); CMD authorized 11/17/06 to proceed with construction via the annual contractor; construction task order approved and NTP issued for 1/16/07; construction 100%% complete 7/9/07 (awaiting a VDOT permit release).

Mount Vernon Zahirieh, ShahlaBuckley, BethMinnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/06 11/06 09/06 07/0701/07NANA

Monthly RemarksProject Description

307 Post-Construction

K00447

Richmond Hwy Public Transport Initiative: Walkways Phase 4H

RS254

Route 1 SB: Belle Haven Towers - Phase 2

$137,500$0

550 LF of 5' Concrete Sidewalk and Service Drive Crossing

Project is part of Four-Year Transportation Program; part of multi-phased Route 1 Corridor project (Ft. Belvoir to Huntington Metro) with $55 million TPE; design funded thru VDOT revenue sharing agreement (additional county, state, and federal funds to be used); survey and utility designation complete; utility coordination in progress; design public hearing (PH) conducted 9/25/07 in accordance with state and federal guidelines; BOS endorsed plans presented at PH 12/3/07; submitted PH documentation to VDOT for state approval; sending revised plans to VDOT and County agencies for review; land acquisition required (LAD authorized to order title research and begin preliminary contact with property owners 12/12/07; consultant authorized 4/22/08 to prepare plats); PH approval (required before initiating formal easement negotiations) pending VDOT approval of design waivers and exceptions for some of the plans presented at hearing; schedule to be determined once waivers, exceptions, and PH approved.

Mount Vernon Zahirieh, ShahlaBuckley, Beth

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Planning and Design

W00100

Braddock District WalkwaysW109

Roberts Road @ GMU

$570,000$0

1,700 LF 6' asphalt trail Project is part of the Second Four-Year Transportation Program and was approved by the BOS on 10/15/07; project funded for design and land acquisition only; design by annual consultant 95% complete; LAD authorized to acquire 1-easement (GMU Board has approved the project); LAD coordinating revisions to the easement document with GMU legal counsel (concurrence on wording obtained and will be signed by GMU in near future); coordinating with proposed Roberts Road/Braddock Road Intersection Improvements; additional funds for construction included in the approved Fall 2007 Transportation Bond Referendum; utility designation recertification and VDOT plan review comments obtained; negotiations in progress with design engineering to update the plans (RFP sent 6/9/08).

Braddock Popoola, LarryBarnes, DianneLim, SamMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/08 12/08 12/0808/08NA 12/05

Monthly RemarksProject Description

307 Land Acquisition

Thursday, June 19, 2008 Page 39 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

W00200

Dranesville District WalkwaysW202

Georgetown Pike

$608,000$377,000

Total Project Scope: 2 mile 6-foot wide stone dust trail (Phase I: 1,260 LF of trail from Applewood Lane to the Village Center)

Project scope reduced to trail section west of the village center due to citizen opposition east of the village center to granting easement (2 of 14 easements acquired); land acquisition finalizing negotiations (2 of 3 easements acquired ~ easement at fire station in the process of being recorded) and design engineer finalizing the plans and updating the environmental recertification (pre-final plans to VDOT 10/31/07 for review); VDOT approved Project Agreement for Scenic Byway Grant (NVRC proceeding with Route Feasibility Study); negotiations continuing with VDOT on the approval of Supplemental Agreement to utilize the additional enhancement funds ($387,000) including evaluating new walkway scope (Seneca Road to Utterback Store Road); survey work on Krop property complete; design alternatives prepared and presented to the property owner.

Dranesville Flowers, RandallKresge, CarolFarsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/08 05/08 05/0910/08NA 05/07

Monthly RemarksProject Description

307 Land Acquisition

W00200

Dranesville District WalkwaysW212

Walker Road Phase I

$350,000$0

6-foot wide stone dust trail (Phase I: 1200 LF of trail north of Village Center to north end of Great Falls Elementary School property)

TEA-21 funding approved ($200K in VDOT funds); approval in progress for an additional $40,000 in Enhancement funds (BOS item proposed for 5/3/08 meeting); topographic and property site survey, design, and environmental reviews complete; property owners not receptive to granting easements (0 of 6 easements acquired); VDOT 12/5/06 approved reduced project scope; FCSB permit received 2/6/08; land acquisition continuing on outstanding easements but will not impact current construction scope; design engineer finalizing the design and updating the environmental recertification; Federal right of way authorization requested 5/19/08.

Dranesville Flowers, RandallKresge, CarolFarsad, NahidJensen, Chris

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/08 04/0909/08NATBD TBD 05/07

Monthly RemarksProject Description

307 Planning and Design

W00300

Hunter Mill District WalkwaysW304

Wiehle Avenue Walkway

$435,000$0

700 LF 5' wide walkway Design (including landscaping plan) and geotechnical engineering report complete and building permit obtained; Land Acquisition Division authorized to acquire easement 1/30/02; BOS 9/24/07 authorized acquiring the outstanding land rights from homeowners association via condemnation; P&DD presented project to Reston Design Review Board for approval at their 2/19/08 meeting (requested design changes including options for the facing of the retaining wall reviewed at a workshop conduced on 5/27/08).

Hunter Mill Guarino, MichaelZore, Tasneem

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/08 12/09 12/0902/09NA NA 12/08

Monthly RemarksProject Description

307 Land Acquisition

Thursday, June 19, 2008 Page 40 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

W00300

Hunter Mill District WalkwaysW308

Clarks Crossing Road Walkway

$108,000$0

250' 8-foot wide asphalt trail Original design complete; land acquisition complete 1/24/07 (FCPA easement obtained but one property owner refuses to grant the other easement); alternate walkway alignment design prepared to eliminate the need for the outstanding easement (guardrail proposed but subsequently deleted at request of VDOT); VDOT has installed the culvert extension; Cox authorized 3/1/07 to adjust their conflicting facilities; CMD authorized 7/6/07 to construct the project (construction NTP pending receipt of VDOT permit).

Hunter Mill Flowers, RandallZore, TasneemGharavi, Mo

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0705/06 11/06 08/06 08/0806/0801/07

Monthly RemarksProject Description

307 Planning and Design

W00300

Hunter Mill District WalkwaysW311

Beulah Road Trail

$165,000$0

830 ' 10 foot wide trail (Section D) Enhancement grant funds approved to prepare a trail feasibility study, including preliminary engineering survey, along Beulah Road in the vicinity of the Meadows Lark Gardens Regional Park; final report distributed 1/07; Phase I implementation of Section D in progress (830 LF 10-foot wide trail); Supplemental Project Agreement for additional Enhancement Funding signed 1/19/08 by VDOT and concurrence to use the annual task order consultant received; task order approved (NTP issued contact negotiations complete and in progress.

Hunter Mill Popoola, Larry

Murdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

NATBD TBD TBD TBDTBDNA

Monthly RemarksProject Description

307 Pre-Design

W00400

Lee District WalkwaysW413

Florence Lane Walkway

$155,739

850 LF of 5-foot wide concrete sidewalk along the east side of Florence Lane between Rebecca Jane Way and Beech Tree Drive

Original citizen survey notification letter sent 9/7/06; project was on hold due to property owner opposition to the site survey; coordination with District Supervisor and the community conducted and project to proceed as proposed per Lee District request; survey notification letters sent on 4/25/08 with survey to begin 5/15/08 (scheduled completion 7/1/08); project completion schedule to be prepared once survey is completed.

Lee Adams, Shanna

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

307 Pre-Design

Thursday, June 19, 2008 Page 41 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

W00500

Mason District WalkwaysW505

Old Col Pike-Elmdale

$290,000$272,000

700 LF of 6-foot wide walkway Funding for design only; survey and design (including geotechnical investigation and design for 2 pedestrian bridges) complete; citizen's meeting conducted (easements will be required); additional funding required; project on hold pending approval of additional funding.

Mason Guarino, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

08/03307 On-Hold

W00600

Mt. Vernon District WalkwaysW611

West Potomac High School Walkway

$576,969$0

500 LF of 5-foot wide concrete sidewalk with curb and gutter and storm drainage improvements

Project is part of the Second Four-Year Transportation Program and was approved by the BOS on 10/15/07; survey and design by annual consultant; design in progress; citizen meeting/field walk complete; VDOT review comments addressed and final plans distributed for review on 3/12/08; Traffic signal plans approved by VDOT; LAD authorized 6/29/07 to acquire easements (5 of 6 easements acquired ~ remaining easement obtained and being recorded) and a letter of permission from the FCSB; LAD schedule adjustment 3/37/08; utility relocations in progress; Fairfax Water plans completed; additional funds for construction included in the approved Fall 2007 Transportation Bond Referendum.

Mount Vernon Royse, AndyBarnes, DianneGharavi, MoJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0806/07 06/07 02/09 02/0908/0804/08

Monthly RemarksProject Description

307 Land Acquisition

W00600

Mt. Vernon District WalkwaysW612

Mount Vernon High School Walkway

$160,000$145,000

950 LF of 6-foot wide asphalt trail Project funded for design only; survey and design by annual design consultant; citizens' meetings to present preliminary design complete; coordinating with District Supervisor's office to determine if final design should proceed based on issues raised at the citizen's meeting.

Mount Vernon Guarino, MichaelPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

12/04307 On-Hold

Thursday, June 19, 2008 Page 42 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

W00600

Mt. Vernon District WalkwaysW613

Mason Neck Trail Segment II

$1,906,000$1,163,718

2.3 miles of 8-foot wide asphalt trail

Funded for design and land acquisition only; final design in progress (90% plan submission received); wetlands and historic report approved; VDOT approved environmental report 7/28/06; Phase I Archeological Study complete; easement plats and LAD directed 4/28/06 to initiate pre-acquisition activities; VDOT approval to proceed with land acquisition negotiation activities outstanding pending VDOT approval of additional MS-19 engineering drainage calculations and environmental recertification; second contract addendum with A/E to address VDOT comments approved; Supplemental Agreement for additions Enhancement funds presented to the BOS on 11/19/07 and signed 1/19/08 by VDOT.

Mount Vernon Royse, AndyKresge, CarolNolan, BillJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/06 04/06 TBD TBD05/07

Monthly RemarksProject Description

307 Land Acquisition

W00700

Providence District WalkwaysW705

Woodford Rd @ Wolftrap

$110,000$75,000

270 LF of 6-foot wide walkway replacement including extensive site grading and drainage facilities

Funding approved for replacement of an existing walkway; site survey, design, utility designation, and geotechnical engineering report complete and VDOT permit obtained; easement from HOA acquired; HOA 9/29/06 withdrew support for the project; follow up meeting with HOA conducted 2/27/07 and site review meeting conducted 3/10/07 (citizens generally do not support the project, and HOA submitted letter 3/26/07 stating they do not support the proposed design); project on-hold pending resolution of HOA issues; coordinating with District Supervisor's office.

Providence Guarino, MichaelKresge, Carol

Jozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0610/05 10/05 09/06 TBDTBD04/06

Monthly RemarksProject Description

09/06307 On-Hold

W00700

Providence District WalkwaysW719

Lido Place Walkway

$194,500$0

600 LF of 4-foot wide sidewalk Survey and utility designation complete; alternative design concepts evaluated in coordination with the District Supervisor and community due to limited space and safety considerations; additional design work complete and VDOT review comments addressed; LAD 5/16/08 obtained all outstanding land rights; final VDOT plan review (addressing drainage comments) and utility coorindation in progress.

Providence Gallo, MichaelBarnes, Dianne

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0804/07 04/07 05/09 05/0912/0810/08

Monthly RemarksProject Description

12/05307 Planning and Design

Thursday, June 19, 2008 Page 43 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

X00826

Extension ProjectD014

Old Courthouse/Besley Road

$175,000$0

550 LF of 8-inch sanitary sewer to serve 6 dwellings

Initial citizen opposition encountered which required extensive follow-up coordination including the Health Department reevaluation of the area; project scope and alignment issues resolved; site survey and preliminary design complete; LAD directed on 10/25/05 to acquire easements (3 of 9 easements acquired); P&DD preparing revised plans and plats to address alignment change requested by property owner during easement negotiations (VDOT approved revised jack & bore alignment across Old Courthouse Road 10/23/07); new jump back schedule approved 1/4/08 due to the redesign and schedule adjustment approved 6/4/08 due to plat preparation.

Hunter Mill Gallo, MichaelBarnes, DianneKnizner, AnthonyHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0904/08 06/08 11/09 11/0906/0901/09

Monthly RemarksProject Description

402 Planning and Design

X00826

Extension ProjectD016A

Portland Place E & I, Phase I

$350,000$0

1,000 LF 8-inch sanitary sewer and 6 grinder pumps

BOS approved expansion of Sewer Service Area on February 27, 2006, to include additional properties with potentially failing septic systems; Phase I serves properties with potentially failing systems (including those in expansion area); scope of work revised to include the use of grinder pumps to address constructability issues associated with deep excavations (grinder pump easements will be required); design to be prepared by A/E (Dewberry); task order approved 12/5/07 (NTP issued 12/6/07); obtaining additional survey required for grinder pump design (notifications sent to property owners and obtaining authorizations to access properties) in progress; coordinating proposed grinder pump locations with property owners and follow up citizen meeting being scheduled.

Dranesville Gallo, MichaelBarnes, Dianne

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0910/08 10/08 06/10 06/1010/0905/09

Monthly RemarksProject Description

402 Planning and Design

X00826

Extension ProjectD016B

Portland Place - Phase II

$200,000$0

525 LF 8-inch sanitary sewer Phase II serves section of neighborhood south of Portland Place and requires easements; survey complete(updated information in progress); design to be prepared by A/E (Dewberry); task order approved 12/5/07 (NTP issued 12/6/07); coordinating proposed grinder pump locations with property owners and follow up citizen meeting being scheduled.

Dranesville Gallo, MichaelBarnes, Dianne

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0910/08 10/08 06/10 06/1010/0905/09

Monthly RemarksProject Description

402 Planning and Design

Thursday, June 19, 2008 Page 44 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

X00826

Extension ProjectE004

River Oaks

$7,300,000

3,266 LF 8-inch sanitary sewer, 69grinder pumps, and 18,570 LF force main

Construction NTP issued for 1/16/07 (construction 75% complete).

Dranesville Flowers, RandallColeman, MichaelKnizner, AnthonyMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/05 09/07 09/0810/06NA 12/05

Monthly RemarksProject Description

402 Construction

X00826

Extension ProjectE005

Saigon Subdivision E & I

$2,530,000$0

3,100 LF 8-inch sanitary sewer, 20 grinder pumps, and 1,800 LF force main

Feasibility study and site survey complete and design in progress; meeting with property owners on proposed grinder pump locations conducted; LAD authorized 6/21/06 to proceed with acquisition of easements (34 total plats including 20-grinder pumps and 1-off site easement); obtaining appraisals easements requiring compensation with negotiations in progress for non compensated easements; meeting with new District Supervisor conducted 3/26/08; Health Department scheduled to re-evaluate the condition of the existing on-site disposal systems in the project area in May 2008; land acquistion continuing concurrently with addressing outstanding project issues with the District Supervisor's office.

Dranesville Royse, AndyBuckley, Beth

Jozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/06 06/06 12/08TBD TBDTBD05/07

Monthly RemarksProject Description

05/07402 Land Acquisition

X00826

Extension ProjectEI01

Piney Run Drive

$381,000$0

1,450 LF of 8'' sanitary sewer Project to provide sanitary sewer service to 11 houses; coordinated with off site property owners to develop alignment plan; field survey 95% complete; general citizen's meeting conducted 2/15/06; coordination with DPZ completed to require an adjacent land development project to provide an alternate sanitary sewer outfall (possibly in late 2008) via a proffered development condition; project schedule to be prepared once alignment is finalized.

Lee Adams, Shanna

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

12/06402 On-Hold

Thursday, June 19, 2008 Page 45 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

X00826

Extension ProjectEI02

Stryker Avenue

$665,000

2,000 LF 8" sanitary sewer & 5 grinder pumps and modifications to an existing pump station

Design complete; LAD 2/20/07 acquired all required temporary construction easements, grinder pump easements, and 1-sanitary sewer lateral easement; Wastewater Planning requested that existing pump station be upgrade to accommodate the additional flow; Dewberry prepared grinder pump electrical design and pump station upgrade plan via two task orders (100% design plans received); addressed final CMD comments; CMD authorized 5/22/08 to proceed with construction bid advertisement; P&DD coordinating the acquisition of the VDOT permit (anticipated resolution 6/6/08); construction schedule includes both the gravity sewer and the pump station upgrade work; project status update letter to property owners 4/14/08.

Hunter Mill Adams, ShannaKresge, CarolKnizner, AnthonyHousley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0709/07 09/06 11/08 06/0907/0807/07

Monthly RemarksProject Description

402 Construction

X00826

Extension ProjectEI03

Kenmore Subdivision

$914,000$0

2,400 LF 8-inch sanitary sewer Project design complete and all land rights acquired; final CMD comments addressed and construction bid package prepared and CMD plan sign off obtained; design waiver approved; request for approval of a waiver to impact the RPA pending the resolution of tree removal issues in a conservation easement with the Northern VA Conservation Trust (NVCT); letter sent to NVCT on 4/18/08 requesting resolution to easement issue and negotiations in progress on the scope of the mitigation required to address this issue (site review meeting scheduled 6/12/08).

Dranesville Royse, AndyBarnes, DianneSteele, TerrenceJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0711/06 11/06 12/08 05/0908/0808/07

Monthly RemarksProject Description

402 Planning and Design

X00826

Extension ProjectEI04

Fairfax Acres Subivision

$2,500,000$0

6,450 LF of 8-inch sanitary sewer Property and topographic survey by Rice & Associates complete; proposed alignment coordinated with impacted citizens: design in progress (preliminary design complete and final review comments being addressed); LAD authorized 3/27/08 to acquire easements (9 of 20 easements acquired); project status update letter to property owners 4/14/08.

Providence Adams, ShannaFinnell, Richard

Jozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/0812/07 03/08 12/09 12/0911/0809/08

Monthly RemarksProject Description

402 Land Acquisition

Thursday, June 19, 2008 Page 46 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

X00826

Extension ProjectEI05

Turkey Run Road Sewer E&I

$650,000$0

1,800 LF 8-inch sanitary sewer Project will service 11 lots with existing homes and 2 vacant lots; UDB authorized 7/27/06 to proceed with survey and design; project scope reviewed and alternative alignment plans coordinated with the impacted property owners; survey complete (additional survey will be required); citizen meeting conducted 6/19/07 and additional coordination in progress to define limits of project scope and alignment plan; additional survey work complete 10/5/07; briefing on new District Supervisor conducted 3/26/08; project on hold pending a further review of outstanding issues.

Dranesville Royse, AndyBuckley, Beth

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBDTBDTBD

Monthly RemarksProject Description

03/08402 On-Hold

X00826

Extension ProjectEI06

Colewood Street

$250,000$0

8" sanitary sewer (length TBD) BOS 9/24/07 approved expansion of the limits of sewer service area; project scope being reviewed; Total Project Estimate to be prepared after alignment plan is finalized; citizen meeting conducted 11/14/07; site survey and utility designation complete; design in progress.

Sully Schmidt, Natasha

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0903/09 03/09 04/10 04/1010/0908/09

Monthly RemarksProject Description

402 Planning and Design

X00826

Extension ProjectF017B

Langley Forest E&I Phase II

$200,000$0

700 LF 8-inch sanitary sewer Initial citizen's meeting conducted; survey and utility designation complete; design in progress; LAD authorized 12/5/07 to acquire easements (1 of 4 easements acquired); stream crossing permits (Army Corps of Engineers and Virginia DEQ) obtained; coordination with homeowners continuing.

Dranesville Zahirieh, ShahlaFinnell, Richard

Murdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0810/06 12/07 12/07 02/0909/0804/07

Monthly RemarksProject Description

402 Land Acquisition

Thursday, June 19, 2008 Page 47 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project NameTPE ($)FUT ($)

On HoldDesign DatesDistrict CAP Assignments

Project Managers

Land Acquisition DatesBid OpeningCurrentApproved

CompletionCurrentApproved

CompletionCurrent

CompletionApproved

Completion

Construction Dates

Project Status - Phase

Utilities Design BranchCAP UDB - Monthly Summary Status Report May 2008

X00826

Extension ProjectM050

Pine Ridge

$375,000

952 LF 8-inch sanitary sewer Project was on hold one approximately 5-years pending the receipt of an additional prepayment of availability fee which was received 8/07 (5 properties with 3 payments received from locations with non-failing systems); major design update required; site survey complete and FCPA concurrence received on proposed sewer alignment; design in progress (preliminary design plans being reviewed); 4 easements will be required.

Providence Royse, AndyBarnes, Dianne

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0911/08 11/08 03/10 03/1008/0905/09

Monthly RemarksProject Description

402 Planning and Design

X00826

Extension ProjectM058

Glenbrook Road E & I

$315,000$0

1,000 LF of 8-inch sanitary sewer Citizen's meetings conducted; survey and utility designation complete; LAD coordinated with County Attorney on the use of a combined sanitary sewer/storm sewer easement as requested by property owners; second citizen's meeting conducted; revised preliminary sanitary sewer alignment prepared and scope revised to include resolution of existing storm drainage issues, which is required to properly install the sanitary sewer; sanitary and storm drainage design to be completed by Dewberry via a task order authorization (design NTP issued 5/28/08).

Providence Zahirieh, ShahlaKresge, CarolSteele, TerrenceMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0903/09 03/09 02/11 02/1103/1012/09

Monthly RemarksProject Description

402 Pre-Design

Thursday, June 19, 2008 Page 48 of 48developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

26006G

Richmond Highway Intersection Improvement Phase 4D

06001

Intersection Design - Sacramento Drive, Southgate Drive, Lockheed Boulevard and Arlington Drive

$1,200,000$1,200,000

Engineering and construction of intersection improvements for express bus service stops at Sacremento Dr., Southgate Dr., Lockheed Blvd. and Arlington Dr.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Schedule for this phase will be determined following completion of other phases.

Mount Vernon Madhusudhan, GPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 07/06Lee102Fund

26006G

Richmond Highway Intersection Improvement Phase 4B2

06002

Intersection Design - Lukens Lane and Frye Road (Phase2)

$600,000

Engineering and construction of intersection improvements for express bus service stops at Lukens Lane and Frye Road.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Schedule for this phase will be determined following completion of other phases. Land acquisition is required. Design exception and design waiver packages submitted to VDOT for review 6/11/08.

Mount Vernon Madhusudhan, GBarnes, DianneMinnix, ToddJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 07/06Lee102Fund

26006G

Richmond Highway Intersection Improvement Phase 4C

06002

Intersection Design - Ladson Lane

$400,000

Engineering and construction of intersection improvements for an express bus service stop at Ladson Ln.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Schedule for this phase will be determined following completion of other phases. Land acquisition is required. Design waiver package submitted to VDOT for review 6/11/08.

Mount Vernon Madhusudhan, G

Minnix, Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 07/06Lee102Fund

26006G

Richmond Highway Intersection Improvement Phase 4B1

06002

Intersection Design Frye Road (Phase I)

$200,000

Engineering and construction of intersection improvements for express bus service stop at Frye Road.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Draft construction package submitted to CMD 5/23/08. Comments have been received and are being addressed. Minor traffic signal modification plans approved by VDOT on 5/2/08.

Mount Vernon Madhusudhan, GBarnes, DianneWolfe, MikeJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0605/06NA NA NA NA

Project Description Monthly Remarks

07/06 11/08 12/08 05/0908/0710/08

Lee102Fund

Thursday, June 19, 2008 Page 1 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

26006G

Richmond Highway Intersection Improvement Phase 4C1

06002

Intersection Design Kings Highway

$400,000

Engineering and construction of intersection improvements for express bus service stop at Kings Highway.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Draft construction package submitted to CMD 5/23/08. Comments have been received and are being addressed.

Mount Vernon Madhusudhan, G

Wolfe, MikeJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0605/06NA NA NA NA

Project Description Monthly Remarks

07/06 11/08 12/08 05/0908/0710/08

Lee102Fund

007701

Route 50 Interchange/Waples Mill Road

00000

$4,584,000

Design and construction of at-grade improvements.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. Construction substantially complete 12/18/06. Final signal inspection punch list completed. Signal accepted by City of Fairfax. Awaiting final inspection by VDOT.

Springfield Gharavi, MoFinnell, RichardGharavi, MoHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0410/02 07/03 04/04 10/04NA

Project Description Monthly Remarks

10/04 05/05 06/05 12/0610/0604/05

Providence301Fund

007702

Tall Timbers Drive00000

$1,450,000$0

Construction of 700 linear feet of roadway connecting existing portions of Tall Timbers Drive.

Construction substantially complete 10/10/07. Preparing final Street Acceptance Package.

Springfield McCorkle, LisaBuckley, BethMinnix, W. ToddHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0706/06 12/05 02/07NA TBD

Project Description Monthly Remarks

08/06 02/07 03/07 10/0701/0801/07301Fund

008801

Stone Road00000

$2,084,000$0

Construct a raised median from Lee Hwy to Billingsgate Ln., widen roadway from Battery Ridge Ln. to Awbrey Patent Dr.

Construction substantially complete 4/25/08. VDOT inspection has been requested.

Sully Ayers, RobertBuckley, BethFarsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0711/02 10/04 05/05 08/05 05/06

Project Description Monthly Remarks

06/06 05/07 06/07 04/0803/0804/07301Fund

Thursday, June 19, 2008 Page 2 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

008803

Route 29 Widening00000

$4,400,000$985,000

Phase II: Trail improvements from Stevenson Street to Holly Avenue.

VDOT completed widening of westbound lane between Dixie Hill Road and Holly Avenue. TPE includes future phases to be identified. Environmental investigation is in progress. Consultant revising proposal for archaeological survey. Phase II Final design comments are being addressed. A meeting with Archstone Properties has been scheduled for 6/24/08 to discuss impact to property.

Springfield Madhusudhan, GFinnell, RichardMinnix, ToddJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/06 04/07TBD TBD TBD TBD

Project Description Monthly Remarks

11/07TBD TBD TBDTBDTBD

301Fund

009913

Dolley Madison Blvd. (Rt. 123)00000

$8,946,000

Widening Dolley Madison Blvd. to six lanes from I-495 to Dulles Toll Road.

Construction is complete. Final street acceptance package returned 4/24/07 with comments. A meeting was held with VDOT 9/18/07 to discuss redline composite plat issues. Plat has been returned to surveys to resolve formatting issues and is due back by end of June.

ProvidenceGlass, LisaGoudarzi, BehrooStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0002/00 11/00 11/00 03/01NA

Project Description Monthly Remarks

11/00 03/01 04/01 07/0207/0212/00301Fund

009444

Laurel Hill Development - Transportation Analysis

00000

$400,000

Preliminary design of 7 miles of roadway in Laurel Hill area includingdata collection, traffic analysis, and update Countywide transportation plan.

TPE is for preliminary design only. Final conceptual design plans and quantities were received 4/23/08 for Silverbrook Road, Furnace Road and Hooes Road.

Mount Vernon Madhusudhan, GPM PDD:PM LAD:PM CMDE:PM CMDS:

04/08NANA NA NA NA

Project Description Monthly Remarks

NA NA NA NANANA303Fund

006495

Wiehle Avenue Phase III00000

$7,399,000

Four lane road from Dranesville Road to Fairfax County Parkway.

Construction is complete. Preparing final Street Acceptance package. A meeting was held with VDOT 9/18/07 to discuss redline composite plat issues.

Dranesville Gharavi, MoKnutsson, RobertFarsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0003/89 07/90 11/99 11/99 06/00

Project Description Monthly Remarks

08/00 03/01 04/01 08/0208/0202/01304Fund

Thursday, June 19, 2008 Page 3 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

006495

Wiehle Avenue, Phase II00000

$7,933,000

Four lane road from Fairfax County Parkway to Reston Avenue.

Construction is complete. Final street acceptance package returned 4/24/07 with comments. A meeting was held with VDOT 9/18/07 to discuss redline composite plat issues. Plat has been returned to surveys to resolve formatting issues. Coordination with Colonial Pipeline is on going regarding Quitclaim package.

Hunter Mill Gharavi, MoKnutsson, RobertFarsad, NahidStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/9803/89 01/90 03/98 03/98 10/98

Project Description Monthly Remarks

10/98 05/99 06/99 04/0004/0001/99

Dranesville304Fund

064103

South Van Dorn/I-95, Phase II00000

$11,300,000

Design and construct a ramp from northbound South Van Dorn Street to eastbound I-95.

Construction is complete. Street Acceptance Package being prepared for submission to VDOT. Vacation of a Portion of Oakwood Road and a Dedication of a Temporary Drainage Easement and a Sanitary Sewer Easement was forwarded to DOT at the end of August 06. PDD is working to secure the easements with the property owners.

Lee Gharavi, Mo

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/9707/94 01/96NA NA NA

Project Description Monthly Remarks

09/97 01/98 02/98 01/9901/9901/98304Fund

064233

Spring Hill Road00000

$10,400,000

Widening Spring Hill Road between Route 7 and International Drive.

Funding provided by VDOT in accordance with its 6-year plan. Environmental documentation comments have been received and are being addressed. VDOT construction plan review comments are being addressed.

Providence Gharavi, MoKresge, CarolGharavi, MoMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/0307/02 12/03 05/05 10/05NA

Project Description Monthly Remarks

09/03 08/08 09/08 03/1006/0807/08304Fund

064237

Roberts Road/Braddock Road00000

$644,000$0

Additional right turn-lane from southbound Roberts Road to Braddock Road.

Construction substantially complete 5/23/08.

Braddock Hojatzadeh, MaxBarnes, DianneFarsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0607/03 10/06 10/06 04/07NA

Project Description Monthly Remarks

11/04 07/07 09/07 05/0812/0706/07304Fund

Thursday, June 19, 2008 Page 4 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064240

Leesburg Pike at Glen Carlyn Road00000

$90,000

Extend left turn-lane on eastbound Leesburg Pike.

Project is part of the Governor's Congestion Relief Program, funded by VDOT. Construction complete 1/12/07. VDOT permit released.

Mason Roberson , Jean

Lim, SamJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0510/04NA NA NA NA

Project Description Monthly Remarks

02/05 11/06 12/06 01/0708/0710/06304Fund

064242

West Ox Road/Monroe Street00000

$600,000$0

Eastbound left turn-lane from West Ox Road to Monroe Street.

Construction substantially complete 4/7/08. VDOT permit released 5/29/2008.

Hunter Mill Chase, StevenKresge, CarolGharavi, MoHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

03/0705/06 01/07 01/07 08/07NA

Project Description Monthly Remarks

02/07 12/07 01/08 04/0808/0811/07304Fund

064243

Poplar Tree Road00000

$675,000

Additional left turn-lane on westbound Poplar Tree Road at the intersection with Stringfellow Road.

Project is part of the Governor's Congestion Relief Program, funded by VDOT. Construction substantially complete 8/22/07. Signal inspection has been completed. Addressing punch list items. VDOT permit revision received for additional drainage inlet at project limit. Contractor authorized to proceed with installation of additional inlet.

Sully Hojatzadeh, Max

Lim, SamStrecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0604/05NA NA NA NA

Project Description Monthly Remarks

01/06 11/06 12/06 08/0708/0710/06304Fund

064246

South Van Dorn/Franconia Interchange

00000

$7,574,399

Design of grade-separated interchange.

Project is funded for design and partial land acquisition only with $8 million in the VDOT Six-Year Improvement Program. Awaiting approved Value Engineering recommendations from VDOT. Revised traffic count completed by VDOT. Preliminary design is in progress.

Lee Salahuddin, KhaliFinnell, Richard

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0909/08 02/09TBD TBD TBD

Project Description Monthly Remarks

10/07TBD TBD TBDTBDTBD

304Fund

Thursday, June 19, 2008 Page 5 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064248

Fairfax County Parkway Widening00000

$3,325,000

Widening of Fairfax County Parkway to six lanes from Rugby Road to Dulles Toll Road for a total of 6.5 miles. Additional lane to be HOV lane.

Funding for preliminary engineering and environmental studies only. Traffic analysis extended south to include section between I-66 and Rugby Road. Air quality analysis is in progress. Draft noise report was received 5/29/08. Phase II archaeological and architectural survey is underway. A meeting with DOT is scheduled for 6/26/08 to discuss preliminary VISSIM results.

Sully Salahuddin, KhaliPreston, ClintonMinnix, Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/08TBDTBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBDHunter Mill304Fund

064251

Guinea Road/Falmead Road00000

$100,000

Extend sidewalk, drop inlet, drainage improvements, and install a crosswalk at Guinea Road and Falmead Road.

Final design is in progress. Construction to be completed by annual contractor.

Braddock Madhusudhan, GPreston, ClintonWolfe, MikeMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0806/05NA NA NA NA

Project Description Monthly Remarks

02/06 10/08 10/08 02/0907/0710/08304Fund

064257

Centreville Road Trail at Dulles Toll Road Phase II

00000

$250,000$0

Provide pedestrian improvements and traffic signal modifications to cross Centreville Rd. @ Dulles Toll Rd. Interchange.

Intermediate design is in progress.

Hunter Mill Madhusudhan, G

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/0907/08NA NA NA NA

Project Description Monthly Remarks

01/09 04/09 05/09 08/0908/0903/09304Fund

064258

Colts Neck Road Trail/Sidewalk00000

$100,000

Construct trail/sidewalk on Colts Neck Road/South Lakes Drive to Hunter Wood Shopping Center (west side).

Final design is in progress. Construction to be completed by annual contractor.

Hunter Mill Madhusudhan, GZore, TasneemWolfe, MikeMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0807/05 06/06 09/06NA NA

Project Description Monthly Remarks

03/06 12/08 12/08 04/0909/0712/08

Mason304Fund

Thursday, June 19, 2008 Page 6 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI001

Arlington Boulevard / Patrick Henry Drive

$150,000

Pedestrian improvements at the intersection of Arlington Boulevard and Patrick Henry Drive.

Pre-final design was submitted to VDOT 10/1/07. Final comments have been received and are being addressed. Environmental documents submitted to VDOT for review on 2/7/08.

Mason Hojatzadeh, Max

Lim, SamMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0806/07NA NA NA NA

Project Description Monthly Remarks

09/07 10/08 11/08 02/0907/0809/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI002

Leesburg Pike / Glen Carlyn Road

$150,000

Pedestrian improvements at the intersection of Leesburg Pike and Glen Carlyn Road.

Scope is being re-evaluated due to conflict with church sign located within the right-of-way. Project was put on hold at the request of the supervisors office until issues are resolved. Environmental documents submitted to VDOT for review on 2/7/08.

Mason Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/0806/07NA NA NA NA

Project Description Monthly Remarks

09/07 05/08 05/08 08/0807/0805/0802/08

304Fund

064267

Pedestrian Improvements - VDOT Funded

PI003

Arlington Boulevard / Graham Road

$200,000

Pedestrian improvements at the intersection of Arlington Boulevard and Graham Road.

Environmental documents submitted to VDOT for review on 2/7/08. Preliminary design is complete. Signal design is in progress.

Providence Hojatzadeh, Max

Lim, SamMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0907/08NA TBD TBD TBD

Project Description Monthly Remarks

02/09 10/09 11/09 02/1002/1009/09304Fund

064267

Pedestrian Improvements - VDOT Funded

PI005

Chain Bridge Road / International Drive

Pedestrian improvements at the intersection of Chain Bridge Road and International Drive.

Environmental investigation is required. Project on hold due to potential conflict with Metro Project.

Providence Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 08/07304Fund

Thursday, June 19, 2008 Page 7 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI006

Lee-Jackson Highway / Stringfellow Road

$150,000$0

Pedestrian improvements at the intersection of Lee-Jackson Highway and Stringfellow Road.

Construction is 85% complete.

Springfield Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/07NA NA NA NA

Project Description Monthly Remarks

08/07 03/08 03/08 06/0803/0803/08

Sully304Fund

064267

Pedestrian Improvements - VDOT Funded

PI007

Leesburg Pike / Magarity Road

$150,000$0

Pedestrian improvements at the intersection of Leesburg Pike and Magarity Road.

Pre-final design submitted to VDOT 1/3/08. Partial comments received. Environmental documents submitted to VDOT for review on 2/7/08.

Dranesville Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07NA NA NA NA

Project Description Monthly Remarks

04/08 11/08 12/08 03/0911/0810/08

Providence304Fund

064267

Pedestrian Improvements - VDOT Funded

PI008

Lee-Jackson Highway / Majestic Lane

$150,000$0

Pedestrian improvements at the intersection of Lee-Jackson Highway and Majestic Lane.

Construction is 90% complete.

Springfield Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/07NA NA NA NA

Project Description Monthly Remarks

08/07 03/08 03/08 06/0803/0803/08

Sully304Fund

064267

Pedestrian Improvements - VDOT Funded

PI010

Loisdale Road / Loisdale Court - Springfield Mall Entrance

Pedestrian improvements at the intersection of Loisdale Road/Loisdale Court and the Springfield Mall Entrance.

Environmental documents submitted to VDOT for review on 2/7/08. Project has been cancelled due to future redevelopment of Springfield Mall.

Lee Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 05/08304Fund

Thursday, June 19, 2008 Page 8 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI011

Leesburg Pike / Patrick Henry Drive

$500,000$0

Pedestrian improvements at the intersection of Leesburg Pike and Patrick Henry Drive.

Environmental documents submitted to VDOT for review on 2/7/08. Preliminary design submitted to VDOT for review 6/10/08.

Mason Hojatzadeh, Max

Lim, SamMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0906/08 10/08 05/09NA TBD

Project Description Monthly Remarks

05/09 11/09 11/09 02/1002/1011/09304Fund

064267

Pedestrian Improvements - VDOT Funded

PI012

Lee Highway/Monument Drive

$150,000

Pedestrian improvements at the intersection of Lee Highway and Monument Drive.

Pre-final design was submitted to VDOT 10/1/07. Final comments have been received and are being addressed. Environmental documents submitted to VDOT for review on 2/7/08. .

Providence Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0806/07NA NA NA NA

Project Description Monthly Remarks

09/07 10/08 11/08 02/0907/0809/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI013

Old Keene Mill Road / Sydenstricker Road

$150,000$0

Pedestrian improvements at the intersection of Old Keene Mill Road and Sydenstricker Road.

Construction substantially complete 5/22/08.

Springfield Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/07NA NA NA NA

Project Description Monthly Remarks

08/07 03/08 03/08 05/0803/0803/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI014

Leesburg Pike / Dranesville Road

$150,000$0

Pedestrian improvements at the intersection of Leesburg Pike and Dranesville Road.

Pre-final design submitted to VDOT 1/3/08. Partial comments received. Environmental documents submitted to VDOT for review on 2/7/08.

Dranesville Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07NA NA NA NA

Project Description Monthly Remarks

04/08 11/08 12/08 03/0911/0810/08304Fund

Thursday, June 19, 2008 Page 9 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI015

Centreville Road / Compton Road

$150,000

Pedestrian improvements at the intersection of Centreville Road and Compton Road.

Pre-final design was submitted to VDOT 10/1/07. Final comments have been received and are being addressed. Environmental documents submitted to VDOT for review on 2/7/08.

Springfield Hojatzadeh, Max

Lim, SamNA, Not Applicabl

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0806/07NA NA NA NA

Project Description Monthly Remarks

09/07 10/08 11/08 02/0907/0809/08

Sully304Fund

064267

Pedestrian Improvements - VDOT Funded

PI016

Centreville Road / Green Trails Boulevard

$150,000$0

Pedestrian improvements at the intersection of Centreville Road and Green Trails Boulevard.

Construction is 80% complete.

Sully Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/07NA NA NA NA

Project Description Monthly Remarks

08/07 03/08 04/08 06/0803/0803/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI018

Braddock Road / Wakefield Chapel Road

$150,000$0

Pedestrian improvements at the intersection of Braddock Road and Wakefield Chapel Road.

Environmental documents submitted to VDOT for review on 2/7/08. Preliminary design submitted to VDOT for review 3/14/08. Partial comments received 5/21/08.

Braddock Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0803/08 05/08 10/08NA NA

Project Description Monthly Remarks

08/08 01/09 02/09 05/0905/0912/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI019

Dolley Madison Boulevard / Great Falls Street - Lewinsville Road

$150,000$0

Pedestrian improvements at the intersection of Dolley Madison Boulevard/Great Falls Street and Lewinsville Road.

Pre-final design submitted to VDOT 1/3/08. Partial comments received. Environmental documents submitted to VDOT for review on 2/7/08.

Dranesville Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07NA NA NA NA

Project Description Monthly Remarks

04/08 11/08 12/08 03/0911/0810/08304Fund

Thursday, June 19, 2008 Page 10 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI020

Lewinsville Road / Balls Hill Road

$150,000$0

Pedestrian improvements at the intersection of Lewinsville Road and Balls Hill Road.

Pre-final design submitted to VDOT 1/3/08. Partial comments have been received. Environmental documents submitted to VDOT for review on 2/7/08. Land acquisition complete 4/10/08. Utility relocations are in progress.

Dranesville Hojatzadeh, MaxZore, TasneemLim, SamMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07 02/08 04/08NA NA

Project Description Monthly Remarks

04/08 11/08 12/08 03/0911/0810/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI022

Leesburg Pike / Baron Cameron Avenue - Springvale Road

$200,000$0

Pedestrian improvements at the intersection of Leesburg Pike/Baron Cameron Avenue and Springvale Road.

Environmental documents submitted to VDOT for review on 2/7/08. Survey is complete. Preliminary design is in progress. Signal design proposal was requested 6/10/08.

Dranesville Hojatzadeh, Max

Lim, SamMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0912/08NA TBD TBD TBD

Project Description Monthly Remarks

05/09 12/09 01/10 04/1004/1011/09

Hunter Mill304Fund

064267

Pedestrian Improvements - VDOT Funded

PI023

Fairfax County Parkway / Old Keene Mill Road

$150,000

Pedestrian improvements at the intersection of Fairfax County Parkway and Old Keene Mill Road.

Pre-final design was submitted to VDOT 10/1/07. Final comments have been received and are being addressed. Environmental documents submitted to VDOT for review on 2/7/08.

Springfield Hojatzadeh, Max

Lim, SamNA, Not Applicabl

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0806/07NA NA NA NA

Project Description Monthly Remarks

09/07 10/08 11/08 02/0907/0809/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI024

Old Keene Mill Road / Shiplett Boulevard

$150,000$0

Pedestrian improvements at the intersection of Old Keene Mill Road and Shiplett Boulevard.

Construction substantially complete 5/22/08.

Springfield Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/07NA NA NA NA

Project Description Monthly Remarks

08/07 03/08 03/08 05/0803/0803/08304Fund

Thursday, June 19, 2008 Page 11 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064267

Pedestrian Improvements - VDOT Funded

PI025

Braddock Road / Guinea Road

$150,000$0

Pedestrian improvements at the intersection of Braddock Road and Guinea Road.

Environmental documents submitted to VDOT for review on 2/7/08. Survey is complete. Preliminary design is in progress. Signal design proposal was requested 6/10/08.

Braddock Hojatzadeh, Max

Lim, SamTBD, To be Deter

PM PDD:PM LAD:PM CMDE:PM CMDS:

05/0912/08NA TBD TBD TBD

Project Description Monthly Remarks

05/09 12/09 01/10 04/1004/1011/09304Fund

064267

Pedestrian Improvements - VDOT Funded

PI026

Fairfax County Parkway / Hooes Road - Seabrook Lane

$150,000$0

Pedestrian improvements at the intersection of Fairfax County Parkway/Hooes Road and Seabrook Lane.

Due to the impact of project to existing bridge, further study is required. Feasibility study is in progress. Schedule to be developed upon completion of feasibility study. Environmental documents submitted to VDOT for review on 2/7/08.

Springfield Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

064267

Pedestrian Improvements - VDOT Funded

PI027

Little River Turnpike / Backlick Road

$150,000$0

Pedestrian improvements at the intersection of Little River Turnpike and Backlick Road.

Pre-final design submitted to VDOT 1/3/08. Partial comments received. Environmental documents submitted to VDOT for review on 2/7/08.

Mason Hojatzadeh, Max

Lim, Sam

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07NA NA NA NA

Project Description Monthly Remarks

04/08 11/08 12/08 03/0911/0810/08304Fund

064267

Pedestrian Improvements - VDOT Funded

PI028

Arlington Blvd - Olin Drive

$150,000$0

Pedestrian improvements on Arlington Boulevard near Olin Drive.

Preliminary design is in progress. Environmental documents submitted to VDOT for review on 2/7/08. Additional survey has been requested.

Mason Hojatzadeh, Max

Lim, SamMurdoch, Guy

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/0908/08NA NA NA NA

Project Description Monthly Remarks

09/08 05/09 06/09 09/0905/0904/09304Fund

Thursday, June 19, 2008 Page 12 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064270

Beverly Rd/Fleetwood Rd00000

$120,000$0

Provide raised concrete median on northbound and southbound approach of Beverly Road.

Intermediate design was submitted to VDOT for review 3/31/08. Partial comments have been received and are being addressed.

Dranesville Ayers, RobertZore, Tasneem

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0803/08 01/08 03/08NA NA

Project Description Monthly Remarks

02/08 10/08 11/08 03/0903/0909/08304Fund

064271

Annandale Rd/Kerns Rd00000

$225,000$0

Intersection improvements including left and right turn lanes.

Preliminary design submitted to VDOT 10/10/07 for review. Comments from DOT and VDOT have been received. A meeting was held with DOT on 1/10/08 to discuss comments that have the potential to change scope. A meeting with VDOT was held on 1/25/08 to discuss these issues. Due to numerous design exceptions, DOT is reviewing feasibility of project.

Mason Khorashadi, Broo

Gharavi, MoHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/0810/07NA TBD TBD TBD

Project Description Monthly Remarks

04/08TBD TBD TBDTBDTBD 01/08

304Fund

064272

South Van Dorn Street Walkway00000

$325,000$0

Concrete sidewalk along west side of South Van Dorn Street from Greendale Village Drive to Telegraph Road.

Design waiver package and final design plans were submitted to VDOT for review 6/5/08.

Lee El Kaissi, Moham

Gharavi, MoJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0809/07NA NA NA NA

Project Description Monthly Remarks

06/08 11/08 12/08 07/0905/0910/08304Fund

064273

Silverbrook Rd/Hooes Rd Intersection Imp.

00000

$350,000$0

Intersection improvement to configure turn lanes at Silverbrook Road and Hooes Road intersection.

Pre-final design is in progress. Geotechnical report received 5/20/08.

Mount Vernon Madhusudhan, G

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0812/07NA NA NA NA

Project Description Monthly Remarks

10/08 02/09 03/09 07/0907/0901/09304Fund

Thursday, June 19, 2008 Page 13 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

064274

Route 29 Walkway00000

$250,000$0

Provide 10' wide asphalt trail on south side of Route 29 between Shreve Road and Fairview Park Drive.

Intermediate design was submitted to VDOT for review 3/12/08. Partial comments have been received and are being addressed.

Providence Ayers, Robert

Housley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0803/08NA TBD TBD TBD

Project Description Monthly Remarks

08/08 11/08 12/08 09/0909/0910/08304Fund

064275

Braddock Rd/Rte 123 EB RTL00000

$300,000$0

Extension of eastbound Braddock Road right turn lane at Route 123.

Pre-final design submitted to VDOT for review 4/8/08.

Springfield Roberson , JeanPreston, Clinton

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0812/07NA NA NA NA

Project Description Monthly Remarks

05/08 11/08 12/08 04/0904/0910/08304Fund

064276

West Ox Rd/Fairfax County Parkway00000

$500,000$0

Extend right turn lane on southbound Fairfax County Parkway. Add dual left turn lanes on northbound Fairfax County Parkway.

Pre-final design and signal modification plans are in progress. Geotechnical report has been received.

Sully El Kaissi, Moham

Gharavi, MoJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0809/07NA NA NA NA

Project Description Monthly Remarks

04/08 03/09 04/09 01/1005/0902/09

Hunter Mill304Fund

064288

Fairfax County Parkway/Sunrise Valley Drive

00000

Fairfax County Parkway/Sunrise Valley Drive

$925,000$0

Addition of dual left-turn lane on northbound Fairfax County Parkway.

Second pre-final design was submitted to VDOT for review 5/28/08. Utility relocations are in progress. A meeting with Sprint was held on-site 5/14/08 to discuss land right issues.

Hunter Mill Salahuddin, KhaliPreston, ClintonMinnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0809/05 10/07 08/08NA NA

Project Description Monthly Remarks

10/07 11/08 12/08 05/0912/0810/08304Fund

Thursday, June 19, 2008 Page 14 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP012

South Kings Highway/Harrison Lane00000

$3,000,000

Addition of left-turn lane from South Kings Highway to Harrison Lane.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. Final design is in progress. Land acquisition public hearing is scheduled for 9/22/08. A meeting with Supervisor McKay and homeowners was held on-site 4/24/08 to discuss driveway drainage issues. VSMP permit has been received.

Lee Salahuddin, KhaliBarnes, DianneMinnix, ToddJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0803/06 08/06 03/07 07/07 09/08

Project Description Monthly Remarks

03/07 12/08 01/09 01/1012/0811/08304Fund

4YP013

Route 236/Beauregard Street00000

$1,000,000

Add a second left-turn lane from eastbound Route 236 to northbound Beauregard Street.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. Construction is 10% complete.

Mason Ayers, RobertZore, TasneemGharavi, MoHousley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0707/05 04/06 05/06 11/06NA

Project Description Monthly Remarks

01/07 03/08 03/08 01/0905/0802/08304Fund

4YP014

Braddock Road/Route 23600000

$1,440,000$0

Realign eastbound lanes through the intersection.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. Construction is 50% complete.

Mason Roberson , JeanPreston, ClintonFarsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0608/05 12/05 02/06 04/06 11/06

Project Description Monthly Remarks

05/06 05/07 06/07 07/0801/0803/07304Fund

4YP020

Hunter Mill Road Walkway00000

$840,000

Walkway along Hunter Mill Road from Chain Bridge Road to Corbalis Park for a total distance of approximately 1900 linear feet.

Project is part of the Four-Year Transportation Program and was approved by the BOS on 3/21/05. VDOT permit application was submitted on 6/11/08.

Providence El Kaissi, MohamKresge, CarolGharavi, MoHousley, Gregg

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0801/06 05/06 03/08NA NA

Project Description Monthly Remarks

09/06 08/08 09/08 01/0908/0807/08304Fund

Thursday, June 19, 2008 Page 15 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB002

Browns Mill Rd Walkway-Victoria Farms to Windstone

$460,000$0

Pedestrian improvements along the south side of Browns Mill Road from Victoria Farms Lane to Windstone Drive. Project is approximately 1,600 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being processed for approval. Schedule to be developed upon authorization of task order.

Dranesville Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB003

Lewinsville Rd Median

$150,000$0

Installation of a pedestrian safety median on Lewinsville Road at Spring Hill Elementary School. Project is approximately 975 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey has been received. Intermediate design is in progress.

Dranesville Shively, Erik

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0911/08NA NA NA NA

Project Description Monthly Remarks

12/09 04/10 05/10 10/1010/1003/10304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB004

Spring Hill Rd - Old Dominion to Pettit Ct

$480,000$0

Pedestrian improvements along the east side of Spring Hill Road from Old Dominion Drive to Pettit Court. Project is approximately 1,550 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Dranesville Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 03/09 10/09NA

Project Description Monthly Remarks

10/09 05/10 06/10 12/1012/1004/10304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB005

Turner Ave Walkway - Williamsburg Pond to Haycock

$50,000$0

Pedestrian improvements along the east side of Turner Avenue from Williamsburg Pond Court to Haycock Road. Project is approximately 200 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being revised. Survey is in progress. Schedule to be developed upon authorization of task order and completion of survey.

Dranesville Shively, Erik

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

Thursday, June 19, 2008 Page 16 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB006

Westmoreland St Walkway - Chain Bridge to Dillion

$230,000$0

Pedestrian improvements along the east side of Westmoreland Street from Chain Bridge Road to Dillon Avenue. Project is approximately 700 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. This project was put on hold pending completion of VDOT's project in this area. Project scope to be re-assessed upon VDOT's project completion.

Dranesville Shively, Erik

McMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 06/08304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB007

Westmoreland St Walkway - Haycock to Temple

$230,000$0

Pedestrian improvements along the west side of Westmoreland Street from Haycock Road to Temple Rodef Shalom. Project is approximately 845 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being revised. Survey is in progress. Schedule to be developed upon authorization of task order and completion of survey.

Dranesville Shively, Erik

McMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB008

Westmoreland St Walkway - Temple to Chesterbrook

$150,000$0

Pedestrian improvements along the west side of Westmoreland Street from Temple Rodef Shalom to Chesterbrook Presbyterian Church. Project is approximately 550 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being revised. Survey is in progress. Schedule to be developed upon authorization of task order and completion of survey.

Dranesville Shively, Erik

McMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB009

Beulah Rd Walkway - Abbotsford to Clarks Crossing

$1,000,000$0

Pedestrian improvements to alternate sides of Beulah Road from Abbotsford Drive to Coral Crest Lane and along Clarks Crossing Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey is in progress. Design proposal is being processed for approval. Schedule to be developed upon approval of design contract proposal.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

Thursday, June 19, 2008 Page 17 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB010

Colts Neck Rd Walkway - Lakes to Winterhur

$130,000$0

Pedestrian improvements along the east side of Colts Neck Road from South Lakes Drive to Winterthur Lane. Project is approx. 850 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey is in progress.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

09/0909/08 01/09 08/09NA TBD

Project Description Monthly Remarks

09/09 11/09 12/09 03/1003/1010/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB011

Fox Mill Rd Walkway - Pkwy to Mill Heights

$100,000$0

Pedestrian improvements along the south side of Fox Mill Road from Fairfax County Parkway to Mill Heights Drive. Project is approximately 600 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress. Utility designations have been completed.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 09/09NA TBD

Project Description Monthly Remarks

10/09 12/09 01/10 04/1004/1011/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB012

Glade Dr Walkway - Colts Neck to Shire Ct

$110,000$0

Pedestrian improvements along the north side of Glade Drive from Colts Neck Road to Shire Court. Project is approx. 800 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey is in progress.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

07/0909/08 01/09 08/09NA TBD

Project Description Monthly Remarks

07/09 03/10 04/10 08/1008/1002/10304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB013

McLearen Rd Walkway - Quincy Adams to Reston Pkwy

$150,000$0

Pedestrian improvements along the north side of McLearen Road from Quincy Adams Drive to Reston Parkway. Project is approx. 600 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress. Utility designations have been completed.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

02/0908/08 12/08 07/09NA TBD

Project Description Monthly Remarks

02/09 09/09 09/09 12/0912/0909/09304Fund

Thursday, June 19, 2008 Page 18 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB015

Reston Ave Walkway - Southington to Shaker Dr

$110,000$0

Pedestrian improvements along the west side of Reston Avenue from Southington Lane to Shaker Drive. Project is approximately 700 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

06/0909/08 01/09 08/09NA TBD

Project Description Monthly Remarks

06/09 11/09 12/09 04/1004/1010/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB016

Soapstone Dr Walkway - Sweetbay to Glade

$20,000$0

Pedestrian improvements along the west side of Soapstone Drive from Sweetbay Lane to Glade Drive. Project is approximately 100 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Hunter Mill Chase, StevenPM PDD:PM LAD:PM CMDE:PM CMDS:

03/0908/08 12/08 01/09 08/09NA

Project Description Monthly Remarks

03/09 11/09 12/09 04/1004/1010/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB017

Sunset Hills Rd Walkway - W&OD to Michael Faraday

$240,000$0

Pedestrian improvements along the north side of Sunset Hills Road from W&OD Trail to Michael Faraday Court. Project is approx. 1,500 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey is in progress.

Hunter Mill Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 03/09 10/09NA

Project Description Monthly Remarks

10/09 05/10 06/10 12/1012/1004/10304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB018

Silverbrook Rd Walkway - Southrun to Monacan

$60,000$0

Pedestrian improvements along the north side of Silverbrook Road from Southrun Road to Monacan Road. Project is approximately 820 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Mount Vernon Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 09/09NA TBD

Project Description Monthly Remarks

10/09 12/09 01/10 04/1004/1011/09304Fund

Thursday, June 19, 2008 Page 19 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB019

Lee Jackson Hwy Walkway - Fair Ridge to Fire Station

$100,000$0

Pedestrian improvements along the south side of Lee Jackson Hwy from Fair Ridge Dr East to the police/fire station. Project is approx 675 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design submitted to VDOT for review 6/16/08.

Springfield Chase, StevenPreston, Clinton

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0906/08 01/09 08/09NA TBD

Project Description Monthly Remarks

07/09 11/09 12/09 06/1006/1010/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB020

Silverbrook Rd Walkway - Silverthorn to Bayberry Ridge

$220,000$0

Pedestrian improvements along the north side of Silverbrook Road from Silverthorn Road to Bayberry Ridge Road. Project is approximately 650 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Springfield Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 09/09NA TBD

Project Description Monthly Remarks

10/09 12/09 01/10 04/1004/1011/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB021

Sydenstricker Rd Walkway - Briarcliff to Galgate

$180,000$0

Pedestrian improvements along the south side of Sydenstricker Road from Briarcliff Drive to Galgate Drive. Project is approximately 1,350 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Springfield Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 09/09NA TBD

Project Description Monthly Remarks

10/09 12/09 01/10 04/1004/1011/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB022

Ashburton Ave Walkway - at Cedar Run

$476,000$0

Pedestrian improvements along the west side of Ashburton Avenue at Cedar Run. Project is approximately 250 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Sully Gilbert, JenniferPM PDD:PM LAD:PM CMDE:PM CMDS:

10/0910/08 02/09 09/09NA TBD

Project Description Monthly Remarks

10/09 12/09 01/10 04/1004/1011/09304Fund

Thursday, June 19, 2008 Page 20 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB023

Telegraph Rd Walkway - South Kings Hy to Lee District Park

$800,000$0

Pedestrian improvements along alternate sides of Telegraph Road from South Kings Highway to Lee District Park. Project is approximately 3,500 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been authorized and notice-to-proceed has been issued. Survey is in progress. Schedule to be developed upon completion of survey.

Lee Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB024

Backlick Rd Walkway - Wilburdale Comm to Braddock

$150,000$0

Pedestrian improvements along the west side of Backlick Rd from Wilburdale community to Braddock Rd. Project is approx. 1,100 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Mason Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0909/08 01/09 02/09 09/09NA

Project Description Monthly Remarks

08/09 12/09 01/10 06/1006/1011/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB025

Backlick Rd Walkway - Opposite Wilburdale Comm

$150,000$0

Pedestrian improvements along the east side of Backlick Rd opposite the Wilburdale community. Project is approx. 360 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Mason Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/0909/08 01/09 02/09 09/09NA

Project Description Monthly Remarks

08/09 12/09 01/10 05/1005/1011/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB026

Columbia Pike Walkway - Downing St to Lincolnia

$430,000$0

Pedestrian improvements along the south side of Columbia Pike from Downing Street to Lincolnia Road. Project is approximately 900 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Survey is complete. Intermediate design is in progress.

Mason Shively, Erik

Harper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

01/1011/08 06/09 07/09 02/10NA

Project Description Monthly Remarks

01/10 05/10 06/10 12/1012/1004/10304Fund

Thursday, June 19, 2008 Page 21 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB027

Columbia Pike Walkway - Maple Ct to Blair

$200,000$0

Pedestrian improvements along the north side of Columbia Pike from Maple Court to Blair Road. Project is approximately 1,000 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Mason Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0907/08 11/08 12/08 07/09NA

Project Description Monthly Remarks

06/09 02/10 03/10 09/1009/1001/10304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB028

Columbia Pike Walkway - Gallows to Annandale Church

$190,000$0

Pedestrian improvements along the south side of Columbia Pike from Gallows Road at the Annandale Methodist Church. Project is approximately 450 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being revised. Schedule to be developed upon authorization of task order. A field meeting with VDOT and DOT was held on 5/6/08 to discuss design issues. Input from this meeting is pending from VDOT.

Mason Shively, ErikPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB029

Leesburg Pike Walkway - Falls Church to Alexandria

$4,000,000$0

Route 7 Pedestrian Initiative -construction of missing segments of pedestrian walkway along Leesburg Pike from Falls Church to Alexandria. Project is approximately 13,200 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design proposal is being revised. Survey is in progress. Schedule to be developed upon authorization of task order and completion of survey.

Mason Shively, ErikPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB030

Lincolnia Rd Walkway - Deming Ave to N Chambliss

$50,000$0

Pedestrian improvements along the north side of Lincolnia Road from Deming Avenue to North Chambliss Street. Project is approx. 240 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Mason Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/0910/08 02/09 03/09 10/09NA

Project Description Monthly Remarks

09/09 01/10 02/10 06/1006/1012/09304Fund

Thursday, June 19, 2008 Page 22 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB031

Montrose St Walkway - Braddock to Grafton

$90,000$0

Pedestrian improvements along the west side of Montrose Street from Braddock Road to Grafton Street. Project is approximately 520 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress. Utility designations have been received.

Mason Shively, Erik

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

09/0910/08 02/09 03/09 10/09NA

Project Description Monthly Remarks

09/09 01/10 02/10 07/1007/1012/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB032

Tyler St Walkway - Columbia Pike to Lake St

$140,000$0

Pedestrian improvements along the east side of Tyler Street from Columbia Pike to Lake Street. Project is approximately 650 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been approved and notice to proceed was issued 3/27/08. Survey is in progress. Schedule to be developed upon completion of survey.

Mason Shively, Erik

Jones, Don

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB033

Annandale Rd Walkway - Brice to Falls Church City Line

$80,000$0

Pedestrian improvements along the east side of Annandale Road from Brice Street to Falls Church City line.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been approved and notice to proceed was issued 3/27/08. Survey is in progress. Schedule to be developed upon completion of survey.

Providence Shively, Erik

Jensen, Chris

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB034

Courthouse Rd Walkway - Chain Br to Plantation Ln

$140,000

Pedestrian improvements along the north side of Courthouse Rd from Chain Bridge Rd to Oakton Plantation Lane. Project is approx. 410 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress.

Providence Shively, Erik

Jozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/0907/08 11/08 06/09NA TBD

Project Description Monthly Remarks

04/09 09/09 10/09 03/1003/1008/09304Fund

Thursday, June 19, 2008 Page 23 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB035

Edgelea Rd Walkway - Oleander to Courthouse

$120,000

Pedestrian improvements along the east side of Edgelea Road from Oleander Avenue to Courthouse Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design was submitted to VDOT for review 6/10/08.

Providence Shively, ErikBuckley, Beth

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

04/0906/08 11/08 06/09NA TBD

Project Description Monthly Remarks

04/09 09/09 10/09 03/1003/1008/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB036

Jefferson Ave Walkway - Summerfield to Marshall St

$250,000

Pedestrian improvements along the south side of Jefferson Av from Summerfield Rd to Marshall St. Project is approx 1,300 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design has been distributed for in-house review on 5/12/08. Comments have been received and are being evaluated.

Providence Shively, Erik

McEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

07/0907/08NA TBD TBD TBD

Project Description Monthly Remarks

07/09 10/09 11/09 05/1005/1009/09304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB037

Lee Highway Walkway - at Blake Ln

$100,000$0

Construction of missing segment of pedestrian walkway along Lee Highway at Blake Lane.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been approved and notice to proceed was issued 3/27/08. Survey is in progress. Schedule to be developed upon completion of survey.

Providence Shively, Erik

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB038

Oak St Walkway - Sandburg to W Morgan Ln

$120,000$0

Pedestrian improvements along the south side of Oak Street from Sandburg Street to west of Morgan Lane.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Notice to proceed with design issued 6/2/2008. Intermediate design is in progress.

Providence Shively, Erik

Strecker, Mathias

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0911/08 04/09 12/09NA TBD

Project Description Monthly Remarks

12/09 03/10 04/10 09/1009/1002/10304Fund

Thursday, June 19, 2008 Page 24 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP201

Pedestrian Improvements - Bond Funded

PB039

Sutton Rd Walkway - at Marywood Rd

$50,000$0

Construction of missing segment of pedestrian walkway along Sutton Road at Marywood Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been approved and notice to proceed was issued 6/2/2008. Survey is in progress. Schedule to be developed upon completion survey.

Providence Shively, Erik

Tomlinson, Russ

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB040

Wolftrap Rd Walkway - Briarcliff Ct to G W Rd

$140,000$0

Pedestrian improvements along Wolftrap Road from Briarcliff Court to George Washington Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been approved and notice to proceed was issued 6/2/2008. Survey is in progress. Schedule to be developed upon completion survey.

Providence Shively, ErikPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP201

Pedestrian Improvements - Bond Funded

PB041

Franconia Rd Walkway - N side Governor's Hill Dr to Telegraph

Pedestrian improvements along the north side of Franconia Road from Governor's Hill Drive to Telegraph Road. Project is approximately 350 LF.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design task order has been authorized and notice-to-proceed has been issued. Survey is in progress. Schedule to be developed upon completion of survey.

Lee Shively, Erik

Jensen, Chris

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP203

Spot Improvements - Braddock Road/Backlick Road

$500,000$0

Install an additional left-turn lane on westbound Braddock Road to Southbound Backlick Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Preliminary design is in progress. Received conceptual plans on 4/17/08. A meeting was held on 5/9/08 to discuss design alternatives. DOT coordinating with DPZ regarding land right issues.

Mason Madhusudhan, GPM PDD:PM LAD:PM CMDE:PM CMDS:

12/0908/08 03/09 05/09 06/09 01/10

Project Description Monthly Remarks

12/09 04/10 05/10 10/1010/1003/10304Fund

Thursday, June 19, 2008 Page 25 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP204

Spot Improvements - Shirley Gate Rd/Route 29

$1,000,000$0

Add additional left turn lane to northbound side.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Preliminary design was submitted to VDOT for review 6/4/08. Signal design is in progress.

Braddock Khorashadi, BrooBarnes, Dianne

PM PDD:PM LAD:PM CMDE:PM CMDS:

02/1006/08 11/08 01/09 03/09 10/09

Project Description Monthly Remarks

02/10 05/10 06/10 01/1101/1104/10304Fund

4YP205

Spot Improvements - Zion Drive

$1,000,000$0

Reconstruct horizontal curve on Zion Drive east of Windsor Hill Drive.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Preliminary design is in progress. Utility designations are complete.

Braddock Chase, StevenPM PDD:PM LAD:PM CMDE:PM CMDS:

11/0906/08 10/08 02/09 04/09 11/09

Project Description Monthly Remarks

11/09 03/10 04/10 12/1112/1101/10304Fund

4YP207

Spot Improvements - Braddock Rd/Randolph Dr

$500,000$0

Extension of left turn lane on eastbound Braddock Road from the entrance into Thomas Jefferson High School (TJHSS&T) to Randolph Drive.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design submitted to VDOT for review 5/2/08.

Mason El Kaissi, MohamPM PDD:PM LAD:PM CMDE:PM CMDS:

01/0905/08NA TBD TBD TBD

Project Description Monthly Remarks

01/09 04/09 05/09 08/0908/0903/09304Fund

4YP210

Poplar Tree Road Improvements

$5,500,000$0

Widening Poplar Tree Road to four lane divided section from Sully Station Drive to Braddock Ridge Drive.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Intermediate design is in progress. Geotechnical report has been received. MACTEC to complete pavement design. Value Engineering study is scheduled for June 17-19, 2008. Signal warrant study to be completed by VDOT by mid-July.

Sully Khorashadi, BrooFinnell, RichardMinnix, W. ToddMcEntire, Vickie

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0910/07 08/08 10/08 11/08 06/09

Project Description Monthly Remarks

06/09 09/09 10/09 10/1010/1008/09304Fund

Thursday, June 19, 2008 Page 26 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

4YP212

Route 29 Widening

$4,000,000$0

Phase III: Widen northbound Route 29 to 3 lanes on from Legato Road to Shirley Gate Road.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. VDOT widened westbound lane between Dixie Hill Road and Holly Avenue. Design proposal was received 6/11/08 and is under review.

Springfield Madhusudhan, G

Minnix, W. Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

4YP213

Lorton Road

$40,000,000$20,000,000

Widen Lorton Rd. to 4 lanes from Rte. 123/Furnace Rd. to Silverbrook Rd. and from Rte. 123/Lorton Rd. to Furnace Rd.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Preliminary design is in progress. Utility coordination in progress. On 3/26/08, requested VDOT for concurrence of LID practices in right-of-way. Coordinating lane configuration, turn lane lengths and bike lane typical section with DOT.

Mount Vernon Roberson , JeanPM PDD:PM LAD:PM CMDE:PM CMDS:

01/1109/08 08/09 01/10 02/10 09/10

Project Description Monthly Remarks

01/11 04/11 05/11 12/1212/1203/11304Fund

4YP214

Cinder Bed Road Improvements

$5,000,000$0

Improvements to the intersection of Cinder Bed Road and Newington Road. Relocate entrance to County vehicle maintenance facility.

Project is part of the Second Four-Year Transportation Plan endorsed by the BOS on 10/15/07. Design contract to be presented to Board of Supervisors 6/30/2008. Schedule to be developed once design proposal is authorized.

Mount Vernon Chase, StevenPM PDD:PM LAD:PM CMDE:PM CMDS:

TBDTBD TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD304Fund

K00447

Richmond Hwy Public Transport Initiative Phase 4A

RS102

Intersection Design - Belford Drive Old Mill Road, and Mohawk Lane

$357,000

Engineering and construction of intersection improvements at express bus service stops for Belford Drive, Old Mill Road, and Mohawk Lane.

Project is part of the Four-Year Transportation Program endorsed by the BOS on 2/9/04. This project will be completed in phases. Schedule for this phase will be determined following completion of other phases. Land acquisition is required. Design waiver package submitted to VDOT for review on 6/11/08.

Mount Vernon Madhusudhan, GPreston, ClintonMinnix, W. ToddJozsa, Steve

PM PDD:PM LAD:PM CMDE:PM CMDS:

TBDNA TBD TBD TBD TBD

Project Description Monthly Remarks

TBD TBD TBD TBDTBDTBD 07/06Lee307Fund

Thursday, June 19, 2008 Page 27 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

W00900

Sully District WalkwaysW903

Rt 29/I66 Underpass Trail

$726,000

1,800 linear feet of 8' asphalt trail, including crossing under I-66 overpass.

Project is part of the Four-Year Transportation Program endorsed by the Board 2/9/04. Construction substantially complete 11/5/07. Awaiting final inspection.

Sully Foxx, Keith

Minnix, W. ToddHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

11/0505/05NA NA NA NA

Project Description Monthly Remarks

11/05 07/06 09/06 11/0707/0706/06307Fund

009217

Stonecroft Boulevard Widening00000

$500,000

Widen Stonecroft Boulevard to a six-lane section from Conference Center Drive to Westfields Boulevard.

Fairfax County responsible for 800 linear feet of improvements in front of Sully District Governmental Center with the remaining portions to be completed by developers. Construction to be managed by developers. Developer is in the process of soliciting bids from prospective contractors. Marriott dedication plat has been approved by LDS. Utility relocations are in progress. Construction agreement with WBOA is being drafted.

Sully Salahuddin, KhaliKresge, Carol

PM PDD:PM LAD:PM CMDE:PM CMDS:

08/05 04/07 10/07 01/08TBDNA

Project Description Monthly Remarks

03/06NA NA NANANA

312Fund

008909

Annandale Streetscape Columbia Pike - Annandale Fire Station

00000

$1,600,000$369,000

Streetscape improvements on north side of Columbia Pike from Backlick Road to Annandale Fire Station.

Enhancement Grant funding will be utilized to supplement project funds. Plans being updated. LAD is in the process of acquiring additional land rights. Proposal for due diligence and NEPA process was received 6/11/08 and is under review. Schedule to be developed upon receipt of funding agreement from VDOT.

Mason Ayers, RobertBuckley, BethLim, SamMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

06/0702/98 01/99 10/99 12/00 12/02

Project Description Monthly Remarks

09/06TBD TBD TBDTBDTBD

315Fund

008912

McLean CRP00001

McLean Streetscape Demonstration Project

$1,700,000

Streetscape improvements to Chain Bridge Road from Westmoreland Street to Cedar Avenue.

This project is funded with VDOT Transportation Enhancement Grants. Construction is 30% complete.

Dranesville Roberson , JeanBarnes, DianneFarsad, NahidHarper, Greg

PM PDD:PM LAD:PM CMDE:PM CMDS:

12/0501/04 06/04 08/04 03/06NA

Project Description Monthly Remarks

12/05 11/07 02/08 07/0807/0810/07315Fund

Thursday, June 19, 2008 Page 28 of 29developed by, Robert Hockersmith

Project #

Project NameSubProject #

Sub Project Name

TPE ($)

FUT ($)On Hold

Design Dates

Estimated Completion

District CAP Assignments

Project ManagersLand Acquisition Dates

Construction Award

IntermediatePreliminary Utility Plats

Project Plats

Bid OpenApproved Completion

Estimated Completion

Bid Advertisement

CurrentFinal

Approved Completion

Construction Dates

Summary Status ReportTransportation Design Branch

May 2008

008912

McLean CRP00002

McLean Utilities

$1,800,000

Underground utilities along Chain Bridge Road from Corner Lane to Laughlin Avenue.

Evaluating project budget. Anticipate additional funding required due to increased material and utilities costs. Final design is in progress. A meeting with McLean Revitalization Group, Supervisor's Office, and the Developer was held on 6/10/08 to discuss potential revision to duct bank layout. Developer will present their proposed revisions to Fairfax County for concurrence in the near future.

Dranesville Khorashadi, BrooFinnell, RichardMinnix, Todd

PM PDD:PM LAD:PM CMDE:PM CMDS:

03/04 12/05 09/06TBD TBD TBD

Project Description Monthly Remarks

06/06TBD TBD TBDTBDTBD

315Fund

013918

Jefferson Manor IIB00000

$2,000,000

Improvements to Fort Drive for a total of 1,550 linear feet.

Construction is 85% complete.

Lee Ayers, RobertColeman, MichaelMinnix, W. ToddMcMillen, Barry

PM PDD:PM LAD:PM CMDE:PM CMDS:

10/0611/94 12/04 08/05 08/05 02/07

Project Description Monthly Remarks

03/06 08/07 08/07 08/0801/0807/07340Fund

Thursday, June 19, 2008 Page 29 of 29developed by, Robert Hockersmith