Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An...
Transcript of Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An...
![Page 1: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/1.jpg)
Cost and Schedule Integration: An Industry UpdateAn Industry Update
J 27 30 2013January 27‐30, 2013Sheraton New Orleans
![Page 2: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/2.jpg)
Outline• Speaker Introduction
• Government Contracting Perspective• Government Contracting Perspective
• Commercial Contracting Update
• Conclusion
2
![Page 3: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/3.jpg)
Introduction
• Michael R. Nosbisch, CCC, PSP– Currently
• PT&C Vice President and EVMS Practice Lead
• Immediate Past President of AACE International
• Active member of NDIA’s Program Management SystemsActive member of NDIA s Program Management Systems Committee (PMSC)
– FormerlyVi P id f EVM f SM&A• Vice President of EVM for SM&A
• VP of Project Controls for Parsons Government Services
3
![Page 4: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/4.jpg)
Government Contracting Perspective
4
![Page 5: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/5.jpg)
DI‐MGMT‐81861 states clearly that …
5
1.2.1 Integrate cost and schedule performance data with objective technical measures of performance.
![Page 6: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/6.jpg)
The 100,000 foot view of what is new …
6
OSD EVM Data Requirements Integrated Program Management Report (IPMR) Data Item Description (DID) & Work Breakdown Structures (WBS) NDIA, PMSC meeting, August 15, 2012
![Page 7: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/7.jpg)
How can we measure performance?
7
![Page 8: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/8.jpg)
Integrated CPR, IMS, CSFR
Format 1 – WBS
Format 2 OBSFormat 2 – OBS
Format 3 – Baseline
Format 4 StaffingFormat 4 – Staffing
Format 5 – Explanations and Problem Analysisand Problem Analysis
Format 6 – IMS
F t 7 Hi t d
8
Format 7 – History and Forecast
![Page 9: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/9.jpg)
One Big Hitter – Variance Analysis• Formal variances are limited to a total of 15 WBS Elements.• Two methods allowed for determining which variances are
addressedaddressed– Top 15 WBS Elements approach– Allows for Government selection approach or a defined
contractor process that covers all aspects (current, cumulative p p ( ,and at‐complete)
• Allows contractor or government to temporarily increase the number of reported variances to cover emerging tread(s)p g g ( )
• Linked Formats 1–4 and 6 discussions to Format 5– Significant Format 6 changes. Require SRA, Health Assessment
and drivers as applicable
9
and drivers as applicable
• Reconcile Best/Worst/Most Likely EACIntegrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
![Page 10: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/10.jpg)
The IMS has one new format …• The Integrated Master Schedule (IMS) had been a
separate deliverable with its own DID– Now merged with the CPR as Format 6 in the IPMR– IMS analysis requirements will be submitted as part of Format 5
• Added significant language to eliminate most needs for statement of work clarification– Defined minimum level of subcontractor integration– Reached agreement on the definition of Schedule Margin and
Schedule Visibility Tasks (SVTs)Required disclosing of justification for Leads Lags and most– Required disclosing of justification for Leads, Lags and most Constraints
– Defined minimum fields– Expanded when SRA is required and how it is reported
10
p q p
Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
![Page 11: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/11.jpg)
Format 6• Consistency with Format 1 Addressed
– Included “The WBS numbering system in the IMS must be consistent with the Format 1 structure.”
• Schedule Margin – Allowed before program events. §3.7.2.4.
• Critical & Driving Paths• Critical & Driving Paths – Included definition that tasks with “0” or negative total
float are not by default the critical path §3.7.1.3.5.9.– Driving path and interim milestones defined (not in 2005– Driving path and interim milestones defined (not in 2005
IMS DID) §3.7.1.3.5.8.– Excessive constraints and incomplete, incorrect, or overly
constrained logic shall be avoided.§3.7.1.3.5.9.
11
g §
Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
![Page 12: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/12.jpg)
Format 6 (cont’d)• Relationships & Float
– All non‐constrained discrete tasks/activities/milestones shall have at least one predecessor and successor, except p pthe start and end of the program or interim delivery
• Subcontractor Integration– Subcontractor discrete work shall be incorporated as tasks p
within the prime IMS at a level necessary for a realistic critical path
• Calendars– The IMS shall contain all calendars that define working and
nonworking time periods or other information that may impact the schedule
12
Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
![Page 13: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/13.jpg)
New Format 7• New requirement not in CPR DID, but similar
information was previously required by the EVM Central Repository (called historical file)Central Repository (called historical file)
• Time phased BCWS, BCWP, ACWP, ETC from contract award to completion as applicable
• Must reconcile with Format 1 BAC and EAC for the month submitted
• Due as a minimum annually at the same time as• Due as a minimum annually, at the same time as other Formats. Recommend quarterly according to the government fiscal calendar.
13
• Purpose to support Government planning cycle Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
![Page 14: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/14.jpg)
Commercial Contracting Perspective
14
![Page 15: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/15.jpg)
Commercial Contracting Perspective• General Observations
• The Contractors’ Side• The Contractors Side
• The Owners’ Side
• Recommended Practice(s)
15
![Page 16: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/16.jpg)
General Observations• Commercial contracting environment much more
reliant on FFP/FUP contract types for large projects– Cost and performance risk “transferred” from owners to
contractors
– Nuances will exist between different project delivery p j ymethods
• Schedules usually integrated with cost only when ll i d b i f li icontractually required as basis for pay applications
– Formalizes requirement to perform monthly updates
– Often times leads to secondary “field schedule”
16
Often times leads to secondary field schedule
![Page 17: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/17.jpg)
The Contractors’ Side• Parsons Corporation
– A current Acumen customerB i i ifi f ll d i– Began as engineering‐specific, now full scope design‐build/EPC contractor
• Specializes in first of a kind, one of a kind projects
– Three primary business units• Parsons Government Services (formerly PI&T)
• Parsons Environment & InfrastructureParsons Environment & Infrastructure– Commercial Technology
– Water & Infrastructure
• Transportation Group
17
Transportation Group
![Page 18: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/18.jpg)
The Contractors’ Side
• Summary of Parsons Requirements1. Hierarchical Work Breakdown Structure (WBS) and
WBS Dictionary• Unique WBS numbers assigned to the lowest level elements of the WBS
• One responsible individual for each WBS element (one person can manage multiple WBS elements)
2 Metrics identified for consistently establishing2. Metrics identified for consistently establishing physical progress• Budgets match the structure and detail of the metrics used f h i l
18
for physical progress
![Page 19: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/19.jpg)
The Contractors’ Side• Summary of Parsons Requirements (cont’d)
3. Logic‐based schedules that identify the sequence of work d i ifi t t k l ti hiand significant task relationships
• WBS reflected within schedule so that activities can be associated with specific control accounts
4. Time‐phased budget baselines (i.e. overlay or budget‐load the schedule)• Both cost and revenue required to generate cash flow curve q gfor large projects during proposal review
• Level‐of‐effort activities are identified and isolated in a separate control account
19
![Page 20: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/20.jpg)
The Contractors’ Side
• Summary of Parsons Requirements (cont’d)5. Baseline plan is controlled
• Prevent unauthorized changes
• Ensure that authorized changes are immediately incorporatedp
6. Monthly or more frequent comparison of progress and costs to the baselines
C l l i f d h d l i d i d i h• Calculation of cost and schedule variances and indexes, with explanations provided for significant variances
• Corrective actions implemented as appropriate
20
![Page 21: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/21.jpg)
The Owners’ Side• Orange County Sanitation District
– Responsible for safely collecting, treating and disposing the wastewater generated by 2 5 million people living in a 479wastewater generated by 2.5 million people living in a 479‐square‐mile area of central and northwest Orange County (CA)
– Ongoing Capital Improvements Program comprised of multiple rehabilitation and expansion projects totaling app $3 billionrehabilitation and expansion projects totaling app. $3 billion
• Most projects are FFP, design‐bid‐build
• OCSD Scheduling Specification Review– Submittal/acceptance of baseline schedule
• Required for full payment of mobilization line item
• $300K or 10% of line item
21
$
![Page 22: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/22.jpg)
The Owners’ Side• OCSD Scheduling Specification Review (cont’d)
– Cost loading of activities• Required on all discrete work activities• Required on all discrete work activities
– Not procurement and submittal preparation/review (except for baseline schedule)
• Cost loading should be equal to value of contract price (revenue)• Cost loading should be equal to value of contract price (revenue)– Not required to be integrated with resource loading (crew‐based)
– Overhead/profit prorated and added to each activityOverhead/profit prorated and added to each activity
– Cost (revenue) curve required as separate submittal
– Schedule updates used as basis for progress payments, but not exclusively
22
y
![Page 23: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/23.jpg)
Recommended Practice(s)• Contractors’ Side
– If internal decision is made to cost load schedule, should be performed at summary (control account) level onlyperformed at summary (control account) level only
• Should not be integrated with resource loading to allow for more flexibility
– In addition to initial cash flow curve generated by cost loaded– In addition to initial cash flow curve generated by cost loaded schedule, “earned value” curves should be developed
• Based on what has been approved (“earned revenue”) for monthly progress paymentprogress payment
• Facilitates trend for how much work is required on monthly basis to complete in accordance with forecasted date in CPM schedule
23
![Page 24: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/24.jpg)
Recommended Practice(s)
• Owners’ Side– Specifying cost (revenue) loading as basis of progress payments helps to ensure timely schedule updates
• Should also specify that each discrete activity be subdivided into “substantial completion” and “final completion” to p pprevent widespread out‐of‐sequence progress
• Should allow for overhead/profit to be loaded outside of discrete activities
– Also, should be loaded in activity with fixed duration equal to contractual PoP (not hammocked over entire schedule)
– Will allow contractor to recover overhead/profit as originally
24
planned, lessening cash flow impact of delays/claims
![Page 25: Cost and Schedule Integration: An Industry Update - Cost … · Cost and Schedule Integration: An Industry Update ... number of reported variances to cover emerggging ... – Overhead/profit](https://reader034.fdocuments.us/reader034/viewer/2022042801/5ab7c03e7f8b9ad5338bf35f/html5/thumbnails/25.jpg)
Revenue‐based Application
Time
25
Source: SM&A EVMS Seminar 25