Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to...

24
Company Profile Automation Solutions for Oil & Gas Onshore Production Pipeline & Gas Compression Offshore Production Export Terminals & Buoys FPSO & FSO LNG Production/ Liquefaction Wellheads LNG Terminal Containment Vessels Petrochemicals Shale Oil & Gas Refineries

Transcript of Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to...

Page 1: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company Profile

Automation Solutionsfor

Oil & Gas

Onshore Production Pipeline & Gas Compression Offshore Production Export Terminals & BuoysFPSO & FSO LNG Production/ LiquefactionWellheads LNG Terminal Containment Vessels PetrochemicalsShale Oil & Gas Refineries

Page 2: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

INTECH Process Automation is a renowned system integrator and automation solution provider for the oil & gas sector globally. Over a period of more than 20 years it has helped major Oil & Gas End Users to solve their most pressing issues of Instrumentation, Control & Electrical automation. INTECH’s broad automation solution product portfolio, technical skills, knowledge & expertise on equipment of all major OEMs and its asset-application specific approach to solution design is what differentiates it from a typical system integrator.

Introduction

01 Introduction Company Profile 02Introduction Company Profile

Present OfficesFuture Offices

Global Reach

Regional Operations in 13 Countries across 5 Continents

Experience

2000+Engineering Man-Years

25+Continuous

years

Local Presence

Project Foot Print in 35+ Countries

Vendor Experience

Partnerships

Oil & Gas Producing Countries

8 Out of Top 10

Instrumentation, Control & ElectricalIntegrated Control Systems Advance Software Solutions

Wellhead SolutionsMetering, Storage &

Fuel systemsOperations & Maintenance

Product Portfolio

End Users EPC OEM

Our Clients: Growth Partners

Vendor Neutral – Best Fit Approach

DiverseCustomerBase

GloballyLocal

Project Experience

Product Portfolio

Oil & Gas Companies

10 Biggest MNCs

Page 3: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

History

INTECH started as an entrepreneurial venture with three engineers and a single room office. Over the course of more than twenty years INTECH has transformed into a global organization with 400+

employees, 13 regional offices across five continents, 23+ nationalities, and an automation products & solutions portfolio that spans the entire lifecycle of an oil & gas asset.

03 04History Company Profile History Company Profile

INTECH starts off with 03 engineers

INTECH incorporates in USA

INTECH extends its presence in Singapore and Nigeria

1992

1998 1999-2000

INTECH ventures into specialized solutions for Wellhead. Successfully delivers Hydraulic Wellhead Control

Panels and associated Remote Terminal Unit (RTU) to OMV Pakistan

INTECH's first large project in Equatorial Guinea

INTECH extends its regional presence in CIS region; opens office Kazakhstan

INTECH Indonesia office opens with the strategic

objective of serving the Asia Pacific market

INTECH Iraq office opens

INTECH becomes part of the first responders by providing complete MAC scope for containment vessel in Alaska

INTECH opens its China Office to strengthen its

presence in Asia Pacific and reach out

to Greater China

INTECH upgrades control systems across all four offshore fields at OML-100 for Total E&P Nigeria

2006

2007

2008 2012 2013 2016 20172002 2003

INTECH awarded its first ever Greenfield project, Sanha

Condensate project in Angola

INTECH opens office in Angola

INTECH extends its project footprint in Iraq, successfully

commissions the largest offshore terminal off the coast of Iraq

INTECH's expertise augmented to include

sub-sea controls

INTECH secures long-term maintenance contract for the world’s largest FPSO, Abgami.

2004 2005

INTECH extends its regional presence to KSA

Engineering and Supply of Smartwells and Choke

automation in RussiaINTECH sets up its world headquarters operations in UAE. A second manufacturing facility is set up to cater the needs of the Eastern Hemisphere efficiently

Compressor Controls Upgrade at Saudi Aramco

Supply of Control System and WHCP for 20 sites;

SCADA for 200+ well sites

20152010 2011 2014

Page 4: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Corporate StructureINTECH has divided its global operations into three geographic regions. Each region is an independent business unit (BU) with its own sales & front-end engineering team. A Central Engineering Pool, HR Finance, G&A, I.T., and QHSE along with Marketing and Solution Center work in a matrix organization with the business units. An advanced solution group works on bringing new technology to the market though these BUs. The technically astute sales team work in tandem

with the engineering, solution centre and client team to ensure customer satisfaction throughout the engagement process. The Solution Center is a highly efficient group of engineers that make designs for best in class products and solutions, which are in line with the latest Oil & Gas technological advancements and regional best practices. The engineering team lies at the core of our delivery excellence promise.

05 Company ProfileCorporate Structure

Americas - BU Asia - BU

MIddle East & Africa - BU

INTECH World Wide

75+

15+

Employees

Nationalities

Offices

300+13

40+

150+

Page 5: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

06Corporate Structure Company Profile

Typical BU Organization

Organizational Structure

Legend:CM: RSM:O&M:QHSE:

Country ManagerRegional Sales ManagerOperations & MaintenanceQuality, Health, Safety, Environment

CEO/CFO/President

Finance & Accounts

Marketing

Solution Center

HumanResource

Director Sales -GCC CM Angola CM KSACM Nigeria

O&M ManagerRegional Ops.

Manager

Front Office Engg. Team O&M Engineers

RSM UAE/Iraq

Vice President – MEA

FinancialController

MarketingManager

Central Engineering

Manager

Solution Center Manager

QHSEManager

Vice President –Americas

Vice President –MEA

General Manager –Asia

General Manager –SENSYS

DirectorOperations

ManagerProject Controls

ManagerIT/IS

Human Resource Manager

CEO/CFO/President

Director Operations

Engineering Manager

QHSE

Project Controller

Page 6: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company ProfileEngineer

INTECH’s engineers lie at the core of its growth strategy. INTECH recognizes the fact that its long-term growth and success will be fuelled by the quality of its human resource in general and engineers in specific. INTECH invests heavily in the training development and retention of its employee base. The recent growth has been fuelled by the company’s quality engineering

team. It has clearly defined career paths and training and development plans for all its employees, especially engineers. Employee training and motivation is emphasized upon as it is a company-wide belief that well trained and motivated employees are the lifeline for the company.

Engineers

Our Engineers

07

EngineersAmericas

Asia

22%

Engineers

Middle East & Africa

66%

Engineers22%

Page 7: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company ProfileEngineer

Talented

Trained

Experienced

Typical INTECH Engineer Profile

08

Engineering Base Growth

150

100

50

250

300

200

02011 2012 2013 2015 20162014 2017

1. 8+ years of project experience2. Design and Engineering lead of at least 4 major projects3. Training and hands-on experience on at least 4 major OEM equipments4. At least 100 formal training hours per year 5. PMP trained and certified

Years

Engin

eerin

g Bas

e

Page 8: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Integrated Control Systems

09 Company ProfileIntegrated Control Systems

INTECH’s Integrated Control Systems offer a complete array of control automation and integration solutions ranging from basic Process Control, Safety, F&G and Power Management applications to data networks, site security, instrument management and fully integrated control and safety systems. Our third party start-up and commissioning services ensure minimum downtime and accelerated glitch-free execution. INTECH’s ICS is a field-proven “One-Stop Automation Solution” that improves plant safety, reliability and efficiency while lowering costs and increasing returns.

Process Control SystemsSafety Instrumented SystemsFire & Gas (F&G) SystemsCondition Monitoring Systems (CMS)Power Management SystemsInstrument Asset Management Systems (IAMS)Industrial Data Networks Communication Systems & PAGA SystemsSecurity: CCTV, Anti-Intrusion SystemsProcess Historian - Plant Information Management System (PIMS)

1.2.3.4.5.6.7.8.9.

Page 9: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

10

Engineering, Design and Supply of Integrated Control & Safety System (ICSS) for gas processing plant

The location is approximately 100 miles southeast of Lagos and 37 miles west of Warri. The plant processes approx. 680 million standard cubic feet of natural gas per day. The customer had planned a Gas Gathering & Compression Platform and a Non-Associated Gas (NAG) Wellhead Platform facility in the offshore field for its ongoing flare reduction efforts.

INTECH was called in to provide automation solution for the above mentioned project. INTECH’s scope included engineering, design, fabrication, integration, testing, documentation and supply of a complete integrated & operable Integrated Control and Safety Systems (ICSS).

Integrated Control & Safety System and High Integrity Pressure Protection System, for gas processing plant in Angostura, Trinidad & Tobago.

Trinidad and Tobago are islands that are located between the Caribbean Sea and the North Atlantic Ocean. These locations are well known for their liquefied natural gas, oil and petrochemicals. The customer was setting up new offshore platforms for Greater Angostura field and required a High Integrity Pressure Protection System (HIPPS) to be installed at GEP HP offshore platform located off the east coast of Trinidad.

INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration and start-up of Process Historian, along with start up and commissioning services for the afore mentioned systems.

Refinery Upgrade Project, Kuwait

The Refinery is located in southern Kuwait approximately 60 km from Kuwait City. The refinery occupies an area of 7.9 sq. having a processing capacity of 270 MBPD.The customer wanted to upgrade obsolete automation system installed on multiple applications at the facility. The upgrade had to be done as a hot cutover job, as some of the applications could not be shutdown.INTECH was selected as the Main Automation Contractor (MAC) by the customer to develop and execute a hot cutover procedure. The upgrade was performed on various units within the refinery including coke handling, Water treatment plant, ship loading and tank farms.

Selected Project References

“After successful commissioning I would express my satisfaction at duly meeting the project schedule. The work was done in the most professional manner and we shall favourably consider your company for future work.”

Project Manager,Total E&P

Company ProfileIntegrated Control Systems

Page 10: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

ICE - Instrumentation, Control & Electrical

11 Company ProfileICE

INTECH’s ICE solutions leverage on years of system integration experience and outstanding vendor relations into a turnkey solution for any control, instrumentation & electrical needs of the Oil & Gas Industry. INTECH positions itself as a worldwide Main Automation Contractor (MAC) through its ICE offering with solutions that start from engineering and design of ICE systems to construction, manufacturing and supply of control rooms, e-buildings, and switchgear & MCC packages. Coupled with commissioning and startup services, ICE provides a complete end-to-end solution for project and asset lifecycles.

Packaged Control Rooms & E-buildingsElectrical Switch Gear and MCC Package SupplyInstrumentation Package SupplyInstrumentation, Control & Electrical Construction ServicesControl system Engineering & Design ServicesElectrical System Engineering & Design ServiceInstrumentation Engineering & Design ServicesElectrical Startup & Commissioning ServicesInstrumentation Startup & Commissioning Services

1.2.3.4.5.6.7.8.9.

Page 11: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Main Automation Contractor for an Early Production Facility, Kurdistan IraqThe location of the project was Sarong Block which is in the Kurdistan Region of Iraq. The Sara Tina - 1 exploration well had been drilled and was initially tested. The customer wanted to place the well on an extended production test with oil sales. Estimated production from ST-1 was around 4,000 BPD while EPF was designed for 20,000 BPD. INTECH was awarded the project to provide turnkey solution for instrumentation, control and electrical (MCC) for the Early Production Facility (EPF). Project was extremely fast track. INTECH made all the equipment ready within 5 weeks and then mobilized a team of about 26 personnel to site to complete site construction, installation and commissioning. All the logistics of local and expat resources were taken care by INTECH internally.

Main Automation Contractor for a Central Processing Facility, KazakhstanKazakhstan, a country rich in natural resources, has oil reserves that are estimated to be 1.635 million bbl/day (2011 est.) and natural gas of about 20.2 billion cubic meter (2011 est.). The customer was expanding its facilities of Arskum, Kazalkiya, Kumkol regions. INTECH was called in for Design, Engineering, Supply, Commissioning and Site Services for DCS, F&G, HMI, associated fiber optics & Packaged Control Room and E-building. Additional scope included supply of Tank Radar System and associated construction work. All construction work including logistics and local labor resources were managed by INTECH.

Main Automation Contractor for a Containment Barge, AlaskaA part of the Arctic Ocean is formed by the Chukchi Sea. The estimated oil and gas reserves that come from the US side of Alaska alone are estimated to be 30 billion barrels of oil. The end user required an incident containment barge to be available for the offshore 2011 drilling program in Alaska to allow rapid deployment and containment of any spill situation.INTECH was called in as a Main Automation Contractor (MAC) and system integrator bringing together the Engineering, Design, Supply, Fabrication and delivery expertise for supply of PCS, SIS, F&G, LER building e-house and onsite MCC. Some of the challenges faced by INTECH were; HSE consideration due to an environment of -40°C, remoteness, tight project timescales, and meeting customer’s high work standard.

12

“I would like to take this opportunity to express my gratitude for the services your company has provided over the last 12 months. Your expertise and professionalism have been a major contribution to the completion of our project. I would not hesitate to recommend your company.”

Project Manager

Selected Project References

Company ProfileICE

Page 12: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company ProfileWellheads

Wellhead Solutions

13

INTECH’s Wellhead Solutions cover the entire lifecycle of wellhead systems anywhere in the world from frozen Russian fields to scorching Middle Eastern deserts. Our solutions cover the entire automation scope of a wellhead from vanilla hydraulic wellhead control panels and skids to technologically advanced solutions for well flow measurements, containerized well pad controls, master control stations, pump-off control, remote well monitoring and lift optimization. State of the art manufacturing facilities in USA and UAE coupled with regional offices around the world allow us to deliver in the industry’s shortest lead times.

1.2.3.4.5.6.7.

Hydraulic Wellhead Control PanelRemote Terminal Units (RTU) – PCS, SIS, F&GIntelligent Well Flow ControlWellhead SCADA SolutionsSubsea Master Control Station (MCS)Chemical Injection & Wellhead SkidsArtificial lift optimization solutions

Page 13: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company ProfileWellheads 14

Main Automation Contractor for Wellhead Solutions, PakistanThe Sawan Gas Field is a located in Sindh, Pakistan. This is a joint venture of OMV Pakistan, Government Holdings (Private) Limited, PPL, ENI Pakistan and Moravské naftové doly. There are a total of 15 wells that have been drilled in Sawan It is one of the largest gas reserves discovered in Pakistan producing 400 MMSCFD of raw gas.INTECH was asked by the customer for the engineering, supply and design of Hydraulic Wellhead Control Panel, RTU associated control and safety systems as well as Shelter, Venturi and Solar Systems for three wellhead sites in the area. The installation commissioning of the control panels and associated systems with the shelter were also a part of INTECH’s scope of work.

Upgrade of Subsea Master Control Station, Equatorial GuineaThe Ceiba Field is in Block G off the continental coast of Equatorial Guinea. The customer is the operator of two adjacent blocks which together encompass an area of approximately 1 million acres.INTECH’s project scope included design, engineering, and hardware for the upgrade to the MCS PLC. Software upgrades and designing of new HMIs, implementation of new signals and relay logic, documentation of the current hardware and systems and setting up of the new upgraded hardware were also included in INTECH’s scope of work.

Main Automation Contractor for Wellhead Solutions, IndonesiaDuri field located in Indonesia, is spread over 11,000 sq. km with various remote collection stations with an overall production of about 400,000 bpd. The customer is a major part of the Indonesian oil & gas sector and is an active member of the community.INTECH was called in for technical support and services for a large number of wellhead SCADA systems installed at disparate remote locations. Additional scope included Engineering, Design, Supply, and Installation & Commissioning for new SCADA units. The remote locations were connected through communication over the GSM network.

“INTECH exceeded all our expectations during project execution right from design to project management. We will be recommending INTECH for future projects.”

Project Manager

Selected Project References

Page 14: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Company ProfileO&M

ON-CALL O&M SERVICESGlobal maintenance engineer deployment when called Response time as early as 24 hours Standard engineering, maintenance & optimization trainings Support for remote locations

1.2.3.4.

FACILITY SURVEY & TROUBLESHOOTING Problem Alarm Baseline Survey Facility Bottleneck Survey Loop Optimization Survey Plant Optimization Survey

1.2.3.4.

RESIDENT/ONSITE O&M SERVICES Resident engineer with scheduled 40 hours/week on-site Multi-disciplinary engineers Standard engineering, maintenance & operations trainings Support for remote locations

1.2.3.4.

REMOTE O&M SERVICES Immediate 24/7 support availability Connect with senior engineers & consultants

1.2.

O&M TRAINING SOLUTIONS Training for operators of key assets Enable operator-driven reliability and field checks Get solutions for any environment and control requirement Deliver & enhance operations’ exellence

1.2.3.4.

Optimization & Maintenance Solution

15

INTECH’s O&M services provide long-term asset healthcare, maintenance and upgrades ensuring sustained operation of assets for their planned life and beyond. Our project experiences help us gain valuable knowledge of systems, improving our learning curve in comparison to a third-party O&M provider, thereby reducing O&M risks & costs. With INTECH’s diverse expertise of control systems and oil & gas application, we also help reduce hassle of managing multiple vendors for any O&M situation. A single INTECH resource is skilled at handling multiple systems – saving both finances and time.

Services Scope

Page 15: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

O&M Company Profile 16

Optimization and Maintenance services for a FPSO, Nigeria

Agbami FPSO is the world’s largest FPSO operating at the Nigeria’s largest deep water oil field. It operates nearly 70 miles offshore the central Niger Delta. The field is operated by the customer. The FPSO has multiple vendor equipment installed base with equipment as old as 15 years to new state of the art automation systems.

INTECH’s scope includes services for long term health care & maintenance, training of operators & engineers, startup and commissioning of new equipment/upgrades including multi-vendor supervision. INTECH has been proving services on all electrical and control related systems on the FPSO.

I,C &E Optimization and Maintenance services for entire field assets, Angola.

The customer is the operator of two concessions off the west coast of Angola, north of the Congo River. INTECH has been working with the customer for the past 10 years to provide operations and maintenance services for the instrumentation, control and electrical automation systems installed at Takula, Sanha condensate, Molongo, Area-B, BBLT and Molongo terminal facilities of the customer.

INTECH’s was called in to provide maintenance support for different operating facilities (Ranging from Well Jackets, Gathering Stations, Storage, Export & Refining), update documentation, procedures and firmware for the control systems. INTECH was also responsible for planning and co-ordination with the operations team for a design review of major capital projects and their commissioning.

Tengiz is located in north-western Kazakhstan's low-lying wetlands. It covers an area of about 2,500 km long the northeast shores of the Caspian Sea. The average oil production at the location is estimated to be about 400,000 BPD.

INTECH’s was awarded an optimization and maintenance contract which included reverse engineering the systems to develop detailed documentation for the F&G, ESD and PLC systems. During the project support was provided on multi-vendoor systems through a team of 18 operations and maintenance engineers deployed on site to meet the expectations of the customer

Optimization and Maintenance services at Tengiz, Kazakhstan

“In all honesty, most of the elements regarding the project, INTECH support either met or exceeded my expectations. Also, we greatly appreciated the flexibility of the home office to keep the PM engaged until we completed the Cutover.”

Project Manager BOT

Selected Project References

Page 16: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Advance Software Solutions

17

INTECH offers consultancy solutions (consultancy, algorithms, technology) targeting operations, production & maintenance to discover hidden efficiencies in plants’ operating envelope. Working together with the customers, it gets more out of people, processes, and technology. INTECH’s partners are directly involved with, and influence the development of virtually all industry recognized alarm management standards and other influential documents, including the ISA-18.2 standard, the API-RP-1167 recommended practice, and the EEMUA 191 guideline document.

Operations Management Solutions

Production Management SolutionsCyber Security Solution

Alarms Management SolutionControl Loop Optimization SolutionAdvanced Process Control Optimization

1.

2.3.

“INTECH was able to address a significant portion of the Alarm System issues we had at [the] Gas Plant through Rationalization of Alarms. They are very competent in complete Alarms Management Life Cycle”.

Plant Operator

The concerned gas plant is located near a distributary of the Niger River in southern Nigeria. The location is approximately 100 miles southeast of Lagos and 37 miles west of Warri. This Gas Plant processes approximately 600 million standard cubic feet of gas per day.INTECH identified an opportunity for an alarm system improvement project to enhance the safety, reliability and profitability of the said Gas Plant. The activity reduced alarm average count by 60% in just D&R. A large portion of nuisance non-critical equipment alarms were removed and over 120 instruments with possibly faulty chattering alarm were identified.

Alarm Optimization & Installation of Alarm Management System

1. Analysis of Existing Alarm System (Over 8,000 Alarmable Tags)2. Supply of Alarm Management Software Server & Client3. Integration of Alarm Management System with DCS & Safety System4. Configuration of Process Safety Metrics Reporting in accordance to Engineering Standards and ISA 18.25. Automated Alarm System Performance Reporting System for Operations & Maintenance Team6.Training of the Plant’s Operations and Maintenance Team on utilizing System to achieve Alarm Management Lifecycle

Company ProfileAdvanced Software Solutions

Page 17: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Metering, Storage & Fuel Systems

18

INTECH’s solutions designed for metering, storage and fuel systems help address the unique issues faced by oil and gas specialized applications like buoys, metering skids, tank gauging and burner management. Keeping these applications’ exclusive operational needs in mind, INTECH’s solutions help deliver reliable and robust solutions customized to the needs of each customer with strict conformance to industry and OEM standards.

Flow Metering & Custody TransferBuoy Automation SolutionBurner Management SystemTank gauging & Oil Movement

1.2.3.4.

Arman field is situated in the north-west part of Bouzachi half-island in Mangystau region of Kazakhstan. The total proven and probable oil reserves at Arman are estimated to be 11.5 million metric tons (84 million barrels). The total proven and probable gas reserves are estimated to be 82 million cubic meters.

INTECH was invited by Arman JV LLP to bid for the Engineering, Design and Supply of the new metering skid. INTECH was awarded the project based on its impressive track record in oil and gas automation projects as well as long-term successful business presence in Kazakhstan. INTECH scope of services

Design and Supply of Crude Oil Custody Transfer Metering Skid

1. Engineering design 2. Procurement 3. Configuration/integration4. Integrated Test 5. Start-up – Site services 6. Commissioning – Site Services 7. Post installation services – Site Services

Metering, Storage & Fuel Systems Company Profile

Page 18: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Execution Methodology

Our Project execution methodology ensures that the customer needs are met cost effectively while remaining within the project deadlines. The core of our expertise lies with INTECH’s technically competent regional team, which is responsible for customer engagement and project management right from scope definition till the final delivery and handover of the project. The offshore engineering offices work in tandem with regional teams to

ensure that solutions are delivered as per global best practices and in compliance with the worldwide standards of QHSE. The centralized manufacturing facilities are strategically based out of Houston and UAE, the global hubs of oil & gas. Being located at the heart of oil & gas hubs, enables INTECH to design products and solutions that are abreast with latest advancements in technology and deliver superior value to oil & gas industry worldwide.

Engineering Office

INTECH’s Global Presence

1. Customer engagement & scope definition

2. Engineering, Design & Project Management

3. Regional Supply Chain Management

4. Procurement

5. Technical Support & Global Best Practices Sharing

6. Panel Manufacturing

7. Internal QA & FAT

8. Packaging & Shipment

9. Installation & Commissioning

10. SAT

11. Long-term maintenance & After Sales Support

19 Company ProfileExecution Methodology

Client World HQInternational HQ

INTECH Factory

Page 19: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Functional & ProcessUnderstanding

Design & EngineeringProcurement

Manufacture

Testing IFAT / FAT

Documentation

Mobilization

Deployment InstallationCommissioning

& Startup Training & Hand-Over

Monitoring &Maintenance

Optimize&

Enhance

Accelerate Development - Reduce time to Startup

Strong Regional Engineering BaseRemote Support from global Engineering OfficePlant Personnel trainingReal time performance monitoringDocumentation, Handover & Completion

Best Fit SolutionModular Design ApproachCompliance to Global, Local and Corporate StandardsProject Management PMIProven and field tested solution designUL certified laboratoryGlobal Network of Vendors

Safe & Reliable Operations

Operational ExcellenceOperational & Business KPI alignmentEnhancing & Maximizing ROAMoving to the Next Level of Efficiency

Performance Metric ManagementChange Management Identity Improvement OpportunitiesInventory Management24/7 local Remote SupportPreventive Maintenance Management

Complete Lifecycle Services

5. Technical Support & Global Best Practices Sharing

20Company ProfileExecution Methodology

Page 20: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Automation Lab

A key piece of INTECH’s edge includes the automation lab concept. With years of experience doing projects, INTECH has enhanced and developed its automation lab such that:

State of the art technological process solutions are researched and designedEquipment & Resources of major vendors like: SMAR, Honeywell, Rockwell, Yokogawa, Invensys, HIMA etc. are available to our subject matter experts for design and testing of best fit solutionsActs as a classroom training centre for customers

Our engineers and SMEs possessing more than 10 years of experience conduct research and develop new technological solutions in these labs to suit customer requirementsKeep our engineering team abreast with the latest developments in the automation domain

21 Company ProfileAutomation Lab

Vendor Expertise

Page 21: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

22Company ProfileAutomation Lab

Page 22: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Quality

The long-term business success of INTECH depends on our ability to continuously improve our products and services while exceeding customers’ expectations. Right from the start of the project we make sure that quality is maintained not only as per international standards, but in-line with our specialized & customer centric standards as well. Regardless of the number of changes in the proposal or the original scope of the project, we make sure that quality is maintained throughout. The quality standards of INTECH have been very instrumental in its continuous growth and development. To ensure these standards are maintained in all our offices, the company has a comprehensive set of procedures and frameworks that monitor customer satisfaction during Project Execution Life cycle.

INTECH is the member of multiple international organizations and certification bodies which ensure quality of work process and output. These organizations include:

The Country Manager provides a leadership role in all quality related matters with assistance from QHSE Lead of that particular region. The evaluation for the team executing a project is tied with the feedback score, ensuring commitment towards customer satisfaction. The root cause for any issue is marked by incorporating feedback from all the stakeholders and identifying all sources that may have caused non-compliance; corrective actions are identified, marked and implemented with mutual consent of all parties involved. A log of issues encountered and lessons learnt is maintained for future reference.

Standards & Compliances

23 Company ProfileQuality

Fire SystemsNFPA72NFPA85NFPA86API RP14GIEC 60331IEC 60332

Safety SystemsAPI RP14BAPI RP14CAPI RP14HIEC 61508IEC 61511SP 84 Alarm Management

EEMUA 191

OthersIEC 61131 IEC 61000 API RP14F EEMUA 201 EEMUA 189 NEC409NEC490

Enclosure TypeNEMA250IEC60529

Hazardous AreasAPI RP14J API RP500 API RP505 IEC 60079 NEC 500/505

NRTL/ MarksUL FMCSA TUVCE ATEXBASEEFA

Classification SocietiesABS DNV

LR

Other BodiesMMS USCG

Page 23: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Health, Safety and Environment at the INTECH have primary importance in every activity we perform. We are committed to deliver our projects and operational activities with no harm to employees, community, subcontractors, visitors and the environment as a whole. INTECH’s due diligence in maintaining and implementing the best practices and HSE procedures worldwide has ensured that our objectives of achieving international and national standards are met and exceeded.

Health, Safety & Environment

Health Safety & Environment Record

Occupational Casualties

Occupational LTIs (Loss Time Injuries)

RWI (Restricted Work Injuries)

Tolerance on Near Misses

Environmental incidences

ZERO LTI SINCE THE LAST 5 YEARS

24Company ProfileHealth, Safety & Environment

Page 24: Corporate Profile compressed - INTECH Process Automation · 2018-09-13 · INTECH was asked to provide the complete design, engineering & supply of PCS, SIS, F&G and HIPPS, integration

Notice: All registered logotypes, trademarks, brands, product and services marks used in this document are acknowledged as properties of their respective companies/owners and such companies/owners have not consented to their use by INTECH (Term INTECH is used for INTECH Process Automation Inc. and its affiliates). INTECH is not affiliated with these logotypes, trademarks, brands, product and services marks and any use by INTECH should not be construed as an endorsement of INTECH or its services. The services described herein are provided solely by INTECH. © 2017. All rights reserved by INTECH Process Automation Inc. facebook.com/Intechprocessautomation

linkedin.com/company/intech-process-automation

Vendor Expertise Standards & Certifications

End User EPC

What Our Customers Say...“I commend you on your efforts in customizing the business analysis software for trial deployment for a Web Based Alarm Management Dashboard. It meets our objectives and has produced the desired results.”

Control & Automation Leader

“[We] commend INTECH’s knowledge of alarm management, dedication, commitment and effort. Most importantly, works have been completed safely and INTECH has been able to work successfully in our diverse environment”

Central Maintenance Coordinator

“INTECH’s team worked with extraordinary zeal & efforts at the Adhi Electronic Flow Metering Project which included on-line trends and alarms of sales gas parameters’ limits. The competency level and performance of their deputed team is satisfactory and commendable. “

Deputy Chief Engineer

PPL

OEM

AmericasWORLD HQINTECH Process Automation Inc.4903 W. Sam Houston Parkway N. Suite A-100Houston, TX 77041, USATel: +1 713 849 1000 Fax: +1 713 856 0785

INTECH Process Automation Perú S.A.C.Av. República De Panamá N°3030 Oficina 7a San Isidro, Lima, Perú Tel: +511 606 6849Cel: +51 982117562

EuropeINTECH Process Automation Sarl168 Avenue Charles De Gaulle, 92 522 Neuilly-sur-seine Cedex, [email protected]

Central AsiaINTECH Process Automation LLP.Office No. 7, St. Sevastopolskaya 1V,Atyrau, Republic of KazakhstanTel: +771 2250 8529

AsiaINTECH Process Automation Pte. Ltd600 North Bridge Road, #23-01 Parkview Square, Singapore 188778Tel: +65 68289118Fax: +65 68289112

PT INTECH Process AutomationRukan Permata Senayan, Blok C Nomor 5, 4th Floor,Jalan Tentara Pelajar, Kebayoran Lama,Jakarta Selatan, 12210 IndonesiaTel & Fax: +62 21 579 49 444

INTECH Process Automation (Shanghai) Co. Ltd.Room 1605c, 16f Feidiao International Building, No.1065 Zhaojiabang Road, Xuhui District,Shanghai 200030 – P.R.C.Tel: +86 21 2426 1951Fax: +86 21 2426 1877

INTECH Process Automation Pvt. Ltd.2nd Floor, Commercial Building #2PCSIR Phase – IILahore 54782, PakistanTel: +92 42 111 468 324Fax: +92 42 3531 4149

Middle EastINTERNATIONAL HQINTECH Process Automation FZCOP.O. Box 61479, RA08ZC01, JAFZA, DUBAI, United Arab EmiratesTel: +971 4 8810056Fax: +971 4 8810057

INTECH Process Automation Inc. Br.G-201 Al-salah Tower, P.O. Box 4270, Al-khobar - 31952,Kingdom Of Saudi ArabiaTel: +966 13 8966052, +966 13 8966053

INTECH Process Automation FZCO Br. 470, Italian City, Erbil, Iraq Tel: +964 780 131 2198, +964 750 309 3766

North Africa OperationsTel: +971 55 607 3230, +971 553768482

Email: [email protected]

AfricaINTECH Process Automation Nigeria Ltd.64b, Abacha Link Road, G.R.A. III,Port Harcourt, Rivers State, Nigeria

Liaisons Office, Victoria Islands, Lagos, Nigeria

Tel: +234 807 5396201Tel: +234 705 1404326Tel: +234 805 [email protected]

INTECH Process Automation Inc.(Sucursal De Angola)Casa Nº B07, Condominio Boulevard, Via Al16, Talatona, Luanda - Republica De AngolaTel: +244 222 720 471Fax: +1 281 377 3455 [email protected]

[email protected]

www.intechww.com