1 New Substation Project Electric System Upgrades • New transmission lines and a substation are needed on the south side due to: – Federal (NERC) standards involving transmission planning (enforceable since July of 2007) – To serve future load growth in the southern portion of the electric territory

Transcript of Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New...

Page 1: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

1

New Substation Project

Electric System Upgrades

• New transmission lines and a substation are needed on the south side due to:– Federal (NERC) standards involving

transmission planning (enforceable since July of 2007)

– To serve future load growth in the southern portion of the electric territory

Page 2: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

2

Project History

• 2007: Assessment process identified the need for a new substation and transmission lines

• Spring 2008: SEGA hired to help with site selection and line routing

• Substation site needs to be established before transmission line routes are finalized

Page 3: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

3

Project History

• January 2009: Ten possible sites identified, landowners were contacted, and an “Interested Parties”meeting was held•None were interested in selling property

• Spring 2009: A property owner approached the city about a site on Peach Tree Court

Page 4: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

4

Project History

• Summer 2009: At the request of an area landowner, more property was investigated

• September 3, 2009: Water & Light Advisory Board unanimously recommended Council pursue 1.77 acres on Peach Tree Court

Page 5: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

5

SEGA

Substation Site Criteria

• Distribution system loading• Proximity to existing distribution line• Proximity to transmission lines• Existing neighbors and land use• Accessibility to equipment &

maintenance• Availability & cost of site

Page 6: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

6

Mapping and initial line route selection

• Building footprints• Overhead and underground utilities• Proposed roadways and widening• Known environmental constraints

Route evaluation and elimination

• Transmission line characteristics• Buildings and other facilities• Crossings• Right of way characteristics• Costs

Page 7: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

7

Page 8: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

8

Conclusions

• After field reconnaissance trips, reviewing GIS data, considering preliminary transmission line routes & site availability, lot 6 was determined to be preferred site

Page 9: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

9

Questions?

THE FOLLOWING SLIDES CONTAIN COPIES OF THE ACTUAL REPORT FROM SEGA, THE WATER & LIGHT ADVISIORY BOARD MEMO, AND AN EXERPT OF THE WATER & LIGHT ADVISORY BOARD MINUTES HIGHLIGHTING THE PORTION RELAVANT TO THE SUBSTATION.

THEY ARE NOT INTENDED FOR DISPLAY.

Page 10: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

10

Page 11: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

11

Page 12: Copy of New Substation Project - Columbia, Missouri · Microsoft PowerPoint - Copy of New Substation Project Author: seshelby Created Date: 9/30/2009 11:15:47 AM ...

12