White Flint Substation Project

12
White Flint Substation Project August 12, 2021

Transcript of White Flint Substation Project

Page 1: White Flint Substation Project

DAY RENDERING - NORTHEAST

White Flint Substation Project August 12, 2021

Page 2: White Flint Substation Project

Agenda

1. Introductions2. Background3. Project Overview, Design and Status4. Upcoming Project Construction5. Keeping You Informed6. Q&A

2

Page 3: White Flint Substation Project

Background• North Bethesda is quickly becoming

a center for economic development• The area is transitioning from a

suburban to an urban environment• Major development is occurring

along the I-270 corridor and the White Flint area

• Significant capacity growth is expected in the region

3

North Bethesda Future Development

North Bethesda continues to grow, with more than 10 million sq. ft. of development slated for the area

Page 4: White Flint Substation Project

Project Overview• We are constructing a new 69kV/13kV

distribution substation in the White Flint area• The White Flint substation will allow us to

continue to deliver safe, reliable, affordable, and sustainable energy to nearby families and businesses in the growing North Bethesda area

• Reliability enhancement work includes extending current 69kV and 13kV feeders from surrounding substations to White Flinto This involves both underground transmission and

overhead transmission construction

4

DAY RENDERING - NORTHEAST

NIGHT RENDERING - NORTHEAST

Page 5: White Flint Substation Project

Targeted Locationand Affected Area

55

16 MWMID-PIKE PLAZA

NORTH BETHESDA P.12.5 MW

WHITE FLINT MALL.

10 MW

NIH5.5 MW

HR2 MW

Parlkawn Sub.White Flint Sub.Parklawn supp. area

New Sub supp. areaFuture New load

Page 6: White Flint Substation Project

Project Design

• The design of the project was a multi-year process including several alternative analyses, community meetings, and discussions with permitting authorities

• After extensive analysis, Pepco and its specialty vendors designed the substation and feeder extensions to meet the demands of the surrounding area with consideration for future growth

• All aspects of the design – location, equipment type, and architectural aesthetic –were considered and incorporated into the final design

6

Substation Layout

69kV Feeder Extension Design

Page 7: White Flint Substation Project

Project Status• Substation construction started in April 2020• The steel structure was completed in April 2021• Pre-cast panels were installed in April and May 2021• Major equipment installation and building completion is scheduled to run through 2022

7

Construction start

Excavating substation basement

Pre-cast panels installed

Substation steel structure

Page 8: White Flint Substation Project

Project Status• 13kV and 69kV underground duct banks are

being installed along Nebel St., Marinelli Rd., Old Georgetown Rd., Citadel Ave., Randolph Rd., and Parklawn Dr. to provide a pathway for electrical cabling

• Civil construction started in April 2020 and is expected to be completed in 2022

• Seven new overhead steel poles will be installed along Randolph Rd., Parklawn Dr., and Nicholson Ln.

8

Underground duct bank construction

69kV (yellow) and 13kV (red) underground duct bank overview

Page 9: White Flint Substation Project

Upcoming Project Construction• On Aug. 30, Pepco's construction contractor, CW &

Sons, will begin a 6-month construction effort on thewestbound lanes of Randolph Rd., between Nebel St.and Parklawn Dr.o Work includes excavation of two micro-tunnels under the

CSX railroad tracks

• Westbound lanes of Randolph Rd. will be closed, and allwestbound traffic will be detoured to Parklawn Dr.

• Eastbound lanes on Randolph Rd. will remain open totraffic

• Businesses located along the westbound side of thisstretch of road will remain open throughout theconstruction and will be accessible via the eastboundlanes of Randolph Rd.

• Sidewalks on Randolph Rd. will remain open topedestrians throughout construction

9For construction updates, please contact Shamyra Edmonds, Project Ombudsman, CW & Sons

[email protected]

Page 10: White Flint Substation Project

Safety Is Our Top Priority

• We’re coordinating with the Montgomery County Department of Transportation to create traffic control plans to ensure work is done safely and to minimize disruption o Appropriate signage and flaggers will be used to direct

traffic for the detour and to access businesses o Please use caution when driving near work zones

• We’re committed to minimizing impacts to pedestrians and businesses and appreciates the cooperation and understanding of residents as we continue to perform this important reliability enhancement work in the area

10

Page 11: White Flint Substation Project

Keeping You Informed• We welcome the opportunity to work with residents and

business owners to gather feedback and input • We’re committed to keeping you informed every step of

the way

11

Ways to Stay Connected• Visit pepco.com/Reliability• Connect with us on social mediao twitter.com/pepcoconnecto facebook.com/pepcoconnect

• Email: Pepco External Affairs Managers Tony Ruffin at [email protected] and Tami Watkins at [email protected]

Page 12: White Flint Substation Project

Q&A