Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 1
Controlling Project Costs
Jon Grunzweig
Vision Business Systems
Leading IT to Business Excellence
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 2
Ever Happen?
• Great project plan, good resources, design
• Before you know it…..
– Delivery date slipping
– Going over budget
• Project keeps going along
– Start ignoring the budget, so far overspent
– Timeline goes into oblivion…
Shuttle Route
Endeavor’s Last Mission
• Great preparation
Things happen….
• $$
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 3
Credibility Issues….
Blame game starts……
Which leads to…….
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 4
Why ?
• Many moving parts (very few fixed parts)
• Circumstances occur different
• Things left out / Estimates incomplete
• Poor cooperation within business, people
• Events and changes
• Issues with service providers
• Outside uncontrolled events
• Unknowns….
Most Projects
• Predictability
• Been done, or very similar (not one of a kind)
• Experienced resources
• Therefore:
– Should be on time and on schedule (or very near)
What’s the disconnect?
• Good plan, design, resources, project mgt
but……..
• Poor alignment of Accountability Cycle
• Poor hours accountability
• Elements unplanned for
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 5
Our focus today….
• Alignment of Accountability Cycle
• Accountability of hours
• Areas short-changed in estimates
Foundation for Control
Technology Vision and Strategy
Methodologies & Processes:
Design, Project, Change Control
Contract & Vendor Management
Governance & Project Management
Project Planning & Agreements
Project Execution Cycle
Spend & Execution Cycles
Spend Authority Cycle
Budgets
Proposals
SOWs
Execution Cycle
Project Plans
Timesheets/ Billing
Status Reporting
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 6
Accountability Cycle
Methodology
Proposals
SOW’s
Project Plan / Est
Time Sheets
Billing
Status Reporting
Accountability Alignment
Prop SOW Plan Time Invoice Status
Total 120 120 120 90 70 130
Task 1 40 40 40 30 20 35
Task 2 80 80 80 60 50 95
Accountability Hours
A B C
Plan Actual
Remain
A-B
Total 120 90 30
Task 1 Rsc 1 40 30 10
Task 2 Rsc 2 80 60 20
How Much --->
<--
--- W
hat
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 7
Accountability Hours – Plan
A B C
Plan Actual
Remain
(Plan -
Act)
Total 120 90 30
Task 1 Rsc 1 40 30 10
Task 2 Rsc 2 80 60 20
How Much --->
<--
--- W
hat
Accountability Hours – Actual
A B C
Plan Actual
Remain
(Plan -
Act)
Total 120 90 30
Task 1 Rsc 1 40 30 10
Task 2 Rsc 2 80 60 20
How Much --->
<--
--- W
hat
Accountability Hours - ETC
A B C D
Plan Actual
Remain
(Plan -
Act) ETC
Total 120 90 30 40
Task 1 Rsc 1 40 30 10 5
Task 2 Rsc 2 80 60 20 35
How Much --->
<--
--- W
hat
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 8
Accountability Hours – Proj Total
A B C D E F G
Plan Actual
Remain
A-B ETC
Proj
Total
B+D
Var
A-E Billing
Total 120 90 30 40 130 (10) 70
Task 1 Rsc 1 40 30 10 5 35 5 20
Task 2 Rsc 2 80 60 20 35 95 (15) 50
How Much --->
<--
--- W
hat
Accountability Hours - Summary
A B C D E F G
Plan Actual
Remain
A-B ETC
Proj
Total
B+D
Var
A-E Billing
Total 120 90 30 40 130 (10) 70
Task 1 Rsc 1 40 30 10 5 35 5 20
Task 2 Rsc 2 80 60 20 35 95 (15) 50
How Much --->
<--
--- W
hat
Accountability Hours - Keys
• Must do it timely (daily or weekly)
– With additional early warning protocol
• Accountability at the resource level
• Accountability of the group
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 9
Problems with Estimates
• More than initial coding or configuration
• Testing � Unit, integration, system, regression
• Rework � It will occur
• Deployment (prepare, deploy, verify)
• Post live support (immediate)
Summary - Key Elements
• Appropriate Project Plan
– Watch out for common items left out
– Resources own estimates & updates
• Accountability Cycle lines up
• Solid relationship with vendors
• Timely reporting (within 1-2 days of cutoff)
• Stick to methodologies/processes
• Plan for contingencies and issues
• Measure your success rate
If control costs…..
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 10
Footnotes
• Types of Projects: ERP vs. Development
• Not Covered: All other types of issues
• Hard Costs (hardware, equipment, etc.)
• Challenges
– Putting time in without regard to estimate
– Getting systems, processes aligned
Questions / Discussion
?
Controlling Project Costs
SoTecConference 2012
10/26/2012
Jon Grunzweig 11
Controlling Project Costs
Jon Grunzweig
Thank You!