    Project Implementation: Procurement &Contract Management

    April 2012

  • 8/12/2019 Contracts and Management

    2/40

    We would like to acknowledge the contribution of theProgramme Management Department in the

    preparation of this presentation that will introducesome concepts and guiding principles for

    Procurement & Contract Management

    For more information on the topic please refer to the supervision training material of February 2012

    Project Implementation: Procurement & Contract Management

  • 8/12/2019 Contracts and Management

    3/40

    2

    What are IFADs role and responsibilityin procurement for projects?

    What are the tasks involved inprocurement supervision?

    How is procurementsupervisionconducted?

    How are contractsmanaged?

    Project Implementation: ProcurementLearning Objectives

  • 8/12/2019 Contracts and Management

    4/40

    3

    Inefficient or ineffective procurement may have seriousconsequences:

    expected project results and impacts not achieveddelays in project implementation

    higher cost of implementation

    Procurement is a sensitive activity:can be conducive to corruption and fraud

    complexity of certain procurement actionscombined use of national & IFAD regulations / guidelines

    Project Implementation: ProcurementIntroduction

    Purchasing goods, services and works (procurement) is a

    critical element of project implementation. . .

  • 8/12/2019 Contracts and Management

    5/40

  • 8/12/2019 Contracts and Management

    6/40

    5

    Project Implementation: ProcurementTendering Process

    Formation of Bid Evaluation Committee;N-O by IFAD

    Prepare Specifications and tenderdocuments (Advertisement/ ITBs/RFPs/ RFQs as applicable) and No-

    Objection (if required)

    Key

    ITB Invitation toBid

    RFP Requestfor Proposal

    RFQ Request forQuotation

    Bid Evaluation and draft contractIFAD Prior Review and No-Objection (if

    required)

    Contract Award to best evaluated bid

  • 8/12/2019 Contracts and Management

    7/40

    Project Implementation: ProcurementCommon Procurement Methods

    International CompetitiveBidding (ICB): for high valuerequirements (1)

    Advertise in widelycirculated newspapers,local representatives,Embassies, UNDevelopment ForumPre-qualificationPublic bid openingBid evaluation based onpoint scoring system(technical + financial)

    National Competitive Bidding(NCB): for public procurement inBorrowers country (2)

    Advertise in localnewspapers (note: foreign

    suppliers may bid)

    Same

    SameSame

    6

  • 8/12/2019 Contracts and Management

    8/40

    7

    Project Implementation: ProcurementCommon Procurement Methods

    International Shopping (3):short-list at least three

    reputable suppliers in atleast two member countries ofIFAD

    issue ITB to the short-listed

    suppliersreceive bids in original form(not faxed)

    bid evaluation based onlowest cost for compliantoffers

    sign contract

    Local Shopping (4):prepare specifications andrequest for quotationsshort-list at least three reputablesuppliers

    issue request for quotations tothe short-listed suppliers

    Same

    Same

    Same

  • 8/12/2019 Contracts and Management

    9/40

    Direct Contracting (5):

    Extension of/ addition to an existing contractStandardisation of goods with existing project assets

    Note: Competitive process is not required

    Project Implementation: ProcurementCommon Procurement Methods

    8

  • 8/12/2019 Contracts and Management

    10/40

    9

    Difference Between Procuring Goods and Works and SelectingConsulting Services . . .

    GOODS, WORKS AND TECHNICALSERVICES

    CONSULTING SERVICES

    Product based Knowledge based

    Open competition Selective competition

    Public bid opening Non-public bid opening of technical offersPublic opening of financial proposals

    Price is a major factor Quality is a major factor

    Detailed specification Terms of Reference(general work program)

    Single-stage procedure Two-stage procedure

    Negotiations rarely Negotiations usual

    Project Implementation: ProcurementGoods & Works vs. Consulting Services

  • 8/12/2019 Contracts and Management

    11/40

    10

    Procurement rules and proceduresapplicable to a particular project comefrom different sources:

    national procurement rules andregulations

    IFAD Procurement Guidelines project appraisal report loan agreement

    Applicable rules, methods andprocedures are specified in the Letter tothe Borrower, as well as IFADprocurement review requirements

    Project Implementation: ProcurementRegulatory Framework

    Must adhere to regulatory framework . . .

  • 8/12/2019 Contracts and Management

    12/40

    11

    Procurement planning (in line withproject objectives and AWPB)

    Preparation and issuance of biddingdocuments and invitation to bid

    Opening and evaluation of offers

    Negotiation, award and signature ofcontract

    Monitoring of contract execution(technical and financial/administrative)

    Delivery of goods/works/services

    Payment

    Project Implementation: ProcurementRole of Borrower/PMU in Procurement

    PMU has overall responsibility for

    Procurement

  • 8/12/2019 Contracts and Management

    13/40

    12

    IFADs Fiduciary responsibility:

    Proper use of loan funds: IFAD must ensure loan proceedsare used only for intended purpose: while FMresponsibilities lie with CFS-Finance Officers, procurementrelated activities are in PMD, specifically CPM and SupportStaff

    Economy and efficiency requirements in projectimplementation in general and procurement in particular:IFAD must ensure contract awards result from acompetitive process

    IFAD must ensure equity, integrity,transparency and good governancein procurement process

    Concept of no objection

    Project Implementation: ProcurementImportance of Procurement IFAD Guidelines

  • 8/12/2019 Contracts and Management

    14/40

    13

    CPM must ensure:

    coherence of procurement actions with project objectives, AWPB andprocurement plan, and timing within project implementation period

    funds availability : cost of procurement must not exceed fundsallocated in loan agreement and annual budget

    transparency and equity: procurement must be conducted incompliance with applicable rules and procedures

    best value for money: procurement must be the result of a competitiveprocess

    - IFAD staff must maintainneutrality and impartiality

    - Flexibility is a must but knowrules and regulations

    Project Implementation: ProcurementRole of IFAD in Procurement

  • 8/12/2019 Contracts and Management

    15/40

    14

    A complete financial and administrative procedures manual(Implementation/ Operations Manual)

    A well-prepared start-up workshop with a technical sessionThe technical session should include discussions about theimportance of quality submissions, frequent causes of delays,timing issues

    A procurement plansummarizing procurementmethods, applicable rulesand prior reviewrequirements as providedin the financing agreement

    Project Implementation: ProcurementKey Tools for Successful Procurement (1)

  • 8/12/2019 Contracts and Management

    16/40

    15

    Assessment of procurement capacity at thenational/project level

    Training of relevant PMU and national partners inall aspects of procurement

    Procurement expertise at national/project level(complemented by on-going capacity building)

    Procurement expertise atIFAD level (procurement

    specialist to assist CPMin supervision)

    Project Implementation: ProcurementKey Tools for Successful Procurement (2)

  • 8/12/2019 Contracts and Management

    17/40

  • 8/12/2019 Contracts and Management

    18/40

    17

    I. Review of pre-qualification of bidders(for large/complex works or expected significant time/cost savings =>need advanced procurement skills)

    Prior to issuance of invitations to pre-qualify, IFAD reviews:draft advertisement and invitation to pre-qualify

    draft pre-qualification documents, including pre-qualificationquestionnaire and evaluation criteria and methodology

    After borrowers evaluation of bidders submissions, IFADreviews:

    draft evaluation report

    list of pre-qualified bidders and statement of their qualificationsreasons for excluding any applicant from pre-qualification

    Project Implementation: ProcurementPrior Review Procedures (1)

    (refer to workflow 1 & checklists)

  • 8/12/2019 Contracts and Management

    19/40

    18

    II. Review of procurement of goods and works

    Prior to issuance of invitations to bid, IFAD reviews: conformity of procurement with applicable rules/procedures,approved AWPB/procurement plan and funds availabilitydraft bidding documents, including invitation to bid, instructions tobidders, technical specifications, evaluation criteria, contractualconditionsproposed composition of the bid evaluation committee (forcomments)

    After borrowers evaluation of bidders submissions, IFADreviews:

    minutes of public bid openingbid evaluation report, including evaluation and comparison of bidsand award recommendationevidence of individual evaluations by each committee memberdraft contract

    Project Implementation: ProcurementPrior Review Procedures (2)

  • 8/12/2019 Contracts and Management

    20/40

    19

    III. Review of procurement of consulting services

    Prior to issuance of request for proposal (RFP), IFAD reviews: conformity of procurement with applicable rules/procedures, approvedAWPB/procurement plan and funds availabilitydraft RFP, including instructions to consultants, terms of reference,selection method and evaluation criteria, shortlist of consultants, costestimate, contractual conditions

    After borrowers evaluation of technical proposals, IFAD reviews:technical evaluation report, including description of the process,summary of scores and award recommendationtechnical scores/ranking given to each consultant on each evaluationcriterion

    scores given by each evaluation committee membercopy of proposals, if requested by IFAD

    Project Implementation: ProcurementPrior Review Procedures (3)

  • 8/12/2019 Contracts and Management

    21/40

    20

    III. Review of procurement of consulting services using thefollowing methods:Quality and cost-based selectionSelection under a fixed budgetLeast-cost selection

    After borrowers evaluation of financial proposals, IFAD reviews:minutes of public bid openingaccount of adjustments made to prices of the proposals anddetermination of the evaluated pricefinal evaluation report and award recommendation

    (The above review step is not applicable for quality-based selection, selectionbased on consultants qualifications, single source selection or individual

    consultant selection)

    In all cases, IFAD reviews and provides No-Objection to thenegotiated draft contract

    Project Implementation: ProcurementPrior Review Procedures (4)

  • 8/12/2019 Contracts and Management

    22/40

    21

    Project Implementation: ProcurementExample of Weights for Consultant Evaluation Criterion

    EVALUATION CRITERION: POINTSConsultants / firms specific experience 5 - 10Methodology 20 - 50Key personnel (general qualificationsadequacy for the assignment) 30 - 60

    Transfer of knowledge 0 - 10Participation by nationals 0 - 10

    TOTAL 100

    Could be divided into sub-criteria, but should be kept to the

    essential For training - high points on key Personnel Points may be adjusted for specific circumstances

  • 8/12/2019 Contracts and Management

    23/40

    22

    At HQ Post-award review of procurement actions aspart of the withdrawal applications approvalprocess

    Documents submitted by PMU mustinclude bidding documents, evaluationreports, award recommendations, signedcontracts and updated contract record

    IFAD reviews conformity of procurementwith applicable rules/procedures, projectobjectives, approved AWPB/procurementplan and funds availability

    Project Implementation: ProcurementEx-Post Review Procedures (1)

  • 8/12/2019 Contracts and Management

    24/40

    23

    Project Implementation: ProcurementEx-Post Review Procedures (2)

    During IFAD supervision/Implementation supportmissions

    Post-award review of procurement actionsbased on selection of a sample of transactions

    PMU makes available to the supervision review team all procurement andpayments files, updated contract record and individual contract monitoringforms

    Focus of supervision missionreview is conformity of procurementwith applicable rules/procedures,project objectives,approved AWPB/procurement plan,and funds availability

  • 8/12/2019 Contracts and Management

    25/40

    24

    Project Implementation: ProcurementEx-Post Review Procedures (3)

    The IFAD supervision/Implementation mission teamalso:

    assesses the physical and financial progress ofprocurement actions and the quality of final products(through site visits for works, review of consultantsreports, review of the contract monitoring forms, etc.)

    identifies procurement issues and constraints

    briefs/coaches borrower and/or PMU staff onprocurement issues

    issues recommendations for improvement (e.g.training of staff, fielding of implementation supportmissions, streamlining of workflows, )

  • 8/12/2019 Contracts and Management

    26/40

    25

    Project Implementation: ProcurementHow to avoid delays in procurement (1)

    Lack of procurement plan or inadequate/incomplete procurement plan

    Poorly designed and/or unrealistic AWPB

    Imprecise and ambiguous terms or documents for the bid evaluationmethod and selection criteria

    Absence of confidentiality at various stages of the bid evaluation processand/or selection of winning bid

    Failure to justify rejection of bids or non-selection of a competitive bid

    Political interference in the procurement process

    Corruption, fraud, conflicts of interest and miss-procurement

  • 8/12/2019 Contracts and Management

    27/40

    26

    Project Implementation: ProcurementHow to avoid delays in procurement (2)

    Poor qualification of evaluation committee members

    Lack of procurement capacity at borrower and/or project level

    Poor understanding of IFAD procedures at borrower and/or project level

    Confusion between national procedures and IFAD guidelines /loanagreement procedures

    Cumbersome procedures and bureaucracy for approval of procurementdocuments at borrower level

    Long delays in issuance of no-objections by IFAD

    Long response time by IFAD to queries from PMU

  • 8/12/2019 Contracts and Management

    28/40

    27

    Project Implementation: ProcurementMonitoring of Procurement at HQ

    Several source documents for monitoring procurement . . .

    AWPB and updated procurement plan

    Results of prior reviews and ex-post reviews at HQ

    Supervision mission reports

    Progress reports

    Based on monitoring results, follow-up on issues and problems identified

  • 8/12/2019 Contracts and Management

    29/40

    28

    Project Implementation: ProcurementProcurement in Project Completion Process

    To ensure that all goods are delivered/workscompleted/services rendered by the projectcompletion date:

    Closely review and monitor the final procurement planand progress reports during the last year of the projectTake measures to facilitate completion of physicalexecution of contractsCancel contracts that cannot be executed within the

    completion date

    Ensure that only contracts executed by projectcompletion date are paid

    Ensure that procurement files are completeand obtain missing documents from project

    Report on lessons learned and makerecommendations for future projects

  • 8/12/2019 Contracts and Management

    30/40

  • 8/12/2019 Contracts and Management

    31/40

    Project implementation: Contract ManagementFive Stages of Contract Management

    Monitoring & Control of performance

    Change Management

    Dispute Resolution

    Financial Management & Payment

    Contract Administration

    30

  • 8/12/2019 Contracts and Management

    32/40

    Project implementation: Contract ManagementMonitoring & Control of Contract Performance (1)

    Establishment of Contracts Register

    Establishment of Contract Monitoring Register

    Establishment of Individual Contract Monitoring Sheet

    Establishment of Contract Monitoring Form

    Key tip

    Contract management Guidelines- Service provider

    31

    http://www.ifad.org/operations/finance/pack/refdoc/B_4.2_pg%2031b.xlshttp://www.ifad.org/operations/finance/pack/refdoc/B_4.2_pg%2031a.xlshttp://www.ifad.org/operations/finance/pack/refdoc/B_4.2_pg%2031c.doc
  • 8/12/2019 Contracts and Management

    33/40

    Project implementation: Contract ManagementMonitoring & Control of Contract Performance

    Key IndicatorsConsulting Services

    Goods

    Works

    Timely delivery of key outputsResponsiveness to reasonable requestsThe quality services of services provided

    The timeliness of deliveryQuantity deliveredCompliance with specifications

    Timeliness of each stage of the worksCompliance with the bill of worksThe quality of the works

    32

  • 8/12/2019 Contracts and Management

    34/40

    Project implementation: Contract ManagementMonitoring & Control of Contract Performance

    Tips

    indicate actual delivery date of goods/ works/ services (or agreedmilestones)

    written reminders to contractors/ consultants where there is adefault (including penalties)

    file response from contractors/ consultants record agreed changes in delivery dates & penalties exactedInspection

    As necessary, especially for works, it is necessary to ensure thatqualified independent oversight is provided to ensure that worksare constructed according to industry standards

    33

  • 8/12/2019 Contracts and Management

    35/40

    Project implementation: Contract Management

    Acceptance

    Service

    Goods

    Works

    written confirmation that the required services

    have been delivered on time & of an acceptable quality

    completion of the Receipt and Inspection Report (RIR) . It may be necessary for the supply ofgoods to ensure that suitably qualified staff or

    consultants are involved in the RIR

    engineers report that timely construction ofacceptable standard has been completed

    34

  • 8/12/2019 Contracts and Management

    36/40

    Project implementation: Contract ManagementChange Management

    Includes avoiding unnecessary changes as well as

    incorporating necessary changes into contract

    It is important is ensure necessary prior approval is

    obtained including a no objection from IFAD if the value

    of cumulative change exceeds 15% of contract value

    35

  • 8/12/2019 Contracts and Management

    37/40

    Project implementation: Contract ManagementRemedies

    Termination

    Dispute resolution

    seek legal advice

    determine if liquidated damages should apply inaccordance with contract

    negotiation

    arbitration

    36

  • 8/12/2019 Contracts and Management

    38/40

    Project implementation: Contract ManagementFinancial Management and Payments

    Payments need to be made in line with the contract terms (normallywithin 30 days of submission of a valid invoice)

    It is important to maintain an expected payment schedule as part

    milestone of the Contract Monitoring Register to ensure that there is

    sufficient liquidity in the Special Designated Account or to promptly

    process request for direct payment

    Delayed payments negatively affect the cost of future contracts wheredelayed payments are a regular feature, suppliers & contractors build in

    margins to cover anticipated delays in payment or refuse to tender

    37

  • 8/12/2019 Contracts and Management

    39/40

    Project implementation: Contract Management

    Performance Securities

    Where required these should be provided by thesupplier/contractor in a timely manner. Theseshould be returned within 30 days of finalacceptance (contract completion as per

    contract terms), including any warranty ormaintenance period