Contractor's Design Portion - Designing Buildings Wiki

download Contractor's Design Portion - Designing Buildings Wiki

of 4

Transcript of Contractor's Design Portion - Designing Buildings Wiki

  • 7/25/2019 Contractor's Design Portion - Designing Buildings Wiki

    1/4

    1/21/2016 Contractor's design portion - Designing Buildings Wiki

    http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion

    Register Sign in

    Search

    Designing BuildingsWikiThe construction industry knowledge base

    Home / news Site info / toolsProject plans Project activities Legislation and standards Industry context

    Contractor's design portion

    The contractors designed portion (sometimes referred to as 'contractor's design portion' or CDP)

    is associated with JCT construction contracts. It is an agreement for the contractor to design

    specific parts ofthe works. The contractor may in turn sub-contract this design work to specialist

    sub-contractors. This should not be confused with design and build contracts where the

    contractor is appointed to design the whole of the works.

    Until 2005, the JCT Standard Building Contract had a contractors designed portion supplement

    for use where the appointed contractor was required to design specific parts of the works. This

    provision has now beenincorporated into themain contract, but a separate sub-contractor design

    agreement isavailable where the main contractor is to design specific parts of the works and a

    sub-contractor is to design part or all of the sub-contract works. The JCT Intermediate Building

    Contract still has a separate contractors design agreement, as well as a sub-contractor's design

    agreement. The JCT Minor Works Contract has a with contractors design option and a separate

    sub-contract with sub-contractors design.

    Theclients requirements for contractor's design will generally be set out in the tender documents

    as Employers Requirements in response to which the contractor will submit ContractorsProposals.

    Contractors design may be used with a Pre-Construction Services Agreement or Pre-

    Construction Services Agreement (Specialist) to provide early consultancy services to the

    project before the main construction contract commences.

    Often, the portion of design left to the contractor is the detailing work undertaken by specialist

    manufactures and installers. The main contractor has responsibility for managing the

    procurement of its specialist sub-contractors design in an orderly fashion and to an agreed

    programme so it can be approved by the clients design team (who within their conditions of

    engagement avoid liability for specialist design). The main contractor also has to ensure that

    various specialist sub-contractors under its control co-ordinate their emerging designs with each

    other. For instance the services sub-contractors need to know both the grid system and position

    of fixings for a suspended ceiling and likewise the ceiling sub-contractor needs to know details of

    plant above ceilings which require maintenance access. To carry out this management function

    'design managers' have become a regular addition to the main contractors project staff.

    The main contractor may be given the responsibility for ensuring that its sub-contractors design

    is submitted for and obtains building regulations approval. The clients design team will usually

    submit specialist design to the planning authorities when necessary to satisfy planning

    conditions since it is generally the design teams responsibility to obtain full planning consent.

    Share Follow

    Create an article

    Related articles

    Building Information Modelling.

    Contractor.

    Design manager.

    JCT.

    Nominated sub-contractor.

    Performance specification.

    Pre construction services agreement.

    Prime cost sum.

    Featured articles

    New model for town centres

    Report promotes radical new model to

    revitalise Britain's high streets.

    Immigration skills charge

    Last edited 24 Nov 2015

    See full history

    http://www.designingbuildings.co.uk/wiki/Maintenancehttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Minor_works_contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Intermediate_building_contracthttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.pnghttps://twitter.com/#!/DesigningBhttp://www.designingbuildings.co.uk/w/index.php?title=Contractor%27s%20design%20portion&action=historyhttp://www.designingbuildings.co.uk/w/index.php?title=Special:CreateArticlehttp://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&type=signup&returnto=Homehttps://www.ice.org.uk/http://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/w/index.php?title=Contractor%27s%20design%20portion&action=historyhttp://www.designingbuildings.co.uk/wiki/Immigration_skills_chargehttp://www.designingbuildings.co.uk/wiki/New_model_for_Britain%27s_high_streetshttp://www.designingbuildings.co.uk/wiki/New_model_for_Britain%27s_high_streetshttp://www.designingbuildings.co.uk/wiki/Prime_cost_sumhttp://www.designingbuildings.co.uk/wiki/Pre_Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/w/index.php?title=Special:CreateArticlehttp://www.youtube.com/user/designingbuildingshttps://twitter.com/#!/DesigningBhttp://www.facebook.com/pages/Designing-Buildings-Wiki/349836558377133http://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.pnghttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Planning_conditionshttp://www.designingbuildings.co.uk/wiki/Planning_authoritieshttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Building_regulationshttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Maintenancehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Suspended_ceilinghttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Procurementhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Construction_contracthttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractor%E2%80%99s_proposalshttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Employer%E2%80%99s_Requirementshttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Minor_works_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Intermediate_building_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Design_and_build_contracthttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Construction_contractshttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&returnto=Homehttp://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&type=signup&returnto=Homehttp://www.burohappold.com/http://www.rsh-p.com/https://www.bsria.co.uk/http://www.uandiplc.com/http://www.ciob.org/http://www.bre.co.uk/bretrusthttps://www.ice.org.uk/
  • 7/25/2019 Contractor's Design Portion - Designing Buildings Wiki

    2/4

    1/21/2016 Contractor's design portion - Designing Buildings Wiki

    http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion

    Share Add a comment Send us feedback

    Design consultants need to judge how far to take their design before handing over its completion

    to specialists. Furthermore it must be made abundantly clear exactly what the specialist has to

    design within the work section. A performance specification must describe quality both in terms

    of function and form, bearing in mind that contractors tendering in competition will respond with

    the cheapest option available to meet the specification. The use of a sub-contractor design

    approval procedures to improve what was tendered has been the source of back door variations

    and many contractual disputes in relation to cost and/or delay. On the other hand it is a waste of

    designers resources and time to develop the design of systems that may or may not be used.

    Closed specifications reduce options in the specialist market and this is not in the best interestsof the client.

    It is sensible for the main tender documents to ask for a sub-contractor design programme to be

    submitted by the main contractor within a certain period after the contract has been placed. This

    should track specialist design, the approval process, manufacture and installation and fit into the

    overall contract programme. It is reasonable for the design team to insist on an even workload of

    sub-contractor drawing submittals so it can balance its resources in relation to the comment and

    approval process.

    The introduction of building information modelling (BIM) is likely to have a profound effect on

    contractor's design. If at the time of the main contractor's appointment, a fully-integrated and

    collaborative building model has been prepared, it is unlikely that this will simply be handed over

    to the main contractor. The model is more likely to remain under the management of the client's

    design team. Whoever is managing the model will be the party that has to manage the collective

    input of specialist designers. The main contractors role in this process could therefore become

    redundant, which is not satisfactory under the current terms of contractor's design agreements

    because it effectively means the designers would be controlling activities of the main

    contractors sub-contractors. However, the main contractor carries the risk of a fixed price and

    meeting the contract completion date. For this and for programme reasons, contractor's design in

    the way that we know it now could become a thing of the past. In any case the advent of BIM is

    likely to alter the timing of the inclusion of specialist design so it takes place in the pre-

    construction design stage rather than in the construction stage. Consequently the design team

    will work on the design with specialists in the pre-construction stage and insist that the tendering

    contractors adopt the specialist and its design as part of the tender offer. So the scope of

    specialist work, its price and programme will be included within the main contractor's bid. The

    main contractors tender documents will also give the main contractor the choice of seeking

    alternative sub-contractors thus avoiding the legal problems associated with nominated sub-

    contractors when the courts judged that a main contractor was not liable for the performance of a

    sub-contractor forced upon it by the client or its agents.

    Find out more

    Related articles on Designing Buildings Wiki

    Building Information Modelling.

    Contractor.

    Design manager.

    JCT.

    Nominated sub-contractor.

    Performance specification.

    Pre construction services agreement.

    Prime cost sum.

    Responsibility for design.

    Sub-contractor.

    Migration Advisory Committee proposal for a1,000 a year immigration skills charge is

    seen as yet another burden by industry

    leaders.

    BSRIA launch new smart technology topic

    guide

    BSRIA launch new smart technology guide

    aimed at providing an informative introduction

    to the latest trends in smart homes and the

    Internet of Things.

    BRE articles

    There is a great collection of more than 50

    articles by BRE available for free on Designing

    Buildings Wiki.

    BIM practice note

    http://www.designingbuildings.co.uk/wiki/Building_Information_Modelling_(BIM),_Collaborative_and_Integrated_Team_Workinghttp://www.designingbuildings.co.uk/wiki/Building_Information_Modelling_(BIM),_Collaborative_and_Integrated_Team_Workinghttp://www.designingbuildings.co.uk/wiki/BRE_articles_on_Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/BRE_articles_on_Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/BSRIA_launch_smart_technology_topic_guidehttp://www.designingbuildings.co.uk/wiki/BSRIA_launch_smart_technology_topic_guidehttp://www.designingbuildings.co.uk/wiki/Immigration_skills_chargehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Responsibility_for_designhttp://www.designingbuildings.co.uk/wiki/Prime_cost_sumhttp://www.designingbuildings.co.uk/wiki/Pre_Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/Find_out_morehttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Tenderhttp://www.designingbuildings.co.uk/wiki/Contractorshttp://www.designingbuildings.co.uk/wiki/Tenderinghttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Bimhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Completion_datehttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Designershttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Specialist_designershttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Client%27shttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Bimhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_programmehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Specificationshttp://www.designingbuildings.co.uk/wiki/Designershttp://www.designingbuildings.co.uk/wiki/Disputeshttp://www.designingbuildings.co.uk/wiki/Variationshttp://www.designingbuildings.co.uk/wiki/Tenderhttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Specificationhttp://www.designingbuildings.co.uk/wiki/Tenderinghttp://www.designingbuildings.co.uk/wiki/Contractorshttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Consultanthttp://www.designingbuildings.co.uk/wiki/Special:Contact?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/w/index.php?title=Talk:Contractor%27s_design_portion&action=edit#commentStarthttp://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.png
  • 7/25/2019 Contractor's Design Portion - Designing Buildings Wiki

    3/4

    1/21/2016 Contractor's design portion - Designing Buildings Wiki

    http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion

    JCT publish an introductory practice note:

    Building Information Modelling (BIM),

    Collaborative and Integrated Team Working.

    Top 10 skyscrapers in the UAE

    With an ever-increasing number of skyscraper

    completions, this list looks at the 10 most

    impressive structures in the UAE.

    Pendulum arbitration

    Robert Fenwick Elliott explains why pendulum

    arbitration may be preferable to the risk of a

    conventional trial and the bottomless pit of

    legal expense.

    Building of the week - Shanghai Tower

    http://www.designingbuildings.co.uk/wiki/Shanghai_Towerhttp://www.designingbuildings.co.uk/wiki/Pendulum_arbitrationhttp://www.designingbuildings.co.uk/wiki/Pendulum_arbitrationhttp://www.designingbuildings.co.uk/wiki/Top_10_skyscrapers_located_in_the_UAEhttp://www.designingbuildings.co.uk/wiki/Top_10_skyscrapers_located_in_the_UAE
  • 7/25/2019 Contractor's Design Portion - Designing Buildings Wiki

    4/4

    1/21/2016 Contractor's design portion - Designing Buildings Wiki

    http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion

    Designing Buildings Ltd. 2016 About Help Privacy Policy T&Cs Contact Feed Report Abuse Press

    Read about the newly-completed Shanghai

    Tower, the second tallest building in the world

    and one of the most advanced in terms of

    'green' architecture.

    BIM is about the Planet

    Read Keith Snook's fascinating analysis of the

    past, present and future of BIM.

    For more news, go to the home page.

    http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/wiki/File:Fig_1_Earthrise_270.jpghttp://www.designingbuildings.co.uk/wiki/BIM_-_it%27s_about_the_Planet_-_Part_1http://www.designingbuildings.co.uk/wiki/Shanghai_Towerhttp://www.designingbuildings.co.uk/wiki/Press_contacthttp://www.designingbuildings.co.uk/wiki/Special:Contact/Report?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/w/index.php?title=Special:RecentChanges&feed=atomhttp://www.designingbuildings.co.uk/wiki/Special:Contact?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/wiki/Terms_and_Conditionshttp://www.designingbuildings.co.uk/wiki/Privacy_policyhttp://www.designingbuildings.co.uk/wiki/Helphttp://www.designingbuildings.co.uk/wiki/About