Transcript of Contractor's Design Portion - Designing Buildings Wiki
-
7/25/2019 Contractor's Design Portion - Designing Buildings Wiki
1/4
1/21/2016 Contractor's design portion - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion
Register Sign in
Search
Designing BuildingsWikiThe construction industry knowledge base
Home / news Site info / toolsProject plans Project activities Legislation and standards Industry context
Contractor's design portion
The contractors designed portion (sometimes referred to as 'contractor's design portion' or CDP)
is associated with JCT construction contracts. It is an agreement for the contractor to design
specific parts ofthe works. The contractor may in turn sub-contract this design work to specialist
sub-contractors. This should not be confused with design and build contracts where the
contractor is appointed to design the whole of the works.
Until 2005, the JCT Standard Building Contract had a contractors designed portion supplement
for use where the appointed contractor was required to design specific parts of the works. This
provision has now beenincorporated into themain contract, but a separate sub-contractor design
agreement isavailable where the main contractor is to design specific parts of the works and a
sub-contractor is to design part or all of the sub-contract works. The JCT Intermediate Building
Contract still has a separate contractors design agreement, as well as a sub-contractor's design
agreement. The JCT Minor Works Contract has a with contractors design option and a separate
sub-contract with sub-contractors design.
Theclients requirements for contractor's design will generally be set out in the tender documents
as Employers Requirements in response to which the contractor will submit ContractorsProposals.
Contractors design may be used with a Pre-Construction Services Agreement or Pre-
Construction Services Agreement (Specialist) to provide early consultancy services to the
project before the main construction contract commences.
Often, the portion of design left to the contractor is the detailing work undertaken by specialist
manufactures and installers. The main contractor has responsibility for managing the
procurement of its specialist sub-contractors design in an orderly fashion and to an agreed
programme so it can be approved by the clients design team (who within their conditions of
engagement avoid liability for specialist design). The main contractor also has to ensure that
various specialist sub-contractors under its control co-ordinate their emerging designs with each
other. For instance the services sub-contractors need to know both the grid system and position
of fixings for a suspended ceiling and likewise the ceiling sub-contractor needs to know details of
plant above ceilings which require maintenance access. To carry out this management function
'design managers' have become a regular addition to the main contractors project staff.
The main contractor may be given the responsibility for ensuring that its sub-contractors design
is submitted for and obtains building regulations approval. The clients design team will usually
submit specialist design to the planning authorities when necessary to satisfy planning
conditions since it is generally the design teams responsibility to obtain full planning consent.
Share Follow
Create an article
Related articles
Building Information Modelling.
Contractor.
Design manager.
JCT.
Nominated sub-contractor.
Performance specification.
Pre construction services agreement.
Prime cost sum.
Featured articles
New model for town centres
Report promotes radical new model to
revitalise Britain's high streets.
Immigration skills charge
Last edited 24 Nov 2015
See full history
http://www.designingbuildings.co.uk/wiki/Maintenancehttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Minor_works_contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Intermediate_building_contracthttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.pnghttps://twitter.com/#!/DesigningBhttp://www.designingbuildings.co.uk/w/index.php?title=Contractor%27s%20design%20portion&action=historyhttp://www.designingbuildings.co.uk/w/index.php?title=Special:CreateArticlehttp://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&type=signup&returnto=Homehttps://www.ice.org.uk/http://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/w/index.php?title=Contractor%27s%20design%20portion&action=historyhttp://www.designingbuildings.co.uk/wiki/Immigration_skills_chargehttp://www.designingbuildings.co.uk/wiki/New_model_for_Britain%27s_high_streetshttp://www.designingbuildings.co.uk/wiki/New_model_for_Britain%27s_high_streetshttp://www.designingbuildings.co.uk/wiki/Prime_cost_sumhttp://www.designingbuildings.co.uk/wiki/Pre_Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/w/index.php?title=Special:CreateArticlehttp://www.youtube.com/user/designingbuildingshttps://twitter.com/#!/DesigningBhttp://www.facebook.com/pages/Designing-Buildings-Wiki/349836558377133http://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.pnghttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Planning_conditionshttp://www.designingbuildings.co.uk/wiki/Planning_authoritieshttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Building_regulationshttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Maintenancehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Suspended_ceilinghttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Procurementhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Construction_contracthttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Pre-Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractor%E2%80%99s_proposalshttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Employer%E2%80%99s_Requirementshttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Minor_works_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Intermediate_building_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_contracthttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Design_and_build_contracthttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Sub-contracthttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Construction_contractshttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&returnto=Homehttp://www.designingbuildings.co.uk/w/index.php?title=Special:UserLogin&type=signup&returnto=Homehttp://www.burohappold.com/http://www.rsh-p.com/https://www.bsria.co.uk/http://www.uandiplc.com/http://www.ciob.org/http://www.bre.co.uk/bretrusthttps://www.ice.org.uk/ -
7/25/2019 Contractor's Design Portion - Designing Buildings Wiki
2/4
1/21/2016 Contractor's design portion - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion
Share Add a comment Send us feedback
Design consultants need to judge how far to take their design before handing over its completion
to specialists. Furthermore it must be made abundantly clear exactly what the specialist has to
design within the work section. A performance specification must describe quality both in terms
of function and form, bearing in mind that contractors tendering in competition will respond with
the cheapest option available to meet the specification. The use of a sub-contractor design
approval procedures to improve what was tendered has been the source of back door variations
and many contractual disputes in relation to cost and/or delay. On the other hand it is a waste of
designers resources and time to develop the design of systems that may or may not be used.
Closed specifications reduce options in the specialist market and this is not in the best interestsof the client.
It is sensible for the main tender documents to ask for a sub-contractor design programme to be
submitted by the main contractor within a certain period after the contract has been placed. This
should track specialist design, the approval process, manufacture and installation and fit into the
overall contract programme. It is reasonable for the design team to insist on an even workload of
sub-contractor drawing submittals so it can balance its resources in relation to the comment and
approval process.
The introduction of building information modelling (BIM) is likely to have a profound effect on
contractor's design. If at the time of the main contractor's appointment, a fully-integrated and
collaborative building model has been prepared, it is unlikely that this will simply be handed over
to the main contractor. The model is more likely to remain under the management of the client's
design team. Whoever is managing the model will be the party that has to manage the collective
input of specialist designers. The main contractors role in this process could therefore become
redundant, which is not satisfactory under the current terms of contractor's design agreements
because it effectively means the designers would be controlling activities of the main
contractors sub-contractors. However, the main contractor carries the risk of a fixed price and
meeting the contract completion date. For this and for programme reasons, contractor's design in
the way that we know it now could become a thing of the past. In any case the advent of BIM is
likely to alter the timing of the inclusion of specialist design so it takes place in the pre-
construction design stage rather than in the construction stage. Consequently the design team
will work on the design with specialists in the pre-construction stage and insist that the tendering
contractors adopt the specialist and its design as part of the tender offer. So the scope of
specialist work, its price and programme will be included within the main contractor's bid. The
main contractors tender documents will also give the main contractor the choice of seeking
alternative sub-contractors thus avoiding the legal problems associated with nominated sub-
contractors when the courts judged that a main contractor was not liable for the performance of a
sub-contractor forced upon it by the client or its agents.
Find out more
Related articles on Designing Buildings Wiki
Building Information Modelling.
Contractor.
Design manager.
JCT.
Nominated sub-contractor.
Performance specification.
Pre construction services agreement.
Prime cost sum.
Responsibility for design.
Sub-contractor.
Migration Advisory Committee proposal for a1,000 a year immigration skills charge is
seen as yet another burden by industry
leaders.
BSRIA launch new smart technology topic
guide
BSRIA launch new smart technology guide
aimed at providing an informative introduction
to the latest trends in smart homes and the
Internet of Things.
BRE articles
There is a great collection of more than 50
articles by BRE available for free on Designing
Buildings Wiki.
BIM practice note
http://www.designingbuildings.co.uk/wiki/Building_Information_Modelling_(BIM),_Collaborative_and_Integrated_Team_Workinghttp://www.designingbuildings.co.uk/wiki/Building_Information_Modelling_(BIM),_Collaborative_and_Integrated_Team_Workinghttp://www.designingbuildings.co.uk/wiki/BRE_articles_on_Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/BRE_articles_on_Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/BSRIA_launch_smart_technology_topic_guidehttp://www.designingbuildings.co.uk/wiki/BSRIA_launch_smart_technology_topic_guidehttp://www.designingbuildings.co.uk/wiki/Immigration_skills_chargehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Responsibility_for_designhttp://www.designingbuildings.co.uk/wiki/Prime_cost_sumhttp://www.designingbuildings.co.uk/wiki/Pre_Construction_Services_Agreementhttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/JCThttp://www.designingbuildings.co.uk/wiki/Design_managerhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Designing_Buildings_Wikihttp://www.designingbuildings.co.uk/wiki/Find_out_morehttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Nominated_sub-contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Tenderhttp://www.designingbuildings.co.uk/wiki/Contractorshttp://www.designingbuildings.co.uk/wiki/Tenderinghttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Bimhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Completion_datehttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Sub-contractorshttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Designershttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Specialist_designershttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Client%27shttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Contractorhttp://www.designingbuildings.co.uk/wiki/Bimhttp://www.designingbuildings.co.uk/wiki/Building_Information_Modellinghttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Design_teamhttp://www.designingbuildings.co.uk/wiki/Main_contractorhttp://www.designingbuildings.co.uk/wiki/Design_programmehttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Tender_documentshttp://www.designingbuildings.co.uk/wiki/Clienthttp://www.designingbuildings.co.uk/wiki/Specificationshttp://www.designingbuildings.co.uk/wiki/Designershttp://www.designingbuildings.co.uk/wiki/Disputeshttp://www.designingbuildings.co.uk/wiki/Variationshttp://www.designingbuildings.co.uk/wiki/Tenderhttp://www.designingbuildings.co.uk/wiki/Sub-contractorhttp://www.designingbuildings.co.uk/wiki/Specificationhttp://www.designingbuildings.co.uk/wiki/Tenderinghttp://www.designingbuildings.co.uk/wiki/Contractorshttp://www.designingbuildings.co.uk/wiki/Performance_specificationhttp://www.designingbuildings.co.uk/wiki/Consultanthttp://www.designingbuildings.co.uk/wiki/Special:Contact?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/w/index.php?title=Talk:Contractor%27s_design_portion&action=edit#commentStarthttp://www.sharethis.com/share?publisher=832c94fd-9945-4b2b-b15f-599ff8a8df60&url=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fwiki%2FContractor%27s_design_portion&title=Designing+Buildings+Wiki+-+Contractor%27s+design+portion&img=http%3A%2F%2Fwww.designingbuildings.co.uk%2Fskins%2Fdesigningbuildings%2Fdesigning-buildings-logo-square.png -
7/25/2019 Contractor's Design Portion - Designing Buildings Wiki
3/4
1/21/2016 Contractor's design portion - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion
JCT publish an introductory practice note:
Building Information Modelling (BIM),
Collaborative and Integrated Team Working.
Top 10 skyscrapers in the UAE
With an ever-increasing number of skyscraper
completions, this list looks at the 10 most
impressive structures in the UAE.
Pendulum arbitration
Robert Fenwick Elliott explains why pendulum
arbitration may be preferable to the risk of a
conventional trial and the bottomless pit of
legal expense.
Building of the week - Shanghai Tower
http://www.designingbuildings.co.uk/wiki/Shanghai_Towerhttp://www.designingbuildings.co.uk/wiki/Pendulum_arbitrationhttp://www.designingbuildings.co.uk/wiki/Pendulum_arbitrationhttp://www.designingbuildings.co.uk/wiki/Top_10_skyscrapers_located_in_the_UAEhttp://www.designingbuildings.co.uk/wiki/Top_10_skyscrapers_located_in_the_UAE -
7/25/2019 Contractor's Design Portion - Designing Buildings Wiki
4/4
1/21/2016 Contractor's design portion - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Contractor's_design_portion
Designing Buildings Ltd. 2016 About Help Privacy Policy T&Cs Contact Feed Report Abuse Press
Read about the newly-completed Shanghai
Tower, the second tallest building in the world
and one of the most advanced in terms of
'green' architecture.
BIM is about the Planet
Read Keith Snook's fascinating analysis of the
past, present and future of BIM.
For more news, go to the home page.
http://www.designingbuildings.co.uk/http://www.designingbuildings.co.uk/wiki/File:Fig_1_Earthrise_270.jpghttp://www.designingbuildings.co.uk/wiki/BIM_-_it%27s_about_the_Planet_-_Part_1http://www.designingbuildings.co.uk/wiki/Shanghai_Towerhttp://www.designingbuildings.co.uk/wiki/Press_contacthttp://www.designingbuildings.co.uk/wiki/Special:Contact/Report?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/w/index.php?title=Special:RecentChanges&feed=atomhttp://www.designingbuildings.co.uk/wiki/Special:Contact?request_uri=%2Fwiki%2FContractor%27s_design_portionhttp://www.designingbuildings.co.uk/wiki/Terms_and_Conditionshttp://www.designingbuildings.co.uk/wiki/Privacy_policyhttp://www.designingbuildings.co.uk/wiki/Helphttp://www.designingbuildings.co.uk/wiki/About