Contract Laws & Claims Final

download Contract Laws & Claims Final

of 10

Transcript of Contract Laws & Claims Final

  • 7/23/2019 Contract Laws & Claims Final

    1/10

    CONTRACT LAWS & CLAIMS

    (CASE STUDY OF DISPUTE BETWEEN ATHENS GENERATING COMPANY AND BECHTEL POWER CORPORATION )

  • 7/23/2019 Contract Laws & Claims Final

    2/10

    CONTRACT DETAILS

    Contract - Construction of 1080 megawatt power plant in New York

    ( includes installation of 3 gas turbines manufactured by Siemens esting!ouse po

    Client - #t!ens generating company

    Contractor - $ec!tel power corporation

    Sub contractor % Siemens esting!ouse power corporation

    &ype of contract - 'C

    Contract price - )*++millionContract start date - 1+ t! ,une +001

    Contract completion date - 1+ t! #ugust +003

    #ctual completion date % 18 t! marc! +00

    .i/uidated damage - )000 day turbine

  • 7/23/2019 Contract Laws & Claims Final

    3/10

    CONTRACTORS PERSPECTIVE

    2eason for delay

    i" 4odi5cation in t!e products by t!e client ( as per clause +061 "

    ii" &ornado (as per clause 161 7 "

    iii" 2egional power outage

    i" client suspended t!e use of fuel gas for 3* days due to !ike in price ( a

    clause 86* b 9 c "

    Contractor also argued t!at daily rate of ) 000 day turbine constituteimpermissible penalty

  • 7/23/2019 Contract Laws & Claims Final

    4/10

    CLIENTS PERSPECTIVE

    roduct modi5cation are wit!in t!e scope of contractors contract (as per clause

    Contractor was aware t!at Siemens tec!nology for gas turbine is immature6( as

    6 "

    Some of t!e modi5cation are not needed for t!e substantial completion of cont

    made for t!e conenience of bot! contractor and sub contractor6(as per clause

    :n any point of time t!e actiities are not on t!e critical pat! of work6

    $ecause of tornado ; Contractor was entitled to one day of e

  • 7/23/2019 Contract Laws & Claims Final

    5/10

    RULING

    &!e panel of arbitrators found t!at t!e product modi5cation and prbetterments alleged by t!e contractor were wit!in t!e scope of concontract because it is an 'C contract; t!e time delays and cost cau

    implementation of product modi5cations s!ould be borne by t!e co

  • 7/23/2019 Contract Laws & Claims Final

    6/10

    Contractors ExpertWitness

    .aurie ?ppel;w!o testi5ed t!e t!ings regarding t!e economics ofoperating t!e generating plant at t!e time Contractor claimed6

    @er opinion addressed t!e actual damages #t!ens incurred as a result oflate completion rat!er t!an t!e estimate used at t!e time of contract

    formation6

    Clients Expert Witn

    4ic!ael , Aing;a representatie of client;in cestimates used in arriing at t!e daily rate of )0

    @e testi5ed t!at t!is !ad been reasonable fcontract formation ; of t!e actual damages #

    re

  • 7/23/2019 Contract Laws & Claims Final

    7/10

    RELEVANT FIDIC ( EPC / TURNKEY PROJECTS) CLAU

    Clause +061 Contractor>s Claim

    Clause 161 ( 7" force ma=eure

    Clause 86* (b" Contractors work !as been disrupted by t!decision of aut!orities6

    Clause 86* (c" Belay caused by aut!orities due tounforeseeable reasons 6

    Clause 1361 7ariations 9 ad=ustments (2ig!t to ary "

    Clause 6 Subcontractors ( &!e contractors s!all beresponsible for acts of Subcontractor"

    Clause *68 Besign errors

    Clause +6* employers claim

  • 7/23/2019 Contract Laws & Claims Final

    8/10

    FINAL VERDICT

    &!e arbitrators found clients testimony credible and rulet!e li/uidated damages clause in t!e contract is enforce

    @ence; t!e contractor was awarded remaining contract B'BC&:ND t!e li/uidated damages6(as per clause +6*"

    Contract balance E ) +8;303;FF

    .i/uidated damages E ) +G;*0;000

    rice awarded E ) 1;3*3;FF

  • 7/23/2019 Contract Laws & Claims Final

    9/10

    REFERENCE OF THE CASE

    Construction Claims #disor

    eekly e-letter

    7olume-F :ssue-G

    +3 No +00

    www6constructionclaims6com

    www6constructionrisk6com

    http://www.constructionclaims.com/http://www.constructionrisk.com/http://www.constructionrisk.com/http://www.constructionclaims.com/
  • 7/23/2019 Contract Laws & Claims Final

    10/10

    &@#NA Y?