Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON...

218
CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of requirements for the degree of MASTER OF SCIENCE May 1991 Major Subject: Civil Engineering

Transcript of Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON...

Page 1: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY

CONSTRUCTION PROJECTS

A Thesis

by

MICHAEL PETER LEHMANN

Submitted to the Office of Graduate Studies of Texas A&M University

in partial fulfillment of tt,,~ requirements for the degree of

MASTER OF SCIENCE

May 1991

Major Subject: Civil Engineering

Page 2: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 3: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY

CONSTRUCTION PROJECTS

A Thesis

by

MICHAEL PETER LEHMANN

Donn E. Hancher (Chair of Committee)

William . Smith (Member)

May 1991

~~ orge StlJkhart (Member)

Page 4: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 5: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

ABSTRACT

Contract Claims and Disputes on Texas Highway

Construction Projects. (May 1991)

Michael Peter Lehmann, B.S., Texas A&M University

Chair of Advisory Committee: Dr. Donn E. Hancher

iii

This thesis documents the efforts to determine the major causes of the

numerous construction contract claims and disputes against the Texas State

Department of Highways and Public Transportation. Surveys of departmental

personnel and contractors who do construction for the State were used to

locate these problem areas. These surveys, along with a study of 18 claims

against the State, found design errors, delays by the State, and additional work

to be the main sources of claims. These three factors account for 53 percent

of the number of claims, and for 90 percent of the financial impact of claims.

In order to reduce the impact of claims, therefore, the Department should

concentrate its efforts on the reduction of these causes.

Page 6: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

iv

ACKNOWLEDGEMENTS

Extra special thanks to the Administration of the Highway Department,

the members of the Advisory Committee, the Lehmanns, and the Hobsons.

Special thanks to all who contributed information: Bob Templeton and

the people at 0-6; Franklin Young and all of the District 20 folks; Edward

Dominguez and the Silsbee crew; Tom Johnson and the Associated General

-Contractors; and finally, all of you who completed the surveys.

Thanks to the great people at Texas Transportation Institute: my office

mates - Shariq, Johnnie, Roy, David, Kevin, Bill, and Beverly (not all at once);

the secretaries - Sheri, Usa, and Jerri; the other contributors - Pat (for

preserving my sanity), Dan (slides), Bryant (computer expertise), Kelly and Amy

(sparkling conversations), Scott (computer games and assistance), and Ron

(what a chef); the professors; and finally, the other Highway Department

students at A&M - Yvonne, Gus, Pat, David, Mark, and Curtis.

Honorable mentions - Fatburger, McDonald's, Mr. Gatti's, and the Dixie

Chicken for feeding my body; CN N Headline News, the Battalion, PGA Golf

(computer version), and Tetris for feeding my mind.

Finally, for tolerating a house, two cats, a dog, two litters of puppies, and

weekend visits for one full year by herself, extra special thanks to my wife,

Tracy. Without her help and support, this thesis would not have been possible.

Page 7: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

v

DEDICATION

Dedicated to the memory of Raymond E. Stotzer, whose dedication to

the Highway Department was exceeded only by his determination to improve

it Mr. Stotzer's efforts resulted in the creation of the Highway Department

Graduate Studies program. Without his efforts, this thesis would not have been

possible.

Page 8: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

vi

TABLE OF CONTENTS

Page

ABSTRACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . " iii

ACKNOWLEDGEMENTS .................................. iv

DEDICATION •......................................... v

LIST OF FIGURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. x

LIST OF TABLES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. xi

CHAPTER Page

l. INTRODUCTION AND BACKGROUND ..................... 1

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 1

Background information . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 2

Study objectives ..................................... 5

Study methodology ........... . . . . . . . . . . . . . . . . . . . . . . .. 5

Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 6

Contracts in general . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 6

Contracts with SDHPT ...•. . . . . . . . . . . . . . . . . . . . . . . . . .. 7

The construction claim . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 9

Contractual provisions ...... . . . . . . . . . . . . . . . . . . . . . . . . . .. 10

Why claims have increased ............................. 11

Dispute resolution alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . .. 13

Contract appeals board ................ . . . . . . . . . . . . .. 13

Page 9: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

vii

TABLE OF CONTENTS

(Continued)

CHAPTER Page

Litigation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 15

Arbitration . • . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 18

Dispute review board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 22

Mediation ........................................ 26

Mediation-Arbitration ................................ 28

Mini-Trials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 30

II. THE CURRENT DISPUTE RESOLUTION SYSTEM IN TEXAS ..... 32

General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 32

Chain-of-command dispute resolution ......... . . . . . . . . . . . .. 37

Resolution at the project level . . . . . . . . . . . . . . . . . . . . . . . . .. 37

Resolution at the resident engineer level .................. 38

Resolution at the district level ...................... . . .. 39

Resolution at the central headquarters level . . . . . . . . . . . . . . .. 40

General observations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 45

Indirect cost of dispute resolution ....................... 46

III. SURVEY OF SDHPT PERSONNEL ........................ 49

General . • • . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 49

Page 10: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

viii

TABLE OF CONTENTS

(Continued)

CHAPTER Page

Statistical analysis methodology .......................... 51

Results of the SDHPT survey ............................ 58

Response rates of the SDHPT survey .................... 58

Discussion of results of the SDHPT survey ................ 59

IV. SURVEY OF CONTRACTORS ........................... 79

General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 79

Results of the contractor survey .............. . . . . . . . . . . .. 81

Response rates of the contractor survey ...... . . . . . . . . . . .. 81

Discussion of results of the contractor survey .............. 82

Differences between SDHPT and contractor surveys. . . . . . . . . . .. 97

V. SUMMARY AND CONCLUSIONS ......................... 108

Summary .......................................... 108

Conclusions ........................................ 111

The need for improved contract documents . . . . . . . . . . . . . . . . 111

The need to provide timely decisions during construction ..... . 117

The need to consider financial impact of additional work . . . . . . . 118

The need for consistent interpretation of plans and specifications ..................................... 119

Page 11: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

IX

TABLE OF CONTENTS

(Continued)

Page

The need for Pre· Bid Conferences for complex projects ....... 120

The need to provide utility-free construction zones ........... 121

The need for early, third party dispute resolution ............ 121

The need for a quantitative dispute measurement system .... . . 122

Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123

Recommendations for implementation . . . . . . . . . . . . . . . . . . . . 123

Recommendations for additional research ........... . . . . . . 124

REFERENCES .•.......•............................... 125

APPENDIX A. SURVEY FORMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127

APPENDIX B. SURVEY RESULTS ........................... 141

APPENDIX C. CATMOD METHODOLOGY, INPUT, AND OUTPUT .... 161

APPENDIX D. SUPPORTING CALCULATIONS (SAS OUTPUT) ....... 187

APPENDIX E. SAMPLE SDHPT CONSTRUCTION FORMS .......... 191

VITA • . • • . • . . . . . . • . . • . . . . . • • . . . . . . . . . . . . . . . . . . . . . . . . . . 198

Page 12: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

x

LIST OF FIGURES

FIGURE Page

1. SDHPT Construction Projects and Spending, 1982 to 1988 . . . . . .. 3

2. Claims Against SDHPT, 1977 to 1989 ...................... 3

3. Total Value of Claims Against SDHPT, 1977 to 1989 . . . . . . . . . . .. 4

4. Average Value of Claims Against SDHPT, 1977 to 1989 ......... 4

5. Dispute Review Board Flow Chart ....................... " 24

6. Condensed SDHPT Organization Chart . . . . . . . . . . . . . . . . . . . .. 33

7. Dispute Decision Flow Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 34

8. Resolution of Claims Against SDHPT, 1982 to 1988 ............ 42

9. The Chi-Square Test for Equality of Distributions .............. 52

10. Construction Contract Revisions .......................... 112

11. Reasons for Claims Against SDHPT, 1984 to 1989 ............. 113

Page 13: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

xi

LIST OF TABLES

TABLE Page

1. Costs of Litigation .................................... 18

2. Costs of Arbitration for Complex Cases . . . . . . . . . . . . . . . . . . . .. 21

3. Yearly Estimate of SDHPT Indirect Costs for Claims. . . . . . . . . . .. 47

4. Average Ratings of Contractor Practices by SDHPT Survey Respondents .................................. 62

5. Average Ratings of SDHPT Practices by SDHPT Survey Respondents .................................. 63

6. Average Ratings of Contract Documents by SDHPT Survey Respondents .................................. 64

7. Average Ratings of Contract Administration by SDHPT Survey Respondents .................................. 65

8. Average Ratings of All Categories by SDHPT Survey Respondents 66

9. Summary of Average SDHPT Responses to Multiple-Answer Questions .......... . . . . . . . . . . . . . . . . . . . . . . . . .. 68

10. Summary of SDHPT "Yes" Responses to Question 8 ........... 69

11. Average Ratings of Dispute Resolution Alternatives by SDHPT Survey Respondents ............................ 71

12. Average SDHPT Responses to Question 12 . . . . . . . . . . . . . . . . .. 72

13. Summary of SDHPT HYes" Responses to Questions 16, 17,18, and 20 ••..................................... 74

14. Ten Most Common SDHPT Comments to Question 19 . . . . . . . . .. 76

15. Ten Most Common SDHPT Comments to Question 21 . . . . . . . . .. 78

16. Average Ratings of Contractor Practices by Contractor Survey Respondents .................................. 83

Page 14: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

xii

LIST OF TABLES

(Continued)

TABLE Page

17. Average Ratings of SDHPT Practices by Contractor Survey Respondents .................................. 85

18. Average Ratings of Contract Documents by Contractor Survey Respondents .................................. 85

19. Average Ratings of Contract Administration by Contractor Survey Respondents .................................. 87

20. Average Ratings of All Categories by Contractor Survey Respondents .................................. 88

21. Average Contractor Responses to Multiple-Answer Questions . . . .. 89

22. Summary of Contractor "Yes" Responses to Dichotomous Questions ............................... 90

23. Five Most Common Contractor Comments to Question 10 ....... 92

24. Summary of Contractor "Yes" Responses to Question 17 ........ 95

25. Seven Most Common Contractor Comments to Question 18 . . . . .. 96

26. Average Ratings of Dispute Resolution Alternatives by Contractor Survey Respondents .... . . . . . . . . . . . . . . . . . . . . .. 98

27. Results of Comparison of Surveys Using Chi-Square ........... 99

28. Average Ratings of Contractor Practices by SDHPT and Contractor Survey Respondents . . . . . . . . . . . . . . . . . . . . . . . 101

29. Average Ratings of SDHPT Practices by SDHPT and Contractor Survey Respondents . . . . . . . . . . . . . . . . . . . . . . . 102

30. Average Ratings of Contract Documents by SDHPT and Contractor Survey Respondents . . . . . . . . . . . . . . . . . . . . . . . 103

Page 15: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

xiii

LIST OF TABLES

(Continued)

TABLE Page

31. Average Ratings of Contract Administration by SDHPT and Contractor Survey Respondents . . . . . . . . . . . . . . . . . . . . . . . 104

32. Average Ratings of All Categories by SDHPT and Contractor Survey Respondents . • . . . . . . . . . . . . . . . . . . . . . 105

33. Average Ratings of Dispute Resolution Alternatives by SDHPT and Contractor Survey Respondents . . . . . . . . . . . . . . . . . . . . . . . 107

34. Average Claimed and Paid Values for Claims ................. 114

35. Maximum Likelihood Analysis of Variance Table for Contractor Practices .................................. 164

36. Maximum Likelihood Parameter Estimates for Contractor Practices .•................................ 164

37. Maximum Likelihood Analysis of Variance Table for SDHPT Practices . • • . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165

38. Maximum Likelihood Parameter Estimates for SDHPT Practices .... 165

39. Maximum Likelihood Analysis of Variance Table for Contract Documents .................................. 166

40. Maximum Likelihood Parameter Estimates for Contract Documents .•.•.............................. 166

41. Maximum Likelihood Analysis of Variance Table for Contract Administration .....•.•••.......•.............. 167

42. Maximum Likelihood Parameter Estimates for Contract Administration ••.......•••......•............. 167

43. Maximum Likelihood Analysis of Variance Table for All Categories .. 168

44. Maximum Likelihood Parameter Estimates for All Categories ...•.•..•..•........... . . . . . . . . . . . . . . . . 168

Page 16: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

XIV

LIST OF TABLES

(Continued)

TABLE Page

45. Maximum Likelihood Analysis of Variance Table for Dispute Resolution Alternatives ........................ 169

46. Maximum Likelihood Parameter Estimates for Dispute Resolution Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . 169

47. Maximum Likelihood Analysis of Variance Table for Contractor Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 174

48. Maximum Likelihood Parameter Estimates for Contractor Practices .................................. 174

49. Maximum Likelihood Analysis of Variance Table for SDHPT Practices .................................. 175

50. Maximum Likelihood Parameter Estimates for SDHPT Practices .... 175

51. Maximum Likelihood Analysis of Variance Table for Contract Documents ............................... 176

52. Maximum Likelihood Parameter Estimates for Contract Documents .................................. 176

53. Maximum Likelihood Analysis of Variance Table for Contract Administration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176

54. Maximum Likelihood Parameter Estimates for Contract Administration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 177

55. Maximum Likelihood Analysis of Variance Table for All Categories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 178

56. Maximum Likelihood Parameter Estimates for All Categories . . . . . . 178

57. Maximum Likelihood Analysis of Variance Table for Dispute Resolution Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179

Page 17: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

xv

LIST OF TABLES

(Continued)

TABLE Page

58. Maximum Likelihood Parameter Estimates for Dispute Resolution Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179

59. Maximum Likelihood Analysis of Variance Table for All Categories .. 182

60. Maximum Likelihood Parameter Estimates for All Categories . . . . . . 182

Page 18: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

1

CHAPTER I

INTRODUCTION AND BACKGROUND

INTRODUCTION

In fiscal year 1990, the Texas State Department of Highways and Public

Transportation (SDHPT) spent $1.713 billion to construct, repair, or rehabilitate

approximately 715 segments of the 77,000 mile state-maintained highway

system UJ. Departmental estimates for fiscal year 1991 show a decline in the

volume of work, with total lettings down to about $1.3 billion (1). And as the

State struggles to maintain the quality of its highways on a tighter budget, the

Department has spent more than $17 million dollars over a 12-year period to

settle disputes with contractors. From 1977 to 1989, contractors filed an

average of 8.85 claims per year, costing the State $1.43 million annually. That

one-tenth of one percent of the State's annual construction budget could be

used to construct 0.72 projects each year. When the indirect costs associated

with dispute resolution are considered, this figure rises to 6.5 projects annually.

Although it is not feasible to think claims can be eliminated altogether,

the Department must seek a means for reducing the number of claims so tax

revenues can be utilized for their intended purpose: constructing and improving

the vast system of highways in Texas.

The style and format followed in this thesis was Transportation Research Board.

Page 19: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

2

Background Information

From 1982 to 1988, the competitive bid process was completed 5,008

times, representing a dollar volume of $9.9 billion. Figure 1 shows both the

number of projects and their yearly total values. From 1977 to 1989,

contractors filed 115 claims against the State, with a corresponding dollar value

of $51.4 million. Of these claims to date, the Department has paid

approximately one-third of the claimed value, or $17.1 million to the contractors.

Figure 2 shows the total number of claims during this period, while Figure 3

shows the total claimed value and total paid value for these years. When the

number of claims is considered, the average claim filed and paid values result,

and these data are presented in Figure 4.

From 1977 to 1989, the overall average number of claims per year is

8.85, the average value per claim is $447,498, and the average settlement is

$148,612. Looking at Figure 4, the yearly average claimed value for three of

the past five years plotted is higher than the overall average. Similarly, the

average paid value is above the overall average for two of the past five years.

While the average number of claims per year shows a pattern similar to the

claimed and paid values, the pattern cannot be deemed a trend. Figure 2

shows the number of claims per year to be somewhat erratic. There is

evidence of an upward trend in the value of the claims, even though there is

a lack of a discernable pattern in the number of claims filed per year.

Page 20: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

~ G)

"[ D-

2000---------- =--------r!!::?,000

1500

1

1982198319841985198619871988 Year of Project Letting

I ~ Projects _ Total Dollars

$500

3

(i) c: .2

~ ~

..m 8 ~ .....

Figure 1. SDHPT Construction Projects and Spending, 1982 to 1988.

20

15

1979 1981 1 1978 1980 1982 1984

Year Figure 2. Claims Against SDHPT, 1977 to 1989.

Page 21: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

~ ----,-_.& .. __ ..

:& $1o.oool1l~1~~~~~~E~11::~l[~~1 ~~~~§~

~ ----t!I'-----ilL... .. .. _. . ..

:::::::E::::::: :: ::: ......... ~:

... _ ........ -- ... n-

$100 mmm .~~ ~~mm~ ... !: ::::::::: .:: if::::::: . ............ .

.,

$10 r ,~ n 79 81

.... I

83 85 Vear

.. .~. ,. i , . i

i: I: ,. ! . ,. I

I! .~~.-:::::~

1

:.' f ::::::::::::

f······_-.. · 87 89

I ~ Filed Value • Paid Value I

Figure 3. Total Value of Claims Against SDHPT, 1977 to 1989.

;:::::::::::::::: t·· ..... ~ .......... _ ... ~ ........................... .. ~.w., .. ., ......... " •• ...,

• .· •• _ .......... _ .... ·_ .•••.••• m.· ••. ••··•· ••••• ·........ ................ .. . f················ r .... ············

$10 I::",::" ::: I::::::::: :::

~ :::::::::::::::: '." , .. r.: 'f:::::===: ,. ..... _ .... _ ...

t" •• --_._-

j. I

I: W~~~11f~ , .. ---1 ... _ ..

r"--I

83 85 87 89 Vear

I ~ FUed Value • Paid Value I Figure 4. Average Value of Claims Against SDHPT, 1977 to 1989.

4

Page 22: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

5

STUDY OBJECTIVES

The primary objective of the research effort was to provide insight into

the problem of numerous construction claims against the SDHPT. This goal

could be divided into several subgoals. First, the problem of construction

claims as a whole had to be investigated to determine basic causes. This list

of general causes then was focused to reveal the specific causes of claims

against the SDHPT. Next, the current system used by Texas to settle disputes

and claims was to be evaluated. Once this was accomplished, specific

recommendations to lower the number of claims encountered by the SDH PT

could be made.

STUDY METHODOLOGY

The research effort was divided into four phases. First, a literature

search provided information concerning dispute resolution alternatives and

background information used to design the survey forms. The surveys of

SDHPT personnel and highway contractors determined major problem areas

within the State, and provided information needed to quantify the claims

problem. The responses to the surveys were compiled and statistically

analyzed according to the position of the respondent. For questions common

to both surveys, the contractor responses were compared to SDHPT

responses to determine if the parties shared common opinions. Both survey

Page 23: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

6

forms provided ample space for written comments. These comments were also

compiled and investigated. Interviews with SDHPT personnel and contractors

supplemented the findings of the surveys by providing more detailed insight

into the claims problem. Finally, the research focused on the current system

used by the Department for dispute resolution and claim settlement. Several

claims were studied in detail to evaluate the quality of the documentation and

to fully understand the process followed by the State.

DEFINI1"IONS

Qontracts in General

In general terms, a contract is defined as an agreement, enforceable by

law, between two or more competent parties to do or refrain from dOing

something not prohibited by law for a legal consideration (2). Consideration is

defined as the cause, motive, price or impelling influence which influences a

party to enter into a contract (2).

There are two primary divisions in the construction by contract system.

The first is the single contract method, which is used by the Department for its

highway construction prOjects. Under this system, the contracting agency

enters into a single contract with the party responsible for the actual

construction {3}. This party is referred to as the Contractor, defined as the

"individual, firm or corporation or any combination thereof, Party of the Second

Part, with which the contract is made with the State" ~). The contractor then

Page 24: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

7

enters into as many subcontracts as he desires, with the following limitations:

He cannot sublet more than 49 percent of the work; aU subcontractors must be

approved by the Engineer; and finally, subletting any portion of the work does

not relieve the contractor from his responsibility to conform to the requirements

of the contract ~). By entering into subcontracts, the contractor gains the

designation of the ·prime" contractor. Depending on the terms of each of the

subcontracts, these second-level contractors may be able to enter into third­

level subcontracts, and so forth. Even though multiple contracts exist for the

construction of a single project, this still conforms to the definition of a single

contract system as the State is only a party to contract in one of the contracts.

By way of contrast, the separate contract system has multiple prime

contractors contracting with the owner (3). This system allows the contracting

agency to be more selective in choosing contractors but presents more of a

challenge from a contract-management perspective. Although the use of this

system might be applicable for some highway construction projects, such as

when multiple individual contracts make up a single project, its use by the state

is currently limited.

Contracts with SDHPT

The contract between the Department and contractor is the agreement

between these two parties covering the furnishing of materials and performance

of the work. The work includes the furnishing of all labor, materials, equipment,

and other incidentals necessary or convenient to the successful completion of

Page 25: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

8

the project and carrying out of aU the duties and obligations imposed by the

contract ~). The contract includes the plans, standard specifications, special

provisions. special specifications, and contract bonds. Field changes, extra

work orders, and supplemental agreements are considered to be parts of the

contracts as well ~}.

The plans are the drawings approved by the engineer, or true

reproductions thereof, which show the location, character, dimensions, and

details of the work ~}. The standard specifications are the directions,

provisions, and requirements contained in the current standard specification

issue and referred to by the inclusion of items in the plans directly or as

subsidiary items. The special specifications and special provisions may pre­

empt all or part of any of the standard specification items and may address the

method and manner for performing the work or the quantities and qualities of

materials to be furnished under the contract. These specials cover work

pertaining to particular projects and are included in the proposals as issued to

bidders 00.

In cases of disagreement between the terms of the contract, calculated

dimensions govern over scaled dimensions. plans govern over standard and

special specifications, and special provisions govern over both standard and

special specifications and plans ~}. Many of these special items adjust the

method for calculating payment to the contractor, and many items dictate

portions of the work not to be paid for directly but to be considered subsidiary

to other items of work. When these terms of contract are applied over the

Page 26: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

9

number of projects let in 24 districts and 126 residencies with each office

selecting which special items are to be included in each project, the possible

number of combinations of provisions approaches infinity.

The Construction Claim

The construction claim is an unresolved dispute between the parties to

a construction contract. The dispute always involves questions of entitlement

(the contractual merit of the dispute) and damages (the dollar value of the

dispute) ffi). A valid claim must include both entitlement and damages.

Differing site conditions, defective and deficient contract documents, breach of

contract, acceleration, suspension, termination, directed change, constructive

change, implied warranty, delays, impossibility of performance, weather, strikes,

owner-furnished items, superior knowledge, and maladministration are the

commonly recognized entitlements ~). Once entitlement has been established

and in order to receive relief, the contractor must prove he incurred damages.

In general, the contractor presents his proof of damages in the form of a report

to the State, including documentation of events, photographs, charts,

schedules, correspondence, and calculation of the damages (2). The detailed

process followed by the Department for dispute and claims resolution will be

discussed in detail in Chapter 2.

Page 27: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

10

CONTRACTUAL PROVISIONS

Nearly all construction contracts include provisions spelling out the

process to be followed for dispute resolution. Among the provisions set forth

in federal contracts is the clause stating that disputes concerning a question of

fact • ... shall be decided by the Contracting Officer ..... ~). The contractor may

appeal the Contracting Officer's decision to the head of the agency involved,

and his decision is final unless the decision can be shown to be fraudulent,

capricious, arbitrary, or so grossly erroneous as to imply bad faith. These

exceptions provide the last resort for possible relief for the contractor m).

In Texas, ''the Engineer will act as referee in all questions arising under

the terms of the contract between the parties thereto. and his decisions shall

be final and binding "~). This clause is currently the only mention of the

dispute resolution process in the standard specifications. The process of going

to the claims committee. as will be discussed in detail later, is not mentioned

in writing. When the contractor feels the need to carry a dispute further than

the Engineer, he must either inquire as to the process to be followed, rely on

the experiences of others. or know the process by virtue of having gone

through it previously. The standard speCifications do, however, clearly define

the processes to be followed for the assessment of liquidated damages. for

abandonment of the work or default of the contract. and for termination of

contract ~). The standard specifications also dictate the processes of initiating

Page 28: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

11

extra work orders, how to handle changes and alterations, and increases and

decreases in the quantity of the work ~).

WHY CLAIMS HAVE INCREASED

A study done for the Federal Highway Administration in 1988, entitled

-Highway Contract Claims Avoiding/Handling" reveals some reasons for the

recent increase in the number of claims. The major findings showed three

major reasons for the rise: the effectiveness of exculpatory language; the use

of liquidated damages; and the influence of external factors.

Exculpatory clauses are attempts by contracting agencies to escape

responsibility for any type of damages the contractor might incur (2). An

example of an exculpatory clauses included in Federal contracts state, "no

claim shall be made or allowed to the contractor for any damages which may

arise out of any delay caused by the United States" (1). Many state

departments of transportation (DOTs) include similar statements in their

contracts to provide a variety of coverage. California, for example, provides

some information related to subsurface conditions at the site but thoroughly

disclaims responsibility for the accuracy of the information. Such site

investigations are used for the design of the project and presented in the plans

for the benefit of the contractor. The contractor, therefore, must investigate the

site himself or anticipate deviations from the shown information. The State is

effectively denying the contractor the benefit of price adjustments based on

Page 29: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

12

differing site conditions. Only two states, Colorado and Florida, permit the

contractor to claim for differing site conditions (2).

Another common source of claims is liquidated damages. Contractors

who are assessed liquidated damages can attempt to show they were delayed

by the contracting agency, forcing the completion date past the threshold for

assessing liquidated damages. If the owner-caused delay can be shown to

force the assessment of liquidated damages, the contractor has filed a winning

claim. Commonly, the effects of owner-caused delays are determined by

critical path methods (CPM) analYSis, with the project documentation providing

data for analysis (§). The FHWA studied 18 projects with delay claims, and out

of these projects, 15 contractors were assessed liquidated damages (2).

Although the FHWA study proved inconclusive, it seems logical that contractors

who feel they were delayed by factors beyond their control would attempt to

recover losses.

The external factors studied can be divided into two major categories:

the number of bidders and the rate of inflation. Although the number of bidders

did not show a direct cause-effect relationship with the number of claims, the

climate created by the increased competition among contractors showed some

correlation with the number of claims. In the battle for state construction

projects, contractors may tend to cut their bids to be awarded the projects,

then recover their costs through change orders and claims. Similarly, the

FHWA study did not find a direct relationship between the rate of inflation and

the number of claims, but rather an indirect relationship (2).

Page 30: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

13

DISPUTE RESOLUTION ALTERNATIVES

There are many methods now in use by contracting agencies across the

United States for dispute and claims resolution. Some of the most commonly

used resolution methods are contract appeals boards, arbitration, dispute

review boards, mediation, mediation-arbitration, mini-trials, and finally, litigation.

These methods are presented for consideration by the State Department of

Highways and Public Transportation for possible future implementation, and will

be discussed in detail in the following sections.

Contract Appeals Board

Each federal agency that contracts its construction projects has the right

to establish its own contract appeals board. Some agencies might not be able

to justify the existence of a full-time board because of a low volume of

construction, so they refer any contract disputes to other agencies' boards for

resolution (6). These boards usually are composed of three appointed judges,

who must comply with some prequalification standards. Most commonly, these

judges must have a minimum of five years experience in public contract law (a).

Most importantly, the members must be in a position of complete impartiality.

The main function of the board is to reduce the number of construction claims

that go to litigation for resolution (6). The Contract Disputes Act of 1978 limits

the effectiveness of the board, as contractors are allowed to bypass the board

and go directly to the Court of Claims for dispute resolution (Z).

Page 31: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

14

Procedures for the hearing of the dispute before the board are similar

to those of the court. The judges can administer oaths, subpoena witnesses,

authorize depositions, and so forth (8). The decisions reached by the judges

can be appealed by either party. Findings of fact can be appealed only if the

decisions reached are not supported by sufficient evidence. Conclusions of law

may be appealed as a matter of law. In either case, the appeal usually will be

to the court of claims and eventually to the U.S. Supreme Court if not settled

at a lower level (2).

While the contract appeals board varies widely across the states that use

it, most have been patterned after the Federal Board of Contract Appeals. In

some states, the board is composed of political appointees, and the members

mayor may not have construction experience (Q). In other states, the board

may be made up of members of the contracting agency m). Whatever the

makeup of the board. its functions are much the same across the states. The

board hears the contractor's claim, as well as the defense of the claim by the

members of the agency initially involved in the dispute.

The procedural rules are informal, and often, legal counsel are not

included in the hearings to promote freer communication. The board judges

the claim based on validity, determines if both parties complied with contract

provisions, then determines if the contractor is entitled to relief. If so, the

members decide upon the amount of damages suffered by the contractor. The

board then proposes a settlement to the contractor. In some states, these

findings may not be binding (8).

Page 32: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

15

One advantage of this process is speed. If the decision of the board is

not appealed, the entire process requires considerably less time than litigation.

Another advantage of this system is the usually equitable settlement for both

parties em. Because the findings of the board are generally based on well­

developed principles of law, this process is not well-suited for cases where a

precedent may be set. This fact, along with the frequency of appeals, are the

main disadvantages of this process (9).

Litigation

Usually, the contractor's last resort for attaining relief is litigation. As a

result, litigation is the most commonly used method of dispute resolution within

the United States. In Texas, the claim must pass through all possible avenues

for resolution within the Department before resorting to litigation. While litigation

varies from state to state, there are sufficient similarities to allow for a

generalized discussion of the process.

The process of litigation begins when the claimant files a complaint,

either with the civil court or the federal court ~). All the parties involved in

construction might be a party in the suit. This includes the owner, contractor,

subcontractors, suppliers, consulting firms, manufacturers and sureties.

Usually, however, the prime contractor files the suit against the owner and

every other party conceivably associated with the dispute. The owner

commonly finds himself in a unique position of being the only party with privity

Page 33: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

16

of contract with the contractor. When the claim involves projects designed by

others, the owner's only recourse is to file suit against the designer (S).

After the complaint is filed, the pretrial activities get into full swing. These

activities include investigation and compilation of documents by all parties in the

suit. This period is known as discovery: The pretrial or prehearing procedure

designed to promote full disclosure of all relevant facts related to a contract

dispute (2). During discovery, each party is able to investigate the other's

documents, witnesses, and facts. The time frame for the pretrial activities often

spans up to two years (W.

After the discovery period is complete, the parties commonly find the

issues have been narrowed and that a settlement is possible. Sometimes, the

parties reach an out-of-court settlement because one party sees weaknesses

in his case and wishes to avoid the extra cost of the trial (S).

Barring an out-ot-court settlement, the case eventually will go to trial, with

either a judge or jury as trier-of-tact ~). Commonly, trials in construction cases

begin with opening statements intended to set the stage for the trial and to

show the positions of the parties. The evidence is usually presented in

chronological order. Witnesses are called from both sides to present evidence,

and they are cross-examined in an attempt to discredit their testimony.

Summary statements are made by both sides, and the direction of the case is

left to the trier-of-fact (S). This entire process is strictly structured, and the

possibility of a legal error nullifying the judgment always exists.

Page 34: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

17

There are some advantages uniquely associated with litigation. The

process can be the most time-consuming of all forms of dispute resolution,

especially if litigation is the contractor's last chance at relief. This results in a

huge advantage to the defendant, most commonly the contracting agency.

Public entities are often in no hurry to settle a claim, as interest commonly is

not applied to the settlement amounts (2). Also, the legal fees commanded by

the best claims lawyers create a tremendous drain on the claimant's cash

supply, so he may not have the resources needed to fight a long, drawn-out

claim. Litigation, therefore, is commonly referred to as the "defendant's forum"

m). Another benefit of litigation is the period of discovery. This intimate,

mutual knowledge of the opponent's case can lead to settlement negotiations

and often to settlements before the completion of the trial (.1.Q). Finally, once

the trial has begun, it often proceeds without interruption until completion (.1.Q).

As will be discussed later, some alternate forms of dispute resolution do not

share this benefit.

The primary disadvantage to litigation shares common ground with the

advantages. Because the process can be so time-consuming, both parties can

spend tremendous amounts of money on attorneys' fees. Table 1 provides

some examples of the magnitude of the costs associated with settling claims

through litigation (.11). Another disadvantage of litigation is the lasting

adversarial effects that can result. Often, the feelings of mistrust, loss of

respect, and even hatred can be reflected in future projects. The final

disadvantage of litigation is the importance of documentation. The courts

Page 35: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

18

Table 1. Costs of Litigation.

Project Claimed Settled Defendant's Project Size Amount Amount Legal Costs Overrun

(Millions) (Millions) (Millions) (Millions) (%)

$ 59 $50 $ 37 $9 178.0

$ 9.0 $5.0 $ 3.5 $ 5.0 194.4

$32.0 $10 Pending $ 4 (Est) * 112.5

* Includes only estimated legal fees.

tend to place more weight on the written word than oral testimony m).

Arbitration

After litigation, arbitration is the second most commonly used method of

dispute resolution. Ten of the state DOTs surveyed by Netherton in 1983 (1g),

supplemented by a SDHPT survey of seven states in 1990 m), use arbitration

at one point or another along the dispute resolution trail. Arbitration has a long

history, and is founded on three principles: informality, the use of experts

familiar with the businesses involved in the dispute, and the experts' awareness

of the ever-changing business environment {.1Q).

Arbitration may be defined as Ha separate method of dispute resolution

that utilizes laymen experienced with the type of business involved instead of

a court of law to decide disputes" (lQ). The experts chosen to settle the

dispute can render a fair and equitable decision quickly. often without the need

for a large amount of discovery. Arbitration. therefore. is often more

Page 36: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

19

economical than litigation (0). Generally, the construction contract details the

method for selecting the arbitrating party. There are three methods for

selecting arbitrators; they may be selected directly by the parties concerned,

by the National Panel of Construction Arbitrators as maintained by the

American Arbitration Association (AAA); or each party may select arbitrators,

who in turn choose neutral arbitrator (3). Under the third method, the two initial

arbitrators may resign and allow the third to settle the dispute, while in other

cases the initial arbitrators join the third to form a panel em. As in other methods of dispute resolution, the terms of the contract

dictate the arbitration process. A typical hearing procedure has both parties

presenting their cases to the arbitrators including witnesses, proofs, and other

evidence. All witnesses must submit to questions or other form of examination.

The parties may be contractually allowed to be represented by counsel, if

desired. The arbitrators then decide to grant any remedy to either party

deemed just and equitable within the scope of the construction contract

between the parties. The award must be in writing and must be signed by a

majority of the arbitrators if the panel is used. Each of the parties then receives

a copy of the award (3). The decision of the arbitrators is usually binding by

contract, and an appeal is allowed only in special cases. Some of these

special cases occur if collusion among the arbitrators is found, if the arbitrators

were acting beyond their limits of authority, and if the procedural requirements

as stipulated in the contract are not followed (3).

Page 37: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

20

Arbitration has many advantages over other methods of dispute

resolution. First, arbitration resolves claims faster than litigation. Dispute

settlement through litigation can take years because of the crowded court

dockets. The litigation process can also be prolonged by the availability of

appellate courts (la). Also, because the dispute is resolved through the use

of experts in the field of construction, there is no need to educate the jury or

judge about complex engineering issues. Because the process is informal by

nature, there are no legal technicalities involved. No attorneys are involved,

unless the parties agree beforehand m). This flexibility reduces the cost of

resolution, partially by reducing or eliminating legal fees (1a). This reduction

of cost has a pronounced effect on smaller cases, which often can be settled

in only a few sessions of arbitration.

Arbitrators of construction cases tend to hear the first two days of the

case at no charge. After that time, fees must be paid, with typical arbitrators

commanding $250 to $500 per day. Also, in more complex cases, additional

costs that can be incurred include the costs of the hearing room, transcripts,

expert witnesses, and attorneys (la). The total cost for these hearings range

from $1,200 to $2,000 per day. Additionally, the filing fee for the AAA can be

as high as $20,000 (M). Table 2 shows these costs to be substantial for

complex cases (.11).

One final advantage of arbitration is that the process is confidential.

Awards and findings are not a matter of public record, and third parties are not

allowed to attend the sessions unless both parties agree beforehand. This

Page 38: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

21

Table 2. Costs of Arbitration for Complex Cases

Project Size Claimed Settled Defendant's Project (Millions) Amount Amount Legal Costs Overrun

(Millions) (Millions) (Millions) (%)

$ 146 $ 50 $ 4.5 $5 106.5

$23 $ 15 $ 12 $4 169.6

$ 32 $15 Pending $ 6 (Est) * 118.8

* Includes only estimated legal fees.

advantage can be lost if the dispute cannot be settled at this level, and the

record included in the next step of litigation ~).

These advantages stated above are, however, somewhat outweighed by

the disadvantages. One of these disadvantages is the intermittent nature of the

arbitration sessions. Typically, these sessions are scheduled in short durations

with long recesses to allow the arbitrators to tend to their own businesses. A

complex claim can require numerous sessions spanning a long period of time

to present and discuss the issues involved, thereby reducing one of the positive

points. of this process (13). A second major disadvantage is that the limited

discovery process can lead to surprises during the proceedings. The lack of

prior knowledge of the other party's case can reduce the effectiveness of the

prepared defenses ~). The avoidance of formality in procedure can also be

a double·edged sword, as the predictability of evidence disclosure is lost. Also,

the predictability of the outcome is lost, as the arbitrators do not necessarily

adhere to principles of law as established by prior cases involving similar

Page 39: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

22

circumstances (.1ID. Finally, many of the state DOTs surveyed by Kangun feel

the arbitration process is biased against them. They claim their best interests

are not represented on the list of potential arbitrators (a).

Dispute Review Board

The dispute review board (ORB) is a dispute resolution technique that

has recently gained popularity among contracting agencies across the United

States. This method provides a timely solution to problems, with the focus on

resolving disputes while the facts and events are still fresh on the minds of the

participants and while personnel are still readily available (1Q). This process

has had tremendous success in Washington state, especially in several

tunneling projects for WSDOT, in resolving disputes before they become

formalized claims (lW. The board is typically composed of three members,

one each selected by the parties to the contract, and the third member

selected by the first two. Both the owner and contractor must approve the

other's initial selection. The findings of the board are not binding to either party

~).

The board usually meets several times a year, typically every two or

three months. usually coinciding with major. critical, and claim-prone phases

of the work. These meetings provide the members of the board an intimate

familiarity with the project, along with its peculiarities. personnel, and problems.

Between the meeting times, the board is kept informed of the project progress

and problems through correspondence, and board members are similarly

Page 40: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

23

notified when a dispute arises (1Q). As with arbitration, the procedure for

creating the board is contractually mandated. One significant difference exists

in the fact that the contractors' bid documents including take-offs, calculations,

quotes, notes, computer disks, and the like are required to be set up into an

escrow for future use (1Q). Also, the board members must be contractually

compensated. Typical costs of the ORB are one-tenth of a percent of the cost

of the project, and the amount is split between the owner and contractor.

Because of the cost associated with the ORB, its usefulness may be restricted

to large, complex, dispute-prone projects where the cost of the ORB may be

offset by savings to the owner and contractor alike (9).

When a dispute does arise, the contractor typically requests extra

compensation from the owner, who usually denies the charge. At the meeting

of the ORB. correspondence between the contractor and owner is presented

to the board. Figure 5 shows the process followed by the ORB (11). The

meeting itself is informal, and both sides present their interpretation of the facts

and specifications to the ORB. Both the owner and contractor have the

opportunity to rebut the other's cases. The board analyzes the dispute and

makes a recommendation to both parties within a specified time frame, usually

short in duration. The recommendations of the DAB focus on questions of

entitlement rather than on issues of dollar values. The parties then determine

the dollar amounts of the damages based on the documents escrowed as

described above. and the recommendation of the DAB. If the parties cannot

Page 41: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Initiate Other Action

Appeal to ORB

Order from

Owner

Contractor Written Protest

Organize for Hearing

Written Recommend.

Figure 5. Dispute Review Board Flow Chart.

Accept

Accept

Dispute Resolved

Dispute Resolved

24

Page 42: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

25

reach an agreement on the dollar value of the settlement, the board may be

cal/ed in to assist in the determination of the settlement (.16).

As with all other dispute resolution alternatives, there are advantages

and disadvantages associated with the ORB. Because the board meets on an

ongoing basis, the facts remain fresh with all the parties. Personnel are readily

available for testimony. Also associated with the ongoing meeting process, the

disputes are settled as they arise. The cumulative effect associated with many

after-the-fact methods of dispute settlement is not present. Incidental costs

have little time to accumulate. This process can help foster a positive

relationship between the owner and contractor, as they work together to solve

common problems. Finally, the board is intimately familiar with the project and

its associated problems and personalities. This familiarity allows the ORB to

render its decisions based on the total project, not just on evidence presented

by the parties during discovery (9).

Some disadvantages exist for the ORBs, most notably the cost. The

owner typically pays for secretarial costs and materials, while the other costs

are split between the owner and contractor. Finally, if the members selected

by the parties have little or no expertise on the type of construction or area,

problems could arise. This situation could lead to the third member being the

predominant member, or at worst, the only effective member of the board (9).

Page 43: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

26

Mediation

Mediation, another form of third-party dispute resolution, is defined as

the act of the thi~d person who "interferes" between the two contending parties

with a view to reconcile them or persuade them to adjust or settle their dispute

(.1Q). Mediation shows characteristics of both arbitration and the dispute review

board. Because mediation is a structured negotiation process using a third

party as a dispute resolution facilitator, it is similar to arbitration. The process

is similar to the dispute review board in the fact that the decisions reached

through the mediator are non-binding to both parties. The mediator is usually

an expert in conflict resolution and usually needs to possess some degree of

technical ability. The entire purpose of the mediator is to help the parties

formulate a solution to their problem, and he does impose a decision upon the

parties. Mediation is often a voluntary process and is written into the contract

as a alternative dispute resolution process. The mediator is generally selected

before the onset of the work, and the process is commonly a administered

through an association, such as the American Arbitration Association (a). The

AAA claims a high rate of settlements in projects where mediation is used to

settle disputes (17).

The process begins when one of the parties requests mediation to

resolve a dispute. Both parties agree on a date and then prepare their cases

to present to the mediator. The first mediation session includes both parties

simultaneously with the mediator, when each party presents its case. The

mediator then meets individually with each party. and the discussion

Page 44: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

27

concentrates on that party's weaknesses. The opponents case will not be

discussed. The mediator challenges both parties' cases individually, and hope

to condense the dispute, eliminate non-issues, and seek trade~offs. The

mediator continues to meet individually with both parties, narrowing the

differences between them until he can propose a settlement based on

compromise ca). The advantages that mediation presents are similar to the advantages

of the dispute review board. First, because mediation is not an adversarial

process by nature, the dispute usually can be resolved without damaging the

working relationship between the two parties. The process is less time~

consuming than litigation and is also not restricted by formal procedures. The

outcome is generally confidential, and both parties agree to the settlement.

Finally, the process will dispose of at least some minor issues so later

resolution can concentrate on the most important issues (a).

The disadvantages of mediation are also similar those of the arbitration.

First, there is no discovery period to allow each side to prepare a defense

against the other's charges. Because the settlement of the dispute is based

on compromise, it may be advantageous for each side to inflate its initial claim,

hoping the settlement will be in the vicinity of the initial target amount. Also,

both sides may be unwilling to commit the funds necessary to resolve the

dispute. It is advisable for each party to be represented by an individual with

the authority to commit these funds. If this is not possible, mediation still can

Page 45: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

28

be used as a fact-finding process, with the determination of liability as the sale

goal ~.

Mediation-Arbitration

Mediation-arbitration is sometimes used as a substitute for strict

arbitration. This process is a system of selecting a person in advance to

resolve conflicts between the owner and contractor. As the name implies, the

mediator-arbitrator must employ the functions and skills of the mediator and

arbitrator. One of the main characteristics carried over from the arbitration side

is the binding nature of the decisions made by the mediator-arbitrator (1Q).

The mediator-arbitrator is selected before construction starts, and the

provisions for the selection process will be defined in the contract. The

selection of the mediator-arbitrator should be done directly by the parties

involved, not via selection of two individual parties who then select the third

(1Q). This selection process guarantees the neutrality of the mediator-arbitrator.

The mediator-arbitrator should be selected based on his expertise in the area

of construction and also on his conflict resolution ability. Most importantly, the

person selected should be free from conflicts of interest. Finally, the person

selected should be someone in whom all parties have the utmost confidence.

The flexibility of this system allows the selection of multiple persons to serve as

mediator-arbitrators, with areas of individual specialization being represented

by corresponding experts (1Q).

Page 46: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

29

The first functions of the mediator-arbitrator in the dispute resolution

process are those of a mediator. He meets with all parties involved in the

dispute to investigate the situation for all facts, then assembles the parties

involved for negotiation sessions. For these sessions, the parties may retain

technical experts to provide independent advice concerning the dispute. -rhe

mediator-arbitrator then engages in mediation sessions with the parties, both

separately and together, and attempt to resolve the issues. The mediator­

arbitrator may decide some of the issues cannot be settled through mediation,

and those must be resolved through arbitration. The process then takes the

form of traditional arbitration, with hearings being held, and the mediator­

arbitrator making the final decisions (1ID.

While many of the benefits of mediation-arbitration are the same as those

for the individual processes of mediation and arbitration, the criticisms of the

process are unique. Some experts argue the combination of mediation and

arbitration hinders the process of mediation. This may be due in part to the

tendency of individuals to be more open and free with a person who is not

perceived as being the source of the final, binding decision. Other critics argue

that there are some circumstances when the mediator-arbitrator does not

deserve the confidence of the conflicting parties, and the process does not

provide for the means to determine if this confidence is warranted. As with

some other third party resolution methods, the presence of the third party can

lead to the bringing of common, everyday disputes to the mediator-arbitrator

for resolution. This can dramatically slow the decision-making process at the

Page 47: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

30

project site (:1.Q). One advantage unique to the mediation-arbitration process

is the time-saving potential of the combination of these two processes m).

Mini-Trials

There are two separate dispute resolution techniques that fall under the

classification of mini-trials. One is a witness trial, during which each attorney

summarizes the evidence to be presented during a full-scale trial to a six­

person jury or judge, who renders an advisory verdict. This process allows

both parties to see the effect of their evidence on the outcome of a trial, without

the time and expense required to prosecute a full trial. The advisory verdict

allows each party to evaluate the strengths and weaknesses of its case, which,

in turn. allows more meaningful discussions aimed at resolving the dispute.

Often, mutually acceptable solutions to the dispute arise from these discussions

(1.Q).

The second type of mini-trial is one in which the executives of the

conflicting parties sit on a panel, along with a neutral adviser. The panel hears

the attorneys from both sides present the evidence that would be presented

during the trial. The executives then attempt to resolve the dispute by mutual

agreement. It is this type of mini-trial that shows the most promise for use in

resolving construction disputes (1.Q).

The process of a mini-trial is not really a trial, but a series of hearings

followed by negotiation sessions. The duration of the proceedings depends on

the complexity of the dispute, but most hearings are conducted in a span of a

Page 48: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

31

few days. The negotiation sessions may require substantially more time, but

ideally, the entire process requires less than 90 days (1Q).

SpeE;!d of resolution is the first significant advantage of mini-trials.

Usually, the entire process of the mini-trial requires substantially less time than

arbitration and litigation. The relatively short process means a savings in legal

fees compared with arbitration and litigation. Another main advantage of mini­

trials is that they allow for resolution of the dispute by individuals representing

the parties without involving any of the people responsible for the dispute.

Most mini-trials are conducted according to a written agreement between the

parties that allows them to determine how the proceedings will be conducted.

This flexibility of procedure is another benefit. The final main advantage of mini­

trials is the confidentiality of the process (1Q).

Mini-trials do have some disadvantages, some of which are discussed

below. The mini-trial is well-suited only for cases where compromise is a

possibility. Further, most mini-trials do not include periods for the discovery

process. One major disadvantage of the mini-trial is the lack of enforceability.

Some other disadvantages are the testimony of witnesses not under oath, the

possibility for limited cross-examination, and the lack of formal records. Finally,

it may be difficult for the parties to find executives truly not involved in the

dispute (1Q).

Page 49: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

32

CHAPTER II

THE CURRENT DISPUTE RESOLUTION SYSTEM IN TEXAS

GENERAL

Currently, the State Department ot Highways and Public Transportation

(SDHPT) utilizes the chain-ot-command system for dispute resolution. Figure

6 presents a condensed organization chart ot the Department, and Figure 7

shows a flow chart detailing the process ot dispute resolution followed by the

Department. Under this system, the contractor and project personnel attempt

to resolve the dispute under the provisions of the contract, then move up the

ladder of the chain-ot-command until the dispute is resolved. While many

variations in titles exist across the state, SDHPT personnel assigned to

construction projects typically include general construction inspectors, project

engineers, project inspectors, project bookkeepers, and project managers. The

complexity of the project, weather conditions, availability ot personnel, and the

contractor's work schedule affect the actual staffing ot each project on any

given day. Armed with the plans, standard specifications, special

specifications, special provisions, and general notes, collectively referred to as

the contract documents, this project team is the State's first line ot defense

against claims.

Page 50: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

COMMISSION

ENG-OIR COMMITTEE

I DIST ENGR I

--~

I PROJ ENGR I --]

I INSP

Figure 6. Condensed SDHPT Organization Chart

Page 51: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

.. --........ -.-.-~.-.. ---------.-· r ................ ----- -_ ....... L--.,.-....J

· · · · · · · · · · · . It .----. , --_ ..... _ ...... - .......................... --· . · . · . · . · . · . · . · . · . · . · . · . · . · .

· . · . · . · . · . · . · . · . · . , . · . · .

, -... ----... --.~---. .' ~;-~ · · · · · · · · · ·

: ,

~~---- •• --. L---~

, , ,

f .-_ .... __ ... ____ ........ _____ ............ ..

~-.-.-.-------.--------.--.----.-

Abbreviated Legend

P E - Proj Engr

AE - Aaa Engr

AH - Admin H.ar

LIT - Litigation

DCE - D Conal Engr CP - Contr Proy

DE - Dlat Engr CO - Changa Ordar

D-e - Conat Diy CMO - Commlnlon

CC - ClaIm Comm Minute Ordar

------ Communication Dlaputa Flow Flow

YES

YES

YES

YES

YES

YES

NO

Figure 7. Dispute Decision Flow Chart.

34

Page 52: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

35

To generalize the functions of the members of the project team, the

general construction inspector is the authorized representative of the Engineer

assigned to supervise and inspect any or all parts of the work and materials to

be used within~. The inspector may complete daily pay reports based on his

measurements, then submit these reports to the project engineer for approval.

While the general construction inspector is usually the first member of the

project team to encounter a dispute, he has no authority to resolve the dispute

outside the scope of the contract documents. The inspector does, however,

have authority to reject materials or suspend work until the dispute can be

settled by the Engineer. The inspector is not authorized to revoke, alter,

enlarge, or release any requirement of the specifications, nor to approve or

accept any portion of the work, nor to issue instructions contrary to the plans

and specifications. The inspector should not act as a foreman or perform other

duties for the contractor nor interfere with the management of the work ~).

Project management is accomplished by the project engineer, project

manager, or the project inspector. For the purposes of this paper, these

positions will be referred to singularly as the project engineer. This person is

deemed to be in "responsible charge" of the project, and one of his most

important tasks is maintaining the project diary. The project engineer mayor

may not be the designated as the "Engineer" under the specifications,

depending partially on his status as a professional engineer. The Engineer has

the authority to require the testing, observation, and inspection of the work to

ensure compliance with the specifications. The Engineer has the authority to

Page 53: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

36

decide all questions as to the quality or acceptability of materials furnished and

work performed; the manner of performance and rate of progress of the work;

the interpretations of the plans and specifications; and the acceptable fulfillment

of the contract on the part of the contractor. The Engineer's decisions are

considered to be final, and he has executive authority to enforce and make

effective such decisions and orders as the contractor fails to carry out

promptly. Also, the Engineer acts as a referee in all questions arising under the

terms of the contract between parties thereto ~). Effectively, the on-site chain­

of-command has the general construction inspectors reporting to the project

engineer. The project engineer then reports to the resident engineer in charge

of the project.

The contractor's project team also varies project by project. Usually, the

crews of workers are supervised by a foreman, who in turn reports to the

project superintendent. The superintendent is the representative of the

contractor authorized to receive and fulfill instructions from the Engineer, and

he supervises and directs the construction~. Sometimes, several foremen

report to an operational superintendent. This additional tier of the project

hierarchy may be necessary on larger, more complex projects. The project

superintendent sometimes reports to an area superintendent, or he may report

directly to the central headquarters. Additional personnel on the project site

can provide specific support functions, such as a project engineer, who

performs engineering calculations for the project. Additionally, the contractor

may employ the use of office managers, project bookkeepers. and project

Page 54: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

37

surveyors to perform support functions. For the purposes of this paper, the

project superintendent is the person who negotiates with the State's project

team, and higher levels of authority may become involved as the dispute moves

up the ladder of the chain-of-command toward final resolution. Collectively,

these personnel are referred to as the Contractor: The individual, firm, or

corporation, or any combination thereof, Party of the Second Part, with which

the contract is made by the State ~).

CHAIN-OF-COMMAND DISPUTE RESOLUTION

Resolution at the Project Level

Dispute settlement at the project level takes the form of verbal, informal

conversations between the contractor and the SDHPT project team. The

contractor often includes the foreman under whose authority the dispute

started, as well as the project superintendent in these meetings. He may also

include his surveyor, representatives of the subcontractors, or other party

directly involved in the dispute. The project team includes the project engineer,

and the general construction inspector may be included to provide detailed

information. During these negotiations, the contractor presents his reasons for

the dispute, often making the statement that he is losing money because of

some action or inaction by the project team. The contractor may cite some

part or parts of the contract documents that he feels justify the dispute. The

project team often counters these disputes by citing their own selected

Page 55: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

38

specifications, or presenting a differing interpretation of the contractor's cited

references. Herein lies the basis for most unsettled disputes: the difference in

interpretation of clauses of the contract documents by the SOH PT and the

contracting industry.

Resolution at the Resident Engineer Level

When the dispute cannot be settled at the project level, the project

engineer reports the situation directly to the resident engineer in charge of the

project. The resident engineer is almost always considered to be the

authorized representative of the Engineer-Director, as defined by the 1982

Standard Specifications. Once again, there exists much variance across the

state, but usually, the resident engineer is the person in charge of design,

construction and maintenance for a particular area, commonly a county. There

are more than 125 Resident Engineer offices in the state, with each office

operating somewhat differently. One common thread, however, is the fact that

the contractors attempt to settle disputes with the resident engineer after

negotiations with project personnel have failed to produce an acceptable

solution. The negotiations at the residency level take on somewhat of a

different form than those at the project level. At the project level, the

conversations are usually concentrated on the interpretation of the contract

documents. At the residency level, however, field changes, supplemental

agreements, and/or time extensions may be proposed to settle the dispute.

The project engineer may draft these instruments, and the resident engineer

Page 56: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

39

recommends them for approval. Sample forms for field changes, extra work

orders. and supplemental agreements are included in Appendix E.

Resolution at the District Level

If the dispute still cannot be resolved, the next step in the resolution

process is a meeting with the district construction engineer. The contractor is

represented by the project superintendent, subcontractors. and/or foremen.

The project engineer and resident engineer usually attend the meeting. The

two parties present their sides of the dispute to the district construction

engineer, who attempts to resolve the dispute. The tools he may select from

to propose a resolution to the contractor are the same as those used by the

resident engineer - field change, extra work order. supplemental agreement,

time extensions, or any combination of these. The district construction

engineer may consult with the Construction Division in Austin (0·6) for

assistance with the dispute, or he may simply notify them that a possible claim

is in the making. The district construction engineer also notifies the district

engineer of this situation. Rarely does the district engineer actively participate

in the negotiations or the settlement of the dispute, rather. his office manages

the correspondence between Austin and the contractor.

Currently. there are dollar limitations for change order approval

associated with the levels of authority within the department. Starting at the

bottom of the chain·of-command, the project engineer has no express authority

to approve change orders. In practice, however, the project engineer may

Page 57: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

40

resolve small disputes at the project level by overrunning some project bid

items, thereby paying the contractor for the extra work as required by the

changed conditions. The project engineer must exercise caution in using this

practice, however, as the final project quantities and all over-budget items are

cfosely scrutinized. The resident engineer can also rely on this practice for the

resolution of some small disputes, with the same care. The resident engineer

must submit the written field change, extra work order, and/or supplemental

agreement to the district for approval. as he lacks the authority to approve

these changes himself. The district can approve changes to the plans not

exceeding $25.000. The district engineer himself may reserve this authority, or

he might delegate this authority to the district construction engineer. Changes

to the plans exceeding the district authority, but less than $50,000. can be

approved by the head of the construction division at the request of the district

engineer. Changes over $50,000, but less than $200.000, can be approved by

one of the deputy directors of the Department. Above $200,000, all changes

require the approval of the deputy Engineer-Director (1.a). Regardless of the

level of authority needed for approval within the district, the district proposes

the resolution to the contractor.

Resolution at the Central Headguarters Level

If the contractor is not satisfied with the proposal, the dispute will most

likely become a claim. If so, the three methods of settlement available to the

Page 58: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

41

contractor are the committee hearing, the administrative hearing. and litigation.

Figure 8 shows the percentage breakdown for the resolution of 60 claims from

1982 to 1988. To start the process, the contractor is required to submit a letter

of intent to file a claim to the district, who then notifies the administration, the

construction division, and most importantly, the claims committee. The

contractor is also required to file a petition to the Engineer-Director. After the

claim is filed, all communications are directed to the secretary of the claims

committee. From this point forward, district personnel provide information only,

and the construction division supplies information and expertise. The district

and the construction division collect documents that defend the state against

the claim (m). This process of document compilation may be difficult as claims

are filed an average of 30 months from project letting.

In conjunction with the filing of the claim, the contractor needs to provide

some form of documentation that supports both his position of entitlement and

the damages he incurred. Usually, multiple-part claims are broken down into

individual components. Each of the components may be further itemized to

simplify calculation of the total claimed amount. Whatever the breakdown of

the claim, each component is subjected to the test for validity: both entitlement

and actual damages must be shown (la). The question of entitlement is

determined by a thorough investigation of the events leading up to the claim,

so project documentation is vital. The determination of damages is based on

the records of extra expenses and costs, so original materials invoices, time

sheets, equipment logs, and the like are equally vital. The complexity and

Page 59: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Committee - 50 83%

Litigation - 3

5%

Administrative Hearing - 7

12%

Total of 95% within SDHPT resolution.

Figure 8. Resolution of Claims Against SDHPT, 1982 to 1988.

42

Page 60: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

43

magnitude of the contractor's claim submittal often is proportional to the size

of the claim and varies from several pages of documentation to several

hundred (2).

After the claim is received, the Department fully investigates the validity

of the claim. This investigation starts with a full review and analysis of the

documentation provided by the contractor and district alike. The committee

initiates any correspondence necessary to clarify questions of fact. There are

three initial lines of action from which to choose. The Department may elect to

propose a settlement to the contractor immediately if the claim is deemed to

be valid. The Department may feel a hearing before the claims committee is

warranted, and a meeting is scheduled. Finally, the Department may return the

claim to the contractor along with reasons for doing so. Usually, the claim is

scheduled to be heard before the claims committee (lll).

Once a committee hearing has been scheduled and agreed upon, the

contractor and district representatives are notified. These two parties gather

any remaining documents, arrange for key personnel to attend, and meet in

Austin for the committee hearing. The fomat of the hearing is informal, and the

attendance of attorneys is discouraged as the presence of legal counsel often

restricts the free flow of conversation. Both sides of the dispute make opening

statements to begin the hearing, then the contractor ·presents his arguments

to substantiate the claimed values. The contractor often includes calculations,

documents, testimony, and other proof of damages and entitlement in his

presentation. The district then rebutts the claimed points, referring to plans,

Page 61: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

44

specifications, and departmental policies as pOints of reference in their defense.

The committee members may ask questions of the contractor and/or district

necessary to clarify facts and gain a thorough understanding of the dispute.

The district and contractor then offer final comments. and the process

continues to the next part of the claim, if necessary.

After the claim is discussed to the satisfaction of the committee. the

chairman asks the district and contractor representatives to leave the room

while each item is discussed internally. The committee addresses each point

of claim and discusses these pOints until at least two of the three members

agree on the proposed settlement. The parties re-enter the room, then the

committee chairman discusses reasons for agreement and/or disagreement

with the points of claim. He also discusses the methodology used for arriving

at the offered amounts. The chairman explains that the findings of the

committee will be sent to the contractor by mail. If the contractor intends to file

for an administrative hearing, he is required to respond within 20 days. The

contractor and district are allowed to respond to the findings of the claims

committee.

Should the contractor be dissatisfied with the resolution as proposed by

the committee. the first step in the appeals process is to file for an

administrative hearing. The Engineer-Director of the Department selects the

hearing officers. Commonly lone of the officers is a high-ranking departmental

employee, such as a district engineer or division head not associated with the

claim. The other member is usually a neutral party selected from outside the

Page 62: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

45

Department, and is commonly an attorney familiar with the construction

industry. The Engineer-Director designates one of the members as presiding

officer. The proceedings before the hearing officers closely follow the

procedure as before the claims committee US}.

Should the contractor still not believe he has received the relief he feels

entitled to, his last recourse is to bring suit against the Department (19). A

detailed discussion of the procedures after the claim has left the control of the

Department is not presented here, as it is beyond the scope of the research.

Also, only three out of the 60 claims filed against the State from 1984 to 1990

have gone entirely through the departmental process and into litigation. The

emphasis should be placed on reducing the number of disputes to prevent

them from becoming claims; the number of claims going to court should be

reduced accordingly.

General Observations

The author attended a hearing of a contractor claim before the claims

committee in August of 1990. While the details of the claim are not revealed

to protect the anonymity of the parties, a brief discussion of the author's

observations of the meeting follows.

First, the committee seemed genuinely interested in resolving the claim

fairly. The members attempted to view the contractor's pOints of view with a

high degree of impartiality. They did not seem to feel pressured to pay the

contractor as little as possible, but rather to do what is right and fair. The

Page 63: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

46

chairman stated that the committee is responsible to several parties in resolving

the claim. First, it is responsible to the taxpayers of the state of Texas to

defend their interests. He realizes that contractors who go out of business

reduce the competitiveness of the bid process, thereby lowering the value of

the construction dollar. Second, the committee owes responsibility to the

district, to protect its interests and to keep from undermining its authority.

Third, the committee owes responsibility to the contractor, to attempt to

equitably resolve his claim. Finally. the committee owes responsibility to the

second*lowest bidder. The committee could not justify awarding the low bidder

with enough claim dollars to push the total contract price over that bid price

submitted by the second lowest bidder unless careful consideration is given to

the validity of the claimed changed conditions.

Indirect Cost of Dispute Resolution

As the dispute moves through the departmental chain-of*command, a

great deal of time is spent at each level. Consequently. a great deal of money

is also spent. Table 3 shows the calculation of an estimate of the indirect cost

of handling these disputes by the Department. The estimate of time spent from

the project through district levels is based on results of the SDHPT survey. The

responses to the survey were averaged within each level of the Department.

The total number of hours was calculated by multiplying the survey estimate by

the number of projects, residencies, and districts. The estimate of time spent

within the 0·6 Claims Section was determined by averaging the number of

Page 64: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

47

Table 3. Yearly Estimate of Indirect Costs for Claims.

Title Hours Pay Total Week Year on Year Year

Proj. Engr. 3,647 189,644 $32,400 $2,954,070 ~taff 5,291 275,132 $2,000 $24,000 $3,174,600 ~es. Engr. 702 36,504 $3,200 $38,400 $673,920 Staff 1,911 99,372 $2,000 $24,000 $1,146,600 Dist Const Engr. 115 5,980 $3,750 $45,000 $129,375 Staff 118 6,136 $2,000 $24,000 $70,800 Dist Engr. 60 3,120 $4,500 $54,000 $81,000 Staff 247 12,844 $2,000 $24,000 $148,200 D-6 Claims Section 161 8,375 $4,000 $48,000 $193,275 Yearly Total 637,107 Yearly Total $8,571,840

Plus 33% for OH $2,828,707

Grand Total $11,400,547

Page 65: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

48

hours dedicated to claim resolution over the past four years. This information

was compiled from the records kept within the claims section. Finally, the

average salaries used to calculate the total indirect cost were estimated using

the departmental pay structure.

As the evidence shows, the indirect cost of dispute settlement is

significant. The $11.4 million represents 2.85 percent of the total SDHPT

annual payroll. When combined with the direct cost of claim settlement, the

total cost of claims and disputes to the Department is $12.83 million annually.

The indirect costs, therefore, represent 88.9 percent of the total cost of claims

and disputes to the Department annually. Three-quarters of a percent of the

fiscal year 1990 construction budget was depleted because of these claims and

disputes. In terms of the average project, this money could be used to

construct an additional 6.5 projects annually.

Page 66: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

49

CHAPTER III

SURVEY OF SDHPT PERSONNEL

GENERAL

As previously stated. the primary objective of the research effort was to

provide insight into the problem of construction claims against the SDHPT.

One method for accomplishing this goal was to send surveys to SDHPT

personnel. The sample targeted 300 SDHPT personnel. including all of the

district engineers and district construction engineers (24 each), all of the

resident engineers (126 each). and one project engineer from each resident

engineer's office. The targeted group represents a sample skewed toward the

lower levels of authority because the largest number of disputes are handled

at this level. The results should therefore truly indicate the nature of the

problem. Since the district construction engineers handle the upper level

disputes and claims, input from these personnel is valuable. The district

engineers were included in the sample because they handle correspondence

concerning claims and are required to approve major changes in contract

amounts in the form of field changes and supplemental agreements. A sample

survey form is included in Appendix A.

Questions on the survey form could be broken down into several

groups. First. Questions 1 through 4, and Question 16 provided general

Page 67: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

50

information only. Questions 5.1 and 5.2 divided the potential problem areas

within the state into four categories: contractor practices, SDHPT practices,

contract documents, and contract administration. Questions 6 through 7, and

Question 13 determined problems with the chain-of-command process followed

by the state for dispute resolution. Questions 8 ascertained the frequency of

contractors who use disputes as sources of extra profits. Question 9 followed­

up the previous question, and determined the percentage of contractors who

do so. Questions 10, 11, 14 and 15 provided information necessary for the

determination of the indirect cost of the dispute resolution process. Question

12 determined the most frequently used tool for dispute resolution. Finally,

Questions 17 through 21 determined SDHPT opinions of a specifiC measure

which can be taken to prevent future claims and provided ample space for

written comments.

After the completion of the design of the survey form, copies were sent

to the administration of the Department for review and comments. The form

was reviewed by members of the administration and of the construction division

for content and clairty of the questions. Several comments and corrections

were used in preparing the final survey form. The final form was sent back to

the construction division for distribution through the SDHPT mail system. Each

survey form was accompanied by a cover letter detailing the targeted group

and instructions for completion. Also, an envelope to be used to return the

survey to the researchers was included. Each survey form was to be returned

separately to protect the anonymity of the respondents.

Page 68: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

51

STATISTICAL ANALYSIS METHODOLOGY

The methods for analyzing the results of both the SDHPT and contractor

surveys varied depending upon the format of the question. Questions with

"yes" or "no" type of answers were arranged into tables to allow the use of the

chi-square test for equality of multinomials. Only the "yes" answers for each of

these questions were considered. The observed frequency, Oji' therefore

represents the total number of "yes" responses. Figure 9 shows the general

format used for performing the chi-square tests. The research hypothesis for

the analysis of dichotomous questions was as follows:

Ho : The responses to the questions are distributed the same.

Ha: The distributions differ.

Test Statistic :

Where:

c R,. L 0,

/-1

Page 69: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

52

Levels of respondents or responses

1 2 3 4 j . c

1

2

3

Questions i 0'1 Ri

.

. r

q N

Test Statistic:

Where : 0ij represents the response to Question "i" by respondent "j" or response alternative "j."

E, _ R~CI

c

R, - 1: 0, 1-1

r

C, - 1: 0, 1-1

R "etR' 2 2 eJe eglon: X CIIIc - X dt'-(r-1, c-1) (a- 0.05)

Figure 9. The Chi-Square Test for Equality of Distributions

Page 70: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

53

A 'ctA' 2 2 eje eglon: X CIl1c - X dI-(r-1, c-1) (a- 0.05)

The chi-square test was also used to test for significant difference

among the levels of respondents for all questions where multiple responses

were possible, except for the categorical questions of contractor practices,

state practices, contract documents, contract administration, and resolution

alternatives, The major assumptions satisfied in order to use this test are:

independent, repeated trials, multiple possible responses, and the probability

of these responses was unchanged over the trials, The survey as a whole

could be considered a stratified sample, with district engineers, district

construction engineers, resident engineers, and project engineers representing

individual levels of responses. The research hypothesis for this type of analysis

was as follows:

Ho : The responses to the questions are distributed the same,

Ha : The distributions differ.

Test Statistic :

Page 71: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

54

R 'ctR' 2 2 eJe eglon: X calc - X df-(r-1. C-1) (a.- 0.05)

The surveys included five categorical questions representing contractor

practices, SDHPT practices, contract documents, contract administration, and

alternatives for dispute resolution. Each categorical question included from

three to 12 individual factors. The intent of the survey data analysis was to

determine if significant differences existed between the individual factors, as well

as between the levels of respondents. A procedure was needed which could

determine not only if significant differences existed in the variables, but also

locate the individual sources of the differences.

These tests were performed using the CATMOD (CATegorical data

MODeling) procedure on Statistical Analysis System (SAS). This procedure met

the requirements of the analysis as stated above. CATMOD is designed solely

for the analysis of data that can be represented in a chi-square table, Basically,

CATMOD fits a log-linear model to a function of the response frequencies, and

develops an analysis of variance (ANOVA) table. The significance of the

variables in question can be tested directly using this table, as the degrees of

freedom, chi-square statistics, and probabilities for each variable are reported.

The chi-square statistic generated by the CATMOD procedure is calculated

similarly to the conventional chi-square. The main difference lies in calculation

of the expected cell values. The expected cell value is calculated using the Eij

equation as shown in Figure 9 for the normal chi-square. By way of

Page 72: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 73: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

55

comparison, CATMOD uses an iterative process to generate a maximum

likelihood estimate of each parameter. This estimate of each parameter

maximizes the value of the joint multinomial likelihood function of the response,

thereby locating of the individual sources of differences WZ). These estimates

show how each parameter varies from the overall mean. For the analysis of

the survey data, a negative value indicates the parameter is more critical than

the overall mean. The CATMOD procedure calculates the chi-square statistic

for all but the last parameter within a category. The estimate for the excluded

parameter can be calculated from knowledge that the sum of the estimates

must equal zero. The chi-square and probability statistics, however, cannot be

readily calculated. A detailed account of the statistical testing procedure, and

sample CATMOD input and output are presented in Appendix C.

The research hypothesis for the CATMOD procedure required a two-step

analysis. The null hypothesis tested for equality of three parameters:

respondent, category, and interaction between the two. The research

hypothesis for this initial test was as follows:

Ho : The responses to the questions are distributed the same.

Ha : The distributions differ.

Test Statistic:

Page 74: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 75: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

56

Where : Ej = Maximum likelihood parameter estimate.

Reject Region: X2 c::ak - X2 oY-(k-1) (a - 0.05)

Where : k = number of estimated parameters.

If the initial hypothesis could be rejected, the secondary analysis

determines the parameters which differed significantly from the overall mean.

The research hypothesis for this test was as follows:

Ho : The parameters are equal.

H. : The parameters are not equal.

Test Statistic :

Where : Ej = Maximum likelihood parameter estimate.

Reject Region :

Finally, the contractor survey contained two similar questions (Questions

6 and 12) which were tested for equality of binomial distributions. The research

hypothesis for this test was as follows:

Ho : The binomial distributions are the same.

Page 76: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

57

H. : The binomial distributions differ.

D:1 -~ z - -;:::============ Test Statistic: caJc I

fi (1-fi) + D: (1-iQ n1 ~

Where:

Reject Region: !Zcalc! > Z (a =0.025)

For all tests which were conducted using SAS, the reject regions were

calculated internally, and the probability for each null hypothesis being true was

generated and printed. These values were compared to the alpha level. If the

calculated probability was less than the alpha level, the hypothesis was

rejected: otherwise, it could not be rejected. In other words, if the calculated

probability value is less than 0.05, the responses to the questions differ

significantly. The results of statistical tests other than those performed using

the CATMOD procedure are presented in Appendix D.

Page 77: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

58

RESULTS OF THE SDHPT SURVEY

A total of 276 survey forms were completed and returned, representing

a 92 percent response rate. The responses were as follows: 16 district

engineers, 23 district construction engineers, 120 resident engineers, 112

project engineers, and five general construction inspectors. The results from

the individual groups and the combined results are reported in Appendix B.

Although the general construction inspectors were not part of the intended

sample, their responses were included in the combined results portion of

Appendix B. The responses from the general construction inspectors,

however, were not used in statistical analyses for several reasons. First, only

five responses were received from this group, and this sample is not of

sufficient size to be considered representative of the population. Second, the

intended response group did not include this position. Finally, the lack of

authority for the inspectors to settle disputes precluded them from properly

answering some of the survey questions.

Response Rates of the SDHPT Survw

The first step in statistical analysis of the data was to analyze the

response rates for each individual question. These response rates are shown

in parentheses immediately following each of the questions in Appendix B.

Question 2 was the most difficult to answer, as indicated by the low (67.0%)

response rate. One possible explanation for the low response rate is the higher

Page 78: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

59

degree of difficulty in ranking from one to ten. Another possible explanation is

due to the additional time required to answer this question. The second most

difficult question was Question 15, which had a response rate of 95.3 percent.

The probable source of difficulty with this question is the need to estimate the

man-hours spent handling disputes: The state currently has no method of

measuring time spent handling disputes in the form of time-charge codes. All

other questions had response rates of over 97 percent, with the usual response

rate of approximately 99 percent. These response rates indicate only minimal

problems with the questions.

Discussion of Results of the SDHPT Survey

According to the combined survey results, the most common value of

disputes is in the $1,001 to 5,000 range, followed by $5,001 to 10,000 range,

and then $10,001 to 20,000. The smallest range, $0 to 1,000 was ranked

fourth by the respondents. The larger ranges ranked in order of increasing

value, occupying the ranks of five to ten, respectively. There was no solid

agreement among the levels of the respondents as to the most common value

of disputes. The upper levels handle the larger disputes. According to the

survey, the district engineers and district construction engineers encounter

disputes in the $5,001 to $20,000 range. The project engineers and resident

engineers encounter disputes in the $1,001 to $5,000 range. This trend

indicates the smaller disputes are handled at the lowest levels. The project

engineers and resident engineers tend to take the larger disputes to their

Page 79: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

60

superiors for assistance or settlement. The difference between the responses

proved to be insignificant statistically.

The combined survey responses revealed either a lack of knowledge

about dollar limitations for dispute resolution, or a poorly designed question in

the survey. Only 34.1 percent of the respondents stated they were aware of

such a dollar limitation. Question 4 was designed to be a follow-up to the

previous question. Again, there was no evidence that the question was

answered as designed, or that the SDHPT personnel were aware of their

limitations, as shown by the 46 answers under the "Don't know limit" selection.

Because the responses to these questions seem unreliable, additional analyses

of the data were not warranted, thus none were performed.

The following paragraphs present the findings of the categorical analyses

for contractor practices, SDHPT practices, contract documents, and contract

administration. Appendix C presents a detailed description of the statistical

calculation process and the interpretation of the results. The average ratings

by each level of respondent are presented for each factor in tabular form. Also,

the overall average rating for the category as a whole is presented, along with

overall averages by level of respondent. For comparison purposes, the lower

the average response, the more critical the rating. Under the individual levels

of respondents, and under the "average" column, the most critical problem

areas are identified using heavy lines.

The analysis of the contractor practices category revealed some

significant differences. First, the four levels of respondents answered

Page 80: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

61

differently, as shown in Table 4 (Ratings of Contractor Practices). The district

engineers rated the contractors the most severely, followed by the district

construction engineers, the project engineers, and the resident engineers. The

analysis also revealed that poor planning by the contractors was the most

significant problem. All four levels of respondents shared this opinion.

Inadequate investigation before bidding was also considered to be a significant

problem. The levels of respondents disagreed on the severity of this problem,

however, as the district engineers and district construction engineers rated this

factor more severely than did theresident engineers and project engineers.

Finally, the analysis revealed the use of wrong equipment to be significantly

less of a problem than the other categories.

Under the SDHPT practices category. the respondents again provided

significantly differing opinions. The district engineers rated the Department

most severely, followed by the resident engineers and district construction

engineers. The project engineers provided the most lenient rating. Looking

only at the average rankings by each of these groups, the differences seem

insignificant. The rankings for individual factors, however, differ Sufficiently to

result in a statistically significant difference. For example, the district engineers

selected contract requirements as the top problem area, while the district

construction engineers felt changes in plans and specifications presented the

most difficulty. None of the individual factors can be considered to be

significantly different from the others. The average responses are presented

in Table 5 (Ratings of SDHPT Practices).

Page 81: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Table 4.

Var.

CP1

CP2

CP3

CP4

CP5

CP6

CP7

CP8

CP9

CP10

I

62

Average Ratings of Contractor Practices by SDHPT Survey Respondents

Description Avg. DE DCE RE PE

Inadequate 3.05 2.56 2.74 3.08 3.13 investigation

Bidding below cost 3.12 3.06 3.00 3.17 3.12

Wrong equipment 3.78 3.75 3.87 3.88 3.63

Failure to follow 3.45 3.19 3.61 3.55 3.35 procedure

Unbalanced bidding 3.47 3.31 3.30 3.56 3.45

Poor planning 2.90 2.50 2.87 2.92 2.91

Overoptimism 3.52 3.69 3.30 3.60 3.47

Delay by contractor 3.36 2.44 3.00 3.38 3.54

Delay by 3.16 2.88 3.04 3.29 3.12 subcontractor

Delay by supplier 3.81 3.50 3.78 3.80 3.88

I Overall averages I 3.36 3.09 3.27 3.43 3.38

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

4 Minor

Problem

5 No

Problem

Page 82: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Table 5.

I Var.

SP1

SP2

SP3

SP4

SP5

SP6

63

Average Ratings of SDHPT Practices by SDHPT Survey Respondents

Description Avg. DE DCE RE PE II Changes in plans 3.48 3.63 3.43 3.47 3.46 and specifications

Inadequate bid 3.86 3.75 3.87 3.83 3.91 information issued

Contract 3.45 3.31 3.70 3.45 3.41 requirements

Overly restrictive 4.04 3.75 4.04 4.01 3.13 specifications

Delay by SDHPT 3.72 3.75 3.74 3.70 3.76

Inadequate time for 3.88 3.63 3.70 3.81 4.02 bid preparation

Overall averages 3.76 3.67 3.75 3.73 3.79

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

4 Minor

Problem

5 No

Problem

The analysis of the contract documents category yielded more serious

results than the SDHPt practices category. The levels of respondents differed

significantly. As can be seen in Table 6 (Ratings of Contract Documents), the

district engineers, district construction engineers, and resident engineers

selected ambiguities in the plans and speCifications as the major problem area.

Page 83: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

64

Table 6. Average Ratings of Contract Documents by SDHPT Survey Respondents

Var. Description Avg.

CD1 Errors in plans 3.23

CO2 Ambiguities in plans 3.22 and specifications

CD3 Omissions in plans 3.28

Overa" averages 3.26

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

DE DCE

2.94 3.13

2.81 3.09

2.88 3.13

3.07 3.12

4 Minor

Problem

RE PE

3.30 3.20

3.21

3.26

3.26

5 No

Problem

3.29

3.37

3.29

The project engineers selected errors in the plans as the most severe problem.

This difference in opinion led to the significant differences between the levels

of respondents. Because the variation between the individual factors is small,

the factors were not determined to be significantly different.

The analysis of the contract administration category revealed significant

differences between the respondents, but not between the individual factors.

The district engineers provided the most severe rating. The district

construction engineers, resident engineers, and project engineers followed in

order. These four levels of respondents were within one-hundreth of a point

from unanimous agreement ofthe most critical problem area. Table 7 (Ratings

Page 84: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Table 7.

Var.

CA1

CA2

CAS

CA4

CAS

CA6

CA7

CAB

CA9

CA10

CA11

65

Average Ratings of Contract Administration by SDHPT Survey Respondents

Description Avg. DE DCE W!W PE

Lack of coordination 3.44 3.19 3.48 3.53 3.41 between contractors

Personality conflicts 3.70 3.31 3.43 3.80 3.73

Requests for time 3.63 2.81 3.70 3.66 3.74 extensions

Delays in processing 3.72 3.44 3.87 3.74 3.73 SDHPT paperwork

Quantity 3.82 3.56 3.74 3.90 3.80 disagreements

Construction 3.78 3.63 3.65 3.81 3.83 acceptance or rejection

Interpretation of 3.40 2.75 3.26 3.54 3.38 plans and specs

Time charges 3.87 3.31 3.65 3.88 4.03

Extra work 3.72 3.25 3.70 3.70 3.83

Delays in providing 3.59 3.56 3.61 3.62 3.60 clear right-of-way

Materials acceptance 3.93 3.31 3.78 3.97 4.04 or rejection

Overall averages 3.75 3.52 3.62 3.75 3.81

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

4 Minor

Problem

5 No

Problem

Page 85: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

66

of Contract Administration) shows the district engineers, district construction

engineers, and project engineers felt that interpretation of the plans and

specifications provided the most difficulty. The resident engineers felt that the

lack of coordination between contractors was the most critical problem.

Overall, the category of SDHPT practices is only a minor problem area.

Finally. the four categories of dispute-related factors were compared to

determine the main source of problems. The analysis revealed significant

differences between the levels of respondents and the categories of factors.

As shown in Table 8 (Ratings of All Categories), the district engineers rated the

four categories the most severely. The district engineers, resident engineers,

Table 8.

CP

SP

CD

CA

Average Ratings of All Categories by SDHPT Survey Respondents

Avg. DE DCE RE PE

Contractor 3.36 3.09 3.27 3.43 3.38 practices

SDHPT practices 3.76 3.67 3.75 3.73 3.79

Contract 3.26 3.07 3.12 3.26 3.29 documents

Contract 3.75 3.52 3.62 3.75 3.81 administration

Rating Scale:

1 2 3 4 5 Critical Severe Major Minor No Problem Problem Problem Problem Problem

Page 86: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

67

and project engineers followed in order. All four levels of respondents selected

the contract documents as the most critical problem area. This agreement

between the respondents resulted in the significant differences between the

categories of factors.

Question 6 quantified the problem of contractors bypassing levels of

authority to get disputes resolved. The combined results of the survey

indicated a favorable response, as 62.0 percent answered "rarely" or "almost

never." Only 9.0 percent of the respondents answered unfavorably. As could

be expected. the highest three levels of authority felt they were bypassed at a

lower frequency than did the project engineers. This difference was reflected

in the calculation of the Chi-square statistic, which was significant at the 0.05

level. Nearly one-half of the project engineers (48.2<'1&) felt they were bypassed

·sometimes" or more often. The resident engineers also felt they were

bypassed too often, but the fraction of responses in the "almost always" to

"sometimes" range was only 3O.S percent. This points to a trend where

contractors take disputes to the level of authority where they feel immediate

resolution is possible. The results to this question, as well as other multi­

answer questions are summarized in Table 9 on the following page.

Table 9 also summarizes the responses to Questions 7.1 through 7.3.

These questions further investigated the problem of bypassing levels of

authority by subdividing the process into several parts. Question 7.1

determined the extent to which superiors contact the office of origination for

Page 87: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Table 9.

Number

6

7.1

7.2

7.3

68

Summary of Average SDHPT Responses to Multiple-Answer Questions

Question Avg. DE DCE RE ~I Contractors bypass 3.72 4.06 4.04 3.87 3.51 levels of authority?

Superior gets input 1.43 1.31 1.22 1.35 1.58 before deciding?

Contractor returned 2.28 1.44 1.83 1.93 2.83 for decision?

Superior decides, 3.13 3.50 3.74 3.53 2.58 then informs you?

Rating Scale:

1 Almost Always

2 Frequently

3 Sometimes

4 Rarely

5 Almost Never

input before making a decision. Most of the responses were favorable, as 86.3

percent answered Hal most always" or 1requently". Only a small number

responded totally unfavorably, as less than five percent answered "rarely" or

-almost never". Even though the project engineers felt they were consulted less

frequently than did the upper levels of authority, ·this difference was not

Significant.

Question 7.2 determined the frequency that superiors send contractors

back to the office of origination for decisions. Most of the answers were

somewhat favorable, as 56.1 percent responded "almost always" or ''frequently.''

Page 88: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

69

Only 16.0 percent answered unfavorably. There was a marked difference in

opinion reflected in the responses to this question. The project engineers

responded Significantly lower than the other three levels of authority, with only

37.5 percent of the responses being in the "almost always" to "frequently"

range. By way of comparison, the upper three levels of respondents averaged

68.8 percent in this same range.

Finally, Question 7.3 attempted to ascertain the frequency that the

decision is made at the upper levels of authority, but the office of origination is

informed of the decision. Several respondents commented about this question,

saying it is two questions in one. For this reason, the responses are not clear

and were not considered for analysis.

Question 8 determined the SDH PT's opinion concerning contractors who

use disputes as sources of extra prOfits. The majority of the SDHPT

respondents answered affirmatively (87.7%). The responses to this question

are summarized in Table 10. Question 9 was a follow-up to the prior question

intended to quantify the number of contractors who look for disputes as

sources of extra profits. Calculation of the mean response based on the

midpOints of each category yielded a 20.1 percent average. All four levels of

Table 10. Summary of SDHPT "Yes" Responses to Question 8 (Percent)

Number Question Avg. DE DCE RE PE

8 Contractors seek extra 88.3 93.8 100.0 89.1 84.7 profits using claims?

Page 89: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

70

respondents were significantly in agreement in their responses to these

questions.

Questions 10 and 11 determined the number of disputes encountered

at each of the positions sampled and the perceived percentage of disputes

settled at these levels. Once again, the midpoint of each range was used to

calculate the means. From the combined results, the average number of

disputes encountered per week was 3.9, and of these disputes, 3.3 (85.3%) are

settled. All four levels of authority substantially agreed in their responses to

these two questions. As could be expected, the project engineers and resident

engineers tended to encounter more disputes per week (4.4 and 3.9,

respectively) than the district construction engineers and district engineers (3.4

and 2.5, respectively). The percentage of dispute resolution was the lowest for

the project engineers (79.9%), peaked at the residency level (90.3%), then fell

off slightly for the district construction engineers and district engineers. Again,

these differences are not significant at the 0.05 level.

The analysis of the responses to Question 12 was similar to the analysis

performed for the other categorical questions. This analysis revealed significant

differences between the levels of respondents and between the individual

alternatives. Overall, the field change alone and the combination of the field

change and supplemental agreement were selected as the most commonly

used dispute resolution alternatives. The supplemental agreement alone was

the third most frequently used. These three alternatives were determined to be

used significantly more often than the others. Table 11 (Dispute Resolution

Page 90: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

71

Table 11. Average Ratings of Dispute Resolution Alternatives by SDHPT Survey Respondents

Var. Description Avg.

AL1 Extra work order 3.02

AL2 Field change 2.43

AL3 Supplemental 2.67 agreement

AL4 Field change and 2.43 supplemental agreement

AL5 Agreement between 3.05 PE and contractor

AL6 Agreement between 2.98 RE and contractor

AL7 Agreement between 3.93 DCE and contractor

ALa Agreement between 4.28 DE and contractor

AL9 Time extension 3.32

Rating Scale:

1 Almost Always

2 3 Frequently Sometimes

DE

2.81

2.06

2.56

2.50

3.44

3.31

3.94

4.19

2.94

DCE

2.78

2.21

2.21

2.13

3.35

2.96

3.87

4.26

2.96

4 Rarely

RE

3.12

2.47

2.70

2.43

3.29

3.16

4.24

4.46

3.33

5 Almost Never

PE

3.02

2.47

2.76

2.51

2.68

2.77

3.71

4.21

3.28

Page 91: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

72

Alternatives) shows the most frequently used dispute resolution alternatives as

selected by all four levels of respondents to be either the field change alone.

or the combination of the field change and supplemental agreement. The

analysis also revealed two alternatives which are used significantly less often

than the others. These are the informal agreements between the upper levels

of authority (district engineers, district construction engineers) and contractor.

Question 13 determined the timeliness of receiving answers to dispute­

related questions from the upper levels of authority. Nearly all of the responses

were favorable. as 90.6 percent responded either "almost always" or

"frequently.· Only 1.8 percent responded unfavorably. The respondents were

in significant agreement to this question. Table 12 presents the responses to

this question for comparison purposes.

Questions 14 and 15 quantified the number of hours spent per week

handling disputes. The average respondent spends five hours per normal

week handling disputes, and the average staff spends 10.6 hours per week

Table 12. Average SDHPT Responses to Question 12

Number Question Avg.

13 Receive answers in 1.51 a timely fashion?

Rating Scale:

1 Almost Always

2 Frequently

3 Sometimes

DE DeE

1.38 1.43

4 Rarely

RE

1.54

5 Almost Never

PE

1.52

Page 92: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

73

handling disputes. The project engineer and his staff spend 12.5 hours per

week handling disputes. The resident engineer and his staff spend 20.1 hours

per week, followed by the district construction engineer (9.7 hours) and the

district engineer (12.8 hours). It is interesting that the district engineers

estimated their staff to spend more time on disputes (10.3 hours) than do the

district construction engineers. The responses for these two questions were

not determined to be significantly different.

Question 16 revealed the SDHPT's familiarity with its own claims

resolution and prevention policy. Of the personnel sampled, 85.1 percent said

they were familiar with this policy. There was no evidence of significant

differences among the responses to this question. One would expect the

upper levels of authority to be intimately familiar with the departmental policy

on claims resolution. The district construction engineers were in agreement

with this theory. In fact, Table 13 shows the district construction engineers

unanimously responded "yes" to the question. The district engineers, however,

responded less favorably than the district construction engineers and the

resident engineers. Only the project engineers responded at a lower rate than

the district engineers.

Questions 17 and 18 ascertained the opinion of the respondents

concerning a specific method to lower the number of disputes and then help

the state defend itself against the disputes which become claims. This method

is to require contractors to submit formal, written, itemized notices of disputes

to district personnel. Of the personnel sampled, 64.9 percent thought this

Page 93: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

74

Table 13. Summary of SDHPT ''Yes" Responses to Questions 16, 17, 18, and 20. (Percent)

Number Question Avg. DE DeE RE PE

16 Familiar with SDHPT 85.5 87.5 100.0 93.3 74.8 claims pOlicy?

17 Can written notice 64.9 SO.O 52.2 65.8 67.0 lower claims?

18 Can written notice 75.7 75.0 60.9 93.3 76.8 defend claims?

20 More claims due to SO.4 56.3 56.5 47.9 48.6 Texas economy?

process would reduce the number of disputes, and 75.7 percent felt this

process would help defend the state against those disputes which became

claims. At the upper levels of authority, the opinions expressed were nearly

equally divided. At the lower levels, however, the responses were more

strongly in favor of this requirement, as approximately two-thirds of the project

engineers and resident engineers answered "yes" to the first question. All of

the respondents significantly agreed that requiring the contractors to submit the

written notice would help defend the state against claims. The resident

engineers were the most supportive of this concept, as 93.3 percent were in

favor of it versus only 6.7 percent against it. The district construction engineers

were the least supportive of this idea, as only SO.9 percent answered "yes."

Several district construction engineers commented that this process would only

create additional paperwork. The possibility of increased paperwork probably

Page 94: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

75

led to a less favorable response. These responses are summarized in Table

13 on the previous page.

Question 19 allowed the respondents to make written comments. These

comments were compiled and tabulated according to the position of the person

making the comment. The ten most frequently made comments are shown in

Table 14. The most frequently made comment expressed the need for better

plans and specifications, as over 24 percent of the respondents commented in

this fashion. This reinforces the responses to Question 5.2, contract

documents.

Finally, Question 20 determined if the current Texas economy created

a climate more conducive to claims, while Question 21 allowed written

comments to follow-up the prior question. The responses to the initial question

show a nearly equally divided opinion. Of the 272 responses to this question,

137 "yes" and 135 Rno· responses were recorded. At the individual response

levels. the breakdown of responses closely approximate equal splits.

Consequently, no significant difference was detected among the levels of

authority. The two most frequently made comments to Question 21 were

increasing competition for projects and contractors bidding too low. Both of

these comments directly reflect the poor state of the Texas economy, as many

contractors who did not previously engage in highway construction may have

resorted to this type of project to pay bills. This, in turn, leads to an increase

in the number of bidders. The probability of a claim arising from an otherwise

small change in the plans or delay is thereby increased. In contrast, the third

Page 95: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

76

Table 14. Ten Most Common SDHPT Comments to Question 19.

TOT DE Comment

67 2 6 26 33 Better plans and specifications.

25 3 3 16 3 Be fair but firm with contractors.

24 1 2 9 12 Better trained, educated, experienced SDHPT project personnel.

21 1 3 12 5 Timely response to problems.

17 3 0 8 6 Better project documentation.

14 2 1 7 4 Better prequalification standards.

13 1 0 7 5 More authority to RE and PE.

13 1 4 5 3 Better project level communication.

10 0 2 5 3 Allow more time for bid preparation.

10 0 1 2 7 Maintain partnership attitude.

Page 96: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

77

most common comment is the increase in out-of-state contractors. While this

increase adds to the effect noted above, it does show the economy in Texas

to be better off than in some other states. This apparent contradiction sheds

some light on the nearly equal division of opinions to the previous question.

Table 15 presents the ten most frequently made comments by SDHPT

respondents to Question 21.

Page 97: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

78

Table 15. Ten Most Common SDHPT Comments to Question 21

f~T DE DeE RE p==.Jl Comment

25 0 2 15 8 Increasing competition for projects.

20 1 2 5 12 Contractors bidding too low.

19 2 1 9 7 Increase in out-of-state contractors.

18 0 1 4 13 Contractors using claims as extra profits.

17 1 2 8 6 Introduction of claims consultants & lawyers.

15 3 1 8 3 Claims Committee too free with settlements.

14 2 1 7 4 Increasingly litigious society.

14 1 1 4 8 Poor plans and specification quality.

12 0 0 6 6 Unskilled Contractor supervisors.

8 0 0 5 3 Inexperienced SDHPT personnel.

Page 98: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

79

CHAPTER IV

SURVEY OF CONTRACTORS

GENERAL

To determine the major problem areas within the state from the

contractors point-of-view, 200 surveys were sent to contractors who do

highway construction for the Department. A sample survey form is included in

Appendix A. The contractors were randomly selected from the prequalified

contractors list issued by the State, then grouped into two categories according

to size. Members of the Associated General Contractors (AGC) Highway

Specifications Task Force and the Joint AGC/SDHPT Committee were included

in the sample.

Questions on the survey form could be divided into several groups.

First, Questions 1 and 2 provided general information only. Questions 3.1 and

3.2 determined the major problem areas within the state. Questions 4 and 5

determined problems with the chain-of-command process followed by the state

for dispute resolution. Questions 6 through 12 targeted the number of

contractors who use disputes as sources of extra profits, as well as to correct

bidding mistakes. Questions 13 14, 16 and 19 determined the contracting

community's opinion of the current system for dispute resolution used by the

state. Question 15 determined the most frequently encountered dispute value.

Page 99: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

80

Finally, Questions 17 and 18 determined how the current Texas economy

affects the number of claims, and allowed free form comments from the

respondents.

The SDHPT and the contractor surveys shared 16 common questions,

with five of the questions being multi-part, categorical questions. The remaining

questions in the contractor survey differ only slightly from those in the SDHPT

survey. First, the general information questions were structured to reflect the

organizational differences between the contractors and the SDHPT. Second,

at the request of the AGe Executive Committee, "Utilities not adjusted" was

added to the SDHPT practices portion of Question 3.1, as was "Over-usage of

'As directed by the Engineer'" under the contract administration portion of

Question 3.2. Next, questions regarding the SDHPT chain-ot-command were

altered to determine the contractors' opinions. The questions dealing with extra

profits were expanded to differentiate between claims for extra profits and

claims to minimize losses resulting from bidding errors.

As with the SDHPT survey, the survey was reviewed by members ot the

Department. The survey was also sent to the Executive Committee of the AGe

for their review and approval. The survey was mailed to the contractors with

the cover letter signed by the president of the AGC, hoping to attract more

attention and promote more response. Each form included an individual return

envelope to maintain anonymity.

Page 100: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

81

RESULTS OF THE CONTRACTOR SURVEY

A total of 42 surveys were completed and returned, representing a 21

percent response rate. Nineteen large contractors and 23 small contractors

responded to the survey. Of the respondents, 19 company presidents, 14 vice­

presidents, one managing partner, one general manager, one division head,

and one secretary completed the survey form. The results of the contractor

survey are presented in Appendix B.

Response Rates of the Contractor Survey

Once again, the first step in analyzing the responses was to examine the

response rates for each individual question. Similar to the SDHPT survey, the

ranking of the dollar value of disputes presented the contractors with the

greatest challenge. Only 72.1 percent of the respondents answered this

question properly. Question 2 shows a misleading response rate of only 67.1

percent. Since the structure of each company differs and some positions may

not exist in some companies, some contractors did not respond for each of the

positions listed. The next lowest response rate was for Question 1. In their

attempt to remain anonymous, the contractors responded to this question at

only a 90.5 percent rate. All of the remaining questions were answered at rates

at or exceeding 95 percent, indicating no problems for the contractors to

answer.

Page 101: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

82

Discussion of Results of the Contractor Survey

Question 2 determined the average dollar limitation for dispute settlement

for each of the positions listed. The combined results reveal a limitation of

$892,125 for company presidents, $462,141 for vice-presidents, $74,414 for

project managers, $39,758 for project supervisors, and $58,579 for project

engineers. The means were calculated using the midpoints of each range

Dsted, except for the highest range. For this range, a value of $1,000,000 was

used. Both sizes of contractors were in agreement with dollar limitations for the

president and vice-president. The small contractors, however, tended to place

more severe limits on the lower levels of authority than the large contractors.

These responses were not significantly different.

The analysis of the categorical question regarding contractor practices

was performed using the CATMOD procedure. Appendix C presents the

statistical methods used in more detail. The analysis showed significant

differences between the sizes of contractors, but not between the individual

factors. The small contractors tended to rate the contractor practices category

harsher than the large contractors. The two sizes of contractors singled out

different factors as the major problem areas. As can be seen in Table 16

(Ratings of Contractor Practices), the large contractors rated delay by material

suppliers the most severely. The small contractors, on the other hand, selected

delay by subcontractors as the main problem area. Both sizes of contractors

agreed that the use of wrong equipment for particular construction

requirements presented the least difficulty with regard to claims and disputes.

Page 102: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

83

Table 16. Average Ratings of Contractor Practices by Contractor Survey Respondents

~. Description

CP1 Inadequate investigation

CP2 Bidding below cost

CP3 Wrong equipment

CP4 Failure to follow procedure

CP5 Unbalanced bidding

CP6 Poor planning

CP7 Overoptimism

CP8 Delay by contractor

CP9 Delay by subcontractor

CP10 Delay by supplier

Overall averages

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

Avg. Large smaWI

3.68

3.48

4.31

3.88

4.14

3.62

3.59

3.81

3.17

3.40

3.71

4 Minor

Problem

3.79 3.55

3.63 3.45

4.47 4.17

4.11 3.70

4.26 4.04

3.68 3.57

3.56 3.61

3.84 3.78

3.26 3.09

3.21

3.90

5 No

Problem

3.57

3.65

Page 103: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

84

The second portion of Question 3.1 had the contractors rate SDHPT

practices. The sizes of contractors answered significantly different, as the large

contractors provided the most severe rating. The analysis also revealed a

significant difference between the individual factors. The contractors agreed

that the lack of prior utility adjustments to be the major problem area. Of all the

categorical questions from both surveys, this factor was rated as the most

critical. The contractors also determined two factors within the SDHPT

practices category, overly restrictive specifications and inadequate time for bid

preparation, to be insignificant problem areas. Table 17 (Ratings of SDHPT

Practices) presents these data on the following page.

The analysis for the contract documents once again revealed a

difference between the sizes of contractors. As can be seen in Table 18

(Ratings of Contract Documents), the contractors agreed that ambiguities in the

plans and specifications present the most difficulty. The severity of the ratings

for the individual factors, however, are vastly different. Apparently, since the

large contractors deal with larger projects and therefore more complex contract

documents, the potential for plan errors is increased. Also, these problems

might take more time to correct if a redesign is necessary. The large

contractors reflected the severity of the problem with the contract documents

in their rating of this category. The difference between the factors was

determined to be insignificant, as the individual ratings show all the factors to

be major problems areas.

Page 104: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

85

Table 17. Average Ratings of SDHPT Practices by Contractor Survey Respondents

Var. Description Avg. Large Small

SP1 Changes in plans and 3.29 3.16 3.39 specifications

SP2 Inadequate bid 3.12 3.05 3.17 information issued

SP3 Contract requirements 2.83 2.89 2.78

SP4 Overly restrictive 3.60 3.37 3.78 specifications

SP5 Delay by SOHPT 2.98 2.42 3.45

SP6 Inadequate time for bid 3.64 3.84 3.48 preparation

SP7 Utilities not adjusted 2.37 2.16 2.55

3.12 2.99 .... v.

Table 18. Average Ratings of Contract Documents by Contractor Survey Respondents

Var. Description

CD1 Errors in plans

CO2 Ambiguities in plans and specifications

CD3 Omissions in plans

Overall averages

Rating Scale:

1 Criticaf Problem

2 Severe Problem

3 Major

Problem

Avg. Large Small

2.88

2.57

2.71

2.72

4 Minor

Problem

2.53 3.17

2.26 2.83

2.37 3.00

2.39 ~

5 No

Problem

Page 105: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

86

The second portion of Question 3.2 dealt with contract administration.

The contractors again differed significantly in their ratings of this category,

asthe large contractors provided the most critical rating. The difference

between the factors was nearly significant. As shown in Table 19 (Ratings of

Contract Administration). the two sizes of contractors agreed that the

Department tends to abuse the "as directed by the Engineer" clause. The

second most critical factor was determined to be delays in providing a clear

right-of-way. This consistency between this categorical analysis and that

performed for the SDHPT practices category reinforced the contractors'

opinions that the Department needs to afford the contractors the benefit of a

construction zone free of utility adjustments.

As with the SDHPT surveys, the four categories were compared using

the CATMOD procedure. This analysis revealed a significant difference

between the sizes of contractors. The large contractors rated the four

categories of factors more severely than did their smaller counterparts. More

importantly J however. was the solid agreement that the major problem area with

regard to claims and disputes lies within the contract documents. This

category was determined to be significantly different from the others, rating as

a severe problem. The SDHPT practices and contract administration categories

were rated as major problems. The contractors rated the contractor practices

category as a minor problem. The results of this analysis are presented in

Table 20 (Ratings of All Categories).

Page 106: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

87

Table 19. Average Ratings of Contract Administration by Contractor Survey Respondents

Var. Description

CA1 Lack of coordination between contractors

CA2 Personality conflicts

CA3 Requests for time extensions

CA4 Delays in processing SDHPT paperwork

CAS Quantity disagreements

CA6 Construction acceptance or rejection

CA7 Interpretation of plans and specifications

CAS Time charges

CA9 Extra work

CA10 Delays in providing clear right-of-way

CA11 Materials acceptance or rejection

CA12 Over-usage of "As directed by the Engineer"

I I Overall averages

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

I

Avg. Large Small

3.64

3.43

3.44

3.33

3.62

3.68

3.05

3.50

3.48

2.86

3.52

2.45

3.33

4 Minor

Problem

3.89 3.43

3.32 3.52

3.21 3.64

3.47 3.22

3.58 3.65

3.39 3.91

2.74 3.30

3.32 3.65

3.32 3.61

2.47 3.17

3.53 3.52

2.37 2.52

3.22

5 No

Problem

3.43

Page 107: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

88

Table 20. Average Ratings of All Categories by Contractor Survey Respondents

Description

CP Contractor practices

SP SOH PT practices

CD Contract documents

CA Contract ad

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

Avg. Large

3.71

3.12

2.72

3.33

4 Minor

Problem

3.90

2.99 3.24

2.39 3.00

3.22

5 No

Problem

3.43

Question 4 determined the need to bypass levels of authority to receive

answers in a timely fashion. The SDHPT rated poorly, as only 13.1 percent

answered favorably and 33.3 percent answered unfavorably. Over one·half of

the respondents (53.6%) answered "sometimes." Upon investigating the survey

form as presented in Appendix B, one might observe the responses to this

question as being fractional. One of the survey forms was returned with both

"sometimes" and Rrarely" circled. To account for the indecisiveness of the

respondent, both of the answers were given equal representation. Once again,

the small and large contractors were in significant agreement to this question.

The responses to this question are summarized in Table 21 on the following

page.

Page 108: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

89

Table 21. Average Contractor Responses to Multiple-Answer Questions

Number Question Average

4 Necessary to bypass 2.75 levels of authority?

5 Receive answers in a 3.14 timely fashion?

Rating Scale:

1 Almost Always

2 Frequently

3 Sometimes

Large

4 Rarely

2.71

3.42

Small

2.78

2.91

5 Almost Never

The SDHPT fared somewhat better in Question 5 than in the previous

question. A total of 31.0 percent thought the Department answered questions

in a timely fashion when disputes could not be resolved at the project level.

Although the difference between the sizes of contractors was insignificant,

Table 21 shows the large contractors rated the Department's timeliness in

answering questions more critically than did the small contractors. Once again,

the relative complexity of projects constructed by the two sizes of contractors

leads to this difference, as the larger projects may require more time to

respond to questions.

When asked if some contractors look for disputes as potential sources

of extra profits in Question 6, 76.2 percent of the contractors answered "yes."

Page 109: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

90

Table 22 shows the large contractors to be the most critical in this self-

appraisal. Continuing the self-rating in the following question, the respondents

estimated the fraction of contractors who use disputes as extra profits to be

12.6 percent. Somewhat contradictory to the responses to the previous

question, the small contractors estimated the percentage to be nearly twice as

high as the large contractors (16.9% and 8.5%, respectively). The differences

between the responses were not significant for either question.

The next three questions addressed the impact of contractors who file

many claims against the state. Question 8 determined if these contractors hurt

the image of the contracting community as a whole. Of the combined

responses, 78.6 percent agreed that the composite image is damaged bythese

claims-oriented contractors. The small contractors were again more critical

Table 22. Summary of Contractor "Yes" Responses to Dichotomous Questions (percent)

I Number I Question I Average Large Small

6 Contractors seek extra 76.2 84.2 69.6 profits using claims?

8 Do contractors who file 78.6 68.4 87.0 many claims hurt image?

9 Do contractors who file 54.8 52.6 56.5 many claims hurt competitive bidding?

11 Contractors seek to recover 56.1 47.4 60.9 losses using claims?

Page 110: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

91

than the large contractors in this rating. The responses were more equally

divided when asked if these contractors damage the process of competitive

bidding, as only 54.8 percent answered "yes." Table 22 also summarizes the

responses to questions 8 and 9. Finally, Question 1Q allowed the contractors

to describe how the claims-oriented members of their community damage the

process of competitive bidding. The five most frequently made comments are

presented on the following page in Table 23.

Questions 11 and 12 presented the contractors with additional

opportunities to rate themselves. The first question determined the number of

contractors who bid on projects below their "normal" bid with the predetermined

intention to file claims to recover their losses. This process would allow a

dishonest contractor to be awarded projects at the expense of the honest

contractor. Table 22 shows the small contractors felt this practice to be more

predominant than did the large contractors. Question 12 then provided a

quantitative measure of the fraction of contractors using this practice. Using

the class midpoints, 10.2 percent of the contractors doing highway construction

use this devious tactic. The small contractors were again more critical than the

large contractors concerning this practice. Neither difference was determined

to be significant, however.

The difference between the responses to Questions 6 and 11 was tested

for significance using a binomial comparison test. These two questions satisfy

the three requirements for using this test: independent, repeated trials,

dichotomous responses, and the probability of responding "yes" was

Page 111: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

92

Table 23. Five Most Common Contractor Comments to Question 10.

TOTAL LARGE SMALL Comment

7 1 6 Contractors turn in low bids with preconceived idea to file claims to recover losses.

4 2 2 Contractors who file claims get work at the exclusion of other traditional contractors.

4 1 3 Claims oriented contractors cause SDHPT to treat all contractors alike.

4 2 2 Contractors bidding to claim are not bidding same work as others.

2 2 0 Contractors who claim often are subject to more scrutiny from SDHPT than others.

Page 112: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 113: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

93

unchanged over the trials. Using the combined responses to the survey, the

value of Z calculated equals 1.977. This is greater than the Z tabulated value

of 1.96 for a two-tailed test at a confidence level of 0.05. The results of this test

indicate that there is a significant difference between the responses to these

questions, as the proportion of ''yes" responses to Question 6 was significantly

higher than the proportion of "yes" responses to Question 11. The contractors

believed that there are more contractors who seek disputes as extra profits

than to recover losses.

The combined responses to the follow-up questions (Questions 7 and

12) were tested for difference using the chi-square test for equality of

multinomials. Only the first four possible answers were compared, as the last

six contained zero frequencies. The resulting chi-square was 0.672. The chi­

square value for a 4x2 table and a confidence level of 0.05 is 7.815. The

difference between the responses to these questions is therefore insignificant.

Question 13 determined the number of disputes encountered per

average week. All of the respondents felt from one to ten disputes per week

could be expected, with an average of 3.1 disputes per week. Both sizes of

contractors responded similarly. When these disputes are presented to the

state for resolution, the contractors felt that only 32.8 percent were at least

partially paid by the state (Question 14). When the state does agree to pay the

contractor for at least part of the dispute, the contractors estimated the fraction

of the disputed value actually paid to be one-half (Question 16). The large

contractors felt the state paid out on 37.1 percent of the disputes, while their

Page 114: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

94

smaller counterparts estimated this percentage to be 29.1 percent. Once

again, the difference between these responses was not significant.

When asked to rank the approximate dollar value of disputes from one

to ten, the contractors ranked the smallest disputes first. The most common

dispute value according to the contractors was in the $1,001 to $5,000 range,

followed by the smallest range listed ($0 to $1,000). The dispute values then

decreased in popularity in ascending order, with the largest disputes being the

least common. Since the small contractors tend to construct small projects,

the most common disputes encountered would intuitively be the smallest. The

surveys confirmed this theory, as the small contractors ranked the $0 to $1,000

range first, with the remaining dispute values ranked in order of increasing

value. The large contractors selected the $1,001 to $5,000 range first, followed

by the $5,001 to $10,000 range. The first and fourth ranges tied in third place.

The remaining dispute values ranked in order of increasing value. The

differences reported in the small and large contractors responses were not

significant.

Question 16 asked the contractors to estimate the percentage of the

value of disputes the State pays for disputes. The combined results estimated

this fraction to be one-half. The small contractors estimated this percentage

to be over one-half (57.6%), while the large contractors estimated this

percentage to be lower than the overall average (46.1%). This difference could

be due to the trend for small contractors to encounter smaller disputes. Also,

Page 115: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

95

the State may decline to contest these disputes with the same tenacity of the

larger disputes. Once more, the difference was not significant.

The contractors were asked if the current State economy affected the

number of claims against the Department. Twenty-six contractors (61.9%)

answered affirmatively. The small and large contractors' responses were both

close to this overall mean. The responses to this question are summarized

below in Table 24. The next question allowed the contractors to suggest other

reasons for the increase in the number of claims filed against the state. These

responses summarized in Table 25 on the following page. Two of these

comments confirm the impact of the State economy on the claims problem.

First, the increased competition for projects shows a direct reflection of the

current economy: there are not enough non-highway projects within the State

to keep the contractors busy. The lack of other projects leads contractors to

the Highway Department looking for work. This process is also reflected in the

second most common comment, as the increased competition for work drives

the prices down in order to be awarded the work. The contractors therefore

must neglect the normal contingency markup. Any changes in the scope of

Table 24. Summary of Contractor ''Yes'' Responses to Question 17 (percent)

Number Question Average Large Small

17 More claims due to Texas 63.4 61.1 65.2 economy?

Page 116: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

96

Table 25. Seven Most Common Contractor Comments to Question 18

TOTAL LARGE SMALL Comment

8 6 2 More errors, ommissions, and ambiguities in plans and specifications.

6 3 3 Projects being bid so low, there is no room for error. Contractors likely to claim.

4 3 1 Lack of knowledgable and experienced SDHPT project personnel.

2 2 0 Projects becoming more complex.

2 2 0 Unreasonably strict inspectors.

2 2 0 Contractors feel they can file claims without reprisal from the SDHPT.

2 1 1 More competition for projects.

Page 117: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

97

work without proper compensation is a potential claim.

Finally, the contractors rated the frequency of dispute resolution

alternatives. The CATMOD analysis revealed significant differences between

the sizes of contractors and the individual alternatives. The contractors felt that

the field change was the most commonly used dispute resolution alternative.

This alternative was determined to be used significantly more often than the

others. The analysis also revealed two alternatives, the informal agreements

with the district engineer and the district construction engineer, are used

significantly less often than the others. The average responses to this question

are presented on the following page in Table 26 (Dispute Resolution

Alternatives).

DIFFERENCES BETWEEN SDHPT AND CONTRACTOR SURVEYS

The SDHPT and contractor surveys shared several questions. The

analyses of the differences were accomplished using the same testing

procedures as for the individual surveys.

The *yes" or "no" type of questions were grouped into tables to allow the

use of the chi-square test for equality of multinomials. This test revealed no

significant differences. When asked if contractors look for disputes as extra

profitS, the SDHPT respondents rated the contractors more critically than did

the contractors themselves. The difference was not significant, however. This

agreement between the Department and the contractors for the variable EX 1

Page 118: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

98

Table 26. Average Ratings of Dispute Resolution Alternatives by Contractor Survey Respondents

Var. Description

AL1 Extra work order

AL2 Field change

AL3 Supplemental agreement

AL4 Field change and supplemental agreement

AL5 Agreement between PE and contractor

AL6 Agreement between RE and contractor

AL7 Agreement between DeE and contractor

ALB Agreement between DE and contractor

AL9 Time extensions

Rating Scale:

1 Almost Always

2 Frequently

3 Sometimes

Avg.

2.76

2.46

2.68

2.68

3.29

3.15

4.10

4.32

2.88

4 Rarely

Large Small

2.89

2.68

2.74

2.84

3.16

2.79

4.05

4.11

2.84

5 Almost Never

2.64

2.27

2.62

2.52

3.41

3.45

4.14

4.50

2.91

Page 119: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

99

shows there are indeed contractors who look for disputes as extra profits. The

contractors deemed the current Texas economy to be more of a factor

affecting claims than did the State. This difference was not significant at the

0.05 level of confidence. however.

A total of four multiple-answer questions fit the requirements for

comparison using the chi-square test for equality of multinomials. The results

of these tests are presented below in Table 27. The variable EX2 represents

thefollow up to the contractors looking for extra profits through disputes. There

was a significant agreement between the two surveys regarding this question.

The variable WEEK represents the number of weekly disputes encountered at

the project site. Again. the State and contractors were in substantial agreement

to this question. For the variable BY1. however, the contractors and State did

not agree. This variable represents the need to bypass levels of authority to

get disputes resolved. The contractors believed this practice is necessary more

frequently than did the departmental respondents. As can be seen in Table 27.

Table 27. Results of Comparison of Surveys Using Chi-Square

Variable Degrees of Chi-Square Probability > Freedom Value Chi-Square

EX2 9 9.826 0.365

WEEK 5 2.183 0.823

BY1 4 48.135 0.000

TIMELY 4 98.519 0.000

Page 120: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

100

this disagreement is highly significant, with a chi-square value of 48.1. For the

variable TIMELY, the State and contractors did not agree. This question

addresses the timeliness of SDHPT responses to questions regarding disputes.

Because time to a contractor represents money. their definition of timeliness

may differ from that of the SDHPT. It is no surprise, therefore, that the

contractors rated the timeliness of SDHPT decisions more poorly than did the

departmental respondents.

The categorical questions were analyzed for differences using the

CATMOD procedure as before. Under the contractor practices category,

significant differences were located between the survey respondents. It is not

surprising that the SDHPT respondents rated the contractors the most severely.

It is also not surprising that the different survey respondents selected different

factors as the major sources of claims and disputes. As shown in Table 28

(Ratings of Contractor Practices). the SDHPT respondents selected poor

planning by the contractor as the main problem area. The contractors, on the

other hand, selected delay by subcontractor.

The SDHPT practices category was similarly compared. The SDHPT

respondents rated this category Significantly less severely than did the

contractors. These two groups a/so selected different factors as the major

problem areas. The SDHPT survey indicated overly restrictive specifications as

the main source of problems: the contractors indicated the main problem area

to be contract requirements. Table 29 (Ratings of SDHPT Practices) shows the

average responses to this category. Note that the "utilities not adjusted" factor

Page 121: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

101

Table 28. Average Ratings of Contractor Practices by SDHPT and Contractor Survey Respondents

Var. Description

CP1 Inadequate investigation

CP2 Bidding below cost

CP3 Wrong equipment

CP4 Failure to follow procedure

CPS Unbalanced bidding

CPS Poor planning

CP7 Overoptimism

CP8 Delay by contractor

CP9 Delay by subcontractor

CP10 Delay by supplier

Overall averages

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

SDHPT

3.05

3.12

3.78

3.45

3.47

2.90

3.52

3.36

3.16

3.81

3.36

4 Minor

Problem

CONTR

3.68

3.48

4.31

3.88

4.14

3.62

3.59

3.81

3.17

3.40

3.71

5 No

Problem

Page 122: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

102

Table 29. Average Ratings of SOHPT Practices by SOHPT and Contractor Survey Respondents

Var. Description

SP1 Changes in plans and specifications

SP2 Inadequate bid information issued

SP3 Contract requirements

SP4 Overly restrictive specifications

SP5 Delay by SDHPT

SP6 Inadequate time for bid preparation

Overall averages

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

SDHPT

3.48

3.86

3.45

3.04

3.72

3.88

3.76

4 Minor

Problem

CONTR

3.29

3.12

2.83

3.60

2.98

3.64

3.25

5 No

Problem

has been excluded from the analysis in order to keep factors consistent.

Although the contractors and departmental employees agreed that the

contract documents are the major problem area, the magnitude of the rating

of this category differed significantly. As can be seen in Table 30 (Ratings of

Contract Documents), the contractors rated this category approximately one·

half point lower than the SDHPT respondents. Both survey groups determined

Page 123: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

103

Table 30. Average Ratings of Contract Documents by SDHPT and Contractor Survey Respondents

Var. Description SDHPT CONTR

CD1 Errors in plans 3.23 2.88

CO2 Ambiguities in plans and 3.22 2.57 specifications

CD3 Omissions in plans 3.28 2.71

3.26 2.72

Rating Scale:

1 2 3 4 5 Critical Severe Major Minor No Problem Problem Problem Problem Problem

the problem of ambiguities in the plans and specifications to be the most

critical. The contractors rated this factor nearly three-fourths of a point lower

than did the SDHPT respondents, however.

Under the contract administration category, the contractors again

provided the most critical rating. The results of this comparison are presented

in Table 31 (Ratings of Contract Administration) on the following page. The

difference between the survey groups proved to be significant. "rhe difference

between the individual factors was also significant. Each of the survey groups

selected different factors as being the most critical. The SDHPT survey

indicated the interpretation of the plans and specifications to be the most critical

problem area, while the contractors selected delays in providing a clear right-of-

Page 124: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

104

Table 31. Average Ratings of Contract Administration by SDHPT and Contractor Survey Respondents

Var. Description

CA1 Lack of coordination between contractors

CA2 Personality conflicts

CA3 Requests for time extensions

CA4 Delays in processing SDHPT paperwork

CA5 Quantity disagreements

CA6 Construction acceptance or rejection

CA7 Interpretation of plans and specifications

CAB Time charges

CA9 Extra work

CA10 Delays in providing clear right·of-way

CA11 Materials acceptance or rejection

Overall averages

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

SDHPT

3.44

3.70

3.63

3.72

3.82

3.78

3.40

3.87

3.72

3.59

3.93

3.75

4 Minor

Problem

CONTR

3.64

3.43

3.44

3.33

3.62

3.68

3.05

3.50

3.48

2.82

3.52

3.41

5 No

Problem

Page 125: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

105

way. As with the SDHPT practices category, the additional factor included in

the contractor survey was not considered in this analysis.

The four categorical questions from both surveys were compared to

determine if the responses differed significantly. The responses differed

significantly, as the contractors provided the most critical rating for three of the

four categories. The contractor practices category was the lone exception to

this statement, as the SDHPT respondents provided a more critical rating than

did the contractors. Table 32 (Ratings of All Categories) shows the agreement

between the contractors and SDHPT respondents that the contract documents

provide the most critical problems with regard to claims and disputes.

Finally, the SDHPT and contractor responses to the dispute resolution

alternatives category were compared to locate any differences. The survey

Table 32. Average Ratings of All Categories by SDHPT and Contractor Survey Respondents

~ Description

CP Contractor practices

SP SDHPT practices

CD Contract documents

CA Contract administration

Rating Scale:

1 Critical Problem

2 Severe Problem

3 Major

Problem

I SDHPT

3.36

3.76

3.26

3.75

4 Minor

Problem

CONTR

3.71

3.25

2.72

3.41

5 No

Problem

Page 126: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

106

groups differed significantly, as did the individual alternatives. The contractors

and SDHPT respondents did agree that the field change is the most common

dispute resolution alternative. The respondents also agreed that the informal

agreement between the district engineer and the contractor was used most

seldom. Table 33 (Dispute Resolution Alternatives) presents the ratings of the

alternatives on the following page.

Page 127: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

107

Table 33. Average Ratings of Dispute Resolution Alternatives by SDHPT and Contractor Survey Respondents

Var. Description

AL1 Extra work order

AL2 Field change

AL3 Supplemental agreement

AL4 Field change and supplemental agreement

AL5 Agreement between PE and contractor

AL6 Agreement between RE and contractor

AL7 Agreement between DCE and contractor

ALB Agreement between DE and contractor

AL9 Time extension

Rating Scale:

1 Almost Always

2 Frequently

3 Sometimes

SDHPT

3.02

2.43

2.67

2.43

3.05

2.98

3.93

4.28

3.23

4 Rarely

CONTR

2.76

2.46

2.68

2.68

3.29

3.15

4.10

4.32

2.88

5 Almost Never

Page 128: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

108

CHAPTER V

SUMMARY AND CONCLUSIONS

SUMMARY

In order to gain insight into the Department's current claims problem, the

research effort followed a three-stage plan. First, a literature search provided

information on the claims problem as a whole. The surveys of SDHPT

personnel and highway contractors focused the remaining research on the

problem in Texas. Finally, interviews with SDHPT personnel and highway

contractors supplemented the findings of the surveys.

The Department cannot realistically expect to eliminate claims

completely. Claims are, unfortunately, an unwanted by-product of the

competitive bid process (21). The Department can expect to reduce both the

number of claims and the monetary loss due to these claims by committing to

an overall improvement in the quality of the contract documents. This

improvement must be comprehensive in nature, including the reduction of plan

errors, ambiguities, and omissions. The Department must strive to provide

timely answers to field questions to reduce the potential for delay claims. The

State must consider the financial impact of extra work on the contractor. Also,

the interpretation of the contract documents must become more uniform across

the State to afford the contractor the benefit of predictability. The State must

Page 129: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

109

make every effort to provide the contractor a construction zone free of utilities

needing adjustment. There are several options available to complement the

current system for dispute resolution. Of these, the dispute review board

seems to hold the most promise for future implementation. Along with the pre­

construction conferences, the State should consider the implementation of pre­

bid conferences to clarify design conflicts before the contractors submit bids.

Finally. the State must implement some sort of disputes monitoring system to

provide an accurate measurement of the number of disputes and the reasons

therefore. This system would provide the State a quantitative measure of future

improvements.

Since contracting is not one-sided, the actions required to make

improvements to the system should not be one-sided. Contractors can take

several steps to reduce the number of claims and the financial impact of these

claims. First, contractors should take the time to investigate each project

thoroughly before bidding. If any errors are located, the prospective bidder

should notify the Department and ask for clarification, rather than interpreting

the intent of the plans himself. The estimating team should then exercise more

care in preparing the bid. The contractor should adequately plan and schedule

the work. Contractors should schedule each project with the intent to pursue

the rapid completion of all of the work. Too many projects are started in a

hurry, only to have completion of the project delayed by the contractor himself.

Contractors should also exercise caution in selecting subcontractors and

materials suppliers. as delays by these entities are major sources of problems.

Page 130: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

110

The practice of using the "bid low and file claims to recover losses" approach

to acquire projects must be eliminated.

Once construction begins, the contractor should keep the State's project

inspection team informed of upcoming activities. Only through this

communication can the Department ensure adequate project staffing. Also, the

contractor should inform the project team of any problems encountered, and

require proper compensation for all work performed. In the past, contractors

were willing to perform some work without pay in order to maintain good

working relationships with the Department. In some cases. the Department has

grown accustomed to this practice, thereby failing to realize the need for

payment even for minor changes.

When a dispute arises. contractors should follow established SDHPT

procedures in seeking resolution, paying particular attention to the chain-of­

command system. Contractors who bypass steps in the ladder of dispute

resolution destroy the integrity of the system itself. This process has a

compounding effect, as an inspector or engineer who is often bypassed to

have a decision reversed will soon cease to to make any decision at all.

Finally, when it is necessary to file a claim, the amount claimed should reflect

actual damages only. The questionable practice of inflating the claim with hope

that the settlement covers actual damages further complicates the problem.

Page 131: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

111

CONCLUSIONS

Since the research was done for the State Department of Highways and

Public Transportation, by researchers employed by the Department, the

following conclusions concentrate on actions which can be taken by the

Department in order to mitigate the claims problem.

The Need for Improved Contract Documents

The research produced several major findings. First, there is

overwhelming evidence of the need for improved contract documents. The

respondents to both the contractor and SDHPT surveys were in agreement with

this weakness, as both surveys indicated the category of contract documents

to be significantly more of a problem than the other categories. Apparently,

there is much room for improvement, as indicated by Figure 10. This graphic

indicates the proportion of plans needing some type of revision to be

approximately 40 percent. The percentage is not exact, as the number of plans

produced in each district is not constant.

Also, a study of 18 claims filed against the Department from 1984 to

1989 confirms the problem of bad plans, as design problems were cited as

reasons for claims in one-third of the projects. As shown in Figure 11, design

errors represent 22 percent of the reasons for the claims. The total number of

reasons shown equals 32, as many of the projects cited more than one reason

for the claim. This study revealed two other major categories of reasons for

"

Page 132: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

1-1-1······ .... · .... ········ .. ··········· .. ·••• .. ····•·········· .................................................................................................................................... ..

rn c: f March 1989 to March 1990 0 'en .s; Q)

50 a: '0 e ... c 0 0 Q) C)

S c Q)

~ Q) n.

District

Figure 1 O. Construction Contract Revisions ..... ..... I\)

Page 133: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

113

Delays by SDHPT - 7

Other - 6

19%

22%

Design Errors - 7 22%

Additional Work - 6 19%

Barricades - 2 6%

Materials - 2 6%

Const. Methods - 2 6%

Total of 18 claims

Figure 11. Reasons for Claims Against SDHPT, 1984 to 1989.

Page 134: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

114

claims: delays and extra work. These two factors account for 22 and 19

percent of the cited reasons, respectively. Of these three major contributors

to the claims problem, the delays and design categories are by far the most

costly. Table 34 below presents the average claimed and paid values for the

categories. It is important to note that the average values are presented for

relative comparison of these factors only. Because multiple reasons were cited

for several projects, it is entirely possible that the claimed and paid values for

any particular project can be represented in more than one of the averages.

Despite this fact, the average paid value shows the significance of design

problems, delays, and additional work, as these three reasons account for 89

percent of direct settlement costs.

Table 34. Average Claimed and Paid Values for Claims

Reason Cited Average Average Percent Claimed Paid Value Value Value Paid

Inadequate design $4,978,323 $1,811,469 37.16

Delays by SDHPT $4,288,546 $1,565,431 32.11

Additional work $1,676,024 $970,181 19.90

Materials $983,391 $343,186 7.04

Const. methods $167,366 $1,500 0.03

Barricades $34,210 $27,266 0.56

Other $515,140 $155,661 3.19

Page 135: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

115

The problem of bad contract documents can be divided into three

categories: errors, omissions, and ambiguities. While the concept of plan

errors is a simple one, a plan error can take one of several forms. First, a

mathematical or drafting error can result in the misrepresentation of material

quantities. If the item is not paid according to plan quantity, the error can be

corrected in the field by paying for the in-place quantity. This practice can lead

to extreme over or under payment, however, if unit price for the item in

question is unbalanced. Underpayment resulting from this practice can lead

to a claim. If the item is paid according to plan quantity, a field change and

supplemental agreement may be necessary. Next, an error in the design of the

project can result. Depending on the complexity of the error, this problem can

be solved using the field change and supplemental agreement. The real

danger here is the timeliness of the correction. The contractor can file and win

a delay claim if the redesign is not handled in a timely fashion. Some

omissions in the plans can be relatively simple to correct, while others are more

serious and require more effort to correct. Cases when the plans are drawn

correctly but the pay quantity is not reported can be corrected using the

combination of the field change and the supplemental agreement. When an

entire portion of the detailed design is omitted, however, a complete redesign

may be warranted. This process can require considerable time and effort from

the design team, and can result in major delay to the project schedule. Once

again, the potential for the contractor to file a successful delay claim is present.

Page 136: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

116

Ambiguities represent a large source of the problems with the contract

documents. Any ambiguity in the contract documents is a potential claim.

When a bidder encounters such a conflict in the plans, the bidder may attempt

to interpret the intent of the plans. In order to protect himself against a

erroneous Interpretation. he must mark up his bid to provide for contingencies.

In today's economical climate, where the competition for most construction

projects is stiff, the contractor who marks up his bid to allow for contingencies

cannot expect to be the lowest bidder. The ambiguity may be discovered after

construction begins. In this case, the project personnel must attempt to

interpret the intent of the plans. If the decision is not timely by the contractor's

definition, a delay claim is in the making.

From the State's point-of-view, the resolution of disputes resulting from

plan errors is compounded by the lack of certainty if the contractor had

knowledge of the problem prior to bidding. It is possible that contractors

discover these problems before bidding and attempt to take advantage of the

situation, often by unbalancing their bids. The State can be in the position of

paying the contractor more than he deserves if the unit price and in-place

quantities are paid in full. While the standard speCifications include provisions

to handle major increases or decreases in the quantity of the work through

price adjustments, the contractor can still profit Immensely from prior

knowledge of errors.

Also contributing to the problem of plan errors is the confusion which

can be created through the use of speCial items, special specifications, and

Page 137: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

117

general notes. Subsidiary pay items can also lead to contractor confusion

when bidding, especially such an item had previously been a direct pay item.

The effect of this problem is compounded when the lack of work forces a local

contractor to cross over into a new district or residency. In doing so, he can

encounter an entirely different method of conducting business from that which

he has grown accustomed to. This compounding effect can be even more

dramatic if competition for work forces contractors from out of state to enter

the Texas highway construction market.

The Need to Provide Timely Decisions During Construction

Table 35 shows the second most costly reason for claims against the

Department to be State-caused delays. Any delay caused by subcontractors,

materials suppliers, owner, or contractor can create a significant impact on the

construction schedule. One source of delay by the State arises from the time

required to process paperwork such as field changes, extra work orders, and

supplemental agreements. The respondents to the contractor survey ranked

this factor fourth within the contract administration category. Another source

of State-caused delay comes from the time required to make decisions. The

contractors responding to the survey indicated the decisions reached by the

State are "sometimes" to "rarely" timely. The Department should strive to afford

the contractor the quickest, most accurate decision possible. If this is not

possible due to the complexity of the decision, the time charges against the

project should be suspended, and be resumed following receipt of the decision.

Page 138: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

118

Any failure to complete the project according to schedule would therefore be

caused by delays by parties other than the Department. This strategy would

reduce the financial impact of the delay if the contractor is assessed liquidated

damages. The contractor thereby could not file a successful and justifiable

claim for the return of liquidated damages.

The Need to Consider Financial Impact of Additional Work

Often during construction, the need for additional work arises. In the

past, contractors have been willing to work with the State by performing the

work for little or no compensation. Their losses could be justified by the

favorable working relationship developed through this courtesy. Often when

the State pays for additional work, the total compensation is calculated by

multiplying the unit price for a similar item by the quantity of work. Problems

arise when the bid price was developed assuming conditions consistent with

the work as shown in the plans, but the additional work does not meet these

conditions. For example, the bid for asphaltic concrete pavement was based

on the use of a spreading and finishing machine travelling straight down the

roadway, and the additional work involves hand-work for intersections or

driveways not shown on the plans. The bid price does not include the costs

of additional manpower, nor does it consider the effect of the slower production

rates involved in the hand-work. Additionally, the contractor incurs cost on a

da.ily basis which are not considered. These costs include overhead, bonds,

insurance, and the impact of delay on the project schedule. In situations such

Page 139: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

119

as this, the Department must be sensitive to the impact of the additional work

on the contractor as a whole, and should initiate a field change, supplemental

agreement, or extra work order for compensation.

The Need for Consistent Interpretation of Plans and Specifications

The interpretation of plans and specifications is inconsistent among

districts, residencies. and project personnel. There are three separate factors

contributing to this inconsistency. Discussion of the ''ten percent" engineers

and inspectors, the natural variation among engineers and inspectors, and

clauses contained within the specifications follow.

While the Department has recognized the need to eliminate the so-called

"ten percent" engineers and inspectors, contractors claim a few of these

personnel remain in claim-sensitive positions. By definition, the "ten-percent"

engineer or inspector is one whose reputation with contractors leads to the

raising of the bid by a predetermined percentage to account for this person

being assigned to a project.

The natural variation between engineers and inspectors plays more of

a role in the inconsistencies than does the "ten-percent" employee. It seems

logical that decisions made by different personnel based on identical facts will

not be identical. This type of inconsistency cannot be eliminated without

stripping the freedom of free thinking from the decision-makers. It may be

reduced, however, by continuing to provide training for some of the lesser

experienced project personnel.

Page 140: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

120

The specifications also provide the means for some inconsistencies.

Phrases like "as directed by the Engineer", "in the opinion of the Engineer", and

"unless approved by the Engineer" are necessary to provide the freedom for

project personnel to make decisions to fit field conditions. In the words of one

contractor, " ... in the hands of some individuals, this can be very deadly

ammunition." Project personnel must strive to make well-analyzed, common

sense decisions when faced with this situation.

The Need for Pre-Bid Conferences for Complex Projects

Several SDHPT survey respondents indicated the use of pre-bid

conferences could help reduce the confusion created by design ambiguities or

conflicting special provisions. Currently, when a contractor is interested in

bidding a job, he must visit the office of the engineer in charge of the project

to view the plans. If the contractor is still interested, he may "ride the job" with

the resident engineer. The purpose of this informal meeting is to clarify

questions concerning the job. The resident engineer must be careful to answer

similar questions of different contractors similarly. Major problems could arise

should the resident engineer fail to do so, or if he should be unavailable to

answer questions. The possibility of the successful bidder being the only

contractor privy to some information exists. A pre-bid conference with all

interested parties in attendance could avoid some of these problems. The

major drawback to this process would be getting contractors to openly discuss

plans for prosecuting the work in front of their competitors. This problem might

Page 141: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

121

be avoided if the sole intent of the conference is to clarify questions concerning

the contract documents.

The Need to Provide Utility-Free Construction Zones

Contractors encountering utilities which have not been adjusted prior to

the onset of construction is a major source of claims. As detailed in Chapter

4, "utilities not adjusted" was included in the contractor surveys under the

SDHPT practices category. -rhe analysis of the factors under this category did

not include this factor to retain consistency between the contractor and SDHPT

surveys. By looking at the data as presented in Appendix B, however, it is

evident that this factor would have been determined to be a significant problem

area. Because the contractors rated this factor more critically than the "delay

by SDHPT" factor which was determined to be significantly different from the

rest, it seems logical that -utilities not adjusted" would also have been

significant. The Department seems to be in agreement with the contractors, as

a total of 25 respondents made similar comments.

The Need for Early. Third Party Dispute Resolution

Several alternatives to the current method used by the Department for

dispute resolution were investigated. Of these alternatives, the dispute review

board seems to hold the most promise for future implementation. The states

using the dispute review board have rated this process as a complete success.

As of November 1990, over $4.1 billion in construction has been completed

Page 142: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

122

using the dispute review board as the means for disposing of disputes. Not

one of these projects have had disputes go to litigation as the means for

settlement (11). The cost of the ORB limits the economical use of this process

to farge, complex, dispute-prone projects.

The Need for a Quantitative Dispute Measurement System

The Department currently has no method for counting the number of

disputes encountered annually. An effective measurement system would need

to include time-charge codes for time spent managing disputes. This would

allow personnel from all levels to accurately account for time spent handling

disputes. Also, time-charge codes are needed to account for time spent

collecting documentation needed to defend the State against claims. Finally,

the measurement system would require the modification of field construction

forms including field changes, supplemental agreements, extra work orders,

and time extensions. These forms currently provide space for written

descripitions of the problem encountered. The modification would simplify the

process of data compilation, and allow the data to be entered into a database

for analysis purposes. The compilation of this data would provide an accurate

measurement of the number of disputes and the reasons for the problems.

This information would then provide the means for determining if improvements

are being made over time. One additional benefit of this addition to the

construction forms is that the process of approving these change orders could

Page 143: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

123

be accelerated. Personnel approving the changes would be reminded by the

form itself that a timely decision is imperative in order to avoid claims.

The significance of the indirect cost of dispute settlement as previously

calculated reinforces the need for a measurement system, as the direct cost of

claims settlement accounts for only one-tenth of the total cost. The total would

be higher still if the cost of all of the field changes, supplemental agreements,

and extra work orders that were initiated as a result of disputes could be

determined. The measurement system is needed to determine the magnitude

of the claims problem accurately. Only through the use of a quantitative

measurement system can the impact of future efforts be determined.

RECOMMENDATIONS

The research effort a total of nine areas for improvement which may

warrant further investigation of possible future implementation by the

Department. Also, four areas needing additional research are presented.

These recommendations are listed below.

Recommendations for Implementation

1. Improve quality of plans and specifications.

2. Provide timely answers to field problems.

3. Attempt to provide consistent interpretation of plans and specifications.

4. Consider financial impact of additional work on contractor.

Page 144: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

124

5. rmplement pre-bid conferences.

6. Provide construction zones free of utility adjustments.

7. Implement early, third party dispute resolution process.

B. Modify standard SDHPT construction forms and add time-charge code

for dispute and claim settlement.

9. Continue SDHPT training program.

Recommendations for Additional Research

1. Re-evaluate the current competitive-bid process. Investigate the potential

for design-build contract system for complex projects.

2. Investigate the potential for contractor-determined contract time, using

a combination of low-bid and shortest contract duration as basis for

contract award. If State-determined contract time is necessary,

investigate the potential for contractor·determined sequence of work and

traffic control plan.

3. Investigate the potential for implementing total quality management for

Mure project development.

Page 145: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

125

REFERENCES

1. Spanning the State. State Department of Highways and Public Transportation, 1990.

2. Highway Contract Claims Avoiding / Handling. U.S. Department of Transportation, August 1988.

3. H. Hauf. Building Contracts for Design and Construction. John Wiley & Sons, New York, 1976.

4. Standard Specifications for Construction of Highways, Streets and Bridges. Texas State Department of Highways and Public Transportation, September 1982.

5. J. Butler, H. Casner, and N. Lovejoy. Techniques for Understanding, Controlling and Minimizing Construction Claims. State Department of Highways and Public Transportation, not published.

6. R. Rubin, S. Guy, A. Maevis, and V. Fairweather. Construction Claims Analysis, Presentation, Defense. Van Nostrand Reinhold Company, New York, 1983.

7. J. Cibinic, Jr. and R. Nash, Jr .. Administration of Government Contracts, George Washington UniverSity. 1981.

8. G. Smith and D. Hancher. An investigation of Calims and Disputes Settlement by Arbitration for Highway Construction. Report No. FHWA/INfJHRP-86/8, Purdue University, September 1986.

9. L. Kangun. Dispute Resolution Forums. Texas State Department of Highways and Public Transportation, not published.

10. M. Callahan, B. Bramble and P. Lurie. Arbitration of Construction Disputes. John Wiley & Sons, New York, 1990.

11. J. Rozelle. Personal Interview. October, 1990.

12. Transportation Research Board. Construction Contract Claims: Causes and Methods of Settlement. Report No. NCHRP Synthesis 105, November 1983.

13. J. Allen. Arbitration Vs. Litigation: The Pros and Cons. Kellogg Corporation News, June 1990, pp. 4-6.

Page 146: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

126

14. H. Hohns. Preventing and Solving Construction Contract Disputes. Van Nostrand Reinhold Company, New York. 1979.

15. E. Shanley. A Better Way. Civil Engineering. American Society of Civil Engineers, Vol. 59, No. 12, December 1989, pp. 58-SO.

1S. J. Coffee. Dispute Review Boards in Washington State. The Arbitration Journal, Vol. 43, No.4, December 1988, pp. 58-61.

17. R. lathlaen. Alternative Dispute Resolution. Constructor, December 1988. pg. 77.

18. B. Lay. Personal Interviews, June 1990 - November 1990.

19. Contested Case Procedure. Texas State Department of Highways and Public Transpotration, adopted from Texas Civil Statutes article 6252-13a, ammended June 1988.

20. SAS/STAT Guide for Personal Computers. Version 6 Edition. SAS Institute Inc., Cary North Carolina, 1987.

21. J. Nicholson. Rethinking the Competitive Bid. Civil Engineering. American Society of Civil Engineers, Vol. 61, No.1, January 1991, pp. 66-68.

Page 147: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

127

APPENDIX A

SURVEY FORMS

TEXAS STATE DEPARTMENT OF IDGHWAYS AND PUBLIC TRANSPORTATION

CONIRACI CLAIMS AND DISPUTES SURVEY

1) What is your position with the Highway Department?

District Engineer

District Construction Engineer

Resident Engineer

Project Engineer/Manager

2) Please rank the approximate dollar value of disputes, with 1 being most common and

10 being least common.

SO to 1,000

$ 10,001 to 20,000

S 100,001 to 200,000

S 1,000,001 and up.

S 1,001 to 5,000 $ 5,001 to 10,000

$ 20,001 to 50,000 $ 50,001 to 100,000

$ 200,001 to 500,000 _ S 500,001 to 1,000,000

3) Is there a cenain dollar value limitation associated with your position to settle

disputes? _ Yes _ No

4) If the answer to Question (3) was 'Yes' please indicate the present dollar value

limitation placed on your ability to settle disputes.

$ 0 to 1,000 S 1,001 to 5,000 $ 5,001 to 10,000

S 10,001 to 20,000 $ 20,001 to 50,000 S 50,001 to 100,000

$ 100,001 to 200,000

$ 1,000,001 and up.

$ 200,001 to 500,000 _ $ 500,001 to 1,000,000

Don't know limit.

Page 148: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 149: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

128

5.1) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 Critical Severe Major Minor Problem Problem Problem Problem

Contractor practices 1 2

Inadequate investigation before bidding.

Bidding below cost.

Use of wrong equipment.

Failure to follow authorized procedures.

Unbalanced bidding.

Poor planning.

Overoptimism.

Delay by contractor.

Delay by subcontractor.

Delay by materials supplier.

Other. (Please specify below)

SDHPT Practices 1 2

Changes in plans and specifications.

Inadequate bid information issued.

Contract requirements (DBE, EEO, Wage rales, etc).

Overly restrictive specifications.

Delays caused by SDHPT.

Inadequate time allowed for bid preparation.

Other. (Please specify below)

5 No

Problem

3 4

3 4

5

I

C

5

Page 150: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

129

5.2) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 Critical Severe Major Minor Problem Problem Problem Problem

Contract Documents 1 2

Errors in plans.

Ambiguities in plans and specifications.

Ommissions in plans.

Other. (Please specify below)

Contract Administration 1 2

Lack of coordination between contractors.

Personality conflicts.

Requests for time extensions.

Delays in processing SDHPT paperwork.

Quantity disagreements.

Construction acceptance or rejection.

Interpretation of plans and specifications.

Time charges.

Extra work.

Delays in providing clear right of way.

Materials acceptance or rejection.

Other. (Please specify below)

5 No

Problem

3 4

3 4

5

5

t=L

Page 151: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

'30

6) How often do contractors bypass your level of authority and approach your superiors

with disputes?

1 2 3 4 5 Almost Frequently Sometimes Rarely Almost ~ys tJever

7) If a contractor does bypass your level of authority for disputes;

7.1) How often does your superior contact you for input before making the

decision?

1 Almost Always

2 Frequently

3 Sometimes

4 Rarely

5 Almost Never

7.2) How often does your superior send the contractor back to you for a decision?

1 Almost Always

2 Frequently

3 Sometimes

4 Rarely

5 Almost tJever

7.3) How often does your superior make the decision, but informs you of the

result?

1 Almost Always

2 Frequently

3 Sometimes

4 Rarely

5 Almost Never

8) Do you feel that there are some contractors who look for disputes as opportunities

to make extra profits on projects? _ Yes _ No

9) If the answer to Question (8) was 'Yes', what percentage of contractors do you

estimate do so?

1-10% _ 11-20%

51-60% 61~70%

21-30% _ 3140% _ 41-50%

71·80% _ 81·90% _ 91~100%

Page 152: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

132

13) If a dispute cannot be settled at your level, how often do you receive answers from

your superiors in a timely fashion?

123 Almost Frequently Sometimes Always

4 Rarely

5 Almost Never

14) Please indicate the number of hours you spend handling disputes during the normal

forty hour week.

1 to 5

21 to 25

6 to 10

26 to 30

11 to 15

31 to 3S

16 to 20

36 to 40

IS) Please estimate the number of man-hours your staff spends handling disputes during

the normal forty hour week. (Please include only your directly supervised staff. Do

not include yourself in this estimate.)

1 to 5 6 to 10

21 to 25

41 to 45

61 to 65

26 to 30

46 to 50

66 to 70

80 + (Please show estimate).

11 to 15

31 to 35

51 to 55

71 to 75

16 to 20

36 to 40

56 to 60

76 to 80

16) Are you familiar with the SDHPT claims resolution and prevention policy?

Yes _ No

17) Do you feel that requiring contractors to submit formal, written, itemized notices of

disputes to District personnel can help lower the number of disputes?

_ Yes _ No

Page 153: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

133

18) Do you feel that requiring contractors to submit formal, written. itemized notices of

disputes to the District can help defend the State against disputes which become

claims?

_ Yes _ No

19) What additional measures can the State take to reduce the number of disputes which

become claims?

20) Do you feel Contractors are filing more claims than before due to the current

condition of the State ecomomy ?

Yes No

21) If the answer to Question (20) was 'No', please list other causes for Contractors to

file more claims than before.

TIiANK YOU FOR YOUR TIME AND EFFORT.

Page 154: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

TEXAS STATE DEPARTMENT OF HIGHWAYS AND PUBLIC TRANSPORTATION

CONTRACTORS CLAIMS AND DISPUTES SURVEY

134

Note: This survey should be completed only by personnel with authority to settle claims with the Texas State Department of Highways and Public Transportation.

1) What is your position in the company?

2) Using the following scale, please indicate the limitations for dispute approval for

each of the positions listed by writing the appropriate letter in the blank column.

A - S 0 to 1,000 B - $ 1,001 to 5,000

E· $ 20,001 to 50,000

c· $ 5,001 to 10,000

F - $ 50,001 to 100,000 D - $ 10,001 to 20,000

G - S 100,001 to 200,000

J. $ 1,000,001 and up.

H - $ 200,001 to 500,000 I - $ 500,001 to 1,000,000

Position Title Umiation Code

President

Vice-President

Project Manager

Project Supervisor

Project Engineer

Other. (Please specify below)

Page 155: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

135

3.1) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 5 Critical Severe Major Minor No Problem Problem Problem Problem Problem

Contractor practices 1 2 3 4 5 T. ..:I, lAte' . . hefnre hinning

Biddinll be10w cost.

,r!:e nf wrnna . Failure to fonow au·1. • ~d DTOcedures. ,T .. t. ." ..:I I.' ..:I..:I!

Poor .1

O\i .

Delav hv Contractor.

Delav bv lctor. I

Delav bv •• SUDDlier. II

Oth!!r. (P'!!a~!! snecifv helow)

SDHPT Practices 1 2 3 4 5

Page 156: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

136

3.2) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 5 Critical Severe Major Minor No Problem Problem Problem Problem Problem

Contract Documents 1 2 3 4 S Prrnn: in nhtnc: A •• . ~ •• in nlam; and sneclc

Om .... : .... innc: in n'~nc:

Other. (Please :L. below)

Contract Administration 1 2 3 4 S

TJidc of ..... 1.. .... , ....... (" , .... +"' ....

on ~litv ~onflicts

'R for time

Delavs in inuSDHE'I ,- .1.

Ouantitv diS21rrt'!t'!m",ntc;

n or reiection. T. inn nf ohmc; and ,r.

Time .L

Extra work.

Dela~ in orovidinp clear rilZht of way.

Materialc: a, Ice or rei"'rtinn

Over-usal'1:e of "At; directed bv the Enl'1:int'!er"

Other. (Please sneclfv helow)

Page 157: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

137

4) How often do you feel it is ~ecessary to bypass a level of authority within the

Highway Depanment to receive answers to construction problems in a timely

fashion?

1 Almost Always

2 Frequently

3 Sometimes

4 Rarely

5 Almost Never

5) If a dispute cannot be settled at the project level. how often do you receive answers

from the Highway Department in a timely fashion?

1 2 3 4 5 Almost Frequently Sometimes Rarely Almost Always Never

6) Do you feel that there are some Contractors who look for disputes as opportUnities

to make extra profits on projects?

Yes No

7) If the answer to Question (7) was 'Yes', what percentage of Contractors do you

estimate do so?

1-10%

51-60%

11-20%

61-70%

21·30%

71·80%

_31-40%

_81-90%

_41-50%

_ 91·1()()%

8) Do you feel that the Contractors who file numerous claims against the State hurt the

image of Contractors as a whole?

_ Yes _ No

Page 158: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

138

9) Do you feel these Contractors hurt the process of competitive bidding?

_ Yes No

10) If the answer to Question (9) was 'Yes', please briefly describe how this practice

hurts bidding.

11) Do you feel there are Contractors who intentionally bid low to be awarded a project,

then file claims to recover their losses?

_ Yes _ No

12) If the answer to Question (11) was 'Yes', what percentage of Contractors do you

estimate do so?

1·10% _11·20%

_ 51·60% _ 61·70%

21·30% _ 3140% _ 41·50%

71-80% _ 81·90% _ 91·100%

13) Please indicate the number of disputes your firm encounters per average week.

It05 6tol0 lito 15 16 to 20

_ 21 to 25 _ 26 to 30 _ 31 to 35 _ 36 to 40

Page 159: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

139

14) What percentage of disputes do you estimate result in the State paying the

Contractor at least part of the dispute value?

1·10% _ 11·20%

51·60% _ 61·70%

21-30% _ 31-40% _ 41·50%

71-80% _ 81-90% _ 91·100%

IS} Please rank the approximate dollar value of disputes that you encounter, with a rank

of 1 being most common and 10 being least common.

$ 0 to 1,000

$ 10,001 to 20,000

$ 100,001 to 200,000

S 1,000,001 and up.

$ 1,001 to 5,000

$ 20,001 to 50,000

S 5,001 to 10,000

$ 50,001 to 100,000

$ 200,001 to 500,000 _ S 500,001 to 1,000,000

16) When the State agrees to pay the Contractor as a result of a dispute, what

percentage of the value of the disputes do you estimate the State pays?

1·10% _ 11-20%

51-60% _ 61·70%

21-30% _ 31-40% _ 41·50%

71·80% _ 81-90% _ 91·100%

17) Do you feel some Contractors are filing more claims than before due to the current

condition of the State ecomomy ? _ Yes _ No

Page 160: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

140

18) If the answer to Question (17) was 'No', please list other causes for Contractors to

file more claims tban before.

19) Using the following scale, please rate the most common alternatives in resolving

disputes by placing an 'X' in the appropriate column.

1 2 3 4 5 Almost Frequently Sometimes Rarely Almost Always Never

Alternatives Involved in Resolving Disputes 1 2 3 4 5

Extra Work Order.

Fil"lr1 ("h:.lnofl!

(' ·_-'--... ·nat A

Fip.lr1 C'h:.lnl7p. :.Inri -,

~ntal A tt

Verbal Agreement between Inspector and Contractor.

Verbal Agreement between Resident Engineer and Contractor.

Verbal Agreement between District Construction Engineer and Contractor.

Verbal Agreement between District Engineer and Contractor.

Time ~.

Othl"1" (Pll"::lc:e c:nl".dfv helow)

11IANK YOU FOR YOUR TIME AND EFFORT.

Page 161: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

APPENDIX B

SURVEY RESULTS

TEXAS STATE DEPARTMENT OF WGHWAYS AND PUBLIC TRANSPORTATION

CONTBACf CLAIMS AND DISPUTES SURVEy

COMBINED RESULTS (Numbers in parentheses indicate response rate) [Numbers in brackets indicate calculated values]

1) What is your position with the Higbway Department? (100%)

~ District Engineer

..2l. District Construction Engineer

m Resident Engineer

ll.2... Project Engineer/Manager

....s... General Construction Inspector

141

2) Please rank the approximate dollar value of disputes, with 1 being most common and

10 being least common. (67.0%)

_4_ S 0 to 1,000 ....l- S 1,001 to 5,000 --1.. S 5,001 to 10,000

--L $ 10,001 to 20,000 -L S 20,001 to 50,000 -L $ 50,001 to 100,000

....:L S 100,001 to 200,000 -B- S 200,001 to 500,000 -L S 500,001 to 1,000,000

-1!L S 1,000,001 and up.

3) Is tbere a cenain dollar value limitation associated witb your position to settle

disputes? (96.''1»

-2!. Yes (34.1%)..llJ. No (62.''1» ..L No Answer (3.3%)

4) If the answer to Question (3) was 'Yes' please indicate the present dollar value

limitation placed on your ability to settle disputes.

-2L S 0 to 1,000 -B- S 1,001 to 5,000 -L $ 5,001 to 10,000

-1!L S 10,001 to 20,000 ...ll- S 20,001 to 50,000 -L S 50,001 to 100,000

....L S 100,001 to 200,000 .JL S 200,001 to 500,000 -L S 500,001 to 1,000,000

--'L $ 1,000,001 and up. ~ Don't know limit. ...l1l.. No Answer

Page 162: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

142

5.1) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 S Critical Severe Major Minor No Problem Problem Problem Problem Problem

(99.4%)

Contractor practices NA 1 2 3 4 S Inadequate investigation before bidding. 0 23 40 121 8S 7

Bidding below cost. 3 21 S2 87 89 24

Use of wrong equipment. 0 3 16 63 152 42

Failure to follow authorized procedures. 3 10 24 82 137 20

Unbalanced bidding. 2 12 31 79 112 40

Poor planning. 0 23 S3 132 6S 3

Overoptimism. 3 7 26 78 131 31

Delay by contractor. 1 8 38 96 110 23

Delay by subcontractor. 3 14 56 86 96 21

Delay by materials supplier. 1 4 14 51 163 43

Other. (Please specify below)

(99.4%)

SDHPT Practices NA 1 2 3 4 5

Changes in plans and specifications. 1 11 20 86 138 20

Inadequate bid information issued. 3 9 12 48 132 72

Contract requirements (DBE,EEO,Wages) 1 16 28 83 110 38

Overly restrictive specifications. 2 3 11 38 133 89

Delays caused by SDHPT. 1 9 21 54 140 51

Inadequate time allowed for bid prep. 2 11 20 43 110 90

Other. (Please specify below)

Page 163: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

143

5.2) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 5 Critical Severe Major Minor No Problem Problem Problem Problem Problem

(99.5%)

Contract Documents NA 1 2 3 4 5

Errors in plans. 1 13 47 82 126 7

Ambiguities in plans and specifications. 2 17 44 82 117 14

Ommissions in plans. 1 12 37 100 112 14

Other. (Please specify below)

(98.4%)

Contract Administration NA 1 2 3 4 5

Lack of coordination between contractors. 4 8 26 85 131 22

Personality conflicts. 4 4 20 60 144 44

Requests for time extensions. 5 3 20 68 145 35

Delays in processing SDHPT paperwork. 3 3 20 65 135 50

Quantity disagreements. 5 3 10 45 170 43

Construction acceptance or rejection. 6 3 15 51 148 53

Interpretation of plans and specifications. 5 10 32 77 126 26

Time charges. 3 4 17 47 135 70

Extra work. 4 4 15 74 124 55

Delays in providing clear right of way. 7 26 2S 40 94 84

Materials acceptance or rejection. 3 1 11 37 168 56

Other. (Please specify below)

Page 164: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

144

6) How often do contractors bypass your level of authority and approach your superiors

with disputes? (99.3%)

7)

Almost Frequently Sometimes Rarely Almost Always Never

4 21 78 107 64 (1.4'11) (7.6%) (28.3'11) (38.8'11) (23.2%)

If a contractor does bypass your level of authority for disputes;

7.1) How often does your superior contact you for input before making the

decision? (98.2%)

Almost Frequently Sometimes Rarely Almost Always Never 200 38 20 5 8

(72.5%) (13.8%) (7.2%) (1.8%) (2.9%)

72) How often does your superior send the contractor back to you for a decision?

(98.2%)

Almost Always

89 (32.2%)

Frequently

" (23.9%)

Sometimes

72 (26.1%)

Rarely

27 (9.8%)

Almost Never

17 (6.2%)

7.3) How often does your superior make the decision. but informs you of the

result? (97.5%)

Almost Always

45 (16.3%)

Frequently

41 (14.9%)

Sometimes

61 (22.5%)

Rarely

53 (19.2%)

Almost Never

68 (24.6%)

8) Do you feel that there are some contractors who look for disputes as opportunities

to make extra profits on projects? (99.3%)

~ Yes (81.7%)..lL No (11.6%) ..L No Answer (0.7%)

9) If the answer to Question (8) was 'Yes" what percentage of contractors do you

estimate do so? (100% 242/242) [20.1%]

..J.n2.. 1-10% --ll. 11-20% ...32... 21-30% ..lL 31-40% ...lL 41-50%

~ 51-60% --.1.. 61-70% --L 71-80% ...L 81-90% _4_ 91-1()()%

Page 165: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

145

10) Please indicate the number of disputes you handle per average week. (97.8%)

[3.9 Disputes!Week]

..lZi. 1 to 5

-1.. 21 to 25

-2L 6 to 10

--L 26 to 30

...ll- 11 to 15

.JL.. 31 to 35

-L 16 to 20

.JL.. 36 to 40

11) What percentage of disputes are you able to resolve in order to avoid claims?

(97.1~) [85.3% Resolution]

-1L 1-10% -L 11-20% -L 21-30% -L 31-40% JL 41-50%

-L 51--60% _4_ 61-70% -L 71-80% M- 81-90% ..182... 91-100%

12) Using the following scale, please rate the most common alternatives in resolving

disputes by placing an 'X' in the appropriate column.

1 2 3 Almost Frequently Sometimes Always

(97.9%)

Alternatives Involved in Resolving Disputes NA

Extra Work Order. 4

Field Change. 3

Supplemental Agreement. 6

Field Change and Supplemental Agreement. 6

Informal Agreement between Inspector and 5 Contractor.

Informal Agreement between Resident 5 Engineer and Contractor.

Informal Agreement between District 9 Construction Engineer and Contractor.

Informal Agreement between District Engineer 11 and Contractor.

Time Extensions. 4

Other. (Please specify below)

4 Rarely

1 2

17 66

36 110

21 90

39 106

28 53

21 66

2 11

3 6

7 38

3

114

99

111

89

99

106

67

23

135

5 Almost Never

4

32

22

38

26

44

38

76

69

57

5

43

6

10

10

47

40

111

164

35

Page 166: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

146

13) If a dispute cannot be settled at your level, how often do you receive answers from

your superiors in a timely fasbion? (99.3%)

Almost Frequently Sometimes Always

160 90 19 (58.0%) (32.6%) (6.9%)

Rarely

4 (1.4%)

Almost Never

1 (0.4%)

14) Please indicate the number of hours you spend handling disputes during the normal

forty hour week. (97.5%) [5.0 Hours/Week]

--1Z2.. 1 to 5 ...n... 6 to 10 -1L 11 to 15 -L 16 to 20

---L 21 to 2S -L 26 to 30 ..-JL 31 to 35 -L 36t04O

15) Please estimate tbe number of man-hours your staff spends bandling disputes during

the normal forty hour week. (Please include only your directly supervised staff. Do

not include yourself in this estimate.) (95.3%) [10.6 Hours/Week]

-122.. 1 to 5 -SL 6 to 10 ~ 11 to 15 -1L 16 to 20

-lil 21 to 2S ...lL 26 to 30 --L 31 to 35 --L 36 to 40

--.Jl 41 to 45 -L 46 to 50 -L 51 to 55 -L 56 to 60

---L 61 to 65 -L 66 to 70 ..-JL 71 to 7S ..-JL 76 to 80

~ 80 + (Please show estimate). 90, 120 hrs.

16) Are you familiar with the SDHPT claims resolution and prevention policy? (99.6%)

...m.. Yes (85.1%) ~ No (14.5%) -L No Answer (0.4%)

17) Do you feel that requiring contractors to submit formal, written, itemized notices of

disputes to District personnel can help lower the number of disputes? (100%)

l.7.L Yes (64.9%) .1L No (35.1%) -2- No Answer (0.0%)

Page 167: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

147

18) Do you feel that requiring contractors to submit fonnal, written, itemized notices of

disputes to the District can help defend the State against disputes which become

claims? (100%)

..lO2.. Yes (75.7%) ..JiL No (24.3%) -L No Answer (0.0%)

19) What additional measures can the State take to reduce the number of disputes which

become claims?

20) Do you feel Contractors are filing more claims than before due to the current

condition of the State ecomomy ? (98.6%)

...lJ1. Yes (49.6%) ..ui. No (48.9%) -L No Answer (1.4%)

21) If the answer to Question (20) was 'No', please list other causes for Contractors to

file more claims than before.

THANK YOU FOR YOUR TIME AND EFFORT.

Page 168: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

150

SURVEY COMMENTS TO QUESTION 21

TOT DE DeE RE PE Comment

25 0 2 15 8 Increasing competition for projects.

20 1 2 5 12 Contractors bidding too low.

19 2 1 9 7 Increase In out-of-state contractors.

18 0 1 4 13 Contractors using claims as extra profits.

17 1 2 8 6 Introduction of claims consultants/lawyers.

15 3 1 8 3 Claims Committee too free with settlements.

14 2 1 7 4 Increasingly litigious society.

14 1 1 4 8 Poor plans and specification quality.

12 0 0 6 6 Unskilled Contractor supervisors.

8 0 0 5 3 Inexperienced SDHPT personnel.

5 1 2 2 0 DBE subcontractors.

5 0 1 3 1 Process of disputes too easy.

4 0 1 1 2 Escalating Insurance costs.

4 0 1 1 2 Lack of experienced. skilled workers.

4 0 0 4 0 SDHPT too lenient with contractors.

4 0 0 2 2 Contractors better organized.

3 0 1 1 1 Plans prepared by consultants.

3 0 0 1 2 Projects now are more complex In nature.

2 1 0 0 1 Traffic control plan disputes.

2 0 1 1 0 Contractors spread too thin on projects.

2 0 1 0 1 Extra work.

2 0 0 1 1 New contractors with no experience.

2 0 0 0 2 Utility adjustment delays.

2 0 0 1 1 Contractor not knowing what to expect.

Page 169: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

151

SURVEY COMMENTS TO QUESTION 21 (CONTINUED)

TOT DE DeE Comment

2 1 0 0 1 Poor planning by contractors.

1 0 1 0 0 More projects - more claims.

1 0 1 0 0 Requiring work outside scope of contract

1 0 0 1 0 Negotiated settlements of disputes.

1 0 0 1 0 Not enough time to perform contract.

1 0 0 1 0 Field change process takes too long.

1 0 0 1 0 Additional responsibilities placed on contractors.

1 0 0 1 0 Problems with national economy.

1 0 0 1 0 Increasing number of subcontractor defaults.

1 0 0 0 1 Increase in unbalanced bidding.

1 0 0 0 1 Poor communications.

1 1 0 0 0 Time charges returned to contractor.

1 0 0 0 1 Poor quality of field surveys used for plans.

Page 170: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

TEXAS STATE DEPARTMENT OF HIGHWAYS AND PUBLIC TRANSPORTATION

CONTRACTORS CLAIMS AND DISPUTES SURVEY

COMBINED RESULTS

152

Note: This survey should be completed only by personnel with authority to settle claims with the Texas State Department or Highways and Public Transportation.

Large Contractors --1.!- (45.2%) Small Contractors ~ (54.8%)

1) What is your position in the company? (90.5%)

Presidents • 19 (45.2%) Managing Partner • 1 (2.4%) Division Head • 1 (2.4%)

Vice Presidents • 14 (33.3%) General Manager • 1 (2.4%) Secretary • 1 (2.4%)

2) Using the following scale, please indicate the limitations for dispute approval for

each of the positions listed by writing the appropriate letter in the blank column.

A· $ ° to 1,000

D· $ 10,001 to 20,000

G - $ 100,001 to 200,000

J - $ 1,000.001 and up.

Position N

Title A

President 2

Vice-President 10

Project Manager 13

Project Supervisor 11

Project Engineer 23

Other.

A B

0 0

2 1

6 1

15 9

11 4

B· $ 1,001 to 5,000

E· $ 20,001 to 50,000

H· $ 200,001 to 500,000

(67.1%)

Limitation Code

c· $ 5,001 to 10,000

F· $ 50,001 to 100,000

I - $ 500,001 to 1,000,000

DoUar

C D E F:G:t H 1 J Limitation

0 0 1 o 0 10 28 $892,125

0 3 4 4 2 0 8 8 $462,141

7 3 8 1 0 2 0 1 $74,414

3 2 0 0 1 0 0 1 $39,758

1 1 0 1 0 0 0 1 $58,579

Page 171: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

153

3.1) Using the following scale, please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 Critical Severe Major Minor Problem Problem Problem Problem

(99.3%)

Contractor practices NA 1 2

Inadequate investigation before bidding. 1 1 0

Bidding below cost. 0 5 4

Use of wrong equipment. 0 0 0

Failure to follow authorized procedures. 0 1 3

Unbalanced bidding. 0 0 4

Poor planning. 0 2 5

Overoptimism. 1 0 4

Delay by Contractor. 0 1 1

Delay by subcontractor. 1 4 4

Delay by materials supplier. 0 2 5

Other. (Please specify below)

(99.3%)

SDHPT Practices NA 1 2

Changes in plans and specifications. 0 3 2

Inadequate bid information issued. 0 2 9

Contract requirements. 1 8 8

Overly restrictive specifications. 0 1 4

Delays caused by SDHPT. 0 3 12

Inadequate time allowed for bid preparation. 0 3 5

Utilities not adjusted. 1 14 11

Other. (Please specify below)

3

14

9

5

7

1

8

15

13

16

13

3

19

13

9

9

10

6

6

5 No

Problem

4

23

14

19

20

22

19

16

17

15

18

4

16

18

15

2S

12

18

7

5

3

10

18

11

15

8

6

10

2

4

S

2

0

1

3

3

10

3

Page 172: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

154

3.2) Using the following scale. please rate the severity of each of the factors as they relate

to disputes by placing an 'X' in the appropriate column.

1 2 3 4 Critical Severe Major Minor Problem Problem Problem Problem

(100.0%)

Contract Documents NA 1 2 3

Errors in plans. 0 8 7 11

Ambiguities in plans and specs. 0 7 12 15

Ommissions in plans. 0 10 6 12

Other. (Please specify below)

(99.6%)

Contract Administration r;; 1 2

Lack of coordination between Contractors. 0 3 5

Personality conflicts. 0 0 5

Requests for time extensions. 1 2 4

Delays in processing SDHPT paperwork. 0 2 5

Quantity disagreements. 0 2 4

Construction acceptance or rejection. 1 1 2

Interpretation of plans and specifications. 0 2 7

Time charges. 0 1 8

Extra work. 0 1 5

Delays in providing clear right of way. 0 10 7

Materials acceptance or rejection. 0 1 3

Over-usage of" As directed by the Engineer". 0 13 8

Other. (Please specify below)

3

5

19

15

16

5

9

21

7

14

10

14

11

5 No

Problem

4 5

14 2

8 0

14 0

4

20

13

14

15

28

26

11

21

17

9

21

9

S

9

5

6

4

3

3

1

5

5

6

3

1

Page 173: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

155

4) How often do you feel it is necessary to bypass a level of authority within the

Highway Department to receive answers to construction problems in a timely

fashion? (100.0%)

Almost Always

3 (7.1%)

Frequently

11 (26.2%)

Sometimes

22.5 (53.6%)

Rarely

4.5 (10.7%)

Almost Never

1 (2.4%)

S) H a dispute cannot be settled at the project level. how often do you receive answers

from the Highway Department in a timely fashion? (100.0%)

Almost Always

2 (4.8%)

Frequently

11 (26.2%)

Sometimes

12 (28.6%)

Rarely

13 (31.0%)

Almost Never

4 (9.5%)

6) Do you feel that there are some Contractors who look for disputes as opportunities

to make extra profits on projects? (100.0%)

-.lL Yes (76.2%) ...llL No (23.8%) ~ No Answer (0.0%)

7) If the answer to Question (7) was 'Y est. what percentage of Contractors do you

estimate do so? (103.1% 33/32) [12.6% Responses]

-Z.L 1-10% -L. 11-20%

-L 51-60% -L 61-70%

--L 21-30% -2.. 3140%

.....L 71-80% --.0... 81-90%

~41-50%

--.0... 91·100%

8) Do you feel that the Contractors who file numerous claims against the State hurt the

image of Contractors as a whole? (100.0%)

...3l. Yes (78.6%) -2.. No (1l.4%) ~ No Answer (0.0%)

Page 174: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

156

9) Do you feel these Contractors hurt the process of competitive bidding? (100.0%)

....2l- Yes (54.8%) --12- No (45.2%) -L No Answer (0.0%)

10) If the answer to Question (9) was ·Yes·. please briefly describe how this practice

hurts bidding.

11) Do you feel there are Contractors who intentionally bid low to be awarded a project,

then file claims to recover their losses? (97.6%)

....2l- Yes (54.8%) ...l.a- No (4%.9%) -L No Answer (%.4%)

12) If the answer to Question (ll) was 'Yes', what percentage of Contractors do you

estimate do so? (100.0% 23/23) [10.2% Responses]

JL 1·10% ~ 11·20%

-L 51-60% --2.. 61·70%

~ 21·30% ---2- 31-40%

--2.. 71·80% ~ 81·90%

---1l 41·50%

---1l 91·100%

13) Please indicate the number of disputes your firm encounters per average week.

(95.2%) [3.1 Disputes/Week ]

~ It05

-L 21 to 25

-i 6to 10

--2.. 26 to 30

--2.. 11 to 15 --2.. 16 to 20

--2.. 31 to 35 --2.. 36 to 40

Page 175: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

157

14) What percentage of disputes do you estimate result in the State paying the

Contractor at least part of the dispute value? (97.6%) [32.8% Responses]

...lL 1·10% --1.. 11·20% ~ 21·30% ....l. 31-40% -2. 41·50%

--L 51-60% ---0.. 61·70% ---0.. 71·80% --.6... 81·90% --L 91-100%

15) Please rank the approximate dollar value of disputes that you encounter. with a rank

of 1 being most common and 10 being least common. (72.1%)

--Z.. $ 0 to 1,000

_4_ $ 10,001 to 20,000

--1.. $ 100,001 to 200,000

--1.Q.. $ 1.000,001 and up.

-1- $ 1,001 to 5,000 ....l. S 5.001 to 10,000

..l- S 20.001 to 50,000 ---6.. $ 50,001 to 100,000

....8- $ 200,001 to 500,000 J. $ 500,001 to 1.000,000

16) When the State agrees to pay the Contractor as a result of a dispute, what

percentage of the value of the disputes do you estimate the State pays? (95.2%)

[50.0% Responses]

---L 1·10% ~ 11·20% -..6.. 21·30% -'- 31-40% -12.. 41·50%

--L 51-60% --1.. 61-70% _4 71·80% -1.. 81·90% ....l. 91-100%

17) Do you feel some Contractors are filing more claims than before due to the current

condition of the State ecomomy ? (97.6%)

--'6- Yes (61.9%) ~ No (35.7%) -L No Answer (2.4%)

Page 176: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

158

18) If the answer to Question (17) was 'No', please list other causes for Contractors to

file more claims than before.

19) Using the following scale, please rate the most common alternatives in resolving

disputes by placing an 'X' in the appropriate column.

1 2 3 4 5 Almost Always

Frequently Sometimes

(97.1%)

Alternatives Involved in Resolving Disputes NA

Extra Work Order. 1

Field Change. 1

Supplemental Agreement. 2

Field Change and Supplemental Agreement. 2

Verbal Agreement between Inspector and 1 Contractor.

Verbal Agreement between Resident 1 Engineer and Contractor.

Verbal Agreement between District 1 Construction Engineer and Contractor.

Verbal Agreement between District 1 Engineer and Contractor.

Time Extensions. 1

Other. (Please specify below)

Rarely

1 2

6 12

6 18

4 15

5 13

5 7

2 13

1 1

1 2

3 10

THANK YOU FOR YOUR TIME AND EFFORT.

3

12

12

13

14

12

11

6

3

19

Almost Never

4

8

2

6

6

5

7

18

12

4

5

3

3

2

2

12

8

15

23

5

Page 177: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

159

SURVEY COMMENTS TO QUESTION 10

TOTAL LARGE SMALL Comment

7 1 6 Contractors tum in low bids with preconceived idea to file claims to recover losses.

4 2 2 Contractors who fDe claims get work at the exclusion of other traditional contractors.

4 1 3 Claims oriented contractors cause SDHPT to treat all contractors alike.

4 2 2 Contractors bidding to claim are not bidding same work as others.

2 2 0 Contractors who claim often are subject to more scrutiny from SDHPT than others.

1 1 0 Contractors bidding to claim may be temporarily successful, but not consistently competitive.

1 1 0 Too many claims will result in more restrictive SDHPT specifications.

1 1 0 SDHPT use of stiff pre-quallficatlon standards to limit bidders affects all contractors equally.

1 1 0 Contractors who fDe many claims get good at the process, until SDHPT catches on.

1 1 0 Creates adversarial attitude 0 •

1 0 1 Lack of State laws regulating competetlve bidding hurts process.

1 0 1 SDHPT seems to accept 'Claims Contractors' without prejudice.

1 0 1 Claims cause costs to overrun.

1 0 1 Public feels money Is being wasted on claims.

Page 178: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

160

SURVEY COMMENTS TO QUESTION 18

TOTAL LARGE SMALL Comment

8 6 2 More errors. om missions. and ambiguities in plans and specifications.

6 3 3 Projects being bid so low. there is no room for error. Contractors likely to claim.

4 3 1 Lack of knowledgable and experienced SoHPT project personnel.

2 2 0 Projects becoming more complex.

2 2 0 Unreasonably strict inspectors.

2 2 0 Contractors feel they can file claims without reprisal from the SOH PT.

2 1 1 More competition for projects.

1 1 0 Any hinderance by owner Is potential claim.

1 1 0 Poor quality plans done by consultants. getting design questions answered for these projects.

1 1 0 Increased usage of special speCifications.

1 1 0 Changed conditions.

1 1 0 More delays arising from uncompleted utility adjustments.

1 1 0 Project TCP ambiguous, engineer changes TCP.

1 1 0 Increase In out-of-state contractors.

1 1 0 SoHPT feels contractors getting rich.

1 1 0 Nature of hard dollar contracting.

1 1 0 Increase In use of claims consultants.

1 1 0 Inadequate time allowed for bid preparation.

1 0 1 Contractors feeling slighted will pursue claims.

1 0 1 Poor project level communications.

1 0 1 Late decisions by SOH PT.

1 0 1 Belligerent field engineer attitude.

Page 179: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

1S1

APPENDIX C

CATMOD METHODOLOGY, INPUT, AND OUTPUT

METHODOLOGY FOR SDHPT SURVEYS

The analysis for Questions 5.1 and 5.2 performed at the category level

using the CATMOD prodcedure. Significant differences were located within all

four subgroups. Under the contractor practices section, significant differences

were found between both the levels of authority responding to the survey and

between the individual factors. No significant difference existed for the

interaction between these two variables. Table 35 shows these statistics.

The large chi-square calculated for the position variable indicated a

considerable difference in the levels of respondents. The large chi-square for

the variable CP also showed a significant difference among the individual

factors. Three of these factors proved to be significantly different from the

others. These factors are represented by the variables CP1, CP3, and CPS.

As shown in Table 36 the estimates for variables CP1 and CPS are both

negative, while the estimate for CP3 is positive. This difference in sign indicates

these three factors are significant in opposing ways: Inadequate investigation

before bidding and poor planning by the contractor are both significant

problems, while the use of wrong equipment on construction projects is

significantly not a problem. Table 36 also shows the relative ranking of each

Page 180: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

162

of the factors, as determined by the parameter estimates.

The second part of Question 5.1 had the departmental respondents rate

SDHPT practices. As with contractor practices, the levels of respondents

answered differently. Table 37 shows the calculated values, and Table 38

presents the parameter estimates and ranking of the factors. There was no

significant difference between the factors within the SDHPT practices, nor was

the interaction between the respondents and factors significant.

The first portion of Question 5.2 concerned contract documents.

Significant differences were discovered between the levels of respondents, but

not among the factors. Again, the interaction between the respondents and

factors was insignificant. The results of these calculations are presented in

Table 39 and Table 40 presents the parameter estimates and the ranking of the

factors.

The second portion of Question 5.2 dealt with contract administration.

Once again, a significant difference within the levels of respondents was

discovered. The interaction between the respondents and the factors was

insignificant. These statistics are presented in Table 41. Table 42 shows the

relative ranking of the contract administration factors. Looking at the individual

factors, interpretation of plans and specs stands out as being Significant. Since

there is no significant difference among the factors as a whole, however, this

difference cannot be deemed significant.

The four categories of factors were compared to each other using the

CATMOD analysis procedure. The combined analysis revealed a significant

Page 181: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

163

difference between the levels of SDHPT respondents. More importantly,

however, the categories of factors were significantly different. The interaction

between these two variables was insignificant. Table 43 presents these

statistics, while Table 44 shows parameter estimates and category ran kings.

The SDHPT survey indicates the most significant problems with regard

to claims and disputes arise from the contract documents. As shown by the

parameter estimate for this factor, the contract documents were rated nearly

one full pOint lower than the overall mean for the combined data set. This

difference is highly Significant, as indicated by the large chi-square. The

estimate for the contractor practices is slightly lower than the overall average,

but is not significant when compared to the other categories. The SDHPT

practices category and contract administration categories displayed large chi­

squares (518.32 and 1414.21, respectively) and are therefore significantly

different from the overall mean.

Question 12 discovered significant differences between both the levels

of respondents and the alternatives, but not within the interaction between

these two. Table 45 presents these statistics. Three alternatives are used

significantly more often than the others. These are the field change,

supplemental agreement, and the combination of the two. The informal

agreements between the district construction engineer and contractor, and

district engineer and the contractor are the least frequently used. These two

alternatives are used significantly less than the others. These statistics are

presented in Table 46, along with the relative ranking of the alternatives.

Page 182: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

164

Table 35. Maximum Ukellhood Analysis of Variance Table for Contractor Practices (SDHPT Survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 3603.34 0.0000

CP 9 41.54 0.0000

POS*CP 27 9.27 0.9994

Table 36. Maximum Ukellhood Parameter Estimates for Contractor Practices (SDHPT Survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CP1 Inadequate investigation -0.127 6.40 0.000 2

CP2 Bidding below cost -0.054 1.30 0.255 5

CP3 Wrong equipment 0.150 11.94 0.000 9

CP4 Failure to follow 0.049 1.13 0.288 7 procedure

CP5 Unbalanced bidding 0.044 0.92 0.337 6

CP6 Poor planning -0.154 9.26 0.002 1

CP7 Overoptimism 0.076 2.86 0.091 8

CPS Delay by contractor -0.063 1.59 0.207 3

CPS Delay by sub-contractor -0.057 1.39 0.234 4

CP10 Delay by supplier 0.136 NA NA 10

Page 183: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

165

Table 37. Maximum Likelihood Analysis of Variance Table for SDHPT Practices (SDHPT Survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 2370.86 0.0000

SP 5 6.99 0.2213

POS*SP 15 1.88 1.0000

Table 38. Maximum Likelihood Parameter Estimates for SDHPT Practices (SDHPT Survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

SP1 Changes in plans and -0.060 1.98 0.160 2 specs

SP2 Inadequate bid 0.033 0.66 0.418 5 information issued

SP3 Contract requirements -0.069 2.61 0.107 1

SP4 Overly restrictive specs 0.070 2.93 0.087 6

SP5 Delay by SDHPT 0.007 0.03 0.874 3

SP6 Inadequate time for bid 0.019 NA NA 4 preparation

Page 184: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

166

Table 39. Maximum Ukelihood Analysis of Variance Table for Contract Documents (SDHPT Survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 1033.18 0.0000

CD 5 0.08 0.9593

POS*CD 15 0.55 0.9972

Table 40. Maximum Ukelihood Parameter Estimates for Contract Documents (SDHPT Survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CD1 Errors in plans 0.005 0.01 0.000 2

CO2 Ambiguities in plans and -0.012 0.08 0.255 1 specs

CD3 Omissions in plans 0.007 NA NA 3

Page 185: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

167

Table 41. Maximum Ukelihood Analysis of Variance Table for Contract Administration (SDHPT Survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 4392.82 0.0000

CA 10 10.09 0.4328

POS*CA 30 5.81 1.0000

Table 42. Maximum Ukellhood Parameter Estimates for Contract Administration (SDHPT Survey).

Parm Chi-Sq Prob > VAR Description Est Chi-Sq Rank

CA1 Lack of coordination -0.054 1.38 0.241 2 between contractors

CA2 Personality conflicts -0.006 0.02 0.895

CA3 Requests for time -0.038 0.64 0.422 3 extensions

CA4 Delays in processing 0.029 0.44 0.508 7 SDHPT paperwork

CAS Quantity disagreements 0.045 1.04 0.309 10

CA6 Construction acceptance 0.039 0.79 0.375 9 or rejection

CA7 Interpretation of plans -0.108 5.09 0.024 1 and specs

CAS Time charges 0.033 0.55 0.457 8

CA9 Extra work 0.007 0.03 0.870 6

CA10 Delays in providing clear 0.003 0.00 0.945 5 right-of-way

CA11 Materials acceptance or 0.050 NA NA 11 rejection

Page 186: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

168

Table 43. Maximum Ukellhood Analysis of Variance Table for All Categories (SDHPT Survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 8465.66 0.0000

VARIABLE 4 2089.59 0.0000

POS*VAR 9 3.97 0.9133

Table 44. Maximum Likelihood Parameter Estimates for All Categories (SDHPT Survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CP Contractor practices -0.036 NA NA 2

SP SDHPT practices 0.358 518.32 0.000 3

CD Contract documents -0.878 1357.06 0.000 1

CA Contract administration 0.558 1414.21 0.000 4

Page 187: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

169

Table 45. Maximum Likelihood Analysis of Variance Table for Dispute Resolution Alternatives (SDHPT survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

POSITION 3 2935.10 0.0000

ALTERNATIVE 8 144.97 0.0000

POS*AL 24 16.44 0.8716

Table 46. Maximum Likelihood Parameter Estimates for Dispute Resolution Alternatives (SDHPT survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

AL1 Extra work order -0.030 0.37 0.542 4

AL2 Field change -0.272 24.26 0.000 1

AL3 Supplemental agreement -0.168 10.33 0.001 3

AL4 Field change and -0.235 19.44 0.000 2 supplemental agreement

AL5 Agreement between 0.050 1.21 0.272 7 PE & contractor

AL6 Agreement between 0.008 0.03 0.868 5 RE & contractor

AL7 Agreement between 0.266 38.66 0.000 8 DCE & contractor

ALB Agreement between 0.349 71.28 0.000 9 DE & contractor

AL9 Time extension 0.032 NA NA 6

Page 188: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

170

APPENDIX C

CATMOD METHODOLOGY, INPUT, AND OUTPUT

METHODOLOGY FOR CONTRACTOR SURVEYS

The CATMOD procedure was used to analyze the categorical questions

for the contractor surveys. The analysis for the contractor practices category

located a significant difference between the size of the contractors. The small

contractors tended to rate the contractor practices category harsher than the

large contractors. The factors and the interaction between the size of the

contractors and the factors differed, but not significantly at the 0.05 level. Table

47 shows the calculated statistics on the following page. Also, Table 48 shows

the relative ranking of the factors, as well as the calculated statistics for each

of the parameters.

Within the SDHPT practices category, significant differences were also

discovered between the sizes of contractors, as the large contractors rated the

Department more severely than their smaller counterparts. While the

differences between the SDHPT practices as a group were not significant at the

0.05 level, the contractors singled out contract requirements as a major source

of problems. Once again, there was no significance to the interaction between

the size of the contractors and the factors. Table 49 shows the calculated

statistics, and Table 50 shows the parameter estimates and the rankings of the

Page 189: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

171

factors.

When asked to rate the contract documents as sources of disputes, the

results from the contractors were similar to the SOHPT practices category. The

sizes of respondents were significantly different, but no differences among the

factors or the interaction term were discovered. These calculations are

presented in Tables 51 and 52.

The analysis of the contract administration category produced much the

same result: significant differences between the contractors with no difference

between the factors or the interaction term. The results of these calculations

are presented in Table 53. Also, the results of the analysis between the factors

are presented in Table 54.

Finally, the responses to each of the groups of factors were compared

to each of the other groups of factors. The same method of analysis used for

the comparison of the four categories for the SOH PT survey was used to locate

the differences within the contractor survey. The difference between the sizes

of contractors was not significant at the 0.05 level. The differences between the

categories and the interaction terms, however, were significant. The difference

in the interaction term indicates the small contractors tended to rate the four

categories alike. Similarly, the large contractors tended to answer the

questions alike. In other words, prior knowledge of. the size of the contractor

allowed some degree of predictability of how a respondent rated the

categories. The large contractors tended to rate the contract documents,

contract administration, and SOHPT practices more severely than did the small

Page 190: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

172

contractors. The reverse is true for the contractor practices category, where

the small contractors were the most critical. These differences in the

responses led to the significant differences in the interaction term. The ANOVA

table is presented in Table 55.

Table 56 shows the rankings and the parameter estimates for the

categories. As with the SDHPT survey, the contractors identified the contract

documents as the main source of the Department's claims problems. The

contractors rated the contract documents nearly one full point below the overall

average for all four categories. This difference was significant at the 0.05 level.

The SDHPT practices category was only Slightly below the overall average, and

is not Significant. The contractor practices and contract administration

categories, however, are Significant in the opposite direction.

Finally, the contractors were asked to rate the most common factors

used to resolve disputes with the State. Significant differences were located

between the sizes of contractors and the alternatives. The interaction between

the size of contractors and the alternatives was insignificant. Table 57 presents

these calculated statistics.

Table 58 presents the relative rankings and their corresponding

parameter estimates. The contractors felt the most commonly used tool for

dispute resolution to be the field change. This tool is used significantly more

often than the others. The supplemental agreement, the combination of the

field change and supplemental agreement, the extra work order, and the time

extension completed the list of legitimate dispute resolution alternatives. The

Page 191: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

173

informal agreement with the resident engineer and project engineer followed.

Finally, the informal agreements with the district construction engineer, and

district engineer are the least commonly used alternative for dispute resolution.

The last two alternatives are used significantly less than the others.

Page 192: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

174

Table 47. Maximum Likelihood Analysis of Variance Table for Contractor Practices (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 8.76 0.0031

CP 9 13.54 0.1395

SIZE*CP 9 1.77 0.9946

Table 48. Maximum Likelihood Parameter Estimates for Contractor Practices (Contractor survey).

Parm Chi-Sq Prob > VAR Description Est Chi-Sq Rank

CP1 Inadequate investigation -0.023 0.09 0.764 5

CP2 Bidding below cost -0.051 0.42 0.516 3

CP3 Wrong equipment 0.164 5.25 0.022 10

CP4 Failure to follow 0.060 0.64 0.242 8 procedure

CPS Unbalanced bidding 0.124 2.90 0.089 9

CP6 Poor planning -0.012 0.03 0.873 6

CP7 Overoptimism -0.051 0.42 0.517 4

CP8 Delay by contractor 0.038 0.26 0.612 7

CPS Delay by sub-contractor -0.167 4.07 0.044 1

CP10 Delay by supplier -0.082 NA NA 2

Page 193: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

175

Table 49. Maximum Likelihood Analysis of Variance Table for SDHPT Practices (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 16.20 0.0001

SP 6 18.63 0.0048

SIZE*SP 6 3.01 0.8076

Table 50. Maximum Likelihood Parameter Estimates for SDHPT Practices (Contractor survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

SP1 Changes in plans and 0.075 0.88 0.349 5 specs

SP2 Inadequate bid 0.025 0.09 0.761 4 information issued

SP3 Contract requirements -0.100 1.24 0.266 2

SP4 Overly restrictive specs 0.162 4.37 0.037 6

SP5 Delay by SDHPT -0.071 0.68 0.410 3

SP6 Inadequate time for bid 0.186 5.91 0.015 7 preparation

SP7 Utilities not adjusted -0.277 NA NA 1

Page 194: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

176

Table 51. Maximum Likelihood Analysis of Variance Table for Contract Documents (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 14.45 0.0001

CD 2 0.70 0.7093

SIZE*CD 2 0.00 0.9986

Table 52. Maximum likelihood Parameter Estimates for Contract Documents (Contractor survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CD1 Errors in plans 0.058 0.56 0.453 3

CO2 Ambiguities in plans and -0.055 0.49 0.486 1 specs

CD3 Omissions in plans -0.003 NA NA 2

Table 53. Maximum Likelihood Analysis of Variance Table for Contract Administration (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 27.52 0.0000

CA 11 18.37 0.0733

SIZE*CA 11 4.47 0.9542

Page 195: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

177

Table 54. Maximum Ukellhood Parameter Estimates for Contract Administration (Contractor survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CA1 Lack of coordination 0.108 1.93 0.165 12 between contractors

CA2 Personality conflicts 0.040 0.25 0.617 6

CA3 Requests for time 0.011 0.05 0.825 4 extensions

CA4 Delays in processing 0.018 0.05 0.821 5 SDHPT paperwork

CAS Quantity disagreements 0.097 1.52 0.218 11

CA6 Construction acceptance 0.077 0.93 0.335 10 or rejection

CA7 Interpretation of plans -0.088 1.04 0.308 3 and specs

CAB Time charges 0.059 0.53 0.465 8

CA9 Extra work 0.053 0.43 0.513 7

CA10 Delays in providing clear -0.158 3.17 0.075 2 right-of-way

CA11 Materials acceptance or 0.071 0.80 0.370 9 rejection

CA12 Over-usage of has -0.288 NA NA 1 directed by Engineer"

Page 196: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

178

Table 55. Maximum Ukelihood Analysis of Variance Table for All Categories (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 2.72 0.0990

VAR 3 861.58 0.0000

SIZE*VAR 3 33.20 0.0000

Table 56. Maximum UkeUhood Parameter Estimates for All Categories (Contractor survey).

Parm Chi-Sq Prob> VAR Description Est Chi·Sq Rank

CP Contractor practices 0.541 434.13 0.000 3

SP SDHPT Practices -0.119 NA NA 2

CD Contract documents -0.983 516.36 0.000 1

CA Contract administration 0.551 451.41 0.000 4

Page 197: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

179

Table 57. Maximum Likelihood Analysis of Variance Table for Dispute Resolution Alternatives (Contractor survey).

Source Degrees of Chi-Square Probability > Freedom Chi-Square

SIZE 1 5.57 0.0183

AL 8 44.24 0.0000

SIZE*AL 8 4.03 0.8548

Table 58. Maximum Likelihood Parameter Estimates for Dispute Resolution Alternatives (Contractor survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

AL1 Extra work order -0.107 1.48 0.224 4

AL2 Field change -0.219 5.59 0.018 1

AL3 Supplemental agreement -0.162 3.21 : 0.073 2

AL4 Field change and -0.162 3.20 0.074 3 Supplemental agreement

AL5 Agreement between 0.065 0.62 0.431 7 PE & contractor

AL6 Agreement between 0.009 0.01 0.913 6 RE & contractor

AL7 Agreement between 0.286 14.71 0.000 8 DCE & contractor

ALB Agreement between 0.335 20.90 0.000 9 DE & contractor

AL9 Time extension -0.045 NA NA 5

Page 198: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

180

APPENDIX C

CATMOD METHODOLOGY, INPUT, AND OUTPUT

METHODOLOGY FOR COMPARISON OF SDHPT TO CONTRACTOR

SURVEYS

Finally, the four categorical questions (contractor practices, SDHPT

practices, contract documents, and contract administration) were combined

and compared to the survey respondents (SDHPT and contractor surveys).

The combined data set was analyzed using the CATMOD procedure as before.

ignoring the effects of SDHPT position and contractor size. The analysis

revealed significant differences between the respondents, categories, and the

interaction between the two. The calculated values are presented in Table 59.

The large chi-square for the SURVEY variable indicates the difference

between the respondents. In general, the contractors tended to rate the

factors related to disputes and claims more critically than the SDHPT

respondents. The large interaction chi-square indicates a relationship between

the respondents and the ranking of the categories. As could be expected, the

contractors were critical of the Department, rating the SDHPT practices,

contract documents, and contract administration categories more severely than

the SDHPT respondents. Also according to expectation, the SDHPT

respondents rated the contractor practices more severely than did the

Page 199: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

181

contractors. This two-way finger pointing resulted in the large interaction term.

Finally. the large chi-square value for the parameter VAR indicates a significant

difference among the categories of factors. Consistent with the individual

analyses, the contract documents were Singled out as the main problem area

by the combination of the SDHPT and contractor surveys. This variation from

the mean response was highly significant. The rankings and the parameter

estimates are presented in Table 60. The SDHPT practices category was

ranked second, but is probably not significantly different from the mean. Also

similar to the individual analyses, the contractor practices and contract

administration categories were significantly different from the mean. The

positive values of the parameter estimates indicate these categories less of

problem areas than the contract documents.

Page 200: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

182

Table 59. Maximum Ukellhood Analysis of Variance Table for All Categories (Combined survey).

Degrees of Chi-Square Probability > Source Freedom Chi-Square

SURVEY 1 9877.79 0.0000

VAR 3 874.98 0.0000

SURVEY*VAR 3 38.53 0.0000

Table 60. Maximum Likelihood Parameter Estimates for All Categories (Combined survey).

Parm Chi-Sq Prob> VAR Description Est Chi-Sq Rank

CP Contractor practices 0.535 430.75 0.000 3

SP SDHPT Practices -0.111 NA NA 2

CD Contract documents -0.974 526.47 0.000 1

CA Contract administration 0.550 459.36 0.000 4

Page 201: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

APPENDIX C

CATMOD METHODOLOGY, INPUT, AND OUTPUT

SAMPLE CATMOD OUTPUT

Response: POS*SP Weight Variable: RES Data Set: SOHPTl

SAS 18:35 SU'lday. NOYeIItIer 18, 1990

SOHPT Survey

CA TM(!) PROCEDURE

Response Levels (R)= 24 Populations (S). 1 Total Frequency eN): 6079 Observations (Obs). 1621

MAXIMUM LIKELIHOOD ANALYSIS OF VARIANCE TABLE

Source OF Chi-Square Prob

POS SP pos*SP

3 5

15

LIKELIHOOD RATIO 0

2370.86 6.99 1.88

0.0000 0.2213 1.0000

ANALYSIS OF MAXIMUM LIKELIHOOD ESTIMATES

Standard Chi-Effect Parameter Estimate Error Square Prob

_RESPONSE_ 1 -1.1028 0.0422 681.66 0.0000 2 -0.7101 0.0363 382.54 0.0000 3 0.9318 0.0232 1618.23 0,0000 4 -0.0598 0.0425 1.98 0.1589 5 0.0334 0.0412 0.66 0.4180 6 -0.0691 0.0428 2.61 0.1065 7 0.0699 0.0408 2.93 0.0868 8 0.00659 0.0415 0.03 0.8738 9 0.0579 0.0948 0.37 0.5415

10 -0.00139 0.0932 0.00 0.9881 11 -0.0229 0.0978 0.06 0.8145 12 -0.0380 0.0931 0.17 0:6833 13 0.0254 0.0933 0.07 0.7856 14 -0.0258 0.0836 0.10 0.7576 15 0.000217 0.0801 0.00 0.9978 16 0.0567 0.0820 0.48 0.4891 17 0.00761 0.0789 0.01 0.9232 18 -0.00730 0.0810 0.01 0.9282 19 -0.00651 0.0528 0.02 0.9020 20 -0.00131 0.0511 0.00 0.9796 21 -0.00199 0.0532 0.00 0.9702 22 0.00894 0.0505 0.03 0.8595 23 -0.00n6 0.0516 0.02 0.8804

NOTE: _RESPONSE_ • POS SP POS*SP

184

Page 202: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Response: POS*CP weight Variable: RES Data Set: COMBINED

SAS 19:07 St.nday. Novenber 18. 1990

Contractor Survey

CATMOD PROCEDURE

Response Levels (R)= 20 Populations (S)= 1 Total Frequency eN). 1546 Observations (Obs): 417

MAXIMUM LIKELIHOOD ANALYSIS OF VARIANCE TABLE

Source Df Chi·Square Prob - ...... -_ .. __ ._---_._---.. _---.----------- ..... -_. POS 1 8.76 0.0031 CP 9 13.54 0.1395 POS*CP 9 1.n 0.9946

LIKELIHOOD RATIO 0

ANALYSIS OF MAXIMUM LIKELIHOOD ESTIMATES

Standard Chi· Effect Parameter Estimate Error Square Prob ----.----.--.---.--------.... -----~----.- .. ---------------------_RESPONSE - 1 0.0759 0.0256 8.76 0.0031

2 ·0.0232 0.0775 0.09 0.7643 3 ·0.0510 0.0784 0.42 0.5160 4 0.1636 0.0714 5.25 0.0219 5 0.0598 0.0747 0.64 0.4234 6 0.1236 0.0726 2.90 0.0888 7 -0.0123 o.om 0.03 0.8733 8 -0.0510 0.0787 0.42 0.5165 9 0.0383 0.0755 0.26 0.6121

10 -0.1666 0.0826 4.07 0.0437 11 -0.0358 0.0775 0.21 0.6435 12 -0.0210 0.0784 0.07 0.7887 13 -0.0150 0.0714 0.04 0.8333 14 -0.0329 0.0747 0.19 0.6595 15 -0.00679 0.0726 0.01 0.9255 16 0.00324 o.om 0.00 0.9665 17 0.0541 0.0787 0.47 0.4917 18 0.0119 0.0755 0.02 0.8752 19 -0.0297 0.0826 0.13 0.7194

NOTE: _RESPONSE_ .. POS CP POS*CP

185

Page 203: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAS 18:35 Sunday, November 18, 1990

Comparison of SDHPT to Contractors

CATMOO PROCEDURE

Response: SURVEY*CD Weight Variable: RES Data Set: COMB2

Response Levels (R)= Populations (S)= Total Frequency (N)= Observations (Obs).

7 1

2938 923

Effect

MAXIMUM LIKELIHOOD ANALYSIS OF VARIANCE TABLE

Source

SURVEY CD SURVEY*CD

DF Chi-Square

1 2 2

1280.67 0.63 0.49

Prob

0.0000 0.7294 0.7816

LIKELIHOOD RATIO 0

ANALYSIS OF MAXIMUM LIKELIHOOD ESTIMATES

Standard Chi-Parameter Estimate Error Square Prob

1 -3.9030 2 0.0522 3 -0.0531 4 0.0533 5 -0.0439

0.6744 0.0755 0.0776 0.0805 0.0824

33.50 0.0000 0.48 0.4894 0.47 0.4932 0.44 0.5075 0.28 0.5943

NOTE: _RESPONSE_ • SURVEY CD SURVEY*CD

186

Page 204: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 205: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

APPENDIX D

SUPPORTING CALCULATIONS (SAS OUTPUT)

SAS 18:10 Monday, November 19, 1990 8

TABLE OF SURVEY BY VAR FOR COMPARISON OF SOHPT TO CONTRACTORS DICHOTOMOUS QUESTIONS

SURVEY VAR

Frequencyl Percent I Row Pct Col Pct !EConomy :Extra' : Total ••••••••• + •••••••• + •••••••• +

Contr I 26 I 32 I 58 I 5.95 I 7.32 I 13.27 I 44.83 I 55.17 I I 15.95 I ".68 I

••••••••• + •••••••• + •••••••• +

SOHPT I 137 I 242 I 379 I 31.35 I 55.38 I 86.73 I 36.15 I 63.85 I I 84.05 I 88.32 I

••••••••• + •••••••• + •••••••• + Total 163 274 437

37.30 62.70 100.00

STATISTICS FOR TABLE OF SURVEY BY VAl

Statistic DF

Chi-Square 1 Likelihood Ratio Chi·Square 1 Continuity Adj. Chi'Square 1 Mantel·Kaenszel Chi·Square 1 Fisher's Exact Test (Left)

(Right) (Z·TaH)

Phi Coeff i ci ent Contingency Coefficient Cramer's V

Sample Size = 437

Value

1.620 1.590 1.271 1.617

0.061 0.061 0.061

Prob

0.203 0.207 0.260 O.Z04 0.921 0.130 0.243

187

Page 206: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAS 18:28 Saturday, Novenber 17, 1990 3

--.--------- .•• -•• ---------- •• -- ••. VAR-BY3 •••. --- ••• ---.----.--.-.- ••• ------.

TABLE Of RES BY POS FOR SDHPT SURVEY MULTIPLE'ANSWER QUESTION

RES POS

Frequency' Percent I Row Pct I Col Pct, DEI DCEI REI PEl -_._. __ ._+_ •••••• -+--_ •• _-.+-_ ••• _--+ •• -.-.-.+

1 ' 8 I 15 I 53 ' 13 I I 3.05 I 5.73 I 20.23 I 4.96 I I 8.99 I 16.85 I 59.55 I 14.61 I I 61.54 I 65.22 I 46.09 11.71 I

-_._ •• _-.+_ ••••• _.+-_ •••••• +._----._+.- ••••• _+

2 I 2 I 2 I 31 I 28 I I 0.76 I 0.76 I 11.83 I 10.69 I I 3.17 I 3.17 I 49.21 I 44.44 I I 15.38 I 8.70 I 26.96 I 25.23 I

••••••••• + •••••••• + •••••••• + •••••••• + •••••••• +

3 I 2 I 3 I 21 1 43 I I 0.76 I 1.15 I 8.02 I 16.41 I I 2.90 I 4.35 I 30.43 I 62.32 I I 15.38 I 13.04 I 18.26 38.74 I

-_ ••••••• + •••••••• + •••••••• + ••••••• _+ •••••••• + 4 I 0 I 1 I 6 I 18 I I 0.00 I 0.38 I 2.29 I 6.87 I

I 0.00 I 4.00 I 24.00 I 72.00 I I 0.00 I 4.35 I 5.22 I 16.22 I

••• _ ••••• + •••••••• + •••••••• + •••••••• + •••• __ •• +

51 '1 21 41 91 I 0.38 I 0.76 I 1.53 I 3.44 I I 6.25 I 12.50 I 25.00 I 56.25 I I 7.69 I 8.70 I 3.48, 8.",

.-•• _ •••• +- ••••••• + •••••••• + •••••••• + •••••••• +

Total

89 33.97

63 24.05

69 26.34

25 9.54

16 6.11

Total 13 4.96

23 115 111 262 8.78 43.89 42.37 100.00

STATISTICS FOR TABLE OF RES BY POS

Statistic DF

Ch i . Squa re 12 Likelihood Ratio Chi'Square 12 Mantel'Haenszel Chi'Square 1 Phi Coefficient Contingency coefficient Cramer's V

Sample Size s 262

Value

56.935 61.828 28.746 0.466 0.423 0.269

Prob

0.000 0.000 0.000

WARNING: 35% of the cells have expected counts less than 5. Chi'Square may not be a valid test.

188

Page 207: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAS 18:10 Monday, November 19, 1990 6

TABLE OF VAR BY POS FOR SDHPT SURVEY DICHOTOMOUS QUESTIONS

VAR POS

Frequency I Percent I Row Pc:t I Col Pc:t IDCE IDE IPE IRE I ---_.-... + ..... _--+-----_ .. +--------+-_ ... _--+ Defend I 14 I 12 I 86 I 92 I

I 1.43 I 1.22 I 8.78 I 9.39 I I 6.86 I 5.88 42.16 I 45.10 I I 16.47 I 20.69 I 21.94 I 20.67 I

_._------+-----_._+--------.---_. __ .+_ ... -... + Ec:onomy I 13 I 9 I 54 I 56 I I 1.33 I 0.92 J 5.51 I 5.71 I

I 9.85 I 6.82 I 40.91 I 42.42 I I 15.29 I 15.52 I 13.78 I 12.58 I ---_ ..... +_ ....... +.- ...... + ..... _--+_._ ..... +

Extra1 ' 23 ' 15 I 94 I 106 I I 2.35 I 1.53 I 9.59 I 10.82 I I 9.66 I 6.30 I 39.50 I 44.54 I I 27.06 I 25.86 I 23.98 I 23.82, -_ ....... + ...... _.+_ ....... + •••••••• + ........ +

Lower I 12 I 8 I 75 I 79 I I 1.22 I 0.82 I 7.65 I 8.06 I I 6.90 I 4.60 I 43.10 I 45.40 I , 14.12, 13.79 I 19.13 I 17.75, ......... + .... _-_.+ ........ + ........•........ +

PoLicy I 23 I 14 I 83 I 112 I I 2.35 I 1.43 I 8.47 I 11.43 I I 9.91 I 6.03 I 35.78 J 48.28 I , 27.06 I 24.14 I 21.17 I 25.17 I

••••••••• + ••••••• _+ ••••••• - ••••••••• + ••••••• _+

Total 85 58 392 445 8.67 5.92 40.00 45.41

STATISTICS FOR TABLE OF VAR BY POS

Statistic: OF Value

Total

204 20.82

132 13.47

238 24.29

174 17.76

232 23.67

980 100.00

Prob .. ----------------_.-----_.--_ .. ----------------------Chi-Square 12 Likelihood Ratio Chi'Square 12 Hantel'Haenszel Chi'Square 1 Phi Coefficient Contingency Coefficient Cramer's V

Sample Size = 980

5.510 5.636 0.011 0.075 0.075 0.043

0.939 0.933 0.916

189

Page 208: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAS 18:28 Saturday, November 17, 1990 17

------------------------------.---- VAR=BY1 ------ •• ---.----------- •• -.--------

TABLE OF PaS BY RES FOR CONTRACTOR SURVEYS MULTIPLE·ANSWER QUESTION

PaS RES

Frequency I Percent I Row Pct I Col Pct I 11 21 31 41 Total _._------+._ ...•. _+---_.---+._ •.. ---+--_._---+ Large I 1 I 7 I 7 I 1 I 16

I 3.12 I 21.87 I 21.87 I 3.12 I 50.00 I 6.25 I 43.75 I 43.75 I 6.25 I I 33.33 I 63.64 I 46.67 I 33.33 I _ .. _-----+. __ ._-_.+. __ ._ ..• +.- ..•... +._ .. _-_.+

Small I 2 I 4 I 8 I 2 I 16 I 6.25 I 12.50 I 25.00 I 6.25 I 50.00 I 12.50 I 25.00 I 50.00 I 12.50 I I 66.67 I 36.36 I 53.33 I 66.67 I ------_ .. +--...... +._ .. _ ... +-_ ...... +_._-_ .. _+

Total 3 11 15 3 32 9.38 34.38 46.88 9.38 100.00

STATISTICS FOR TABLE OF PaS BY RES

Statistic OF

Chi'Square 3 likelihood Ratio Chi-Square 3 Mantel'Haenszel Chi'Square 1 Phi Coefficient Contingency Coefficient Cramer's V

Sample Size = 32

Value

1.552 1.575 0.195 0.220 0.215 0.220

Prob

0.670 0.665 0.659

WARNING: 50X of the cells have expected counts less than S. Chi-Square may not be a valid test.

190

Page 209: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

APPENDIX E

SAMPLE SDHPT CONSTRUCTION FORMS State Department of Highways and Public Transportation FORM 112A (ROSCOE 9-B9)

APPROVAL OF CHANGE IN PLANS

191

F.C. Req. Ho. _ Accomp. by Sketches or F.C. Plan-Sheets Numbered Hwy. No. ___ _ County. Federal Proj. No. Control

~TO~T~HE~E~NG~I~NE~E~R~-D~I~R~ECnT~OR~:~ ------------Approval of the following changes in plans and/or specifications is requested. limits: SU. to Sta. _______ _ Description:

ThiS field change is requested for the following reasons:

Supported by Supplemental Agreement No. __ _ and by Extra Work Order No. __ __ Contractor:

,Contract' ,Contract I Item No. Description Unit Quantity Price Amount Quantity Price Amount

Additional Days

Time Extension No.

RESPECTFULLY REQUESTED ey:

(S) Resident Engineer Date

(S) District Construction Engineer Date

Tota 1-------.:.$ _____ _ Tota 1------,:.$ _____ _

Net Underrun$ ""------- Net Overrun~$ _____ _

APPROVED BY:

(5) District Engineer Date

INSTRUCTIONS: This form to be used for changes approved by the District Engineer.

Page 210: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

192

~tate Department of Highways and Public Transportation fORM 1128 (ROSCOE 9-89)

APPROVAL OF CHANGE IN PLANS

F.t. Req. No. Accornp. by Sketches or F.C. Plan-Sheets Numbered Hwy. No. ___ _ ""","""",,",""""""""""""'J"',-'I':"-'" -"'I"II:"I-",,=~County. Federal Proj. No. ContrOl ______ _ TO THE ENGINEER-DIRECTOR:

Approval of the following changes in plans and/or specifications is requested. Limits: Sta. to Sta. _______ _ Description:

This field change ;s requested for the following reasons:

Supported by Supplemental Agreement No. __ _ and by Extra Work Order No. __ _ Contractor:

Item No. Description

Additional Days __

Time Extension No.

RESPECTFULLY REQUESTED BY:

(5) Resident Engineer

(S) District Construction Engr

(S) District Engineer

I NSTRUCTI ONS: To be used for changes approved by the Construction Division or the Administration

Unit

Date

Date

Date

IContractl !Contractl Quantity Price Amount Quantity Price I Amount

I

I I I

Tota 1-------:.=.$ _____ _ Toto.l------.;:.S _____ _

Net Underrun::.S _____ _ Net Overrun . .;:.$ _____ _

RECOMMENDED FOR APPROVAL BY:

Chief Engineer. H1ghway Design Date

Chief Eng •• Safety & Main. Operations Date

Bridge Engineer Date

APPROVED ____ --=:::-r:==~=;::_:_~ __ - _-,,:'=_ Construct1on Engineer Date

APPROVEO._---;::-:-:-~~-",=~_::_..__,.,.--.-.--__ ......-.:~_ Deputy Dir Design & Construction Date

Page 211: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

~tate Uepartment of Highways and Public Transportation Construction FORM 317A (ROSCOE 9-89)

193

EXTRA WORK ORDER NO.

County ______ Project ________ Control, _____ ......:Highway ____ _

Date Statlon'-__________ to Stat;on'-________ _

To,_.....,,~~~~_=--------------__ ----- • contractor on the above project.

This will be your authority to proceed with the following force account work. The Engineer will have an inspector in charge of work at all t1mes, and dally reports are to be rendered, signed by both parties.

Work consists of

and General Specification Items 4.4, 9.3, I II

Equipment IAgreed Ratell

I II I 11

I II I II

I II I II I II I II I II I II . II

Estimated Cost to be.-Z,.$ ____ _

Sealed Copy on file __

Days added __ Time Extension No.

by (5)

agree to do the above work at the rates named.

Contractor's Representative Date

9.4, 9.5, and 9.6 are to govern. I I

Labor IAgreed Ratel

I I I I I I I I I I I I I I I I I I I I I I

by (S) Resident Engineer Date

Approved by: (S)

District Engineer Date

Page 212: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

194

State Department of Highways and Pub11c Transportation Construction FORM 3178 (ROSCOE 9-89)

EXlRA WORK ORDER NO.

County ______ ,Project ________ Control ______ H,ighway ____ _

Date Station ____________ to Station~ _______ _

TO'_~'L'.:":":_:_:=_:;_:_::7"""--------------------' contractor on the above project.

This will be your authority to proceed with the following force account work. The Engineer will have an inspector in charge of work at all times, and daily reports are to be rendered. Signed by both parties.

Work consists of

and General Specification Items 4.4, 9.3, 9.4, 9.5, and 9.6 are to govern. I" I I

Equipment IAgreed Rate I I labor IAgreed Rate I I II I I I II I I I II I I I II I 1 I II I I I II I I I II I I I II I ~ I II : I I II I I I II I I

Estilllated Cost to be'-'S"'--___ _ by (S) Resident Engineer Date

Sealed Copy on File __

Days added __ Time Extension No.

1 agree to do the above work at the rates named.

by (S) Contractor's Representative Date

Approved by: (5)

District Engineer Date

Engr •• Canst. & Cont. Adm. Date

Deputy Dir., Field Oper. Date

Page 213: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAMPLE

(SUPPLEMENTAL AGREEMENT FOR DISPUTE RESOLUTION ON AN ONGOING PROJECT)

SUPPLEMENTAL AGREEMENT NO. _

PROJECT: CONTROL: HIGHWAY: COUNTY :

WHEREAS, on the _ day of ,19_ a contract was entered into by and between the State of Texas represented by the Engineer-Director and , Contractor for construction of certain improvements on that portion of SH _ in County, Texas and designated as Project , and;

WHEREAS, the Contractor has expressed in writing his disagreement with the contract working days charged based upon delays because of conflicts with water lines, sewer lines, power lines and railroad tracks; and further the contractor has paid the power company approximately $3,800 for relocating a power line a second time while reserving all rights of claim, and; (DISCUSSION OF PROBLEM)

WHEREAS, to bring these differences to a mutually satisfactory agreement the parties hereto have met and discussed these problems in depth and; (JUSTIFICATION AND ACTION)

THEREFORE, have agreed that the Contractor is hereby granted 123 additional working days and that this is a fair, reasonable and equitable resolution of the above problems that occurred prior to February 28, 1988 and that it is further agreed that there will be no further claims by the Contractor for delays or otherwise, as may result from these actions.

195

Page 214: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

SAMPLE

(SUPPLEMENTAL AGREEMENT FOR DISPUTE RESOLUTION ON COMPLETED PROJECTS)

SUPPLEMENTAL AGREEMENT NO.

PROJECT: CONTROL: HIGHWAY: COUNTY :

WHEREAS, on the _ day of ,19_ a contract was entered into by and between the State of Texas represented by the Engineer-Director and , Contractor for certain improvements on that portion of SH __ in County, Texas and designated as Project , and;

WHEREAS, during the course of the subject project, the Contractor requested additional compensation in the amount of $28,656.00, such amount allegedly incurred by the Contractor for unpaid borrow tickets, and; (DISCUSSION OF PROBLEM)

WHEREAS, after careful review of the Contractor's request, the project pay records, and the nature of the project, it has been determined appropriate that a portion of the claim in the amount of $14,375.02 be paid, such amount representing compensation to cover said unpaid tickets, and; (JUSTIFICATION AND ACTION)

THEREFORE, have agreed between the parties hereto that a lump sum payment to the Contractor in the amount of Fourteen Thousand Three Hundred Seventy-Five Dollars and Two cents ($14,375.02) in consideration of the above-mentioned items of the claim is fair and reasonable, and constitutes full and final payment for said unpaid tickets, and; (RESOLUTION)

IT IS THEREFORE AGREED, that the Contractor hereby waives any claim for additional compensation due to any and all other expenses or loss of compensation incurred in the performance of this contract to date. (DISCLAIMER)

196

Page 215: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

Project IUghway County

STA'!'S OEPA.RTMEm' OF HIGH' •• I>.YS AND PUBLIC TRANSPORTATION

CONTRACTOR

Resident Engineer Date

Executed for the State Engineer Director and approved for the State Highway and Public Transpor-

{Firm}

By:

tation Commission under Minute SURETY APP~ Order 82513 and Administrative Order 32-87, for the purpose and efffect of activating and/or carrying (Firm) out the orders. established policies or ~~rk programs heretofore approved By: and auth~rized by the State Highway 3nd Public Transportation Commission.-

District £nglneer Date

Date

197

Page 216: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to

MICHAEL PETER LEHMANN 5055 Oriole Beaumont, Texas 77707

198

VITA

Engineer I, Texas State Department of Highways and Public Transportation

EDUCATION

B.S., Civil Engineering, Texas A&M University. December 1984

EXPERIENCE

Engineering Assistant, Texas State Department of Highways and Public Transportation, Hardin County Resident Office, District 20, February 1986 to December 1989.

Engineering Assistant, SDHPT, District 20 Design Office, Beaumont, May 1985 to February 1986.

Engineering Aide, SDHPT, Orange County Resident Office, District 20, May 1984 to August 1984.

Student Laborer, Texas Transportation Institute, Riverside Campus, October 1983 to January 1984 and October 1984 to December 1984.

MEMBERSHIPS AND HONORS

Chi Epsilon American Society of Civil Engineers American Society of Civil Engineers. President, Texas A&M Student Chapter,

1984 ASCE Student Chapter "42" Tournament Co-Champion, Spring 1990

FIELDS OF EXPERIENCE

Mr. Lehmann been a full-time employee of the Highway Department from May 1984 to the present. Experience during this time frame included geometric deSign, schematic deSign, pavement deSign, structure layout, construction management, materials testing, and surveying. He was selected to represent the Highway Department at Texas A&M as a graduate student. This program provided the foundation for the research effort.

Page 217: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to
Page 218: Contract Claims and Disputes on Texas Highway Construction ... · CONTRACT CLAIMS AND DISPUTES ON TEXAS HIGHWAY CONSTRUCTION PROJECTS A Thesis by MICHAEL PETER LEHMANN Submitted to