Contents · ME2016_1135: Case Study: The Detection and Diagnosis of Screw Compres- ... Analysis...
Transcript of Contents · ME2016_1135: Case Study: The Detection and Diagnosis of Screw Compres- ... Analysis...
6
Contents
Part I Keynote Lectures
ME2016_KL01: A Maintenance Programme: Recollections and Reflec-
tions………………………………………………………………..…………….12
John Harris
ME2016_KL02: What Does the Future of Maintenance Engineering Look
Like?................................................................................................... ...................21
Gary Knight
Part II Contributed Papers (also included in Journal
of Maintenance Engineering, Volume 1)
ME2016_1102: Major Accident Hazard (MAH) Prevention – just TIPS of
D’AIS BERG ........................................................................................................33 Mohammad Fuad Bin Abdullah
ME2016_1104: Investigation of High Piping Vibration ...................................39 Keri Elbhbah, Jyoti K. Sinha, Wolfgang Hahn
ME2016_1105: Identifying Organisational Requirements for the Implementa-
tion of an Advanced Maintenance Strategy in Small to Medium Enterprises
(SME) …………………………………………………………………………....48 David Baglee, Erkki Jantunen, Pankaj Sharma
ME2016_1106: Development of a Quantitative Maintenance Model..............58 María del Carmen García Lizarraga, Jyoti K. Sinha
ME2016_1107: A study of unsteady force on the stem in a valves with differ-
ent openings .........................................................................................................69 Yu Duan; Alistair Revell; Jyoti K. Sinha; Wolfgang Hahn
ME2016_1108: In-situ Vibration Behavior of an Offshore Wind Turbine….80 Jyoti K. Sinha, Erfan Asnaashari, Ian Andrew, Andy Morris and Wolfgang Hahn
ME2016_1109: Precaution during the Field Balancing of Rotating Ma-
chines…………………………………………………………………………….90 Sami M. Ibn Shamsah, Jyoti K. Sinha, Parthasarathi Mandal
7
ME2016_1110: An Identification of the Enabling Factors for the Develop-
ment of a Unified Approach to Maintenance Strategy Development within the
Automotive Supply Chain……............................................................................98 Derek Dixon, David Baglee, Kenneth Robson, Antti Ylä-Kujala and Pankaj Sharma
ME2016_1111: Sensitivity Analysis of Peak Decay for Acoustic Input Pulse in
Pipeline Inspection..............................................................................................112 Mohd S A M Yusoff, Jyoti K. Sinha, P Mandal
ME2016_1112: eROMEO Model: A Proposed Maintenance Strategy to En-
hance Plant Reliability.......................................................................................122 Gabriela Fernanda Sánchez Espinoza, Pedro Osvel Nuñez Izaguirre, Jyoti K. Sinha
ME2016_1113: Fault Identifications of Industrial Planetary Gearbox under
Varying Load Operation using Empirical Modeling and Vibration Analysis
Techniques……………………………………………………………………..132 Somporn Duangbuntao and Tutpol Ardsomang
ME2016_1114: A Practical Guide to Implementing a Successful Vibration
Programme………………………………………………………………….....144 Michalis Hadjiandreou
ME2016_1115: Practical Application of Integrated Failure and Decision
Analysis for Maintenance and Reliability Improvement...............................155 Frederick Appoh, Akilu Yunusa-Kaltungo
ME2016_1116: A simplified rotor-related faults detection approach based on
a combination of time and frequency domain features.................................167 Kenisuomo C. Luwei, Jyoti K. Sinha and Akilu Yunusa-Kaltungo
ME2016_1117: Detection of Bearing Fault within Helicopter Gearbox with a
Novel Condition Indicator.................................................................................178 Faris Elasha, David Mba
ME2016_1118: Overlooked Opportunity - Steam Traps Study....................190 Mohammed S. Khulaify
ME2016_1120: Creating a “Plan for Zero” Downtime...................................199 Mick P Saltzer
ME2016_1124: Non-contacting Mechanical Seals Selection Considerations for
Steam Turbines: A Case Study of 102-GT-314 Saudi ARAMCO, ABQAIQ
Plant………………………………………………………………………….…213 Eng. Andres Gonzalez
8
ME2016_1125: Strain Based Monitoring for Flutter Evaluation and Assess-
ment of Mitigation Approaches in Transonic Compressor of a Turbofan En-
gine ................................................................................................................ ......224 Owais Majid Kamili, Reshma Khan, K. Vishwanath, S. Ganga Bhavani,
T.N.Suresh
ME2016_1130: CGTGS Frame-6B Oil Mist Eliminator Reliability Enhance-
ment ................................................................................................................ ....238 Abdullah S. Al-Barqi
ME2016_1133: Learning from Alaska Airlines Flight 261’s Accident..........246 M. Almatani, A. Al-Moqbel, W. Alqurashi
ME2016_1135: Case Study: The Detection and Diagnosis of Screw Compres-
sor Bearing Defects using Vibration-based Condition Monitoring...............259
Jamie Borley
ME2016_1136: The Design and Proposal of a Condition Monitoring and
Analysis System for Rotating Equipment at a Brewery…............................270 Jamie Borley
ME2016_1139: Experimental Studies on Acoustic Leak Detection in Steam
Generators of Fast Breeder Reactor...............................................................283 Ranga Ramakrishna, S.Kishore, S. Chandramouli, V.A. Sureshkumar, I.B.
Noushad, V. Prakash and Dr. K. K. Rajan
ME2016_1140: Obsolescence Management- A Practical Perspective.........296 Javed Habib
ME2016_1142: High Speed Balancing of Rotors – in which Mode?............306 Ronald Janzee, Atul Nath
ME2016_1143: A Holistic Approach for Anticipative Maintenance Planning
Supported by a Dynamic Calculation of Wear Reserve...............................313 Robert Glawar, Christoph Habersohn, Tanja Nemeth, Kurt Matyas, Burkhard
Kittl, Wilfried Sihn
ME2016_1146: Traditional In-Situ Gas Compressor Rotor Balancing: A Case
Study……………………………………………………………………..........325 Mamdouh M. IbnShamsah, Sami M. Ibn Shamsah
ME2016_1148: Gaining Lessons from Previous Failures: A Case Study on
Imperial Sugar Company (ISC) Explosion.....................................................333 Waleed Al-Qurashi, Akilu Yunusa-Kaltungo, Mohammed Almatani , Abdulaziz
Al-Moqbe
9
ME2016_1149: Investigation of Cost Effective Maintenance Framework for
Centrifugal Compressors...................................................................................345 Xiaoxia Liang, Fang Duan, Ian Bennett, David Mba.
ME2016_1150: Multidimensional Prognostics for Rotating Machinery – A
Review ........................................................................................................ .......357 Xiaochuan Li, Fang Duan, David Mba, Ian Bennett
ME2016_1151: Helicopter Gearbox Bearing Fault Detection using Kurto-
gram and Envelope Analysis............................................................................ .374 Linghao Zhou, Fang Duan, Matthew Greaves, Faris Elasha, Suresh Sampath, Da-
vid Mba
ME2016_1154: Frictional Effects on the Diagnostics of Helical Gear Tooth
Defects ............................................................................................................ ...383 Khaldoon F. Brethee, Xiaojun Zhou, Fengshou Gu, Andrew D. Ball
ME2016_1155: Application of Mixture Models to Survival Data................394 Sílvia Madeira, Paulo Infante, Filipe Didelet
ME2016_1159: Prognostic Studies in Fatigue Cracked Rotor System........403 Rahul Pardeshi, A. K. Darpe, K. Gupta
ME2016_1160: A study of two bispectral features from envelope signals for
bearing fault diagnosis…...................................................................................412 Ibrahim Rehab, Xiange Tian, Niaoqing Hu, Tianxiao Yan, Ruiliang Zhang, Feng-
shou Gu and Andrew D. Ball
ME2016_1165: A Framework for Business Model Development for Reaching
Service Management 4.0...................................................................................426
Mirka Kans, Anders Ingwald
ME2016_1166: Ultrasound - Optimizing your Lubrication Process............437 Gary Rees
ME2016_1162: New Level of Performance with Dynamic Maintenance Man-
agement: Achieving Excellence in Four Dimensions…...................................441 Thomas Frost, Jamie McCarthy
ME2016_1163: Analyzing Industrial Failures with Reliability Tools: A Case
Study of a Pipeline Failure................................................................................453 Abdulaziz Al-Moqbel, Akilu Yunusa-Kaltungo, Mohammed Almatani Waleed Al-
Qurashi
10
ME2016_1164: Investigation the need of Total Productive Maintenance
(TPM) Framework Development for Deployment within the Iraqi Power
Generation ........................................................................................................465 Darkam Aljanabi, Martin Birkett, Chris Conner
ME2016_1167: Design of an Online Vibration Monitoring System for a Hy-
draulic Turbine-Generator (TG) Set..............................................................475 Gabriel Orquera, Akilu Yunusa-Kaltungo, Jyoti K. Sinha
ME2016_1168: Review of Pipelines Integrity Management Processes........490 Edet Afangide, K. B. Katnam, Jyoti K. Sinha
ME2016_1169: A Simple Practical Approach for Design of Vibration-based
Condition Monitoring System through a Case Study.....................................503 Buyung Baskoro, Akilu Yunusa-Kaltungo, Jyoti K. Sinha, Abdulaziz Al-Moqbel
ME2016_1170: Reliability Investigation Critique of a Wind Turbine..........511 Richardson Cleetus, Gabriel Orquera
ME2016_1171: Developing Maintenance Strategy for Wind Turbine on Off-
shore Platform………………………………………………………………….523 Yang Cao, Gabriel Orquera
ME2016_1172: Potential Reasons of Turnaround Management Failures....538
Xijiang He
Part III Contributed Papers
ME2016_1103: Technical Economic Evaluation of the Configuration Options
for the Loading Crude System of the Distiller Unit N (DU-N)……………..546
Luis Daniel Khalil
ME2016_1122: Lessons Learned from a Survey of 300 Maintenance Techni-
cians on How to get Satisfied Maintenance Technicians and Increase Reliabil-
ity Culture……………………………………………………………………..563
Wim Vancauwenberghe
ME2016_1123: A Journey Towards Enhancing the Safety and Reliability of
Power Boilers through Steam Boilers Re-tubing Projects…………………572
Mohammed Omar Alghamdi
ME2016_1126: Dry Gas Seal Best Operating Practices and Reliability En-
hancement in Centrifugal Compressor………………………..…………….573
Bibekananda Bisoyi
11
ME2016_1134: Material Forecasting and Procurement Continues Improve-
ment Initiatives in an Oil and Gas Facility…………..………………………581
Nasser Al-Shahrani, Mefleh Al-Hajri
ME2016_1137: Simulating the Impact of Repair Strategies on Repairable
Spare Part Provisioning in a Multi-echelon Replenishment System……….583
Peter Chemweno, Peter Muchiri, Liliane Pintelou
ME2016_1138: Detection of Rotating Machine Faults using Vibro-acoustic
Techniques……………………………………………………………………..584
Mohammed IMT Khandakji, Akilu Yunusa-Kaltungo
ME2016_1141: Enhanced Turnaround Model for Oil & Gas Facility…….585
Nasser Al-Shahrani, Jyoti K. Sinha, Hussain M. Al-Qahtani
ME2016_1147: A Model-based Prognostic Approach to Predict Remaining
Useful Life of Components……………………………..…………………….587
Madhav Mishra, Matti Rantatalo, Johan Odelius, Uday Kumar
ME2016_1156: Condition Monitoring for Predictive Maintenance – Towards
Systems Prognosis within the Industrial Internet of Things…………..…..589
Douglas O. Chukwuekwe, Tommy Glesnes, Per Schjølberg
ME2016_1173: The Impact of Implementing Reliability Analysis on
Maintenance Strategy Optimisation: Case Study of Abu Dhabi Power
Utilities………………………………………………………………………...600
Abdulla Y. Alseiri, Ayedh M. Albreiki, P. Farrell
313
A Holistic Approach for Anticipative
Maintenance Planning Supported by a Dynamic
Calculation of Wear Reserve
Robert Glawar1, Christoph Habersohn
2, Tanja Nemeth
1, Kurt Matyas
1,
Burkhard Kittl2, Wilfried Sihn
1,3
1 Institute of Management Science, Vienna University of Technology, Theresianumgasse 27,
1040 Vienna, Austria
2 Institute for Production Engineering and Laser Technology, Vienna University of
Technology, Getreidemarkt 9/311, 1060 Vienna, Austria
3 Fraunhofer Austria Research GmbH, Division of Production and Logistics Management,
Theresianumgasse 7, 1040 Vienna, Austria
Email: [email protected]; [email protected];
[email protected]; [email protected]; [email protected];
[email protected]; [email protected]
Abstract Production lines are exposed to performance-related wear effects. By
carrying out maintenance measures at the right time, plant availability, product
quality and process efficiency can be secured in modern manufacturing systems.
While conventional maintenance strategies do not combine those strongly related
aspects, holistic and anticipative quality- and maintenance strategies take different
maintenance and load related data into consideration. Therefore, effects such as
unnecessarily high maintenance efforts, wasted resources and the occurrence of
quality and availability losses may be reduced and avoided. In this paper a holistic
approach for maintenance planning, that will be able to forecast and anticipate
failure moments by steadily compiling and correlating various data like condition
monitoring data, wear data, quality and production data via “cause and effect” co-
herences is presented. By breaking down the production facilities on component
level and allocating defined load-data to specific components a basis is set to link
load data and historical data by a dynamic calculation of wear reserve. The con-
sistent compilation of data for each complex of loads acting on a component as
well as its correlation of failures, enables the planning of rule-based anticipative
maintenance measures. A response model based on this logic, performs a multi-
variate optimization of maintenance and repair measures. This approach allows to
anticipatively identify maintenance critical conditions as well as the prediction of
failure moments and quality deviations.
Key words: Maintenance Planning, Predictive Model, Calculation of Wear Re-
serve
Proceedings of 1
st International Conference on
Maintenance Engineering, IncoME-I 2016
The University of Manchester, UK
Paper No ME2016_1143
314
1.0 Introduction
As a result of rising cost pressure in combination with the increasing of
complexity in production, handling and transport facilities as well as the need for
individual products based on customer requirements, maintenance is becoming a
key role in manufacturing systems. The preserving of the function and
performance of a machine or system, which constitutes the main task of
maintenance, is gaining more importance, since the demand for higher quality and
more efficient production processes in highly volatile environments, is
continuously increasing [1, 2]. To achieve the desired production targets, quality
management, maintenance and production control depict essential functions in
manufacturing systems [3].
Based on different reasons, the use of classical maintenance strategies, for
deriving a minimum between maintenance costs and system-wide downtime, is
getting more and more difficult.
Due to incomplete or delayed provision of information regarding the machine
status, it is impossible to ensure a contemporary, exact and wear optimized re-
placements of components.
In case quality of maintenance relevant data is often unsatisfactory, system-
wide standards are missing or the same data sets are processed in different sys-
tems within the period between failures, it is not possible to derive a significant
correlation and analysis of the failure behavior.
Since the theoretical loads vary from the applied load profiles, the explanatory
power of static lifetime calculations for plant components decreases.
Hence the maintenance measures are conducted at a wrong or unfavorable time.
Thus, it is not likely to achieve a replacement of components that is aligned with
the present production status and the required product quality. The approach of
classical maintenance strategies is to buy improved plant availability with
increasing maintenance costs that ensue from wasting resources. For that reason,
existing planning tools are facing little acceptance.
However, in the light of “Industry 4.0” it is foreseeable that more and more data
regarding the machine status will be available in real time and may therefore be
used for maintenance planning [4]. Furthermore, data mining methods are
successfully applied in the field of maintenance, in order to identify failure
patterns out of historical data or condition based monitoring [5]. Therefore, it will
be possible to accomplish and maintain a knowledge management for the
maintenance relevant data [6, 7]. In this context the foundation is set in order to
derive dynamic load profiles depending on the scheduled production program and
consequently use this information for anticipative maintenance planning.
315
2.0 Challenges to Anticipative Maintenance Planning
In order to achieve an improvement in the systems productivity, decisions have to
be made in the area of conflict between economy, safety and availability in order
to simultaneously achieve a minimization of costs, a maximization of equipment
availability and increased product quality by the applied measures.
2.1 Maintenance Strategies
Conventional maintenance strategies can still be applied in context of large-scale
production where constant machine loads are applied. However, this is not the
case for customer order driven production with specific load spectrums. In order
that the increasing demand for higher quality and more efficient production
processes is ensured, new holistic concepts in addition to the three basic
maintenance strategies, failure oriented maintenance, periodic maintenance and
condition-based maintenance have to be developed and established (Figure 1).
Figure 1 Maintenance Strategies [1]
The need for anticipative holistic maintenance strategies, considering sensor
signals from condition monitoring systems, quality and machine data, historical
information regarding the failure behavior as well as the medium-term planning of
production, arises especially in flexible production systems with a high variation
of the production mix and no fixed load spectrums [8-9].
2.2 Maintenance Approaches
One of the central issues within maintenance planning approaches is to predict the
degradation and its effects on the manufacturing processes. Already existing
methods cover different aspects of quality control (product, process and
production infrastructure) (Figure 2).
316
Most existing models, used to forecast machine failures, are based on historical
data or information from long term studies about the condition of the machine or
its components. These data sets are a prerequisite for probability models, like the
Weibull distribution, that describes typical degradation processes of components.
[9]. Traditional quality management methods use product- and process data for
gaining conclusions concerning product quality, which subsequently (after a data
analysis) trigger a re-adjustment of the production process, if a deviation from the
defined specifications is detected. However, neither machine data, nor production
planning and control data are included in this approach. Maintenance strategies
that focus mainly on quality and combine product and machine level by linking
the product quality with failure effects of certain components, are provided in the
literature. In further consequence, a coherence between quality relevant
characteristics and degrading of the machine can be deduced [10]. Load oriented
maintenance strategies statistically determine the remaining life time by using
external measurement parameters. In order to schedule maintenance intervals,
machine- and process perspective are combined by linking the production program
and failure effects of components [11]. Using a load spectrum dependent service
life model allows for aligning operating resources in terms of economical
organizational and technological aspects [12].
Figure 2 Interactions of maintenance related perspectives
However, a holistic maintenance strategy that considers product, process and
machine perspective at the same time, is, even though certain maintenance
policies combine different perspectives, neither applied in the industrial practice
nor published in literature. Currently present solutions for maintenance planning
do not combine condition monitoring data, quality management data, recorded
machine loads as well as acquainted downtime patterns. The correlation of these
data sets in combination with suitable system models may be used as a basis for
decisions regarding optimized maintenance measures, product quality and energy
consumption.
Internal
M achine(components,
failure effects)
External
Maintenance planning
Input
OutputProduct
(quality)
Process(product ion
programme)
Quality oriented
maintenance
Load oriented
maintenance
Tradit ional
maintenance
317
3.0 Methodology to Combine Product, Process and Machine
Perspective
The presented approach is based on the systematic description of product quality-,
process- and machine perspective as well as the analysis of already existing
fractional solutions for this perspectives. In further consequence a reaction model
is able to forecast and anticipate failure moments. This model offers a set of rules
which are proposing maintenance measures anticipatively. Those rules are
supported by condition based fault diagnostics such as simulation processes.
Moreover, data based methods such as data mining will be used to support the
validity of the reaction model.
This model is realized within the following 4 steps (Table1):
Table 1 Model-realisation within a 4 steps-process
Step 1: Development of a framework
Illustration of production facilities on component level incl. their load profiles
Identification of the current condition states of real process objects and
information-transfer to the developed framework
Step 2: Data analysis and simulation study
Selection and preparation of historical data (product quality, process
and machine data), condition monitoring data and load data
Exploration of maintenance relevant parameters to derive conclusions concerning load-induced wear and quality deviations
Step 3: Parameter study
Correlation and compression of the derived parameters
Validation and classification of the determined interrelations of parame-ters
Step 4: Development of the anticipatory maintenance model
Derivation of generally applicable rules
Implementation and test run of the model
Step 1: In order to capture the behaviour of the system, the machine is split up in
its maintenance relevant components. Due to machine-data, such as positioning of
the tool slide, current consumption of drive units, data of accelerator and
temperature sensors etc., load profiles can be determined analytically. If additional
machine or tool-data is necessary, appropriate sensors and measurement devices
have to be installed.
Step 2: Parallel to the development of a generally applicable system-framework,
maintenance relevant historical data from various data collecting systems is
analyzed to enable the identification of failure effects and the detection of quality-
318
relevant cause-and-effect coherences. By a logical linkage of these datasets
maintenance relevant machine parameters are derived.
In order to reveal necessary load profiles (such as rotation speed, speed,
acceleration profiles) as well as cutting volumes of each NC-program, a
simulation study is conducted. Together with the structure of maintenance relevant
components, the simulator is able to estimate the prevalent process forces. As a
result, load/time-functions for each NC-program can be determined.
Step 3: Load spectra of identical machining centers, but with different production
program, are compared and correlated with previous identified failure effects, to
gain further information about maintenance relevant influencing factors. A
validation and classification of the explored parameters is therefore possible.
Step 4: As a last step, generally applicable planning rules for the proposed model
are derived. Data-mining methods within this process-step enable a half automatic
and rule-based data correlation and creation of prognoses concerning the condition
of machine and tool components and variations in product quality.
The generated knowledge about maintenance and quality relevant trends
throughout the manufacturing process is linked with current production planning
data. As a result, the developed model is able to suggest anticipatory quality- and
maintenance measures by the integrated set of rules. These rules can be used in a
maintenance planning tool where they form the basis for decision making. With a
suitable set of rules, it is possible to forecast failure, to visualize wear and to
predict quality trends for single machine components as well as a whole system.
As a consequence, the utilization of necessary resources can be optimized to
reduce maintenance cost and the plant availability can be increased, since
maintenance measures are initiated in time and in coordination with the whole
production line and the production program.
An approach model for the realization of load oriented maintenance planning rules
is described later in this paper (Section 5)
4.0 Dynamic Calculation of Wear Reserve
A requirement for an anticipative maintenance strategy is reliable data, based on
which the foresighted calculation of the time of failure of a machine or a compo-
nent is enabled. For the specific machine components, a stock of wear-out is de-
fined in line with DIN 31051, which is continuously exhausted by the production
processes. By taking into account the scheduled production, reliable forecast of fu-
ture wear-out can be calculated and a timely set maintenance order can be placed
when a certain wear-out limit is reached (Figure 3).
The basis for this calculation is the incremental wear of the component caused by
every single produced part. In large scale production these values can be obtained
319
by an empirical analysis as well as statistical methods (mentioned in Section 3), as
a correlation between a sufficiently big number of similarly produced workpieces
and specific maintenance steps can be distinguished.
For small batch, individual manufacture and new products, the only viable solu-
tion to obtain the incremental wear out of a machine component is an analytic ap-
proach or the use of simulation methods.
Figure 3 Wear-out of a component
Collected machine data is divided into condition- and load data. For the collection
of condition data cyclic and continuous processes are applied in condition moni-
toring systems. Cyclic procedures are used to detect damage curves. The status pa-
rameters are hereby collected based on test programs in de-fined time intervals of
a few days or weeks. Based on the test results, predictions of the damage evolution
are created, using trend analysis [13]. The processing of the sensor signals into a
load profile can be divided into two steps. The raw signal is first compressed at the
control level and then forwarded to the parts- or component level to create the load
spectrum (Figure 4). The sum of the load spectra on the parts level results in the
load spectrum of a single component. The knowledge about the load spectrum en-
ables the determination of the lifespan of the component and thus also of the
availability of the machine.
Figure 4 Processing of sensor signals into a load profile
320
5 0 Approach Model for Load Oriented Maintenance Planning
Rules
The starting point of such an approach is defined by the CAD data of the work-
piece combined with the NC-code for the machine tool, which enable the determi-
nation of real axis motions and accelerations revealing the inertia forces, whereas
the material removal rate leads to the calculation of the cutting forces. Further the
individual switch commands such as tool clamping and coolant activation can be
extracted from the NC-code.
Figure 5 Processing structure
The calculation of the wear of a single processing involves three successive steps
(Figure 5). First the feed path and the ablation volume is calculated by the soft-
ware CHECHitB4, developed by the company Pimpel. An archive file containing
all relevant technological data of a machine tool with a Siemens control can be
preloaded in the software to define the production environment and the NC-
programs. The simulation is based on a NC core by Siemens and hence delivers
the exact feed path of the process. CHECHitB4 then delivers the axis motion data,
the chip volume as well as the switch commands needed for the dynamic compu-
tation. In a second step the drive and guidance loads are calculated using an ana-
lytical multi-body model during dynamic computation, which then are passed on
to wearout calculation. The wearout computation distinguishes three cases (Fig-
ure 6):
1) Switch-dependant components: The lifetime of such components de-
pends on the number of switch-commands they undergo as for example
when one is considering the life-time of a valve. In this case the total
number of switches is counted and normalised to 1.
321
2) Time-dependant components: These components undergo wear only
when subjected to a duty cycle. The wearout calculation takes into account
the total duty cycle time and normalises it again to 1. An example of a
time-dependant component would be a cooling sensor, which is only un-
dergoing wear when subjected to cooling.
3) Load-dependant components: The war of load-dependant components
can be calculated using the actual chronological loading during the pro-
cessing. For rolling bodies such as ball screws, rolling bearings, linear
guidances the lifetime calculation (according to DIN ISO 3408, DIN ISO
281 and DIN ISO 14728) can be transformed and split into single loading
terms. Hence the incremental load of the momentary strain can be calcu-
lated as a defined wearout share of a total load for a given total lifetime.
Figure 6 Approach model for load oriented maintenance planning rules
The derived load oriented planning rules are combined together with quality
oriented planning rules in the reaction model in order to ensure a holistic approach
for maintenance planning.
6.0 Conclusion and Outlook
The key of the presented approach is to build conclusions based on the interaction
between condition- and load data, historical quality- and machine data as well as
the medium-term planning of production. With such an anticipatory maintenance
strategy it is possible to achieve the best possible product quality, optimized plant
availability and reduced maintenance costs. The methodology is going to be
applied in a maintenance control center for production lines in order to anticipate
failure and reveal deviations in quality on real-time basis.
Such a maintenance control center allows the human to make the final decision in
a complex environment. In this context it is important to mention that since the
Product ion
programme
Correlat ion between product ion programme, failure and qualit y ef fects
M aschine
cont rol
data
Failure and qualit y
ef fectsCategorizat ion of
maschine part s
Switch-dependantcomponents
Load-dependantcomponents
Time-dependantcomponents
322
operator is able to apply his implicit knowledge not only the quality of decision
making will increase, but also the acceptance of the planning support will grow
[14].
The linkage of machine, product and process perspective facilitates a change in
thinking. We need to step away from the out-dated motto “What are the costs of
maintenance?” towards a new perspective: “What are the costs maintenance is
able to prevent?” [1].
Acknowledgement
The methodology regarding the holistic maintenance approach mentioned above
has been developed within the research project “Maintenance 4.0”, funded by the
Austrian Research Promotion Agency (FFG), Grant number 843668.
References
[1] Matyas, K., 2016, Instandhaltungslogistik, 6. Vollständig überarbeitete und
erweiterte Auf-lage, Carl Hanser Verlag, München.
[2] Schuh G., Potente T., Thomas C., Hauptvogel A., 2014, “Steigerung der
Kollaborationsproduktivität durch cyber-physische Systeme”, Industrie 4.0
in Produktion, automatisierung und Logistik. Wiesbaden: Springer Fachme-
dien 2014; p.277-295.
[3] Colledani, M., Tolio, T., 2012, Integrated quality, production logistics and
maintenance analysis of multi-stage asynchronous manufacturing systems
with degrading machines, Annals of the CIRP, 61, p.455-458.
[4] Biedermann, H. (2014): Anlagenmanagement im Zeitalter von Industrie 4.0.
In: Biedermann, H. (Hrsg.): Instandhaltung im Wandel; Köln, p.23-32.
[5] Nemeth T., Bernerstätter R., Glawar R., Matyas K., Sihn W., 2015,
Sicherstellung von Produktqualität und Anlagenverfügbarkeit durch einen
echtzeitbasierten Instandhaltungsleitstand – Instandhaltung 4.0, in ZWF
09/2015, p.569-573.
[6] Güntner G., Eckhoff R., Markus M., 2014, Bedürfnisse, Anforderungen und
Trends in der Instandhaltung 4.0, Projektkonsortium Instandhaltung 4.0,
Salzburg Research
[7] Acatech, 2015, Smart Maintenance für Smart Factories – Mit intelligenter
Instandhaltung die Insustrie 4.0 vorantreiben, acatech – Deutsche Akademie
der Technikwissenschaften
[8] Colledani, M., Tolio, T., 2012, Integrated quality, production logistics and
maintenance analysis of multi-stage asynchronous manufacturing systems
with degrading machines, Annals of the CIRP, 61, p.455-458.
323
[9] Siener, M., Aurich, J, 2011, Quality oriented maintenance scheduling, An-
nals CIRP,4, p.15-23
[10] Aurich, J.C., Siener, M., Wagenknecht, C., 2006, Quality Oriented Produc-
tive Maintenance within the life cycle of a manufacturing system, 13th CIRP
International Conference on Life Cycle Engineering, p.669-673.
[11] Boog, M., 2011, Steigerung der Verfügbarkeit mobiler Arbeitsmaschinen
durch Betriebsdatenerfassung und Fehleridentifikation an hydrostatischen
Verdrängereinheiten, (Vol. 4). KIT Scientific Publishing
[12] Renger, U., 2010, Strategischer Betriebsmitteleinsatz auf der Basis von Total
Cost of Ownership, Dissertation, TU Wien.
[13] Schenk, M., 2010, Instandhaltung technischer Systeme, Springer-Verlag,
Berlin/Heidelberg.
[14] Lingitz L., Hold P., Glawar R., Sihn W.,2014, "Integration von
Lösungskompetenz operativer Mitarbeiter des Shop-Floors in die
Produktionsplanung und -Steuerung", in: Kersten, W., Koller, H., &
Lödding, H. (2014). Industrie 4.0, Berlin, p.177-197.
Authors’ Biography
Robert Glawar
Dipl.-Ing. Robert Glawar is a researcher at the Institute
of Management Science of the Vienna University of
Technology since. His main field of research is the
analysis, optimization and implementation of processes
with focus on maintenance planning. He contributed in
numerous industries funded applied research projects
dealing with the optimization of production planning
processes as well as the optimization of ordering
processing.
Christoph Habersohn
Dr. Dipl.Ing. Christoph Habersohn is since 2006 a
research associate at the Institute of Production
Engineering and Laser Technology. Main research
activities are in the fields of automation technology
regarding to the machine control and sensor layer;
construction of special purpose machines for advanced
production technologies like vibration assisted
machining; machine tool measurements and verification.
324
Tanja Nemeth
Dipl.-Ing. Tanja Nemeth is research assistant at the In-
stitute of Management Science of the Vienna University
of Technology since 2013. Her research focus is on holis-
tic maintenance planning and scheduling as well as the
analysis and optimization of production related process-
es. Currently, she is working on the national funded re-
search project “Maintenance 4.0”.
Kurt Matyas
Univ.-Prof. Dr. Dipl.-Ing. Matyas, is professor at the
Institute of Management Science of the Vienna
University of Technology (TU Wien) since 2001.
Currently he is Vice Rector for Academic Affairs at TU
Wien. His research and consulting topics cover
production management, logistics, and maintenance.
Burkhard Kittl
Univ.-Prof. Dipl.-Ing. Dr. Burkhard Kittl is associate
professor for Computer Aided Manufacturing at the
Institute for Production Engineering and Laser
Technology of the Vienna University of Technology (TU
Wien). Main research topics are Manufacturing
Execution Systems and their integration with monitoring
and control level.
Wilfried Sihn,
Univ.-Prof. Prof. eh. Dr.-Ing. Dr. h.c. Dipl.-Wirtsch.-
Ing. Sihn is Professor at the Institute of Management
Science and currently head of the institute. Prof. Sihn is
Director of Fraunhofer Austria and has been active in the
field of applied research and consulting services for more
than 25 years now.