CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA COMMON SET OF DEVIATION - 2 Page 1 of 21 Bidder MMRDA Sr. No. Volume No. Ref. Clause No. Page No Descriptio n Existing Amendment 1 Appendix- D 2.1 B- Stage-II 98 & 107 Fees & Payment Schedule Activ ity No. Description of Work Total fees paya ble for stage Fees paya ble for the sub stage of work 1 (i) On appointing the required staff as mentioned in Appendix- C andtheir acceptance of such assignment. 5% 0.5% (ii) Submission of bio data of the staff as appointed and submission of their permanent address and telephone numbers, mobile numbers etc. along with pass port size colour photograph. 0.5% (iii) On maintaining following instruments on site and 0.5% Activ ity No. Description of Work Total fees paya ble for stage Fees paya ble for the sub stage of work 1 (i) On appointing the required staff as mentioned in Appendix- C andtheir acceptance of such assignment. 3% 0.25 % (ii) Submission of bio data of the staff as appointed and submission of their permanent address and telephone numbers, mobile numbers etc. along with pass port size colour photograph. 0.25 % (iii) On maintaining following instruments on site and submission of their details to 0.25 %

Transcript of CONSULTANCY SERVICES FOR DESIGN WORK OF …

Page 1: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 1 of 21 Bidder                MMRDA 

Sr. No.

Volume No. Ref. Clause

No.

Page No

Description Existing Amendment

1 Appendix- D 2.1 B-

Stage-II 98 & 107

Fees & Payment Schedule

Activity No.

Description of Work Total fees payable for

stage

Fees payable for the sub

stage of

work 1

(i) On appointing the required

staff as mentioned in

Appendix- C andtheir

acceptance of such

assignment.

5% 0.5%

(ii) Submission of bio data of

the staff as appointed and

submission of their permanent

address and telephone

numbers, mobile numbers etc.

along with pass port size

colour photograph.

0.5%

(iii) On maintaining following

instruments on site and

0.5%

Activity No.

Description of Work Total fees payable for

stage

Fees payable for the sub

stage of

work 1

(i) On appointing the required

staff as mentioned in

Appendix- C andtheir

acceptance of such

assignment.

3% 0.25

%

(ii) Submission of bio data of

the staff as appointed and

submission of their permanent

address and telephone

numbers, mobile numbers etc.

along with pass port size

colour photograph.

0.25

%

(iii) On maintaining following

instruments on site and

submission of their details to

0.25

%

Page 2: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 2 of 21 Bidder                MMRDA 

submission of their details to

the MMRDA ;

a) Theodoliteand

Dumpy level with

staff(s);

b) Vernier caliper;

c) Measuring tapes of

5m, 10m, 15m and

30m length;

d) Measuring tapes of

steel of 3m, 5m and

10m length;

e) Helmets of standard

size and make for the

staff of PMC and also

for inspecting

officers of MMRDA.

f) Micrometers.

g) Camber plates.

h) Magnets, etc.

i) Computer with

highest caliber with

web camera and with

the MMRDA ;

a) Theodoliteand

Dumpy level with

staff(s);

b) Vernier caliper;

c) Measuring tapes of

5m, 10m, 15m and

30m length;

d) Measuring tapes of

steel of 3m, 5m and

10m length;

e) Helmets of standard

size and make for the

staff of PMC and also

for inspecting

officers of MMRDA.

f) Micrometers.

g) Camber plates.

h) Magnets, etc.

i) Computer with

highest caliber with

web camera and with

internet connection.

Page 3: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 3 of 21 Bidder                MMRDA 

internet connection.

(iv) On maintaining records

and submission of Xerox

copies of following records to

MMRDA;

1) Attendance register

of PMC staff and

Bio-Data;

2) Labour attendance

register;

3) Work order book.

4) Foundation passing

register;

5) Anti termite

treatment register;

6) Register of Material

broughtby contractor

on site of work in

terms of No. of

vehicle, date,

quantity, etc.

7) Ghani register for

concreting work.

0.5%

(iv) On maintaining records

and submission of Xerox

copies of following records to

MMRDA;

1) Attendance register

of PMC staff and

Bio-Data;

2) Labour attendance

register;

3) Work order book.

4) Foundation passing

register;

5) Anti termite

treatment register;

6) Register of Material

broughtby contractor

on site of work in

terms of No. of

vehicle, date,

quantity, etc.

7) Ghani register for

concreting work.

8) Cement testing

register.

0.25

%

Page 4: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 4 of 21 Bidder                MMRDA 

8) Cement testing

register.

9) Cement consumption

register;

10) Steel consumption

register;

11) Steel testing register

12) Concrete cube testing

register.

13) Deviation register;

14) Accident register;

15) Safety precaution

register.

(v) On maintaining following

books on site and submission

of details of the same to

MMRDA;

a) Standard

specifications(Vol.Iand

II);

b) MORTH

specifications of latest

edition;

c) National Building

0.5%

9) Cement consumption

register;

10) Steel consumption

register;

11) Steel testing register

12) Concrete cube testing

register.

13) Deviation register;

14) Accident register;

15) Safety precaution

register.

(v) On maintaining following

books on site and submission

of details of the same to

MMRDA;

a) Standard

specifications(Vol.Ia

nd II);

b) MORTH

specifications of latest

edition;

c) National Building

Code of latest edition;

d) IS: 456

0.25

%

Page 5: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 5 of 21 Bidder                MMRDA 

Code of latest edition;

d) IS: 456

e) IS: 13920

f) IS: 1893

g) IS: 800

h) SP : 16, 20, 36

i) IS : 10260

j) PWD – Civil

Engineering Handbooks

k) Central Public Health

Engineering Manual

l) Any other IS code or

book as may be required;

etc

(vi) PMC shall prepare

Quality Assurance Manual

(QAM) indicating the

methodology of execution of

various items of work and

submit the same to MMRDA.

0.5%

(vii) On establishing and

submission of details of site

laboratory by contractor to

0.5%

e) IS: 13920

f) IS: 1893

g) IS: 800

h) SP : 16, 20, 36

i) IS : 10260

j) PWD – Civil

Engineering Handbooks

k) Central Public Health

Engineering Manual

l) Any other IS code or

book as may be required;

etc

(vi) PMC shall prepare

Quality Assurance Manual

(QAM) indicating the

methodology of execution of

various items of work and

submit the same to MMRDA.

0.25

%

(vii) On establishing and

submission of details of site

laboratory by contractor to

MMRDA. If the contractor

fails to establish site

laboratory as mentioned in the

0.25

%

Page 6: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 6 of 21 Bidder                MMRDA 

MMRDA. If the contractor

fails to establish site

laboratory as mentioned in the

tender document in full

working condition within 15

days from the date of work

order then PMC shall establish

the laboratory and claim the

expenses and deduct the

amount from the bill of

contractor.

(viii) Maintain the

Measurement Books (MB)

issued by MMRDA for

recording the measurement of

steel and all hidden

measurements. Hidden

measurements will include

foundations, WBM, BBM and

other layers of road

work,Underground water lines

etc. The certified Xerox copy

of this MB shall be submitted

along with the PMC’s bill.

0.5%

tender document in full

working condition within 15

days from the date of work

order then PMC shall establish

the laboratory and claim the

expenses and deduct the

amount from the bill of

contractor.

(viii) Maintain the

Measurement Books (MB)

issued by MMRDA for

recording the measurement of

steel and all hidden

measurements. Hidden

measurements will include

foundations, WBM, BBM and

other layers of road

work,Underground water lines

etc. The certified Xerox copy

of this MB shall be submitted

along with the PMC’s bill.

0.25

%

(ix) PMC should check the

mix design for various grades

of concrete to be used on work

1%

Page 7: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 7 of 21 Bidder                MMRDA 

(ix) PMC should check the

mix design for various grades

of concrete to be used on work

and cast trial cubes as per the

mix design obtained and

verify at least 7 days results

and subsequently for 28 days

results. PMC should calculate

the cement consumption and

maintain the record. This

activity shall be repeated for

each change in mix design.

Note:

This amount will be paid on

completion of R.C.C. work

and satisfactory report of all

NDT of concrete.

1%

2 (i) Complete day to day

supervision of the project

work, Contractor’s bill will be

paid in proportion to the actual

work done by the contractor.

PMC shall submit the certified

27%

and cast trial cubes as per the

mix design obtained and

verify at least 7 days results

and subsequently for 28 days

results. PMC should calculate

the cement consumption and

maintain the record. This

activity shall be repeated for

each change in mix design.

Note:

This amount will be paid in

proportionate of progress of

R.C.C. work and satisfactory

report of all NDT of concrete.

2 (i) Complete day to day

supervision of the project

work, Contractor’s bill will be

paid in proportion to the actual

work done by the contractor.

PMC shall submit the certified

copies of all registers and

documents maintained by him

at site.

PMC shall also submit the

29%

Page 8: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 8 of 21 Bidder                MMRDA 

copies of all registers and

documents maintained by him

at site.

PMC shall also submit the

compliance of inspection

notes issued by MMRDA

during the construction period

since last bill of the

Contractor. Bill will be paid

only after receipt of the data as

above.

Note:

a) Check, certify and

forward the bill to the

MMRDA (either

Running Account i.e. RA

or Final Bill) prepared by

contractor, after due

recording in M.B.

b) Check, certify and

forward the escalation

bill of the contractor

after due recording in

M.B. if clause of

compliance of inspection

notes issued by MMRDA

during the construction period

since last bill of the

Contractor. Bill will be paid

only after receipt of the data as

above.

Note:

a) Check, certify and

forward the bill to the

MMRDA (either Running

Account i.e. RA or Final

Bill) prepared by

contractor, after due

recording in M.B.

b) Check, certify and

forward the escalation

bill of the contractor

after due recording in

M.B. if clause of

escalation included in

contract.

c) PMC or his engineer

shall not indulge in any

way in preparation of the

Page 9: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 9 of 21 Bidder                MMRDA 

escalation included in

contract.

c) PMC or his engineer

shall not indulge in any

way in preparation of the

bill of the contractor.

d) The main

responsibility of the

PMC is getting the work

executed as per the

tender specifications and

drawings and maintain

the desired quality and

workmanship of work.

PMCshall not

recommend and forward

bill of the contractor if

the work is not done

as per the desired

specifications and

quality. If contractor’s

bill is submitted for

payment by the PMC it

will be assumed that the

bill of the contractor.

d) The main

responsibility of the

PMC is getting the work

executed as per the

tender specifications and

drawings and maintain

the desired quality and

workmanship of work.

PMCshall not

recommend and forward

bill of the contractor if

the work is not done

as per the desired

specifications and

quality. If contractor’s

bill is submitted for

payment by the PMC it

will be assumed that the

work is being done as per

the desired

specifications, quantity

and quality with

specified workmanship.

For assurance of

Page 10: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 10 of 21 Bidder                MMRDA 

work is being done as per

the desired

specifications, quantity

and quality with

specified workmanship.

For assurance of

quality PMC should be

that 30% test shall be

carried out in Govt.

lab.& 70% test in other

lab. And also frequency

of the test shall be strictly

observed.

e) PMCshall certify

whether the work for

which payment is

recommended by him is

being executed as per the

specifications, quality

and as per the tender

drawings in the

prescribed format by the

MMRDA.

f) PMC shall notify to

quality PMC should be

that 30% test shall be

carried out in Govt.

lab.& 70% test in other

lab. And also frequency

of the test shall be strictly

observed.

e) PMCshall certify

whether the work for

which payment is

recommended by him is

being executed as per the

specifications, quality

and as per the tender

drawings in the

prescribed format by the

MMRDA.

f) PMC shall notify to

the MMRDA whose

signature on his behalf on

various documents such

as bills of contractor etc.

is to be accepted by

MMRDA as authorized

signatory. Such signature

Page 11: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 11 of 21 Bidder                MMRDA 

the MMRDA whose

signature on his behalf on

various documents such

as bills of contractor etc.

is to be accepted by

MMRDA as authorized

signatory. Such signature

shall specify the name of

the signatory on the

document and date.

3 (i) PMCshall obtain requisite

certificates, viz., plinth

checking certificate, tree

cutting certificate, fire

NOC.Certificates for drainage,

storm water disposal, sewage

disposal, source of drinking

water and other certificates as

may be required from local

statutory authorities during

construction period.

(ii) PMC shall have to visit

the site of work, office of the

10% 2%

2%

shall specify the name of

the signatory on the

document and date.

3 i) PMCshall obtain requisite

certificates, viz., plinth

checking certificate, tree

cutting certificate, fire

NOC.Certificates for drainage,

storm water disposal, sewage

disposal, source of drinking

water and other certificates as

may be required from local

statutory authorities during

construction period.

(ii) PMC shall have to visit

the site of work, office of the

MMRDA, office of the unit

Commander, user, the various

other offices of the Statutory

bodies etc. as and when

required for which no

traveling or daily allowances

or other expenses are payable.

10% 2%

2%

Page 12: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 12 of 21 Bidder                MMRDA 

MMRDA, office of the unit

Commander, user, the various

other offices of the Statutory

bodies etc. as and when

required for which no

traveling or daily allowances

or other expenses are payable.

Note:

Fees prescribed for this stage

will be paid after completion

of the project.

(iii) PMC shall ensure the

visit of Structural PMCas per

Appendix – I to the site who

should personally inspect and

certify in writing the

suitability offoundation strata,

reinforcement checking of

columns, beams and floor

slabs, anchor of bar at column

/ beam junction,required

length of top bar at column

support provided for

seismic/windmomentetc. and

1%

Note:

Fees prescribed for this stage

will be paid after completion

of the project.

(iii) PMC shall ensure the

visit of Structural PMCas per

Appendix – I to the site who

should personally inspect and

certify in writing the

suitability offoundation strata,

reinforcement checking of

columns, beams and floor

slabs, anchor of bar at column

/ beam junction,required

length of top bar at column

support provided for

seismic/windmomentetc. and

other important structures

such as Under Ground Water

Tank, Elevated Storage

Reservoir, Heavy loaded /

Longer span of Beam / Slab,

Overhead water tank, etc. and

all other RCC structures under

such Building infrastructure

1%

Page 13: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 13 of 21 Bidder                MMRDA 

other important structures

such as Under Ground Water

Tank, Elevated Storage

Reservoir, Heavy loaded /

Longer span of Beam / Slab,

Overhead water tank, etc. and

project.

Page 14: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 14 of 21 Bidder                MMRDA 

all other RCC structures under

such Building infrastructure

project.

(iv) PMC shall arrange at

least weekly visit of

Architectas per Appendix – III

to the project and check the

specifications adopted and

advise contractor over the

quality, workmanship,

modification of design,

planning if necessary as per

site condition of the R.C.C.

work and other finishing

works etc.

Note:

If it is observed that Architect

has not visited the work as per

Appendix – III ,then the fees

of PMC will be deducted at

the penal rate i.e. double the

fee as mentioned in the

agreement between them.

2%

(iv) PMC shall arrange at

least weekly visit of

Architectas per Appendix – III

to the project and check the

specifications adopted and

advise contractor over the

quality, workmanship,

modification of design,

planning if necessary as per

site condition of the R.C.C.

work and other finishing

works etc.

Note:

If it is observed that Architect

has not visited the work as per

Appendix – III ,then the fees

of PMC will be deducted at

the penal rate i.e. double the

fee as mentioned in the

agreement between them.

(v) PMC shall approve various

samples according to the

contract agreement with the

contractor during the course of

execution and certify the RA

2%

2%

Page 15: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 15 of 21 Bidder                MMRDA 

(v) PMC shall approve various

samples according to the

contract agreement with the

contractor during the course of

execution and certify the RA

Bills of the contractor by

referring thechapter of list of

approved materials mentioned

in tender document.

The certificate shall clearly

mention whether the entire

work has been carried out as

per the tender drawings and

specifications mentioned in

tender.

(vi) All other PMCs shall also

visit the project during the

period while the particular

activity is going on. Visits of

the

PMC along with his name,

date of report shall be notified

to the MMRDA by the PMC

through M.P.R.

2%

1%

Bills of the contractor by

referring thechapter of list of

approved materials mentioned

in tender document.

The certificate shall clearly

mention whether the entire

work has been carried out as

per the tender drawings and

specifications mentioned in

tender.

(vi) All other PMCs shall also

visit the project during the

period while the particular

activity is going on. Visits of

the

PMC along with his name,

date of report shall be notified

to the MMRDA by the PMC

through M.P.R.

1%

Page 16: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 16 of 21 Bidder                MMRDA 

Note : A) Report of Electrical

Consultant about material,

material quality, specification,

design load, test report, etc,

andsubmission of completion

certificate.

B) Report of water supply and

drainage PMC about material,

material quality, specification,

test report, design calculation

etc., and submission of

completion certificate.

4 (i) On completion of work and

obtaining the completion

certificate from competent

client, ensuring drainage

connection, water connection,

electrical connection and

finally completion and

Occupation Certificate and

other approvals from all

statutory bodies.

5% 3%

4

Note : A) Report of Electrical

Consultant about material,

material quality, specification,

design load, test report, etc,

andsubmission of completion

certificate.

B) Report of water supply and

drainage PMC about material,

material quality, specification,

test report, design calculation

etc., and submission of

completion certificate.

(i) On completion of work and

obtaining the completion

certificate from competent

client, ensuring drainage

connection, water connection,

electrical connection and

finally completion and

Occupation Certificate and

other approvals from all

statutory bodies.

5%

3%

Page 17: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 17 of 21 Bidder                MMRDA 

Note:The actual charges,

deposits and all other dues,

etc. towards obtaining the

various connections will be

paid by the contractor or the

MMRDA as the case may be.

Note:The actual charges,

deposits and all other dues,

etc. towards obtaining the

various connections will be

paid by the contractor or the

MMRDA as the case may be.

Page 18: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 18 of 21 Bidder                MMRDA 

(ii) Actual handing over of

the project to the User

Department and taking the

same on the Printed Register

of Buildings (PRB) of the

PWD.

(iii) Projects for which

maintenance will be done

other than PWD in that case

PMC shall prepare

Maintenance Manual and

Draft for Maintenance

Agreement between user

department and maintenance

agency.

2% (ii) Actual handing over of

the project to the User

Department and taking the

same on the Printed Register

of Buildings (PRB) of the

PWD.

(iii) Projects for which

maintenance will be done

other than PWD in that case

PMC shall prepare

Maintenance Manual and

Draft for Maintenance

Agreement between user

department and maintenance

agency.

2%

Page 19: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 19 of 21 Bidder                MMRDA 

5 Preparation and submission of

AsBuilt Drawings to the

MMRDA alongwith the

multianglecoloured

photographs of A4 size in five

sets and VDO in Pen drive.

3%

3%

5 Preparation and submission of

AsBuilt Drawings to the

MMRDA alongwith the

multianglecoloured

photographs of A4 size in five

sets and VDO in Pen drive.

3%

3%

Page 20: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 20 of 21 Bidder                MMRDA 

III) Payment of fees during actual execution The fee of 50% of total fees for Consultancy, for the post tender activity shall be divided into two categories and paid in the following manner and ratio. a)Time related fees = 70% b) Progress related fees = 30 %

Deleted

iv) Time related fees 1. The  time  related  fees  shall  be  payable  as below: 

2. Fee to be paid every month = 70 x     50     x   Total fees for consultancy 100    100  Original  scheduled  period  of  

completion  for  work  in  month+ variation period. 

3. The monthly fee shall be payable to the consultant as per the above formula for the scheduled period of completion. If the construction work is completed within stipulated time limit, full 70% fees shall be payable.

Deleted

Page 21: CONSULTANCY SERVICES FOR DESIGN WORK OF …

CONSULTANCY SERVICES FOR DESIGN WORK OF ARCHITECTURAL CIVIL, MEP WORKS, DESIGN DEVELOPMENT, PROCUREMENT OF CONSTRUCTION CONTRACT, SUPERVISION DURING CONSTRUCTION AND DLP OF BUILDINGS AT TRUCK TERMINAL WADALA

COMMON SET OF DEVIATION - 2  

Page 21 of 21 Bidder                MMRDA 

v) Progress Related Fees The progress related fees would be paid as below: Fee to be paid every month =  30    x     50       X     %  progress of  the work     X  

100 100 Total fees for consultancy Note: The cost of the work done by agency will exclude the payment made towards price escalation, Mobilization Advance and Machinery Advance. Similarly the recovery of Mobilization Advance and Machinery Advance will not be reflected in working out the fees due to the consultant. In case of time overrun in the construction work, progress related fees shall not be paid beyond the base completion period plus variation period of the consultancy work. The clause no 3 given below shall come into existence for payment during the extended period ( beyond variation period) of the consultancy work.

Deleted