8 The Esplanade – L Tower & 1 The Esplanade – Backstage Construction Summary July 30 - August 3, 2012 Detailed daily schedules are available at: http://ltowerconstructioninfo.com/ Updates are also available via Twitter from “ltowerinfo” or email us at [email protected] o The 30-day road closure of The Esplanade from Scott Street to Yonge Street remains in effect. o A shuttle bus service will be provided during the road closure running approximately every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott Street to Union Station, Bay & Front, King & Yonge and Berczy Park. Please go to http://ltowerconstructioninfo.com/ for copies of the route map. L Tower Summary Monday, July 30 o Yuanda delivery of three (3) containers of windows, starting at 7:00 am. o A rebar (steel) delivery starting at 7:00 am and 12:30 pm. Tuesday, July 31 o A 215M (cubic metre) slab concrete pour, at level 53, starting at 10:00 am. o A rebar (steel) delivery starting at 10:00 am. Wednesday, August 1 o A 96M (cubic metre) part one (1), wall and column concrete pour, levels 53 – 54, starting at 12:00 pm. Thursday, August 2 o Primo Mechanical delivery of Heat Pumps for levels 36 to 40, scheduled to begin at 7:30 am o A 92M (cubic metre) part 2, wall and column concrete pour, levels 53 – 54, starting at 12:00 pm. o A rebar (steel) delivery starting at 12:30 pm. Friday, August 3

Transcript of Construction Summary July 30 - August 3, 2012 · 2012. 7. 27. · Monday, July 30 - Thursday,...

Page 1: Construction Summary July 30 - August 3, 2012 · 2012. 7. 27. · Monday, July 30 - Thursday, August 2 o Sub-contractor, C & M McNally boring the tunnel. o Subcontractor, GFL Excavating

8 The Esplanade – L Tower & 1 The Esplanade – Backstage

Construction Summary July 30 - August 3, 2012

Detailed daily schedules are available at: http://ltowerconstructioninfo.com/

Updates are also available via Twitter from “ltowerinfo” or email us at

[email protected]

o The 30-day road closure of The Esplanade from Scott Street to Yonge Street remains in

effect.

o A shuttle bus service will be provided during the road closure running approximately

every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott

Street to Union Station, Bay & Front, King & Yonge and Berczy Park. Please go to

http://ltowerconstructioninfo.com/ for copies of the route map. L Tower Summary

Monday, July 30

o Yuanda delivery of three (3) containers of windows, starting at 7:00 am.

o A rebar (steel) delivery starting at 7:00 am and 12:30 pm.

Tuesday, July 31

o A 215M (cubic metre) slab concrete pour, at level 53, starting at 10:00 am.

o A rebar (steel) delivery starting at 10:00 am.

Wednesday, August 1

o A 96M (cubic metre) part one (1), wall and column concrete pour, levels 53 – 54, starting at 12:00 pm.

Thursday, August 2

o Primo Mechanical delivery of Heat Pumps for levels 36 to 40, scheduled to begin at 7:30 am

o A 92M (cubic metre) part 2, wall and column concrete pour, levels 53 – 54, starting at 12:00 pm.

o A rebar (steel) delivery starting at 12:30 pm.

Friday, August 3

Page 2: Construction Summary July 30 - August 3, 2012 · 2012. 7. 27. · Monday, July 30 - Thursday, August 2 o Sub-contractor, C & M McNally boring the tunnel. o Subcontractor, GFL Excavating

8 The Esplanade – L Tower & 1 The Esplanade – Backstage

o A rebar (steel) delivery starting at 7:00 am and 12:30 pm.

Backstage Summary

Monday, July 30 - Thursday, August 2

o Sub-contractor, C & M McNally boring the tunnel.

o Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14

loads each, for a total of eighty-four (84) loads. *

Friday, August 3

o Sub-contractor, C & M McNally will be removing the Tunnel Boring Machine from the site with a 500-

ton crane.

o There will be significant impact on traffic on The Esplanade and Scott Street during the removal of the

Tunnel Boring Machine. More precise times and details will be posted when available.

NOTES:

o * Dump truck frequencies are dependent on road and traffic conditions and the amount

excavation materials at any given time on the site.

o Construction activities are dependent on whether.

o A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm

daily to assist with traffic control.