Construction Summaryconstructionsidekick.com/uploads/3/1/4/5/3145799/construction... · MEP...
Transcript of Construction Summaryconstructionsidekick.com/uploads/3/1/4/5/3145799/construction... · MEP...
Construction SummaryConstruction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Item of Work Base Building Total Cost Code
Site Development 2,025,100.00$ -$ 2,025,100.00$ 01211
Foundation 1,726,000.00$ -$ 1,726,000.00$ 02300 s
Landscaping 20,700.00$ -$ 20,700.00$ 02450 s
Cast-in-place Concrete 7,517,000.00$ -$ 7,517,000.00$ 02900 s
Precast Concrete 13,668,600.00$ -$ 13,668,600.00$ 03300 s
Masonry 182,000.00$ -$ 182,000.00$ 03400 s
Metals 1,189,776.00$ -$ 1,189,776.00$ 04200 s
Carpentry 43,500.00$ -$ 43,500.00$ 04200 s
Waterproofing 636,000.00$ -$ 636,000.00$ 05500 s
Insulation 752,000.00$ -$ 752,000.00$ 07100 s
Fireproofing 25,000.00$ -$ 25,000.00$ 07200 s
Metal Panels 282,000.00$ -$ 282,000.00$ 07400 s
Roofing 224,500.00$ -$ 224,500.00$ 07500 s
Doors, Frames and Hardware 68,500.00$ -$ 68,500.00$ 07810 s
Overhead Doors 165,400.00$ -$ 165,400.00$ 08100 m
Traffic Impact Doors 16,400.00$ -$ 16,400.00$ 08300 s
Aluminum and Glass 794,500.00$ -$ 794,500.00$ 08340 s
Louvers 4,350.00$ -$ 4,350.00$ 08400 s
Drywall, Carpentry and Ceilings 961,000.00$ -$ 961,000.00$ 09250 s
Tile 204,500.00$ -$ 204,500.00$ 09300 s
Resilient Flooring 12,300.00$ -$ 12,300.00$ 09450 s
Resinous Flooring 38,700.00$ -$ 38,700.00$ 09650 s
Polished Concrete Floor 120,800.00$ -$ 120,800.00$ 09700 s
Painting 184,000.00$ -$ 184,000.00$ 09900 s
Specialties 29,200.00$ -$ 29,200.00$ 10050 s,m
Signage 109,000.00$ -$ 109,000.00$ 10200 m
Loading Dock Equipment 16,400.00$ -$ 16,400.00$ 10400 s
Parking Equipment 400,000.00$ -$ 400,000.00$ 11150 s
Floor Grilles 31,000.00$ -$ 31,000.00$ 11160 s
Elevators 739,000.00$ -$ 739,000.00$ 12480 s
Fire Protection 698,700.00$ -$ 698,700.00$ 14200 s
Plumbing 1,411,500.00$ -$ 1,411,500.00$ 15300 s
HVAC 2,475,450.00$ -$ 2,475,450.00$ 15400 s
Electrical 4,527,700.00$ -$ 4,527,700.00$ 15500 s
Construction Contingency 5.00% 2,065,029.00$ -$ 2,065,029.00$ 16100 s
Subtotal Construction Hard Costs 43,365,605.00$ -$ 43,365,605.00$
Preconstruction Services 294,336.00$ -$ 294,336.00$ 01620
General Conditions 3,710,137.00$ -$ 3,710,137.00$ 01890
Contractor's Insurance 0.50% 216,829.00$ -$ 216,829.00$ 01001
Building Permit (Allowance) 0.50% 216,829.00$ -$ 216,829.00$ 01610
Builder's Risk Insurance (by others) -$ -$ -$
Subtotal Construction Soft Costs 4,438,131.00$ -$ 4,438,131.00$
Subtotal Construction Hard and Soft Costs 47,803,736.00$ -$ 47,803,736.00$
Construction Management Fee 2.80% 1,338,505.00$ -$ 1,338,505.00$
Performance and Payment Bond 1.00% 496,387.00$ -$ 496,387.00$ Design & Engineering 5,500,000.00$ -$ 5,500,000.00$ 01210
Total Construction Cost 55,138,628.00$ -$ 55,138,628.00$
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Preconstruction
Services
Construction Sidekick
Badley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project NameOwner:Location:
Contract Type:Project Summary:
Section/Item Quantity Unit Unit Price ($) Item Total ($) Section Total ($)
Preconstruction Management 16 wks 178,480
Project Executive 16 wks 687.00 10,992Senior Project Manager 16 wks 5,308.00 84,928MEP Project Manager 16 wks 1,225.00 19,600General Superintendent 16 wks 262.00 4,192Project Superintendent 16 wks 858.00 13,728MEP Superintendent 16 wks 507.00 8,112MEP Coordinator 16 wks 470.00 7,520Project Engineer 16 wks 1,838.00 29,408Administrative Assistant - Field 16 wks 0.00 0Travel and expenses 16 wks 0.00 0Parking 16 ls 0.00 0Postage and Shipping 16 wks 0.00 0
16 wks 0.00 0
Guaranteed Maximum Price 16 wks 115,856
Administrative Assistant - Office 16 wks 205.00 3,280Insurance Coordinator 16 wks 72.00 1,152Director of Preconstruction Services 16 wks 2,450.00 39,200Senior Estimator 16 wks 3,471.00 55,536Procurement Specialist 16 wks 307.00 4,912Contract Administrator 16 wks 0.00 0Outreach Coord/Certified Payroll 16 wks 0.00 0IST technician 16 wks 41.00 656Document Manager 16 wks 695.00 11,120
Total Preconstruction Services Estimate 294,336
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
General Conditions Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project NameOwner:Location:
Contract Type:Project Summary:
Section/Item Quantity Unit Unit Price ($) Item Total ($) Section Total ($)
Construction Mgmt. and Administration 75 wks 19 months 2,256,555
On-site StaffProject Executive 75 wks 858.00 64,350Senior Project Manager 75 wks 2,654.00 199,050Project Manager 75 wks 4,287.00 321,525MEP Project Manager 75 wks 3,471.00 260,325General Superintendent 75 wks 654.00 49,050Project Superintendent 75 wks 4,287.00 321,525MEP Superintendent 75 wks 5,063.00 379,725MEP Coordinator 75 wks 588.00 44,100Project Engineer 75 wks 3,675.00 275,625Administrative Assistant - Field 75 wks 1,062.00 79,650Travel and expenses 75 wks 500.00 37,500Parking 75 wks 230.00 17,250
Support Staff
Administrative Assistant - Office 75 wks 654.00 49,050Insurance Coordinator 75 wks 180.00 13,500
Director of Preconstruction Services 60 wks 613.00 36,780Senior Estimator 75 wks 0.00 0Procurement Specialist 20 wks 1,225.00 24,500Contract Administrator 75 wks 409.00 30,675Outreach Coord/Certified Payroll 75 wks 333.00 24,975IST technician 75 wks 41.00 3,075Document Manager 35 wks 695.00 24,325
Miscellaneous Administrative CostsPostage and Shipping 75 wks 0.00 0Office supplies 75 wks 0.00 0Drinking water/Ice 75 wks 0.00 0
Construction Progress Documentation 499,363
Construction Progress ScheduleScheduler 75 wks 1,225.00 91,875
Construction Cost Control and AccountingCost Engineer 75 wks 3,471.00 260,325Accounting Supervisor 75 wks 333.00 24,975Accountant 75 wks 1,021.00 76,575Accounting Assistant 75 wks 123.00 9,225
Construction DocumentationDocument Reproduction 1 ls 15,000.00 15,000Progressive photography 19 mo 800.00 15,200
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
General Conditions Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project NameOwner:Location:
Contract Type:Project Summary:
Section/Item Quantity Unit Unit Price ($) Item Total ($) Section Total ($)
Monthly reports 19 mo 250.00 4,688Final photography 1 ls 1,500.00 1,500As-built drawings 1 ls 0.00 0
Safety 274,600
Safety and First AidSafety Manager 75 mo 2,858.00 214,350Safety supplies 19 mo 1,000.00 19,000First aid supplies 19 mo 200.00 3,750
Quality Requirements
SurveyBench marks and control points 200 hrs 125.00 25,000Layout 100 hrs 125.00 12,500
Quality ControlSoil testing 1 ls 0.00 by OwnerConcrete testing 1 ls 0.00 by OwnerSteel testing 1 ls 0.00 by OwnerMiscellaneous testing 1 ls 0.00 by Owner
Temporary Facilities and Controls 161,892
Temporary Utility InstallationElectric service to site office 1 ls 15,000.00 15,000Telephone and internet service to office 1 ls 200.00 200Water service to office 1 ls 65.00 65Water service to construction area 1 ls 0.00 By OwnerFire protection for construction area 1 ls 0.00 By Owner
Utility UseageElectric for site office 19 mo 120.00 2,250Electric for construction area - lighting 19 mo 650.00 12,350Electric for construction area - general power 19 mo 1,200.00 22,800Telephone 19 mo 150.00 2,813Internet 19 mo 0.00 0Water for site office 19 mo 100.00 1,875Water for construction area 19 mo 0.00 By Owner
Construction FacilitiesProject Management office
Office Rental 19 mo 1,200.00 22,800Leasehold improvements 1 ls 5,000.00 5,000Restoration at end of lease 1 ls 1,000.00 1,000
Superintendent office
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
General Conditions Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project NameOwner:Location:
Contract Type:Project Summary:
Section/Item Quantity Unit Unit Price ($) Item Total ($) Section Total ($)
Setup 1 ls 4,500.00 4,500Rental 19 mo 750.00 14,063Removal 1 ls 2,600.00 2,600
Conference TrailerSetup 1 ls 3,000.00 3,000Rental 19 mo 650.00 12,188Removal 1 ls 1,500.00 1,500
Site StorageStorage facilities 19 mo 400.00 7,500
Furnishings and EquipmentOffice furniture 1 ls 2,500.00 2,500Office equipment - computers and peripherals 1 ls 2,000.00 2,000Office equipment - copiers (rental) 19 mo 500.00 9,375Office equipment - telephone and fax 1 ls 750.00 750
Sanitary FacilitiesTemporary toilet installation for site offices 0 ls 0.00 0Temporary toilet maintenance 0 mo 0.00 0Portable toilets (average of 6 units) 19 mo 750.00 14,063
Project IdentificationProject identification signage 1 ls 1,200.00 1,200Temporary interior signage 1 ls 500.00 500
Cleaning and Waste Management 387,072
Progressive CleaningLabor foreman (40 hrs/wk) (Union Wages) 52 wks 2,961.00 153,972Office cleaning 75 wks 100.00 7,500
Waste ManagementDumpsters (average 1 pulls per week) 52 wks 2,300.00 119,600
Final CleaningFinal cleaning 400,000 sf 0.20 80,000
Temporary Enclosures, Protection and Conditioning 26,000
Temporary Safety ProtectionRailings 1 ls 0.00 SubcontractRemoval of temporary protection 0 ls 0.00 Subcontract
Temporary Enclosures Temporary enclosure of openings 0 ls 0.00 SubcontractModify and remove perimeter fence 1 ls 5,000.00 5,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
General Conditions Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project NameOwner:Location:
Contract Type:Project Summary:
Section/Item Quantity Unit Unit Price ($) Item Total ($) Section Total ($)
Temporary Heat and Humidity ControlTemporary heating equipment 1 ls 15,000.00 15,000Fuel 4 mo 1,500.00 6,000
Security and Surveillance 104,655
CamerasCamera installation 5 ea 750.00 3,750Web service 19 mo 120.00 2,280Maintenance 1 ls 3,000.00 3,000
SecurityOff-hours watchman (1 watchmen) 75 wks 1,275.00 95,625
Total General Conditions Estimate 3,710,137
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Precon
Rate Schedule
Duration
Construction Sidekick
Bradley beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name Schedule 91 weeks
Owner: Precon 16 weeks
Location: Construction 75 weeks
0 weeks
Contract Type: 0 weeks
Project Summary:0
Section / Item
2.50% increase per year
Current 2013 2014 2015 2016 Current 2013 2014 2015 2016
On-site Staff
Project Executive $168.00 $172.20 $176.51 $180.92 $185.44 4 $672.00 $689.00 $707.00 $724.00 $742.00 $687.00
Senior Project Manager $130.00 $133.25 $136.58 $140.00 $143.50 40 $5,200.00 $5,330.00 $5,464.00 $5,600.00 $5,740.00 $5,308.00
MEP Project Manager $60.00 $61.50 $63.04 $64.61 $66.23 20 $1,200.00 $1,230.00 $1,261.00 $1,293.00 $1,325.00 $1,225.00
General Superintendent $128.00 $131.20 $134.48 $137.84 $141.29 2 $256.00 $263.00 $269.00 $276.00 $283.00 $262.00
Project Superintendent $105.00 $107.63 $110.32 $113.07 $115.90 8 $840.00 $861.00 $883.00 $905.00 $928.00 $858.00
MEP Superintendent $124.00 $127.10 $130.28 $133.53 $136.87 4 $496.00 $509.00 $522.00 $535.00 $548.00 $507.00
MEP Coordinator $115.00 $117.88 $120.82 $123.84 $126.94 4 $460.00 $472.00 $484.00 $496.00 $508.00 $470.00
Project Engineer $90.00 $92.25 $94.56 $96.92 $99.34 20 $1,800.00 $1,845.00 $1,892.00 $1,939.00 $1,987.00 $1,838.00
Administrative Assistant - Field $26.00 $26.65 $27.32 $28.00 $28.70 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel and expenses
Parking
Support Staff
Administrative Assistant - Office $40.00 $41.00 $42.03 $43.08 $44.15 5 $200.00 $205.00 $211.00 $216.00 $221.00 $205.00
Insurance Coordinator $35.00 $35.88 $36.77 $37.69 $38.63 2 $70.00 $72.00 $74.00 $76.00 $78.00 $72.00
Director of Preconstruction Services $150.00 $153.75 $157.59 $161.53 $165.57 16 $2,400.00 $2,460.00 $2,522.00 $2,585.00 $2,650.00 $2,450.00
Senior Estimator $85.00 $87.13 $89.30 $91.54 $93.82 40 $3,400.00 $3,485.00 $3,573.00 $3,662.00 $3,753.00 $3,471.00
Procurement Specialist $60.00 $61.50 $63.04 $64.61 $66.23 5 $300.00 $308.00 $316.00 $324.00 $332.00 $307.00
Contract Administrator $40.00 $41.00 $42.03 $43.08 $44.15 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Outreach Coord/Certified Payroll $65.00 $66.63 $68.29 $70.00 $71.75 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IST technician $40.00 $41.00 $42.03 $43.08 $44.15 1 $40.00 $41.00 $43.00 $44.00 $45.00 $41.00
Document Manager $34.00 $34.85 $35.72 $36.61 $37.53 20 $680.00 $697.00 $715.00 $733.00 $751.00 $695.00
Miscellaneous Administrative Costs
Postage and Shipping
Office supplies
Drinking water/Ice
Construction Progress Documentation
Construction Progress Schedule
Scheduler $100.00 $102.50 $105.06 $107.69 $110.38 16 $1,600.00 $1,640.00 $1,681.00 $1,724.00 $1,767.00 $1,633.00
Construction Cost Control and Accounting
Cost Engineer $85.00 $87.13 $89.30 $91.54 $93.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Accounting Supervisor $65.00 $66.63 $68.29 $70.00 $71.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Accountant $50.00 $51.25 $52.53 $53.84 $55.19 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Accounting Assistant $30.00 $30.75 $31.52 $32.31 $33.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Construction Documentation
Document Reproduction
Progressive photography
Monthly reports
Final photography
As-built drawings
Safety
Safety and First Aid
Safety Manager $70.00 $71.75 $73.54 $75.38 $77.27 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Safety supplies
First aid supplies
Quality Requirements
Survey
Bench marks and control points
Layout
Quality Control
Soil testing
Concrete testing
Steel testing
Miscellaneous testing
Temporary Facilities and Controls
Temporary Utility Installation
Electric service to site office
Telephone and internet service to office
Water service to office
Water service to construction area
Fire protection for construction area
Utility Useage
Electric for site office
Electric for construction area - lighting
Electric for construction area - general power
Telephone
Internet
Water for site office
Water for construction area
Construction Facilities
Hours per
Week
Average
weekly
wage
Estimated Project Duration
Hourly Rates Weekly Rates reflects hours / week
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Precon
Rate Schedule
Duration
Construction Sidekick
Bradley beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name Schedule 91 weeks
Owner: Precon 16 weeks
Location: Construction 75 weeks
0 weeks
Contract Type: 0 weeks
Project Summary:0
Section / Item
2.50% increase per year
Current 2013 2014 2015 2016 Current 2013 2014 2015 2016Hours per
Week
Average
weekly
wage
Estimated Project Duration
Hourly Rates Weekly Rates reflects hours / week
Project Management office
Office Rental - 99 Bayard Street
Leasehold improvements
Restoration at end of lease
Superintendent office
Setup
Rental
Removal
Conference Trailer
Setup
Rental
Removal
Site Storage
Storage facilities
Furnishings and Equipment
Office furniture
Office equipment - computers and peripherals
Office equipment - copiers (rental)
Office equipment - telephone and fax
Sanitary Facilities
Temporary toilet installation for site offices
Temporary toilet maintenance
Portable toilets (average of 6 units)
Project Identification
Project identification signage
Temporary interior signage
Cleaning and Waste Management
Progressive Cleaning
Labor foreman $72.50 $74.31 $76.17 $78.07 $80.03 40 $2,900.00 $2,973.00 $3,047.00 $3,123.00 $3,202.00 $2,961.00
Office cleaning
Waste Management
Dumpsters
Final Cleaning
Final cleaning
Temporary Enclosures, Protection and Conditioning
Temporary Safety Protection
Railings
Removal of temporary protection
Temporary Enclosures
Temporary enclosure of openings
Modify and remove perimeter fence
Temporary Heat and Humidity Control
Temporary heating equipment
Fuel
Security and Surveillance
Cameras
Camera installation
Web service
Maintenance
Security
Off-hours watchman $21.25 $21.78 $22.33 $22.88 $23.46 2 $43.00 $44.00 $45.00 $46.00 $47.00 $44.00
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Construction
Rate Schedule
Duration
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name Schedule 16.00 weeks
Owner: Precon 75.00 weeks
Location: Construction 0.00 weeks
0.00 weeks
Contract Type:
Project Summary: 0.00
Section/Item
Project Team 2.50% increase per year
Current 2013 2014 2015 2016 Current 2013 2014 2015 2016
On-site Staff
Project Executive 168.00$ 172.20$ 176.51$ 180.92$ 185.44$ 5.00$ 840.00$ 861.00$ 883.00$ 905.00$ 928.00$ 858.00$
Senior Project Manager 130.00$ 133.25$ 136.58$ 140.00$ 143.50$ 20.00$ 2,600.00$ 2,665.00$ 2,732.00$ 2,800.00$ 2,870.00$ 2,654.00$
Project Manager 105.00$ 107.63$ 110.32$ 113.07$ 115.90$ 40.00$ 4,200.00$ 4,305.00$ 4,413.00$ 4,523.00$ 4,637.00$ 4,287.00$
MEP Project Manager 85.00$ 87.13$ 89.30$ 91.54$ 93.82$ 40.00$ 3,400.00$ 3,485.00$ 3,573.00$ 3,662.00$ 3,753.00$ 3,471.00$
General Superintendent 128.00$ 131.20$ 134.48$ 137.84$ 141.29$ 5.00$ 640.00$ 656.00$ 673.00$ 690.00$ 707.00$ 654.00$
Project Superintendent 105.00$ 107.63$ 110.32$ 113.07$ 115.90$ 40.00$ 4,200.00$ 4,305.00$ 4,413.00$ 4,523.00$ 4,637.00$ 4,287.00$
MEP Superintendent 124.00$ 127.10$ 130.28$ 133.53$ 136.87$ 40.00$ 4,960.00$ 5,084.00$ 5,212.00$ 5,342.00$ 5,475.00$ 5,063.00$
MEP Coordinator 115.00$ 117.88$ 120.82$ 123.84$ 126.94$ 5.00$ 575.00$ 590.00$ 605.00$ 620.00$ 635.00$ 588.00$
Project Engineer 90.00$ 92.25$ 94.56$ 96.92$ 99.34$ 40.00$ 3,600.00$ 3,690.00$ 3,783.00$ 3,877.00$ 3,974.00$ 3,675.00$
Administrative Assistant - Field 26.00$ 26.65$ 27.32$ 28.00$ 28.70$ 40.00$ 1,040.00$ 1,066.00$ 1,093.00$ 1,120.00$ 1,148.00$ 1,062.00$
Travel and expenses
Parking
Support Staff
Administrative Assistant - Office 40.00$ 41.00$ 42.03$ 43.08$ 44.15$ 16.00$ 640.00$ 656.00$ 673.00$ 690.00$ 707.00$ 654.00$
Insurance Coordinator 35.00$ 35.88$ 36.77$ 37.69$ 38.63$ 5.00$ 175.00$ 180.00$ 184.00$ 189.00$ 194.00$ 180.00$
Director of Preconstruction Services 150.00$ 153.75$ 157.59$ 161.53$ 165.57$ 4.00$ 600.00$ 615.00$ 631.00$ 647.00$ 663.00$ 613.00$
Senior Estimator 85.00$ 87.13$ 89.30$ 91.54$ 93.82$ -$ -$ -$ -$ -$ -$ -$
Procurement Specialist 60.00$ 61.50$ 63.04$ 64.61$ 66.23$ 20.00$ 1,200.00$ 1,230.00$ 1,261.00$ 1,293.00$ 1,325.00$ 1,225.00$
Contract Administrator 40.00$ 41.00$ 42.03$ 43.08$ 44.15$ 10.00$ 400.00$ 410.00$ 421.00$ 431.00$ 442.00$ 409.00$
Outreach Coord/Certified Payroll 65.00$ 66.63$ 68.29$ 70.00$ 71.75$ 5.00$ 325.00$ 334.00$ 342.00$ 350.00$ 359.00$ 333.00$
IST technician 40.00$ 41.00$ 42.03$ 43.08$ 44.15$ 1.00$ 40.00$ 41.00$ 43.00$ 44.00$ 45.00$ 41.00$
Document Manager 34.00$ 34.85$ 35.72$ 36.61$ 37.53$ 20.00$ 680.00$ 697.00$ 715.00$ 733.00$ 751.00$ 695.00$
Miscellaneous Administrative Costs
Postage and Shipping
Office suppliesDrinking water/Ice
Construction Progress Documentation
Construction Progress Schedule
Scheduler 100.00$ 102.50$ 105.06$ 107.69$ 110.38$ 12.00$ 1,200.00$ 1,230.00$ 1,261.00$ 1,293.00$ 1,325.00$ 1,225.00$
Construction Cost Control and Accounting
Cost Engineer 85.00$ 87.13$ 89.30$ 91.54$ 93.82$ 40.00$ 3,400.00$ 3,485.00$ 3,573.00$ 3,662.00$ 3,753.00$ 3,471.00$
Accounting Supervisor 65.00$ 66.63$ 68.29$ 70.00$ 71.75$ 5.00$ 325.00$ 334.00$ 342.00$ 350.00$ 359.00$ 333.00$
Accountant 50.00$ 51.25$ 52.53$ 53.84$ 55.19$ 20.00$ 1,000.00$ 1,025.00$ 1,051.00$ 1,077.00$ 1,104.00$ 1,021.00$
Accounting Assistant 30.00$ 30.75$ 31.52$ 32.31$ 33.11$ 4.00$ 120.00$ 123.00$ 127.00$ 130.00$ 133.00$ 123.00$
Construction Documentation
Document Reproduction
Progressive photography
Monthly reports
Final photography
As-built drawings
Safety
Safety and First Aid
Safety Manager (Per Month) 70.00$ 71.75$ 73.54$ 75.38$ 77.27$ 40.00$ 2,800.00$ 2,870.00$ 2,942.00$ 3,016.00$ 3,091.00$ 2,858.00$
Safety supplies
First aid supplies
Quality Requirements
Survey
Bench marks and control points
Layout
Quality Control
Soil testing
Concrete testing
Steel testing
Miscellaneous testing
Temporary Facilities and Controls
Temporary Utility Installation
Electric service to site office
Telephone and internet service to office
Water service to office
Water service to construction area
Fire protection for construction area
Utility Useage
Electric for site office
Electric for construction area - lighting
Electric for construction area - general power
Telephone
Internet
Water for site office
Water for construction area
Construction Facilities
Project Management office
Office Rental - 99 Bayard Street
Leasehold improvements
Restoration at end of lease
Superintendent office
Setup
Rental
Removal
Conference Trailer
Hours per
Week
Average
weekly wage
91
Hourly Rates Weekly Rates reflects hours/week
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Construction
Rate Schedule
Duration
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name Schedule 16.00 weeks
Owner: Precon 75.00 weeks
Location: Construction 0.00 weeks
0.00 weeks
Contract Type:
Project Summary: 0.00
Section/Item
Project Team 2.50% increase per year
Current 2013 2014 2015 2016 Current 2013 2014 2015 2016Hours per
Week
Average
weekly wage
91
Hourly Rates Weekly Rates reflects hours/week
Setup
Rental
Removal
Site Storage
Storage facilities
Furnishings and Equipment
Office furniture
Office equipment - computers and peripherals
Office equipment - copiers (rental)
Office equipment - telephone and fax
Sanitary Facilities
Temporary toilet installation for site offices
Temporary toilet maintenance
Portable toilets (average of 6 units)
Project Identification
Project identification signage
Temporary interior signage
Cleaning and Waste Management
Progressive Cleaning
Labor foreman 72.50$ 74.31$ 76.17$ 78.07$ 80.03$ 40.00$ 2,900.00$ 2,973.00$ 3,047.00$ 3,123.00$ 3,202.00$ 2,961.00$
Office cleaning
Waste Management
Dumpsters
Final Cleaning
Final cleaning
Temporary Enclosures, Protection and Conditioning
Temporary Safety Protection
Railings
Removal of temporary protection
Temporary Enclosures
Temporary enclosure of openings
Modify and remove perimeter fence
Temporary Heat and Humidity Control
Temporary heating equipment
Fuel
Security and Surveillance
Cameras
Camera installation
Web service
Maintenance
SecurityOff-hours watchman 21.25$ 21.78$ 22.33$ 22.88$ 23.46$ 60.00$ 1,275.00$ 1,307.00$ 1,340.00$ 1,374.00$ 1,408.00$ 1,275.00$
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 1
Design Engineering
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Architect I Architect II Architect III
Concept Design to 30/60% 2,000,000$ 2,100,000$ 2,400,000$
Construction Documents 2,000,000$ 2,000,000$ 2,000,000$
Construction Phase Support 1,500,000$ 1,600,000$ 1,550,000$
Total Guaranteed Maximum Price Estimate 5,500,000$ 5,700,000$ 5,950,000$
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 2
Site
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsSitework
Contractor I
Sitework
Contractor II
Sitework
Contractor III
Submittals and Mobilization 22,000$ 39,000$ 28,000$
Site Demolition 96,000$ 114,000$ 120,000$
Foundation Excav / bkfl 145,000$ 746,000$ 740,000$
Site Curbs, Walks, Paving, Improvements 383,000$ 331,000$ 390,000$
Site Utilities (Storm, Water, Sewer, Electric) 258,000$ 375,000$ 380,000$
Grading, topsoil and stone under slabs 570,000$ 186,000$ 200,000$
Staging and Traffic Control 46,000$ 4,000$ 5,000$
Performance Bond 16,000$ 23,000$ 25,000$
Plan revisions October 2012 56,500$ included included
Crane pad installed and removed 10,300$ 16,000$ 17,500$
perimeter drain , fabric and stone 12,500$ 8,000$ 9,000$
revised sheeting / shoring 175,000$ included included
Basement excavation and backfill 18,000$ included included
Police for traffic control Included Included Included
Temporary water service Allowance 5,000$ 5,000$ 5,000$
Contaminated soil delays Allowance 5,000$ 5,000$ 5,000$
addendum 1 concrete stair Allowance 5,000$ 5,000$ 5,000$
Addendum 2 - reroute storm line 181,000$ 185,000$ 185,000$
Addendum 3 - pipe material change (66,000)$ (52,000)$ (52,000)$
Addendum 4 changes 29,800$ 3,000$ 3,000$
Addendum 5 changes 6,000$ 6,500$ 6,700$
Addendum 6 changes - wall change 51,000$ 58,000$ 59,000$
Total Guaranteed Maximum Price Estimate 2,025,100$ 2,057,500$ 2,131,200$
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 2
Deep Foundations
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsFoundation
Contractor I
Foundation
Contractor II
Foundation
Contractor III
Submittals and Mobilization 176,000 200,000 300,000
Large Diameter Caissons 845,000 1,299,000 1,430,000
Small Diameter Caissons 523,000 included included
Engineering 14,000 included included
Performance bond 18,000 18,000 included
Set anchor bolts included 10,000 included
Lead engineer included 36,000 38,000
Dewatering included 30,500 included
Allowance Caisons 30,000 30,802 30,802
Addendum 2 caisson changes 20,000 20,000 20,000
Allowance for underground obstructions 25,000 25,000 25,000
Out of Sequence remob's / site constraints 50,000 50,000 50,000
traffic control allowance 25,000 25,000 25,000
Total Guaranteed Maximum Price Estimate $1,726,000 $1,744,302 $1,918,802
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 2
Landscaping
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Landscaper I Landscaper II Landscaper III
Submittals and Mobilization
Plants / Shrubs 10,000 8,000 20,000
tree pit soil mix included 10,000 2,500
Topsoil at lawn areas 4,000 4,000 5,000
Excav / Rmv soil from tree pits 700 700 600
lawn mix at grass areas 1,000 6,000 1,000
Provide specified trees 5,000 included included
Total Guaranteed Maximum Price Estimate $20,700 $28,700 $29,100 $0
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 3
Concrete
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsConcrete
Contractor I
Concrete
Contractor II
Concrete
Contractor III
Submittals and Mobilization 200,000 250,000 included
Foundations 7,052,000 6,900,000 1,619,000
Slab on grade included included 724,000
Superstructure included included 3,337,000
Fill slabs and washes included included 1,649,000
Basement included 310,000 350,000
Miscellaneous Concrete included included 251,000
Sales Tax exempt exempt exempt
Performance bond included 100,000 71,000
MEP / Emergency Generator pad included included 10,000
Winter concrete included included included
Lead Engineer included included included
Added cost of bending rebar on site included included included
Delete hoist pad included included included
Traffic control 25,000 25,000 25,000
Late changes to design 240,000 240,000 240,000
Total Guaranteed Maximum Price Estimate $7,517,000 $7,825,000 $8,276,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 3
Pre-Cast Concrete
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Precaster I Precaster II Precaster III
Submittals and Mobilization
Precast Concrete - Garage 13,000,000 13,200,000 14,000,000
Hollow Core Plank included included included
Sales tax tax exempt tax exempt tax exempt
Performance bond 77,000 95,000 200,000
Caulking and expansion joints included 400,000 included
150% crane capacity 324,000 included not included
E/O insurance included 12,000 included
100% tie off (erection in accordance with OSHA Subpart A) not included not included not included
Deck sealer included 85,000 included
Delete helix precast (by CIP contractor) not included (65,000) not included
On site mock-up 12,600 included 15,000
Delete atrium stair not included (17,000) not included
Railroad insurance 10MM (deduct alt) 85,000 52,000 175,000
Spandrel coating included 89,000 included
Police allowance (traffic control) 70,000 76,000 included
Cast iron tread inserts included 15,000 included
Temporary rails and plywood at stairs included 24,000 included
Perimeter spandrel cable included included 210,000
Traffic topping at helix not included not included not included
Changes made to design following award of subcontract 100,000
Total Guaranteed Maximum Price Estimate $13,668,600 $13,966,000 $14,600,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 4
Masonry
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
conrtuctionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Mason I Mason I Mason I
Submittals and Mobilization 7,500 9,000 27,000
CMU Masonry Partitions 100,000 120,000 98,000
CMU elevator door infills 24,000 35,000 20,000
Sales Tax exempt exempt exempt
Performance Bond 4,000 3,500 3,400
CMU Masonry wall at Loading Dock 45,000 33,000 76,000
Perforrmance Bond 1,500 1,000 3,000
Total Guaranteed Maximum Price Estimate $182,000 $201,500 $227,400
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 5
Metals
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsMetals
Contractor I
Metals
Contractor II
Metals
Contractor III
Submittals and Mobilization 60,000 60,000 141,000
Ladders (roof and pits) 970,000 980,000 1,555,000
exterior guardrail system alum powder coat included included included
pipe protectors included included included
stair mesh panels, railings included included included
sumps / pit angles included included included
glass rail at lobbies included included included
Metal stairs - ornamental included included included
Performance Bond 5,000 12,000 25,000
Exterior signage support 28,000 31,000 35,000
Lintels 39,384 93,000 85,000
Corner guards, post guards, and cart stops 10,000 included included
Aluminum and stainless column wraps A-301 10,000 included included
Diamond plate wainscot 11/A-301 20,000 included included
Metal cooler close off panel 6/A-301 10,000 included included
Galvanized curb angle F&I 8/A-301 4,000 included included
Channel / Angle bracing 9/A-652 3,000 4,000 5,000
Performance Bond 392 2,000 3,000
Steel support for coiling doors and fire shutters 30,000 31,000 32,000
Total Guaranteed Maximum Price Estimate $1,189,776 $1,213,000 $1,881,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 6
Carpentry
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Carpenter I Carpenter II Carpenter III
Submittals and Mobilization 10,000 15,000 20,000
Framing 25,000 26,000 30,000
Roof Blocking 7,000 7,000 8,000
Install Toilet accessories 1,500 1,500 1,700
Total Guaranteed Maximum Price Estimate $43,500 $49,500 $59,700
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 7
Waterproofing
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Waterproofer I Waterproofer II Waterproofer III
Submittals and Mobilization 5,000 6,000 3,000
Foundation Waterproofing 30,000 90,000 42,000
Elevated Slab Waterproofing 464,000 420,000 590,000
Flood Testing Horizontal included included 14,000
Crystalline at Elevator pits interior 5,000 16,000 16,000
Traffic Topping - Helix 51,000 72,000 95,000
Caulking excluding precast and internal rain screen 43,000 38,000 41,000
Performance Bond 12,000 22,000 26,000
Addendum 4 21,000 20,000 20,000
waterproof existing foundation wall 5,000 5,000 4,000
Total Guaranteed Maximum Price Estimate $636,000 $689,000 $851,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 7
Sprayed on Insulation
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Insulator I Insulator II Insulator III
Submittals and Mobilization 5,000 6,000 1,000
Spray Insulation - underside 3rd floor 700,000 705,000 786,000
Performance Bond 17,000 20,000 18,000
Insulation material proposed R-13 R-13 GLASS
Allowance for patching insulation during fitouts 30,000 30,000 30,000
Total Guaranteed Maximum Price Estimate $752,000 $761,000 $835,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 7
Fireproofing
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Fireproofer I Fireproofer II Fireproofer III
Mobilizations 500 1,200 1,500
Miscellaneous Fireproofing 25,000 27,500 32,000
Total Guaranteed Maximum Price Estimate $25,000 $27,500 $32,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 7
Metal Panels
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsPanel Contractor
I
Panel Contractor
II
Panel Contractor
III
Submittals and Mobilization 10,000 15,000 1,600
metal panel rain screen floors 2, 3 (6,000 sf) 248,000 200,000 225,000
elevator door surrounds 18,000 85,000 84,000
Performance Bond 6,000 5,000 5,000
Total Guaranteed Maximum Price Estimate $282,000 $305,000 $315,600
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 7
Roofing
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Roofer I Roofer II Roofer III
Submittals and Mobilization 2,000 5,000 1,000
Membrane Roofing 155,000 381,000 780,000
Sheet Metal Trim and Flashing 32,000 included included
roof hatch 2,500 2,500 included
Standing Seam Metal Roofing - stair 4 and low canopy 30,000 30,000 30,000
Performance Bond 3,000 6,000 12,500
Total Guaranteed Maximum Price Estimate $224,500 $424,500 $823,500
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 8
Doors Windows
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Door Supplier I Door Supplier II Door Supplier III
Submittals and Mobilization 1,000 1,200 2,000
Metal Doors 15,000 58,000 20,000
Metal Frames 5,000 included 6,000
Hardware 31,000 included 40,000
Exterior
Metal Doors 1,000 1,200 25,000
Metal Frames 2,500 3,000 included
Wood Doors 5,000 8,000 included
Hardware 8,000 11,000 included
Total Guaranteed Maximum Price Estimate $68,500 $82,400 $93,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 8
Overhead Doors
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsOH Door
Supplier I
OH Door
Supplier I
OH Door
Supplier I
Submittals and Mobilization 1,000 2,000 3,000
One (1) rolling Steel Door 60,000 67,000 126,000
Labor to Install 8,000 Included 10,000
Sales Tax exempt exempt exempt
Performance Bond 1,200 7,000 2,000
Roll Up Doors 1 & 2 6,000 48,000 7,000
Labor to Install 2,000 included 3,000
rolling grilles 14,000 21,000 21,000
Fire Shutters 73,000 76,000 76,000
Sales Tax exempt exempt exempt
Performance Bond 200 200 200
Total Guaranteed Maximum Price Estimate $165,400 $221,200 $248,200
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 8
Traffic Impact Doors
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsTraffic Door
Supplier I
Traffic Door
Supplier II
Traffic Door
Supplier III
Submittals and Mobilization 1,000$ 2,000$ 3,000$
Impact Trafffic Doors DA2 & DA1 11,000$ 12,000$ 20,000$
Labor to Install 4,000$ 6,000$ included
Performance Bond 400$ 400$ Included
Total Guaranteed Maximum Price Estimate $16,400 $20,400 $23,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 8
Aluminum Glass
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsGlass Contractor
I
Glass Contractor
II
Glass Contractor
III
Submittals and Mobilization 1,000 2,000 3,000
Glass and Glazing 762,000 780,000 900,000
Performance Bond 11,000 1,000 20,000
slab edge metal trim at nose (41 x 7 x 100) 20,000 20,000 26,000
Glass and Glazing included 27,000 35,000
Aluminum Entrance and Storefront included included included
Perimeter Caulk included included included
Auto Doors included included included
Sales Tax exempt exempt exempt
Performance Bond 500 600 1,000
Total Guaranteed Maximum Price Estimate $794,500 $830,600 $985,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 8
Louvers
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Louver Supplier ILouver Supplier
II
Louver Supplier
III
HVAC Louvers 4,000 5,000 7,000
Louvers in Electrical Room 350 400 700
Total Guaranteed Maximum Price Estimate $4,350 $5,400 $7,700
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Drywall Acoustical Ceilings
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Carpenter I Carpenter II Carpenter III
Submittals and Mobilization 10,000 11,000 3,000
Set Doors, Frames, Hardware 30,000 35,000 39,000
Rough Carpentry and Blocking 17,000 5,000 14,000
Drywall / Metal Studs /Insulation 147,000 76,000 133,000
Ceilings and soffits 53,000 13,000 3,000
Performance Bond 4,000 2,000 5,000
Second Floor
Set Doors, Frames, Hardware 12,000 36,000 13,000
Rough Carpentry and Blocking 8,000 20,000 10,000
Drywall / Metal Studs /Insulation 216,000 237,000 281,000
Ceilings and soffits 343,000 366,000 437,000
FRP panels 20,000 45,000 62,000
Sales Tax exempt exempt exempt
Performance Bond 1,000 16,000 15,000
Labor for cleanup 100,000 100,000 100,000
Total Guaranteed Maximum Price Estimate $961,000 $962,000 $1,115,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Ceramic Tile
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Tile Contractor I Tile Contractor IITile Contractor
III
Submittals and Mobilization 1,500 2,000 2,000
Exterior Tile Wall 23,000 24,000 24,000
Interior Tilework 51,000 52,000 52,000
Atrium Stair Tile Treads 5,000 5,000 5,000
Ceramic Tile Walls, Floor, Base 74,000 175,000 175,000
Terrazzo Tile 43,000 included included
Performance Bond 7,000 6,000 6,000
Total Guaranteed Maximum Price Estimate $204,500 $264,000 $264,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Vinyl Flooring
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsFlooring
Contractor I
Flooring
Contractor II
Flooring
Contractor III
Submittals and Mobilization 500 600 700
Resilient Floor, Carpet and Base 4,000 4,000 5,000
Performance Bond 100 200 1,500
Resilient Flooring and Base 7,500 8,000 10,000
Performance Bond 200 3,000 200
Total Guaranteed Maximum Price Estimate $12,300 $15,800 $17,400
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Resinous Flooring
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsFlooring
Contrctor I
Flooring
Contrctor II
Flooring
Contrctor III
Submittals and Mobilization 1,000 2,000 3,000
Resinous Flooring and Base 35,000 58,000 60,000
performance bond 700 2,000 2,500
floor protection (5,000 SF) 2,000 3,000 3,000
Total Guaranteed Maximum Price Estimate $38,700 $65,000 $68,500
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Polished Concrete
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Finisher I Finisher II Finisher III
Submittals and Mobilization 1,000 2,000 3,000
Concrete Polishing 9,000 1,000 20,000
performance bond 300 300 400
Concrete Polishing 109,000 130,000 170,000
performance bond 1,500 3,000 4,000
Total Guaranteed Maximum Price Estimate $120,800 $136,300 $197,400
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 9
Painting
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Painter I Painter II Painter III
Submittals and Mobilization 2,000 3,000 4,000
Painting 40,000 70,000 110,000
Sealer 7,000 included included
Line Striping 26,000 26,000 included
Exterior Painting 20,000 included included
Touch Up allowance 2,000 2,000 included
Performance Bond 3,000 2,480 4,000
Elevator lobby wall coating 30,000 30,000 30,000
Painting per RFS 50,000 50,000 50,000
touch up allowance 2,000 2,000 included
Performance bond 2,000 2,000 3,000
Total Guaranteed Maximum Price Estimate $184,000 $187,480 $201,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 10
Specialties
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsSpecialty
Supplier I
Specialty
Supplier II
Specialty
Supplier III
Toilet Room Accessories (1 room) 1,200 1,200 1,200
Fire Extinguishers and cabinets f/o 6,000 7,000 9,000
Toilet Room Accessories 9,000 9,000 9,000
Toilet Partitions including installation 8,000 8,000 8,000
Walk off mats 4,000 4,000 4,000
Fire Extinguishers and cabinets 1,000 1,000 1,000
Total Guaranteed Maximum Price Estimate $29,200
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage 3647
Division 10
Signage
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Sign Supplier I Sign Supplier II Sign Supplier III
Submittals and Mobilization 1,000 2,000 3,000
Garage Signs - material 85,000 70,000 61,000
Garage Signs - install 21,000 38,000 50,000
Performance Bond 2,000 5,000 2,500
Total Guaranteed Maximum Price Estimate $109,000 $115,000 $116,500
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 10
Dock Equipment
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsEquipment
Supplier I
Equipment
Supplier I
Equipment
Supplier I
Submittals and Mobilization 1,000 2,000 3,000
Two (2) Hydraulic Dock Levelers 13,000 14,000 15,000
Two (2) Rubber Dock Bumpers included 500 included
Performance Bond 400 500 included
Labor to Install 2,000 2,000 included
truck restraints on levelers included 6,000 7,000
Total Guaranteed Maximum Price Estimate $16,400 $25,000 $25,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 10
Parking Equipment
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsEquipment
Supplier I
Equipment
Supplier II
Equipment
Supplier III
Submittals and Mobilization
Parking Equipment 390,000 451,000 451,000
Control System by Magnetic Federal ADP Federal ADP
Sawcut loops / vehicle detectors included included included
Central Management Software System included included included
Sales Tax exempt exempt exempt
Performance Bond 10,000 12,000 12,000
Total Guaranteed Maximum Price Estimate $400,000 $463,000 $463,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 12
Floor Grilles
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Grille Supplier I Grille Supplier II Grille Supplier III
Submittals 1,000 2,000 3,000
Entrance Mat and frame 28,000 21,000 27,000
Installation included 8,000 9,000
Perimeter grout in floor grille (allowance) 2,000 3,000 3,500
Total Guaranteed Maximum Price Estimate $31,000 $34,000 $42,500
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 14
Elevators
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsElevator
Contractor I
Elevator
Contractor II
Elevator
Contractor III
Submittals and Mobilization 5,000 6,000 1,000
Traction Elevators 700,000 701,000 780,000
Hydraulic Elevators included 67,000 included
Performance Bond 4,000 4,000 incl
Multiple crews for erection 5,000 included included
Seismic Design per dwg S-001 criteria included included included
Swing car operation for service car 9,000 included 3,000
Front and rear opening cab at pool (Addendum no. 2) 11,000 included included
Fans in glass cabs included 3,000 included
Crane picks 5,000 included 4,000
Total Guaranteed Maximum Price Estimate $739,000 $781,000 $788,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 15
Fire Protection
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items FP Contractor I FP Contractor II FP Contractor III
General Conditions and Mobilization 6,000 7,000 35,000
Fire Service and Fire Pump Room Piping/Valves/Fittings 34,000 640,000 included
Standpipes including bulk mains/fire department conn's 215,000 included 650,000
Sprinkler Risers including Floor Control Valve Assemblies 27,000 35,000 30,000
Fire Pump/Jockey Pump/Controllers 53,000 included 40,000
Wet-pipe and Dry-pipe Sprinkler Systems (not including risers) 266,000 included included
Sprinkler Shop Drawings/Hydraulic Calcs 29,000 included 70,000
Performance Bond 6,000 16,000 included
Fire Protection - Grocery Store (Wet System) 56,000 included included
Engineering 6,000 included included
Performance Bond 700 2,000 included
Total Guaranteed Maximum Price Estimate $698,700 $700,000 $825,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 15
Plumbing
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Plumber I Plumber II Plumber III
General Conditions and Mobilization 53,000 57,000 20,000
Lift Station Pumps and Prefab F/G Pit (LP-2), Domestic Water Booster 1,100,000 14,000 103,000
Foundation Drainage Piping System included 133,700 115,000
Sanitary Drain, Waste, and Vent Piping System and Equipment included 220,000 130,000
Stormwater and Parking Garage Drainage Piping System included 132,000 528,000Domestic Water Piping/Equipment and Parking Garage Washdown
Systems (Base Bid Only) included 251,000 225,000
Natural Gas Piping System included 98,000 115,000
Plumbing Piping/Equipment Insulation included 78,000 35,000
Performance Bond 19,000 19,700 19,000
Cleanup included 10,000 included
Excavation and Backfill included 25,000 included
Permits included 5,000 included
Temporary Water Piping and Heat Trace included 7,500 included
Cost of 6/7/11 IFC Documents included 100,000 included
Sanitary Drain, Waste, and Vent Piping System (Cast Iron) included 488,100 852,000
Domestic Water Piping and Parking Garage Washdown Systems included 185,900 260,000
Natural Gas Piping System included 95,900 100,000
Plumbing Piping/Equipment Insulation included 60,000 40,000
Performance Bond 19,000 17,500 19,000
ADD for stainless steel drip pans 220,500 220,500 included
Cleanup included 10,000 included
Excavation and Backfill included 75,000 included
Permits included 5,000 included
Total Guaranteed Maximum Price Estimate $1,411,500 $2,308,800 $2,561,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 15
Mechanical
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid ItemsHVAC Contractor
I
HVAC Contractor
II
HVAC Contractor
III
General Conditions and Mobilization 25,000 28,000 49,868
Cooling Tower, Pumps, Heat Exchanger, Filtration, Piping 440,000 482,000 283,582
Ductwork, exhaust fans, and air devices/accessories 90,900 100,000 203,890
A/C Units, misc. cooling/heating equipment, refrigerant piping 617,900 175,000 139,130
Ductwork, piping, and equipment insulation 90,000 96,000 238,000
HVAC Controls 115,000 133,000 96,500
Testing, Adjusting, and Balancing 4,000 6,000 19,000
Performance Bond 20,000 20,000 17,830
Outdoor HVAC Units for Fresh Grocer included 289,700 289,700
Duct Insulation in Lobby of Nose 25,350 25,350 25,350
Furnish Indoor HVAC Units for Fresh Grocer included 65,000 65,000
Lead Engineer included 5,000 5,000
Duct Cleaning included 5,000 5,000
Disconnect Switches included 3,500 3,500
Permits included 2,500 2,500
Controls for Indoor & Outdoor HVAC units (allowance) 100,000 100,000 100,000
Ductwork, exhaust fans, and air devices/accessories 415,000 486,000 594,460
A/C Units, misc. cooling/heating equipment, refrigerant piping 156,000 155,000 47,834
Ductwork, piping, and equipment insulation 145,000 177,000 198,448
Testing, Adjusting, and Balancing 7,000 9,500 13,000
Performance Bond 11,300 15,833 15,833
ADD for field-applied Aluminum Jacketing on Ducts/Equip 213,000 213,000 213,000
Lead Engineer included 5,000 5,000
Excavation and Backfill included 7,500 7,500
Total Guaranteed Maximum Price Estimate $2,475,450 $2,604,883 $2,638,925
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Division 16
Electrical
Construction Sidekick
Bradley Beach New Jersey
732-775-3867
constructionsidekick.com
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items Electrician I Electrician II Electrician III
General Conditions, Submittals, and Mobilization 160,000 50,000 92,000
Temporary electric services, power, and lighting 52,000 60,000 93,000
Service, Telephone Service, Generator Ductbanks and Feeders 255,000 450,000 419,000
Distribution Switchboards and Panelboards 260,000 275,000 231,000
Normal low-voltage power distribution and branch circuits 560,000 680,000 284,000
Emergency Generator, ATS, Emergency Panels, Branch Circuits 387,000 250,000 434,000
Site Lighting/Building-mounted Lighting systems 170,000 85,000 305,000
Interior Lighting Fixtures and Controls 590,000 461,500 1,066,000
Fire Alarm System 80,000 155,000 297,000
Security System CCTV cameras, conduit, cabling, and equipment 146,200 146,200 191,000
Telephone, Data, and Low-voltage System Pathways/Cabling 65,000 50,000 39,000
Performance Bond 25,500 23,500 98,000
Excavation, Backfill and Concrete for Ductbanks 30,000 included included
Temporary Power to Elevators 32,000 12,000 included
Site Lighting and pole bases included 20,000 included
Excavation and Backfill for Site Lighting included 25,000 included
Lead Engineer included 5,000 included
Permits included 30,000 12,000
Loading andTrucking of Spoils included 10,000 10,000
Distribution Switchboards and Panelboards 190,000 450,000 184,000
Normal low-voltage power distribution and branch circuits 463,000 252,000 438,000
Normal low-voltage power distribution and branch circuits 142,000 200,000 189,000
Interior Lighting Fixtures and Controls 578,000 808,000 530,000
Fire Alarm System 80,000 60,000 48,000
CPC Control, Remote Annunciation, and Lighting 182,000 400,000 217,000
Telephone, Data, and Low-voltage System Pathways/Cabling 61,000 50,000 2,000
Performance Bond 19,000 21,000 50,000
Clean-up to Dumpster included 15,000 included
Lead Engineer included 2,500 included
Permits included 12,000 included
Install Fresh Grocer-furnished Equip included 40,000 included
Total Guaranteed Maximum Price Estimate $4,527,700 $5,098,700 $5,229,000
C:\Construction Sidekick\Construction Budget Mixed use Retail & Parking Garage
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Summary of Bids Received
Total Bid $0 $0 $0 $0
Page 46 of 47
Your Project Name
Owner:
Location:
Contract Type:
Project Summary:
Bid Items
Total Guaranteed Maximum Price Estimate $0 $0 $0 $0
Page 47 of 47