Construction plan for Concrete Block Tanks – EWB-Case

2
Construction plan for Concrete Block Tanks – EWB-Case Move tools to location Bend Rebar Move gravel to location Move Sand to location Layout tank Excavate tank Move water to location difficulty depends on final location, rainwater catchment off of nearby buildings is an option Move cement to location Move rebar to location Set forms and rebar Mix and pour foundation

description

Construction plan for Concrete Block Tanks – EWB-Case. Move tools to location. Layout tank. Excavate tank. Set forms and rebar. Mix and pour foundation. Move rebar to location. Bend Rebar. Move gravel to location. - PowerPoint PPT Presentation

Transcript of Construction plan for Concrete Block Tanks – EWB-Case

Page 1: Construction plan for Concrete Block Tanks – EWB-Case

Construction plan for Concrete Block Tanks – EWB-Case

Move tools to location

Bend Rebar

Move gravel to location

Move Sand to location

Layout tank Excavate tank

Move water to location – difficulty depends on final location, rainwater catchment off of nearby buildings is an option

Move cement to location

Move rebar to location

Set forms and rebar

Mix and pour foundation

Page 2: Construction plan for Concrete Block Tanks – EWB-Case

Cover foundation Let foundation dry Lay 1st layer of block

Move concrete block to location

Move sand and cement for mortar

Move pipes for input/output, overflow and drainage

Lay rest of block

Set forms for pipes

Pour concrete for pipes

Waterproof Tank

Next trip:

Move Supplies for roof

Build roof and attach to tank

Build baffle and weir

Place baffle and weir in tank