Construction Cost Handbook 2019 - Indonesia
Transcript of Construction Cost Handbook 2019 - Indonesia
PT. Arcadis Indonesia would like to acknowledge the
following projects featured on our cover page:
1. Semanggi Revitalisation, Jakarta
2. Six Senses, Bali
3. Mangkuluhur City, Jakarta
4. Garuda Wisnu Kencana, Bali
5. Sopo Del, Jakarta
1
4
2
5 3
Fifth Edition 2019 © PT. Arcadis Indonesia
All rights reserved. No part of this publication may be re-produced or copied in any form without prior written permission from PT. Arcadis Indonesia.
The information contained herein should be regarded as indicative and for general guidance only. Whilst every effort has been made to ensure accuracy, no responsibility can be accepted for errors and omissions, however caused.
Unless otherwise stated, costs reflected in this handbook are current at 4th Quarter 2018.
Published by Arcadis Indonesia
TABLE OF CONTENTS 4
Table of Contents 4
Introduction 6
Calendars 7
1. CONSTRUCTION COST DATA
Construction Costs for Indonesia 12
M&E Costs for Indonesia 16
Cost Breakdown for different building types 18
Construction Costs for Selected Asian Cities 20
M&E Costs for Selected Asian Cities 26
Major Rates for Selected Asian Cities 32
Utility Costs for Selected Asian Cities 38
Electricity Tariffs for Indonesia 40
Office MEP Cost Components 42
International Construction Cost 44
2. GENERAL CONSTRUCTION DATA
2019 Outlook 47
Construction Cost Trends in Indonesia
a) Material Price Indices 48 b) Consumer Price Indices 50 c) Labour Rates 52 d) Indonesia Construction Cost Indices 53
TABLE OF CONTENTS 5
3. CONTRACT PROCUREMENT
Procurement Model and Contract Forms 56
4. OTHER INFORMATION
Exchange Rates 62
Prime Rates 64
Currency Fluctuations 65
Jakarta Stock Exchange Index 66
Conversion Factors 67
IDD Codes and Time Differences 73
Relevant Websites 74
Current Construction Regulations 75
5. ARCADIS
Arcadis Values 86
Arcadis General Business Principles 87
Cost Management 88
Project and Programme Management 89
Design and Engineering 90
Environmental Services 91
Water Solutions 91
Health and Safety 92
Arcadis Offices 94
Arcadis Asia Leadership Team 108
INTRODUCTION 6
ABOUT US
First established in 1934 in Singapore we have been
through our history the pre-eminent cost
management consultancy in Asia. Project
management followed cost management and
expansion into all other major territories in Asia
followed Singapore. The office in Indonesia was
established in 1972.
Under the legacy names of PT. Rislianto, PT. Davis
Langdon & Seah and PT. Langdon and Seah, the
company has been involved in many of the best-
known and most prestigious projects in the country.
Its varied track record takes in a multitude of projects
from nearly every sector of the construction industry.
After merging with Arcadis in 2012, and now
operating under the name of PT. Arcadis Indonesia,
the company is pushing its business lines beyond
cost management and project management, now
delivering design and engineering in water,
infrastructure, transportation, industry and
environment.
Arcadis is a global natural and built asset design and
consultancy firm working in partnership with clients
to deliver sustainable outcomes that help to improve
the quality of life. Through the work that we do, we
are helping our clients to address the toughest
challenges within the built and natural environments,
delivering value for them and the communities and
cities that we live in.
5
CALENDARS 7
2018
JANUARY FEBRUARY MARCH
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 1 2 3 1 2 3
7 8 9 10 11 12 13 4 5 6 7 8 9 10 4 5 6 7 8 9 10 14 15 16 17 18 19 20 11 12 13 14 15 16 17 11 12 13 14 15 16 17 21 22 23 24 25 26 27 18 19 20 21 22 23 24 18 19 20 21 22 23 24 28 29 30 31 25 26 27 28 25 26 27 28 29 30 31
APRIL MAY JUNE
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 7 1 2 3 4 5 1 2 8 9 10 11 12 13 14 6 7 8 9 10 11 12 3 4 5 6 7 8 9 15 16 17 18 19 20 21 13 14 15 16 17 18 19 10 11 12 13 14 15 16 22 23 24 25 26 27 28 20 21 22 23 24 25 26 17 18 19 20 21 22 23 29 30 27 28 29 30 31 24 25 26 27 28 29 30
JULY AUGUST SEPTEMBER
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 7 1 2 3 4 1 8 9 10 11 12 13 14 5 6 7 8 9 10 11 2 3 4 5 6 7 8 15 16 17 18 19 20 21 12 13 14 15 16 17 18 9 10 11 12 13 14 15 22 23 24 25 26 27 28 19 20 21 22 23 24 25 16 17 18 19 20 21 22 29 30 31 26 27 28 29 30 31 23 24 25 26 27 28 29 30
OCTOBER NOVEMBER DECEMBER S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 1 2 3 1
7 8 9 10 11 12 13 4 5 6 7 8 9 10 2 3 4 5 6 7 8 14 15 16 17 18 19 20 11 12 13 14 15 16 17 9 10 11 12 13 14 15 21 22 23 24 25 26 27 18 19 20 21 22 23 24 16 17 18 19 20 21 22 28 29 30 31 25 26 27 28 29 30 23 24 25 26 27 28 29 30 31
2019
JANUARY FEBRUARY MARCH
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 1 2 1 2
6 7 8 9 10 11 12 3 4 5 6 7 8 9 3 4 5 6 7 8 9 13 14 15 16 17 18 19 10 11 12 13 14 15 16 10 11 12 13 14 15 16 20 21 22 23 24 25 26 17 18 19 20 21 22 23 17 18 19 20 21 22 23 27 28 29 30 31 24 25 26 27 28 24 25 26 27 28 29 30 31
APRIL MAY JUNE
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 1 2 3 4 1
7 8 9 10 11 12 13 5 6 7 8 9 10 11 2 3 4 5 6 7 8 14 15 16 17 18 19 20 12 13 14 15 16 17 18 9 10 11 12 13 14 15 21 22 23 24 25 26 27 19 20 21 22 23 24 25 16 17 18 19 20 21 22 28 29 30 26 27 28 29 30 31 23 24 25 26 27 28 29 30
JULY AUGUST SEPTEMBER
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 6 1 2 3 1 2 3 4 5 6 7
7 8 9 10 11 12 13 4 5 6 7 8 9 10 8 9 10 11 12 13 14 14 15 16 17 18 19 20 11 12 13 14 15 16 17 15 16 17 18 19 20 21 21 22 23 24 25 26 27 18 19 20 21 22 23 24 22 23 24 25 26 27 28 28 29 30 31 25 26 27 28 29 30 31 29 30
OCTOBER NOVEMBER DECEMBER S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 5 1 2 1 2 3 4 5 6 7
6 7 8 9 10 11 12 3 4 5 6 7 8 9 8 9 10 11 12 13 14 13 14 15 16 17 18 19 10 11 12 13 14 15 16 15 16 17 18 19 20 21 20 21 22 23 24 25 26 17 18 19 20 21 22 23 22 23 24 25 26 27 28 27 28 29 30 31 24 25 26 27 28 29 30 29 30 31
99
CALENDARS
CALENDARS 8
2020
JANUARY FEBRUARY MARCH
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 1 1 2 3 4 5 6 7
5 6 7 8 9 10 11 2 3 4 5 6 7 8 8 9 10 11 12 13 14 12 13 14 15 16 17 18 9 10 11 12 13 14 15 15 16 17 18 19 20 21 19 20 21 22 23 24 25 16 17 18 19 20 21 22 22 23 24 25 26 27 28 26 27 28 29 30 31 23 24 25 26 27 28 29 29 30 31
APRIL MAY JUNE
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 1 2 1 2 3 4 5 6
5 6 7 8 9 10 11 3 4 5 6 7 8 9 7 8 9 10 11 12 13 12 13 14 15 16 17 18 10 11 12 13 14 15 16 14 15 16 17 18 19 20 19 20 21 22 23 24 25 17 18 19 20 21 22 23 21 22 23 24 25 26 27 26 27 28 29 30 24 25 26 27 28 29 30 28 29 30
JULY AUGUST SEPTEMBER
S M T W T F S S M T W T F S S M T W T F S 1 2 3 4 1 1 2 3 4 5
5 6 7 8 9 10 11 2 3 4 5 6 7 8 6 7 8 9 10 11 12 12 13 14 15 16 17 18 9 10 11 12 13 14 15 13 14 15 16 17 18 19 19 20 21 22 23 24 25 16 17 18 19 20 21 22 20 21 22 23 24 25 26 26 27 28 29 30 31 23 24 25 26 27 28 29 27 28 29 30 30 31
OCTOBER NOVEMBER DECEMBER S M T W T F S S M T W T F S S M T W T F S 1 2 3 1 2 3 4 5 6 7 1 2 3 4 5
4 5 6 7 8 9 10 8 9 10 11 12 13 14 6 7 8 9 10 11 12 11 12 13 14 15 16 17 15 16 17 18 19 20 21 13 14 15 16 17 18 19 18 19 20 21 22 23 24 22 23 24 25 26 27 28 20 21 22 23 24 25 26 25 26 27 28 29 30 31 29 30 27 28 29 30 31
2021
JANUARY FEBRUARY MARCH
S M T W T F S S M T W T F S S M T W T F S 1 2 1 2 3 4 5 6 1 2 3 4 5 6
3 4 5 6 7 8 9 7 8 9 10 11 12 13 7 8 9 10 11 12 13 10 11 12 13 14 15 16 14 15 16 17 18 19 20 14 15 16 17 18 19 20 17 18 19 20 21 22 23 21 22 23 24 25 26 27 21 22 23 24 25 26 27 24 25 26 27 28 29 30 28 28 29 30 31 31
APRIL MAY JUNE
S M T W T F S S M T W T F S S M T W T F S 1 2 3 1 1 2 3 4 5
4 5 6 7 8 9 10 2 3 4 5 6 7 8 6 7 8 9 10 11 12 11 12 13 14 15 16 17 9 10 11 12 13 14 15 13 14 15 16 17 18 19 18 19 20 21 22 23 24 16 17 18 19 20 21 22 20 21 22 23 24 25 26 25 26 27 28 29 30 23 24 25 26 27 28 29 27 28 29 30 30 31
JULY AUGUST SEPTEMBER
S M T W T F S S M T W T F S S M T W T F S 1 2 3 1 2 3 4 5 6 7 1 2 3 4
4 5 6 7 8 9 10 8 9 10 11 12 13 14 5 6 7 8 9 10 11 11 12 13 14 15 16 17 15 16 17 18 19 20 21 12 13 14 15 16 17 18 18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 25 26 27 28 29 30 31 29 30 31 26 27 28 29 30
OCTOBER NOVEMBER DECEMBER S M T W T F S S M T W T F S S M T W T F S 1 2 1 2 3 4 5 6 1 2 3 4
3 4 5 6 7 8 9 7 8 9 10 11 12 13 5 6 7 8 9 10 11 10 11 12 13 14 15 16 14 15 16 17 18 19 20 12 13 14 15 16 17 18 17 18 19 20 21 22 23 21 22 23 24 25 26 27 19 20 21 22 23 24 25 24 25 26 27 28 29 30 28 29 30 26 27 28 29 30 31 31
910
CALENDARS
CALENDARS 9
PUBLIC HOLIDAYS IN INDONESIA
2019
INDONESIA
New Year's Day
01-Jan
Chinese New Year's (Imlek) 05-Feb
Hindu Day of Quiet (Nyepi) 07-Mar
Ascension of Prophet Muhammad 03-Apr
Election Day 17-Apr
Good Friday 19-Apr
International Labour Day 01-May
Waisak Day 19-May
Ascension Day of Jesus Christ 30-May
Pancasila Day 01-Jun
Idul Fitri 05-06 Jun
Idul Adha Day 11-Aug
National Independence Day 17-Aug
Hijriyah New Year 01-Sep
Prophet Muhammad's Birthday 09-Nov
Christmas Day 25-Dec
Sustainability
Construction Costs for Indonesia
M&E Costs for Indonesia
Cost breakdown for different building types
Construction Costs for Selected Asian Cities
M&E Costs for Selected Asian Cities
Major Rates for Selected Asian Cities
Utility Costs for selected Asian Cities
Electricity Tariffs for Indonesia
Office MEP Cost Components
International Construction Cost
1
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
CO
NS
TR
UC
TIO
N C
OS
TS
FO
R IN
DO
NE
SIA
CONSTRUCTION COSTS FOR INDONESIA
BUILDING TYPE
Low IDR’000/m2
High IDR’000/m2
DOMESTIC
Apartments, high rise, average standard
Apartments, high rise, high end
10,960
15,120
12,400
17,060
OFFICE / COMMERCIAL
Medium/high rise offices, average standard
High rise offices, prestige quality
10,810
15,940
11,980
17,820
12
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
The above costs are at 4th Quarter 2018 levels. Exchange rate used US$ = Rp 15,180
HOTELS Budget hotels - 3-star, mid market Business hotels - 4/5-star Luxury hotels - 5-star
18,780 25,670 27,340
22,180 27,730 30,820
INDUSTRIAL Industrial units, shell only (conventional single storey framed units) Owner operated factories, low rise, light weight industry
4,970 5,390
5,400 5,950
OTHERS Underground/basement car parks (<3 levels) Retail malls, high-end Hospitals (non-public sector)
7,670 10,250
-
9,400 11,080
-
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
13
The above costs are at 4th Quarter 2018 levels. Exchange rate used US$ = Rp 15,180 Note that foundation & sitework are excluded from the rates, as existing soil condition may differ from one area to other area.
1
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
CO
NS
TR
UC
TIO
N C
OS
TS
FO
R IN
DO
NE
SIA
14
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
- 5,000 10,000 15,000 20,000 25,000 30,000 35,000
Apartments, high rise, average standard
Apartments, high rise, high end
Medium/high rise offices, average standard
High rise offices, prestige quality
Budget hotels - 3-star, mid market
Business hotels - 4/5-star
Luxury hotels - 5-star
Industrial units, shell only (conventional single storey framed units)
Owner operated factories, low rise, light weight industry
Underground/basement car parks (<3 levels)
Retail malls, high-end
IDR '000/m2
Construction Cost for Indonesia 2018
IND
ON
ES
IA C
ON
ST
RU
CT
ION
CO
ST
TR
EN
D
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
15
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
2014 2015 2016 2017 2018
IDR
'000/m
2
Indonesia Construction Cost Trend
Apartments, high rise, average standard
Apartments, high rise, high end
Medium/high rise offices, averagestandard
High rise offices, prestige quality
Budget hotels - 3-star, mid market
Business hotels - 4/5-star
Luxury hotels - 5-star
M&
E C
OS
TS
FO
R IN
DO
NE
SIA
CO
NS
TR
UC
TIO
N C
OS
T
T
1
M&E COSTS FOR INDONESIA
BUILDING TYPE
IDR’000/m2
MECHANICAL SERVICES
ELECTRICAL SERVICES
HYDRAULIC SERVICES
FIRE SERVICES
LIFTS/ ESCALATORS
BAS / COMS
RESIDENTIAL
Low Rise Apartments (D2)
High Rise Apartments (D1)
915 - 1,001
1,012 - 1,285
878 - 1,049
953 - 1,113
889 - 1,124
1,012 - 1,199
294 - 343
316 - 343
434 - 798
717 - 894
107 - 246
128 - 321
OFFICE
Average Standard Office High Rise (A2)
Office Super High Rise (A1)
1,028 - 1,183
1,065 - 1,210
830 - 1,060
883 - 1,108
209 - 294
219 - 316
284 - 375
300 - 417
444 - 1,065
589 - 1,188
209 - 294
236 - 316
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
16
The above costs are at 4th Quarter 2018 levels. Exchange rate used US$ = Rp 15,180
HOTELS
Resort Hotels (C1)
1,054 - 1,579
1,054 - 1,868
1,756 - 2,339
187 - 268
455 - 701
246 - 562
3- Star Hotels (C3)
5- Star Hotels (C2)
1,022 - 1,210
1,060 - 1,376
835 - 937
856 - 1,178
835 - 1,054
1,001 - 1,178
284 - 332
332 - 412
434 - 707
707 - 1,103
225 - 257
278 - 530
INDUSTRIAL
Factories (E2)
Warehouses (E3)
466 - 744 316 - 471
589 - 733 471 - 616
139 - 214 118 - 177
150 - 214 118 - 187
N/A N/A
59 - 86 59 - 86
OTHERS
Shopping Centres (B1)
Hospitals (G1) (non-public sector)
Basement Car Parks (L3)
905 - 1,087
755 - 1,285
482 - 589
723 - 910
482 - 963
573 - 696
198 - 305
535 - 1,070
96 - 187
278 - 326
193 - 236
128 - 284
326 - 878
321 - 963
198 - 326
91 - 118
107 - 278
128 - 268
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
17
The above costs are at 4th Quarter 2018 levels. Exchange rate used US$ = Rp 15,180
1
CO
NS
TR
UC
TIO
N C
OS
T
T
COST BREAKDOWN FOR DIFFERENT BUILDING TYPES
BUILDING TYPE STRUCTURAL ARCHITECTURAL M&E SERVICES EXTERNAL WORKS FFE/OSE*
Apartment mid to high Apartment mid to low Offices Hotels Serviced Apartments Retail Factories/Warehouses Hospitals
21% 37% 20% 19% 19% 23% 22% 24%
45% 29% 42% 23% 29% 36% 46% 24%
25% 28% 34% 26% 27% 31% 23% 48%
9% 6% 4%
12% 10% 10% 9% 4%
- - -
20% 15%
- - -
Note: a) Structural includes piling, foundation and structure in good soil condition
b) Architectural includes external walls, internal walls, roof, wall, floor and ceiling finishes, sanitary, windows and doors and joinery fittings
c) M&E includes electrical services, communications, fire protection and prevention, plumbing, vertical transportation and ACMV
d) *Furniture, fixtures and equipment/operating supplies and equipment
18
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
0%5%
10%15%20%25%30%35%40%45%50%
Structural Architectural M&E Services External Works FFE/OSE
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
19
CO
NS
TR
UC
TIO
N C
OS
TS
FO
R S
EL
EC
TE
D
AS
IAN
CIT
IES
1
CO
NS
TR
UC
TIO
N C
OS
T
T
.
BUILDING TYPE JAKARTA $ INDIA G MANILA O HO CHI MINH &
DOMESTIC
Apartments, high rise, average standard
Apartments, high rise, high end Terraced houses, average standard
Detached houses, high end
722 - 817
996 - 1,124
576 - 660
869 - 1,047
937 - 1,135 1,265 - 2,107
645 - 800
820 - 940
383 - 498
1,042 - 1,165
398 - 419
525 - 550
762 - 917
1,631 - 2,724
435 - 510
495 - 605
OFFICE / COMMERCIAL
Medium/high rise offices, average standard
High rise offices, prestige quality
Out-of-town shopping centre, average standard
Retail malls, high end
712 - 789
1,050 - 1,174 611 - 675
675 - 730
435 - 471
544 - 576 424 - 461
592 - 639
933 - 1,076 1,264 - 1,390
762 - 935 1,093 - 1,508
755 - 875
870 - 1,185
N/A
705 - 920
HOTELS
Budget hotels - 3-star, mid market Business hotels - 4/5-star
Luxury hotels - 5-star
1,237 - 1,461
817 - 905
1,195 - 1,312
1,400 - 1,710
1,691 - 1,827
1,801 - 2,030
1,272 - 1,508
1,607 - 1,759
1,347 - 1,607
1,851 - 2,524
N/A
1,765 - 2,120
20
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
US$/m2
INDUSTRIAL
Industrial units, shell only (conventional single storey framed units)
Owner operated factories, low rise, light weight industry
327 - 356
355 - 392
340 - 398
361 - 424
485 - 538
685 - 789
310 - 390
350 - 460
OTHERS
Underground/basement car parks (<3 levels)
Multi storey car parks, above ground
(<4 levels)
Schools (primary and secondary)
505 - 619
327 - 356
N/A
288 - 309
230 - 252
285 - 324
494 - 610
475 - 661
701 - 952
640 - 765
410 - 450
540 - 590
Students' residences
Sports clubs, multi purpose sports/leisure centres (dry sports)
General hospitals - public sector
N/A 1,095 - 1,640
N/A
309 - 340 602 - 628
660 - 723
742 - 937 1,186 - 1,699
1,287 - 1,523
540 - 695
800 - 855
N/A
Exchange rate used : US$1 = IDR 15,180 INR 71.90 PHP 52.88 VND 22,600
The above costs are at 4th Quarter 2018 levels, inclusive of preliminaries but exclusive of contingencies.
O Rates include 12% VAT. $ Rates are nett of VAT.
G Rates are based on projects in Bangalore and are nett of VAT and & Rates are nett of VAT and contingencies. Service Tax. Mumbai costs are generally 8% higher.
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
21
SHANGHAI + BEIJING + GUANGZHOU
/ SHENZEN +
CHONGQING
/ CHENGDU + HONG £
KONG
DOMESTIC
Apartments, high rise, average standard
Apartments, high rise, high end
668 - 740
1,554 - 1,697
613 - 673
1,484 - 1,690
534 - 590
874 - 958
552 - 661
907 - 1,149
3,060 - 3,570
4,020 - 4,690
Terraced houses, average standard
Detached houses, high end
446 - 477 666 - 740
447 - 522
673 - 749
405 - 446 553 - 609
445 - 541
591 - 682
4,130 - 4,860
6,140 up
OFFICE / COMMERCIAL
Medium/high rise offices, average standard
High rise offices, prestige quality
Out-of-town shopping centre, average standard
Retail malls, high end
868 - 1,156
1,158 - 1,445
N/A
1,228 - 1,585
857 - 1,154
1,154 - 1,895
653 - 873
1,181 - 1,626
777 - 860
1,132 - 1,361
749 - 822
1,088 - 1,521
882 - 1,025
1,122 - 1,520
706 - 912
1,067 - 1,505
2,990 - 3,500
3,630 - 4,260 2,970 - 3,540
3,950 - 4,720
HOTELS
Budget hotels - 3-star, mid market
952 - 1,169
966 - 1,191
985 - 1,084
958 - 1,189
3,840 - 4,160
Business hotels - 4/5-star
Luxury hotels - 5-star 1,556 - 2,120
2,117 - 2,538
1,615 - 2,132
2,057 - 2,646
1,592 - 2,273
2,165 - 2,386
1,747 - 2,188 2,159 - 2,592
4,020 - 4,720
4,720 - 5,460
1 C
ON
ST
RU
CT
ION
CO
ST
S F
OR
SE
LE
CT
ED
A
SIA
N C
ITIE
S
1
CO
NS
TR
UC
TIO
N C
OS
T
T
BUILDING TYPE
22
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
US$/m2
24 22
INDUSTRIAL
Industrial units, shell only (conventional single storey framed units)
Owner operated factories, low rise, light weight industry
280 - 342
432 - 540
270 - 329
522 - 598
497 - 547
N/A
426 - 542
N/A
N/A
2,330 - 2,950
OTHERS
Underground/basement car parks (<3 levels)
Multi storey car parks, above ground
(<4 levels)
Schools (primary and secondary)
742 - 1,033
382 - 532
528 - 676
746 - 820
449 - 454
520 - 671
513 - 820
367 - 404
407 - 448
413 - 589
324 - 405
438 - 487
3,200 - 3,840
1,920 - 2,280
2,520 - 2,710
Students' residences
Sports clubs, multi purpose sports/leisure centres (dry sports)
General hospitals - public sector
377 - 527
955 - 1,172
1,418 - 1,839
368 - 520
890 - 897
1,170 - 1,465
264 - 297
754 - 832
N/A
N/A
N/A
N/A
2,930 - 3,310
3,820 - 4,450
4,950 - 5,580
Exchange rate used : US$1 = RMB 6.94 RMB 6.94 RMB 6.94 RMB 6.94 HK$ 7.82
The above costs are at 4th Quarter 2018 levels, inclusive of preliminaries but exclusive of contingencies. + Houses are built to shell and core standard ONLY, where all
tenant or occupant areas are unfurnished. Schools (primary and secondary) are of public authority standard, no a/c and complete with basic external works
£ Offices of average standard are built to the following provisions: (i) Curtain wall/window wall facade (ii) Tenant area with screeded floor, painted wall and suspended ceiling. Schools (primary and secondary) are of public authority standard, no a/c and complete with basic external works
23
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
MACAU 'D SINGAPORE+ KUALA
LUMPUR BANGKOK œ
DOMESTIC
Apartments, high rise, average standard
Apartments, high rise, high end
2,279 - 2,788
3,183 - 4,864
1,305 - 1,485
2,030 - 3,045
345 - 580►
710 - 1,120
703 - 871
978 - 1,207
Terraced houses, average standard
Detached houses, high end 3,884 - 4,635
4,737 - 6,163
1,705 - 1,920
2,175 - 2,900
220 - 345▲
740 - 980 458 - 565
794 - 962
OFFICE / COMMERCIAL
Medium/high rise offices, average standard
High rise offices, prestige quality
Out-of-town shopping centre, average standard
Retail malls, high end
2,623 - 3,387
3,387 - 3,705
2,470 - 3,705
3,884 - 4,686
1,705 - 1,920J
1,920 - 2,100J 1,920 - 2,030
2,030 - 2,245
575 - 745▼
865 - 1255▼ 550 - 715
680 - 1,000
642 - 794
871 - 1,176
626 - 810
840 - 886
HOTELS
Budget hotels - 3-star, mid market
3,451 - 3,909
2,140 - 2,355
1,020 - 1,395
1,146 - 1,268
Business hotels - 4/5-star
Luxury hotels - 5-star 4,686 - 5,602
5,602 - 6,621
2,755 - 3,115
2,755 - 3,115
1,720 - 2,175
1,940 - 2,435
1,466 - 1,680
1,711 - 1,986
CO
NS
TR
UC
TIO
N C
OS
TS
FO
R S
EL
EC
TE
D
AS
IAN
CIT
IES
CO
NS
TR
UC
TIO
N C
OS
T
T
1
BUILDING TYPE
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
24
US$/m2
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
24
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
22
INDUSTRIAL Industrial units, shell only (Conventional
single storey framed units)
Owner operated factories, low rise, light weight industry
N/A
N/A
725 - 930
N/A
320 - 430
430 - 520
489 - 611
N/A
OTHERS
Underground/basement car parks (<3 levels)
Multi storey car parks, above ground (<4 levels)
Schools (primary and secondary)
2,050 - 3,005
1,133 - 1,490
2,266 - 2,623
930 - 1,255
640 - 930¥
N/A
310 - 530
220 - 345
250 - 305◄
550 - 733
183 - 299
N/A
Students' residences
Sports clubs, multi purpose sports/leisure centres (dry sports)
General hospitals - public sector
1,795 - 2,088
N/A
N/A
1,560 - 1,705
1,955 - 2,100
2,755 - 2,900
295 - 360♦
595 - 730
855 - 1,155
N/A
N/A
N/A
Exchange rate used : US$1 = MOP 8.07 S$ 1.38 RM 4.18 BAHT 32.73
The above costs are at 4th Quarter 2018 levels, inclusive of preliminaries but exclusive of contingencies.
'D Rates are exclusive of any management contract fee. + Rates are nett of GST. J Includes raised floor and ceiling to tenanted areas but
excludes office carpets (normally under tenants fit-out). ¥ Open on all sides with parapet. œ Rates exclude VAT
► 6-12 units per floor, 46m2 - 83m2 per unit, exclude air conditioning equipment.
▲ Terraced houses exclude air conditioning. ◄ Offices are average standard and exclude tenant fitout ▼ Schools (primary and secondary) are standard government provisions
♦ Student hostels to university standard.
25
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
M
M&E COSTS FOR SELECTED ASIAN CITIES
CO
NS
TR
UC
TIO
N C
OS
T
T
1
BUILDING TYPE
JAKARTA # INDIA G MANILA Q
HO CHI MINH
IDR’000/m2 INR/m2 PHP/m2 VND'000/m2
MECHANICAL SERVICES
Offices Industrial * Hotels Shopping Centres Apartment
1,028 - 1,183 466 - 744
1,022 - 1,210 905 - 1,087 915 - 1,001
4,800 - 6,805 2,210 - 3,925 5,880 - 6,420 4,585 - 6,005 2,620 - 3,245
4,000 - 5,930 800 - 1,500 3,500 - 9,670 2,890 - 6,840 1,360 - 4,430
2,036 - 2,902 N/A N/A N/A
1,573 - 2,106
ELECTRICAL SERVICES
Offices Industrial ** Hotels Shopping Centres Apartment
830 - 1,060 589 - 833 835 - 937 723 - 910
878 - 1,049
4,250 - 5,840 2,500 - 4,150 4,710 - 6,425 4,050 - 5,420 2,040 - 2,805
3,700 - 7,000 2,000 - 3,500
4,700 - 1,2000 3,600 - 6,000 3,600 - 6,800
2,275 - 2,723 N/A N/A N/A
2,006 - 2,534
HYDRAULIC SERVICES
Offices Industrial Hotels
209 - 294 139 - 214
835 - 1,054
740 - 1,130
510 - 890 3,868 - 5,825
1,230 - 2,200 800 - 1,300 2,250 - 6,820
332 - 621
N/A N/A
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
26
M&
E C
OS
T F
OR
SE
LE
CT
ED
AS
IAN
CIT
IES
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
32
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
24
Shopping Centres Apartment
198 - 305 889 - 1,124
1,100 - 1,990 1,745 - 2,410
1,220 - 1,600 2,250 - 3,600
N/A 647 - 752
FIRE SERVICES
Offices
Industrial Hotels
Shopping Centres Apartment
284 - 375 150 - 214 284 - 332 278 - 326 294 - 343
1,185 - 1,545
540 - 745 1,375 - 1,760 1,130 - 1,310
630 - 750
950 - 1,560 800 - 2,000 1,100 - 2,030 1,090 - 1,730 900 - 1,300
704 - 1,167
N/A N/A N/A
483 - 606
LIFTS / ESCALATORS
Offices
Industrial
Hotels
Shopping Centres
Apartment
444 - 1,065 N/A
434 - 707 326 - 878 434 - 798
985 - 1,250 640 - 825
1,430 - 2,085 1,675 - 2,145 890 - 1,150
1,600 - 4,620 0 - 400
1,800 - 3,400 1,600 - 2,680 850 - 3,440
670 - 1,279 N/A N/A
1,364 - 1,931 761 - 1,101
The above costs are at 4th Quarter 2018 levels, exclusive of contingencies.
* Generally without A/C.
** Excludes special power supply. Q Transformer, included in electrical services. G Rates are based on projects in Bangalore and are nett of VAT and
service tax. Mumbai costs are generally 8% higher.
# All rates are nett of VAT. Rates for electrical services exclude
genset. Rates for hydraulic services exclude sewage treatment plant. Rates for mechanical services refer to ACMV rates only.
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
27
1
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
27 C
ON
ST
RU
CT
ION
CO
ST
DA
TA
M&E COSTS FOR SELECTED ASIAN CITIES
BUILDING TYPE
SHANGHAI
BEIJING GUANGZHOU /
SHENZHEN CHONGQING /
CHENGDU
HONG KONG
RMB/m2 RMB/m2 RMB/m2 RMB/m2 HK$/m2
MECHANICAL SERVICES Offices Industrial * Hotels Shopping Centres Apartment
790 - 1,005
176 - 295 1,010 - 1,316 1,070 - 1,125
320 - 423
775 - 1,071
170 - 280 950 - 1,224
806 - 970 143 - 459
775 - 1,070
155 - 285 1,080 - 1,350
715 - 910 152 - 410
730 - 990 140 - 230
930 - 1,280 890 - 1,010
150 - 300
1,900 - 2,700
160 - 260 2,100 - 2,650 2,200 - 2,750
850 - 2,000up
ELECTRICAL SERVICES
Offices Industrial ** Hotels Shopping Centres Apartment
620 - 700 311 - 440 677 - 864 540 - 677 262 - 383
470 - 717 326 - 459 719 - 962 490 - 690 258 - 406
540 - 795 320 - 459
715 - 1,020 500 - 690 285 - 500
450 - 660 260 - 360 580 - 830 510 - 660 230 - 340
1,750 - 2,450 620 - 860
1,900 - 2,600 1,800 - 2,450
1,100 - 2,100up
HYDRAULIC SERVICES Offices Industrial
112 - 166 89 - 131
97 - 143 97 - 143
128 - 184 89 - 124
85 - 120 85 - 120
700 - 900 500 - 700
Hotels 375 - 498 377 - 490 390 - 500 330 - 450 2,000 - 3,000
28
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
M&
E C
OS
T F
OR
SE
LE
CT
ED
AS
IAN
CIT
IES
Shopping Centres
Apartment 140 - 188 171 - 231
143 - 204 173 - 234
114 - 168 150 - 280
100 - 150 100 - 180
700 - 900
1,500 - 2,400
FIRE SERVICES
Offices Industrial
232 - 325 160 - 268
184 - 270 153 - 230
230 - 350 143 - 272
240 - 290 130 - 230
550 - 700 400 - 500
Hotels
Shopping Centres
Apartment
294 - 397 263 - 391 56 - 105
224 - 383 224 - 383 71 - 138
285 - 425 248 - 383 72 - 152
250 - 350 250 - 370 60 - 110
600 - 850 550 - 700 100 - 600
LIFTS / ESCALATORS
\ Offices
Industrial
Hotels
Shopping Centres
Apartment
288 - 567 139 - 402 226 - 510 335 - 510 170 - 300
294 - 577 145 - 400 232 - 520 327 - 520 175 - 289
295 - 517 150 - 440 250 - 480 325 - 470 130 - 500
300 - 550 150 - 350 250 - 430 290 - 440 140 - 240
700 - 1,200 550 - 750 550 - 850
850 - 1,000 450 - 850
The above costs are at 4th Quarter 2018 levels, exclusive of contingencies.
* Generally without air conditioning. ** Excludes special power supply.
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
29
M&E COSTS FOR SELECTED ASIAN CITIES M&
E C
OS
TS
FO
R S
EL
EC
TE
D A
SIA
N C
ITIE
S
1
CO
NS
TR
UC
TIO
N C
OS
T
T
.
BUILDING TYPE
MACAU SINGAPORE + KUALA
LUMPUR BANGKOK co
MOP/m2 S$/m2 RM/m2 BHT/m2
MECHANICAL SERVICES Offices Industrial *
N/A N/A
153 - 249 34 - 117
320 - 490 85 - 190
4,400 - 4,800 1,550 - 1,600
Hotels Shopping Centres Apartment
2,640 - 3,050 2,400 - 3,000 900 - 1,200
129 - 278 147 - 246 90 - 170
300 - 590 300 - 475 120 - 210
4,600 - 5,100 4,600 - 4,800 4,300 - 4,500
ELECTRICAL SERVICES
Offices Industrial ** Hotels Shopping Centres Apartment
N/A N/A
2,640 - 3,150 2,640 - 3,000 1,020 - 1,320
158 - 258 55 - 136 181 - 356 160 - 304 97 - 213
290 - 460 145 - 190 295 - 550 295 - 460 105 - 210
3,400 - 3,800 1,950 - 2,200 3,800 - 4,500 2,800 - 3,200 2,800 - 3,350
HYDRAULIC SERVICES Offices Industrial Hotels
N/A N/A
1,830 - 2,240
26 - 55 18 - 36
91 - 172
35 - 65 40 - 50
175 - 270
780 - 900 750 - 790
1,400 - 1,650
30
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
Shopping Centres 610 - 810 46 - 80 30 - 35 790 - 950
Apartment 1,520 - 2,030 72 - 146 50 - 100 1,200 - 1,400
FIRE SERVICES
Offices Industrial Hotels Shopping Centres Apartment
N/A N/A
910 - 1,120 610 - 810 250 - 300
33 - 56 23 - 51 28 - 57 37 - 56 25 - 43
60 - 80 45 - 65 65 - 90 55 - 80 15 - 30
780 - 850 730 - 750 780 - 890 780 - 820 720 - 850
LIFTS / ESCALATORS Offices Industrial
N/A N/A
63 - 162 41 - 104
125 - 350 55 - 180
1,100 - 1,350
N/A Hotels Shopping Centres Apartment
610 - 810 460 - 710 460 - 610
49 - 108 56 - 90
41 - 100
100 - 285 95 - 120 65 - 110
1,100 - 1,400 250 - 450 500 - 580
The above costs are at 4th Quarter 2018 levels, exclusive of contingencies.
* Generally without air conditioning.
** Excludes special power supply. + Rates are nett of GST and excluding BAS
co Based upon nett enclosed area and nett of VAT.
31
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
1 M
AJO
R R
AT
ES
FO
R S
EL
EC
TE
D A
SIA
N C
ITIE
S
1
C
ON
ST
RU
CT
ION
CO
ST
T
MAJOR RATES FOR SELECTED ASIAN CITIES
DESCRIPTION
UNIT JAKARTA # INDIA G MANILA HO CHI MINH #
IDR '000 INR PHP VND '000
1. Excavating basement :: 2.00m deep
2. Excavating for footings :: 1.50m deep
3. Remove excavated materials off site
4. Hardcore bed blinded with fine materials
5. Mass concrete grade 15
6. Reinforced concrete grade 30
7. Mild steel rod reinforcement
8. High tensile rod reinforcement
9. Sawn formwork to soffits of suspended slabs
10. Sawn formwork to columns and walls
11. 112.5mm thick brick walls
12 “Kliplok Colorbond” 0.64mm profiled steel sheeting
m3
m3
m3
m3
m3
m3
kg
kg
m2
m2
m2
m2
40
75
35
650
950
1,135
12.5
12.5
200
195
250
300
199
225
NA
4,620
6,248
7,822
70
72
708
761
1,155
1,785
270
500
350
1,800
3,400
4,800
54
55
1,000
950
N/A
1,400
92.4
92.4
84.7
280.9
1,696.4
1,865.65
19.764
19.908
215
245
312.78
401.11 - 597.60
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
32
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
13. Aluminium casement windows; single glazed
14. Structural steelwork - beams, stanchions and the like
15. Steelwork - angles; channels; flats and the like
16. 25mm cement and sand (1:3) paving
17. 20mm cement and sand (1:4) plaster to walls
18. Ceramic tiles bedded to floor screed (measured separately)
19. 12mm fibrous plasterboard ceiling lining
20. Two coats of emulsion paint to plastered surfaces
m2
kg
kg
m2
m2
m2
m2
m2
1,650
27
27
90
100
200
215 æ
30
6,300
126
126
498
409
1,785
1,417
252
11,500 Q
160
160
650
700
1,800
1,400
500
6,315
52.65
52.65
94
144
674.18
234
88.9
Average expected preliminaries % 8 – 10 9 - 13 12 - 18 8 - 12
The above costs are at 4th Quarter 2018 level and are based on lump sum fixed price contract rates exclusive of preliminaries and
contingencies. Q Rate for aluminium with anodized finish; 6mm thick glass. G All rates above are supply and fix, based on projects in Bangalore and
are nett of VAT and service tax. Mumbai costs are generally 8% higher.
# Rates are nett of VAT. æ Rate for 9mm gypsum board.
CO
NS
TR
UC
TIO
N C
OS
T D
AT
A
33
DESCRIPTION
UNIT SHANGHAI BEIJING
GUANGZHOU/ SHENZHEN
CHONGQING / CHENGDU
HONG KONG
RMB RMB RMB RMB HK$
1. Excavating basement :: 2.00m deep
2. Excavating for footings :: 1.50m deep
3. Remove excavated materials off site
4. Hardcore bed blinded with fine materials
5. Mass concrete grade 15
6. Reinforced concrete grade 30
7. Mild steel rod reinforcement
8. High tensile rod reinforcement
9. Sawn formwork to soffits of suspended slabs
10. Sawn formwork to columns and walls
11. 112.5mm thick brick walls
12 ‘Kliplock Colorbond’ 0.64mm profiled steel sheeting
m3
m3
m3
m3
m3
m3
kg
kg
m2
m2
m2
m2
30
30
135
190
540
570
5.8
5.8
90
90
90@
N/A
30
33
60
180
530
550
5.6
5.6
90
85
80
N/A
30
30
105
190
540
580
6.0
6.0
90
85
80
NA
30
26
95
170
420
550
5.30
5.30
65
60
80
N/A
200
180
300&
950
1,100
1,200
9.70
9.70
410
410
400
1,000
MA
JO
R R
AT
ES
FO
R S
EL
EC
TE
D A
SIA
N C
ITIE
S
33 C
ON
ST
RU
CT
ION
CO
ST
DA
TA
1
CO
NS
TR
UC
TIO
N C
OS
T
T
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
34
13 Aluminium casement windows; single glazed 14. Structural steelwork - beams, stanchions
and the like
15 Steelwork - angles; channels; flats and the like
16. 25mm cement and sand (1:3) paving
17. 20mm cement and sand (1:4) plaster to walls
18 Ceramic tiles bedded to floor screed (measured separately)
19 12mm fibrous plasterboard ceiling lining
20. Two coats of emulsion paint to plastered surfaces
m2
kg
kg
m2
m2
m2
m2
m2
700
11
9.5
35
35
160
150
40
815 *
11
9.5
32
32
145
162
32
700
12.5
11.5
35
30
155
190
35
650 *
11
11.1
25
35
130
150
35
3,800 36
42
160
165
400
600
90
Average expected preliminaries % 5 - 10 7 - 10 5 - 12 6 - 12 10 - 15
The above costs are at 4th Quarter 2018 levels and are based on lump sum fixed price contract rates exclusive of preliminaries and contingencies.
@ Rates for 120mm thick concrete block walls.
* Rates for double glazed windows.
& Rates including dumping charges
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
35
MA
JO
R R
AT
ES
FO
R S
EL
EC
TE
D A
SIA
N C
ITIE
S
35 C
ON
ST
RU
CT
ION
CO
ST
DA
TA
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
C
ON
ST
RU
CT
ION
CO
ST
DA
TA CO
NS
TR
UC
TIO
N C
OS
T D
ATA
1
CO
NS
TR
UC
TIO
N C
OS
T
T
DESCRIPTION
UNIT MACAU SINGAPORE + KUALA
LUMPUR BANGKOK co
MOP S$ RM BHT
1. Excavating basement :: 2.00m deep
2. Excavating for footings :: 1.50m deep
3. Remove excavated materials off site
4. Hardcore bed blinded with fine materials
5. Mass concrete grade 15
6. Reinforced concrete grade 30
7. Mild steel rod reinforcement
8. High tensile rod reinforcement
9. Sawn formwork to soffits of suspended slabs
10. Sawn formwork to columns and walls
11. 112.5mm thick brick walls
12 ‘Kliplock Colorbond’ 0.64mm profiled steel sheeting
m3
m3
m3
m3
m3
m3
kg
kg
m2
m2
m2
m2
150
180
150
1,200
1,350
1,250
9.00
9.00
280
280
450 N/A
20
20
15 - 20
50
175 - 185 ++
115 - 120
1.25 - 1.35
1.25 - 1.35
40
40
35 - 40
43
15 - 25
15 - 25
20 - 30
72 - 95
240 - 315
260 - 320
3.4 - 3.8
3.4 - 3.8
38 - 45
38 - 45
42 - 50
65 - 70
120 - 140
140 - 180
120 - 150
650 - 750
2,300 - 2,500
2,600 - 2,800
26 - 29
26 - 28
420 - 480
420 - 480
650 - 750
1,200
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
36
35 C
ON
ST
RU
CT
ION
CO
ST
DA
TA
13. Aluminium casement windows; single glazed 14. Structural steelwork - beams, stanchions
and the like 15. Steelwork - angles; channels; flats and
the like 16. 25mm cement and sand (1:3) paving 17. 20mm cement and sand (1:4) plaster to walls 18. Ceramic tiles bedded to floor screed
(measured separately) 19. 12mm fibrous plasterboard ceiling lining 20. Two coats of emulsion paint to plastered
surfaces
m2
kg kg m2
m2
m2
m2
m2
4,000
35
40
120 150
450
650 200
290
4.0 - 4.5
4.0 - 4.5
21 22
74
30 3.5 - 4.0
380 - 600
7.5 - 9.5
7.5 - 9.5
17 - 25 18 - 25
50 - 70
35 - 45
3.5 – 5.0
7,000
60 - 75
60 - 75
200 - 240 220 - 260
1,200
750 - 850 120 - 160
Average expected preliminaries % 10 12 - 15 6 - 15 12 - 18
The above costs are at 4th Quarter 2018 levels and are based on lump sum fixed price contract rates exclusive of preliminaries and contingencies.
+ Rates are nett of GST. ++ Rate for lean concrete blinding
co Rates are nett of VAT
CO
NS
TR
UC
TIO
N C
OS
T D
ATA
37
39 GENERAL CONSTRUCTION DATA
CONSTRUCTION COST DATA 38
CONSTRUCTION COST T 1
CITY
EXCHANGE
RATE
ELECTRICITY
DOMESTIC COMMERCIAL/ INDUSTRIAL
US$1=
US$/kWh
US$/kWh
Jakarta IDR 15,180 0.097 0.097
Hong Kong HK$ 7.82 0.11 0.13
Macau MOP 8.07 0.17 0.17
Singapore S$ 1.38 0.17 0.17
Kuala Lumpur RM 4.18 0.052 - 0.137 0.091 - 0.122
Bangkok BAHT 32.73 0.072 - 0.136 0.096 - 0.098
Manila PESO 52.88 0.21 0.19
Shanghai RMB 6.94 0.089 (peak) / 0.044 (normal)
0.157 (peak) / 0.075 (normal)
Beijing RMB 6.94 0.071-0.113 0.219-0.221 (peak)
0.124-0.126 (normal)
Guangzhou RMB 6.94 0.085-0.128 0.089-0.124
Chongqing RMB 6.94 0.08 0.11
Bangalore INR 71.90 0.069 - 0.100 0.087 - 0.128
New Delhi INR 71.90 0.069 - 0.111 0.070 - 0.111
Ho Chi Minh VND 22,800 0.11 0.1 / 0.06
UTILITY COSTS FOR SELECTED ASIAN
CITIES
CONSTRUCTION COST DATA 39
WATER FUEL
DOMESTIC COMMERCIAL/ INDUSTRIAL
DIESEL LEADED UNLEADED
US$/m3 US$/m3
US$/litre US$/litre US$/litre
0.069 - 0.491 0.450 - 0.965 0.481 N/A 0.543
0.83 0.59 1.83 N/A 2.21
0.56 - 0.90 0.75 1.70 N/A 1.45
1.99 / 2.67 1.99 1.34 N/A 1.94
0.136 - 0.478 0.495 - 0.545 0.522 N/A 0.526
0.259 - 0.441 0.290 - 0.483 0.895 N/A 0.881
0.29 - 0.74 1.37 0.972 N/A 1.146
0.497-0.840 0.68 1.16 N/A 1.220
0.721 - 1.296 1.296-1.368 1.10 N/A 1.22
0.285-0.571 0.50 0.97 N/A 1.12
0.61 0.85 1.22 N/A 1.28
0.556 - 0.695 1.39 1.001 N/A 1.072
0.35 - 1.05 1.390-2.440 0.992 N/A 1.141
0.24 0.75 / 0.43 0.82 N/A 0.92
1232132132132 132121
ELECTRICTY TARIFFS FOR INDONESIA
CONSTRUCTION COST DATA
1 C
ON
ST
RU
CT
ION
CO
ST
T
1
CUSTOMER CLASS POWER LIMIT USAGE FEES (Rp/kWh) AND
COSTS (Rp/kVArh) PRE PAID (Rp /kWh)
Residential 1a 1300 VA 1,467.28 1,467.28
Residential 1b 2200 VA 1,467.28 1,467.28
Residential 2 3,500 VA (up to 5,500 VA) 1,467.28 1,467.28
Residential 3 6,600 VA and above 1,467.28 1,467.28
Business 1
6,600 (up to 200 kVA) 1,467.28 1,467.28
Business 2 Over 200 kVA Peak hrs = K x Off peak = kVArh =
1,035.78 1,035.78 1,114.74
-
Industrial 1 Over 200 kVA Peak hrs = K x Off peak = kVArh
1,035.78 1,035.78 1,114.74
-
40
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
1232132132132 132121
CONSTRUCTION COST DATA
ELECTRICTY TARIFFS FOR INDONESIA
CUSTOMER CLASS POWER LIMIT USAGE FEES (Rp / kWh) AND
COSTS (Rp / kVArh) PRE PAID (Rp / kWh)
Industrial 2 Above 30,000 KVA Peak hrs and Off peak = kVArh =
996.74 996.74
-
Government and public street lighting 1
6,600 VA (up to 200 kVA) 1,467.28
1,467.28
Government and public street lighting 2
Over 200 kVA Peak hrs = K x Off peak = kVArh =
1,035.78 1,035.78 1,114.74
-
Traction 1,467.28 1,467.28
Special 1,644.52 -
Note: Tariff of December 2018. From 1st January 2015 a floating tariff applies for households with a capacity of 1,300 VA or more.
41
C
ON
ST
RU
CT
ION
CO
ST
DA
TA
43
OFFICE MEP COST COMPONENTS
CONSTRUCTION COST DATA 42
28.50%
0.50%
23%32%
2% 14%
Plumbing and Sanitary
Cold Water Pipework Hot Water Pipework
Soil Waste & Vent Piping Cold Water Central Plant
Hot water Central Plant Rainwater Drainage
24%
4%
4.50%15.50%19%2.50%
14%
12%4.50%ACV
Chillers Cooling Towers
Pumps & Tanks AHU/FCU
Pipework Ventilation
Ductwork Dampers & Grilles
Electrical Works
44
OFFICE MEP COST COMPONENTS
CONSTRUCTION COST DATA 43
6.75%7.50%
10.50%
17.50%
47.25%
5.25% 4%
0.75%0.50%
Electrical
MV Switchboards Transformers
LV Switchboards LV Distribution Boards
Cabling & Containment Lighting Circuits
Small Power Circuits Lightning Protection
Earthing
28.50%
17.50%35%
3%16%
Fire Protection
Central Plant Fire Hydrant Sprinkler
Fire Extinguishers Alarm System
2019 OUTLOOK
47 GENERAL CONSTRUCTION DATA
Following a year of economic volatility over the course
of 2018, Indonesia’s economy is predicted to remain
weak in 2019. After grown 5.2% in 2018, it is expected
that Indonesia’s economy will grow by 5.3% following
the various economic measures that are being
implemented towards the end of 2018.
This is in line with rising political tensions ahead of the
general elections, and the pressure of ongoing trade
war between the country’s two biggest trading partners,
China and the US, and also the prolonged depreciation
of the Rupiah. For this reason, the Indonesia
Government will continue to rely on domestic
investment and household spending to drive the
Country’s economy in 2019.
Commercial sectors will be in stagnant, except industrial
construction business which shows prediction of one-
digit growth in 2019 and infrastructure to support
China’s Belt and Road Initiative (BRI) program. Fitch
Solutions Macro Research in a report on December 18
stated that almost 20 per cent of the value of Indonesia’s
infrastructure projects are now being planned of built, is
part of BRI program.
It is expected that the forecast growth of the sector in
2019 is 4.9 per cent, up marginally “following an
increase in new planned supply in the affordable homes
and industrial segments” said Economic Report 2019 by
the Ministry of Finance (MoF).
2
GE
NE
RA
L C
ON
ST
RU
CT
ION
T
MATERIAL PRICE INDICES
YEAR
Sand
Autoclaved Aerated Concrete
Block
Cement
Ready mix Concrete
Steel Bar
m3 Inflation % m2 Inflation % Sack Inflation % 30 mpa (m3) Inflation % kg Inflation %
2010 (Base) 177,000 - 66,483 - 65,000 - 882,000 - 6,513 -
2012 250,000 141.24 75,406 113.42 55,000 84.62 925,000 101.09 7,176 110.18
2013 257,500 145.48 77,669 116.83 62,375 95.96 970,000 104.86 7,320 112.39
2014 248,770 140.55 80,000 120.33 65,529 100.81 1,020,000 105.15 7,540 115.77
2015 285,700 161.41 83,000 124.84 70,000 107.69 885,000 100.34 6,000 92.12
2016 288,800 163.16 73,500 110.55 78,800 121.23 947,600 107.44 6,200 95.19
2017 251,000 141.81 75,000 112.81 74,000 113.85 880,000 99.77 8,200 125.90
2018 261,000 147.46 76,500 115.07 70,000 107.69 797,500 90.42 8,500 130.51
GE
NE
RA
L C
ON
ST
RU
CT
ION
DA
TA
48
GE
NE
RA
L C
ON
ST
RU
CT
ION
DA
TA
49
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
2012 2013 2014 2015 2016 2017 2018
Material Price Indices
Sand AAC Block Cement Ready Mix Concrete - 30MPa Steel Bar
2
GE
NE
RA
L C
ON
ST
RU
CT
ION
T
CONSUMER PRICE INDICES
Months Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Inflation
Rate
2018 CPI 132.10 132.32 132.58 132.71 132.99 133.77 134.14 134.07 133.83 134.2 134.56 135.39
Inflations 0.62 0.17 0.20 0.10 0.21 0.59 0.28 -0.05 -0.18 0.28 0.27 0.62 3.13
2017 CPI 127.94 128.24 128.22 128.33 128.83 129.72 130.00 129.91 130.08 130.09 130.35 131.28
Inflations 0.97 0.23 -0.02 0.09 0.39 0.69 0.22 -0.07 0.13 0.01 0.20 0.71 3.61
2016 CPI 123.62 123.51 123.75 123.19 123.48 124.29 125.15 125.13 125.41 125.59 126.18 126.71
Inflations 0.51 -0.09 0.19 -0.45 0.24 0.66 0.69 -0.02 0.22 0.14 0.47 0.42 3.02
2015 CPI 118.71 118.28 118.48 118.91 119.50 120.14 121.26 121.73 121.67 121.57 121.82 122.99
Inflations -0.24 -0.36 0.17 0.36 0.50 0.54 0.93 0.39 -0.05 -0.08 0.21 0.96 3.35
2014 CPI 110.99 111.28 111.37 111.35 111.53 112.01 113.05 113.58 113.89 114.42 116.14 119.00
Inflations 1.07 0.26 0.08 -0.02 0.16 0.43 0.93 0.47 0.27 0.47 1.50 2.46 8.36
2013 CPI 136.88 137.91 138.78 138.64 138.60 140.03 144.63 146.25 145.74 145.87 146.04 146.84
Inflations 1.03 0.75 0.63 -0.10 -0.03 1.03 3.29 1.12 -0.35 0.09 0.12 0.55 8.38
2012 CPI 130.90 130.96 131.05 131.32 131.41 132.23 133.16 134.43 134.45 134.67 134.76 135.49
Inflations 0.76 0.05 0.07 0.21 0.07 0.62 0.70 0.95 0.01 0.16 0.07 0.54 4.30
2011 CPI 126.29 126.46 126.05 125.66 125.81 126.50 127.35 128.54 128.89 128.74 129.18 129.91
Inflations 0.89 0.13 -0.32 -0.31 0.12 0.55 0.67 0.93 0.27 -0.12 0.34 0.57 3.79
2010 CPI 118.01 118.36 118.19 118.37 118.71 119.86 121.74 122.67 123.21 123.29 124.03 125.17
Inflations 0.84 0.30 -0.14 0.15 0.29 0.97 1.57 0.76 0.44 0.06 0.60 0.92 6.96
GE
NE
RA
L C
ON
ST
RU
CT
ION
DA
TA
50
G
EN
ER
AL C
ON
ST
RU
CT
ION
DA
TA
51
* Inflation rate for 2019 is a projection
3.503.13
3.613.02
3.35
8.368.38
4.303.79
6.96
2.78
11.06
201820182017201620152014201320122011201020092008
Inflation Rate
2 GENERAL CONSTRUCTION T
LABOUR RATES
52 GENERAL CONSTRUCTION DATA
Labour Unit 2015 2016 2017 2018
Non-skilled general Worker
Day 105,000 103,000 111,000 135,500
Carpenter Day 120,000 135,000 139,000 155,800
Bricklayer Day 120,000 125,000 148,500 155,800
Steel bar worker
Day 120,000 125,000 139,000 170,500
Plumber Day 120,000 125,000 139,000 135,400
Heavy equipment operator
Day 170,000 158,000 175,000 183,200
Welder Day 150,000 125,000 139,000 157,200
Electrician Day 120,000 125,000 139,000 135,500
Data Sources: ‘Journal of Building, Construction, Interior & Material Price’, Market Sources
INDONESIA CONSTRUCTION COST INDICES (Indeks Kemahalan Konstruksi – IKK)
53 GENERAL CONSTRUCTION DATA
Province City CCI (IKK)
BPS* Arcadis**
Aceh Aceh 100.39 -
North Sumatera Medan 101.47 123.45
West Sumatera Padang 99.10 123.45
Riau Pekanbaru 96.86 123.45
Jambi Jambi 92.53 123.45
South Sumatera Palembang 97.64 126.98
Bengkulu Bengkulu 96.76 -
Lampung Lampung 89.31 117.57
Bangka Belitung Pangkal Pinang 99.29 -
Riau Islands Batam" 127.70 146.96
DKI Jakarta Jakarta 109.14 117.57
West Jawa Bandung 103.63 117.57
Central Jawa Semarang 98.64 117.57
D.I. Yogyakarta Yogyakarta 104.88 117.57
East Jawa Surabaya 103.86 117.57
Banten Serang 100.22 117.57
Bali Bali 122.95 117.57
" Batam is a Free Trade Zone, VAT 10% is not applied.
* Based on data of BPS (Badan Pusat Statistik) 2018.
BPS statistics are based on government projects.
** Based on Arcadis data
2 GENERAL CONSTRUCTION T
INDONESIA CONSTRUCTION COST INDICES (Indeks Kemahalan Konstruksi – IKK)
54 GENERAL CONSTRUCTION DATA
Province City CCI (IKK)
BPS* Arcadis**
West Nusa Tenggara Mataram 100.76 135.21
East Nusa Tenggara Kupang 99.79 -
West Kalimantan Pontianak 113.95 -
Central Kalimantan Palangka Raya 102.31 -
South Kalimantan Banjarmasin 105.09 -
East Kalimantan Balikpapan 114.13 137.56
North Kalimantan Tanjung Selor 113.25 -
North Sulawesi Manado 110.83 141.08
Central Sulawesi Palu 97.04 -
South Sulawesi Makasar 101.69 137.56
Southeast Sulawesi Kendari 101.96 -
Gorontalo Gorontalo 96.46 141.08
West Sulawesi Mamuju 91.33 -
Maluku Ambon 126.39 -
North Maluku Sofifi 116.55 -
West Papua Manokwari 134.02 -
Papua Jayapura 227.90 -
* Based on data of BPS (Badan Pusat Statistik) 2018.
BPS statistics are based on government projects.
** Based on Arcadis data
GENERAL CONSTRUCTION DATA 66
PROPERTY 40
Contract Procurement
GEN
ERA
L CO
NSTR
UC
TION
DA
TA
49
CONTRACT PROCUREMENT
3
56 PROCUREMENT
3
PROCUREMENT
PROCUREMENT MODEL AND CONTRACT FORMS
Strategy
Procurement is the process used to obtain construction projects. On any construction project it is vitally important to select the right method of procuring the construction works as it is a key factor contributing to cost efficiency, overall client satisfaction and project success. There are, in essence, three main procurement routes for construction:
• The traditional method whereby a developer employs the design team and a contractor takes on a purely construction role;
• Design and Build, where a contractor employs the design team which takes on responsibility for both design and construction; and
• Turnkey Contracting which get its name from the concept of the developer awarding the construction contract to a contractor and having no further input until 'turning the key' to open the project. In its purest form, the contractor takes on complete responsibility for design, construction and financing.
The traditional method is the most used in Indonesia. Key criteria for selection of the procurement route include:
• Speed of project execution
• Cost certainty;
• Degree of client involvement;
• Apportionment of risk and responsibility.
PROCUREMENT 57
The FIDIC Conditions of Contract
The most commonly used form of contract for
construction projects in Indonesia is the FIDIC suite of
construction contracts, written and published by the
Federation Internationale des Ingenieurs-Conseil
(International Federation of Consulting Engineers).
The suite comprises
• FIDIC 'Conditions of Contract for Construction for
Building and Engineering Works Designed by the
Employer: The Construction Contract’ (The Red
Book) 1999
• FIDIC 'Conditions of Contract for Plant and
Design-Build for Electrical and Mechanical Plant
and for Building and Engineering Works designed
by the Contractor: The Plant and Design-Build
Contract' (The Yellow Book) 1999
• FIDIC 'Conditions of Contract for EPC Turnkey
Projects: The EPC/Turnkey Contract' (The Silver
Book) 1999
3
PROCUREMENT 58
FIDIC Red Book
This contract provides conditions of contract for construction work where the design is carried out by the Employer. This is the most common form of contract used in Indonesia outside of the government sector.
The FIDIC Red Book provides for provisional quantities premeasured on completion. This is typically altered to a fixed lump sum, the quantities provided for information only and at the risk of the contractor.
FIDIC Yellow Book
The FIDIC Yellow Book provides for construction works where the design is carried out by the Contractor. This contract is applicable to the procurement of electrical and/or mechanical plant, as well as building or engineering works. The Contractor’s design will be in accordance with the Employer’s brief.
FIDIC Silver Book
This contract provides conditions of contract for construction works where the design, procurement and construction is carried out by one party, the Contractor.
The Silver Book is primarily used for large civil engineering projects, such as power plants or refineries, where the design is almost wholly of an engineering nature.
FIDIC White Book
The white book is for design consultancy services.
PROCUREMENT 59
Other in-house forms of contract There are other contracts in use by Arcadis, usually employed for smaller projects, for specialist contracts and for supply only contracts. The two most often used are:
• Conditions of Contract for Direct Works, and
• Conditions of Contract for Supply. The Conditions of Contract for Direct works will be used for smaller works and for smaller packages within a larger project. These conditions are based on the FIDIC Short Form of Contract (The Green Book) The Conditions of Contract for Supply will mostly be used for supply only packages such as sanitary appliances and accessories, hardware, loose furniture, soft furnishings and the like, but can also apply to the separate purchase of materials such as tiles, pipework, cabling and the like. Nominated subcontractors are not typically used in Indonesia, instead specialist packages are contracted direct by the Employer. When nominated Subcontractors are a part of the project procurement, Arcadis use a form of contract based on the FIDIC form for subcontracts.
3
PROCUREMENT 60
Insurances
All contracts call for certain insurances to be taken out
by either the Contractor or the Employer. Insurances will
be required for:
• The Works (Insurance of the Works)
• Injury to Persons and Damage to Property (Third
Party Liability)
• Contractor's personnel and work people
(Workman's compensation)
The first two will normally be grouped together as
Contractor's All Risk Insurance, whilst the third will
normally be covered through the government's Workers
Social Security Agency programme. (BPJS
Ketenagakerjaan)
Source: Arcadis Indonesia Practice Manual, Revision
0, March 2013.
OTHER INFORMATION
Exchange Rates
Prime Rates
Currency Fluctuations
Conversion Factors
IDD Codes and Time Difference
Relevant Websites
Current Construction Regulations
OTHER INFORMATION
4 OTHER INFORMATION
OTHER INFORMATION 62
4 4 OTHER INFORMATION
EXCHANGE RATES
Approximate rates prevailing on 1 December 2018.
COUNTRY CURRENCY IDR
per unit US$1
Australia
Dollar 10,455.67 1.37
Brunei
Dollar 10,422.32 1.37
Canada
Dollar 10,767.17 1.33
China
Renminbi 2,057.57 6.95
EU (Euro Zone)
Euro 16,193.81 0.88
Hong Kong
Dollar 1,828.69 7.82
India
Rupee 205.27 69.71
Indonesia
Rupiah 1.00 14,309.22
Japan
Yen 126.00 113.56
Macau
Pataca 1,775.43 8.06
Malaysia
Ringgit 3,419.58 4.18
New Zealand
Dollar 9,843.42 1.45
Source : www.xe.com
OTHER INFORMATION 63
COUNTRY CURRENCY IDR
per unit US$1
Philippines
Peso 273.15 52.39
Qatar
Rial 3,931.10 3.64
Saudi Arabia
Riyal 3,815.79 3.75
Singapore
Dollar 10,422.32 1.37
South Korea
Won 12.78 1,119.83
Switzerland
Franc 14,339.45 1.00
Taiwan
NT Dollar 463.56 30.87
Thailand
Baht 433.94 32.97
United Arab Emirates
Dirham 3,896.32 3.67
United Kingdom
Pound 18,245.21 0.78
United States of America
Dollar 14,309.22 1.00
Vietnam
Dong 0.613 23,317.63
Source : www.xe.com
OTHER INFORMATION
64
4 OTHER INFORMATION
PRIME RATES AND BASE LENDING RATES AS AT 4th QUARTER 2018.
COUNTRY
RATE (%)
China* 4.75
Hong Kong 5.13
India 9.45
Indonesia** 6.75
Macau 5.38
Malaysia*** 4.60
Philippines 4.35
Singapore 5.33
Thailand^ 7.00
United Kingdom 0.75
United States of America 5.25
Vietnam^^ 9.00
* 5 years Benchmark Lending Rate ** In Indonesia, this rate is published by Bank Indonesia with the title “BI Rate”. *** Indicative effective lending rate ^ Minimum Loan Rate % per annum (average based on local bank) ^^ Minimum and in VND per year
60
OT
HE
R IN
FO
RM
AT
ION
65
CURRENCY FLUCTUATIONS
8,000.00
9,000.00
10,000.00
11,000.00
12,000.00
13,000.00
14,000.00
15,000.00
16,000.00
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
US$ TO INDONESIAN RUPIAH
4
OT
HE
R IN
FO
RM
AT
ION
60
OT
HE
R IN
FO
RM
AT
ION
66
1000.00
2000.00
3000.00
4000.00
5000.00
6000.00
7000.00
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
JAKARTA STOCK EXCHANGE INDEX
OTHER INFORMATION
REBAR WEIGHTS
67
Imperial Bar Size
Metric Weight (lb/ft)
Weight (kg/m)
3 10
0.376 0.561
4 13
0.668 0.996
5 16
1.043 1.556
6 19
1.502 2.21
7 22
2.044 3.049
8 25
2.67 3.982
9 29
3.4 5.071
10 32
4.303 6.418
11 36
5.313 7.924
12 40
6.424 9.619
14 43
7.65 11.41
18 57
13.6 20.284
OTHER INFORMATION
CONVERSION FACTORS
68
UNIT
LENGTH
10 mm = 1 cm 12 in = 1 ft
100 cm = 1 m 3 ft = 1 yd
1,000 m = 1 km 1,760 yd = 1 mile
AREA
10,000 m2 = 1 ha 9 ft2 = 1 yd2
100 ha = 1 km2 4,840 yd2 = 1 acre
640 acre = 1 mile2
VOLUME
1,000 ml = 1 l (UK) 8 pt = (UK) 1 gal
(US) 8 pt = (US) 1 gal
1,000 l = 1 m3
MASS
1,000 g = 1 kg 16 oz = 1 lb
1,000 kg = 1 tonne 2,240 lb = 1 ton
16 tael = 1 catty
POWER
TEMPERATURE
4 OTHER INFORMATION
110
OTHER INFORMATION 69
(APPROX)
(APPROX)
1 in = 25.400 mm
1 ft = 30.480 cm
1 yd = 0.914 m
1 mile = 1.609 km
1 cm = 0.394 in
1 m = 3.281 ft
1 m = 1.094 yd
1 km = 0.621 mile
1 ft2 = 0.093 m2
1 yd2 = 0.836 m2
1 acre = 0.405 ha
1 mile2 = 2.590 km2
1 m2 = 10.764 ft2
1 m2 = 1.196 yd2
1 ha = 2.471 acres
1 km2 = 0.386 mile2
(UK) 1 pt = 0.568 l
(US) 1 pt = 0.473 l
(UK) 1 gal = 4.546 l
(US) 1 gal = 3.785 l
(UK) 1 l = 1.760 pt
(US) 1 l = 2.113 pt
(UK) 1 l = 0.220 gal
(US) 1 l = 0.264 gal
1 oz = 28.350 g
1 lb = 0.454 kg
1 ton = 1.016 tonne
1 catty = 0.605 kg
1 gram = 0.035 oz
1 kg = 2.205 lb
1 tonne = 0.984 ton
1 hp = 0.746 kw
1 kw = 1.341 hp
(0F - 32) x 5/9
(0C x 9/5) + 32
FINANCIAL 110 OTHER INFORMATION
70
FLOW RATE CONVERSIONS
Unit To Multiply By
l/s
Cu ft/min Cu ft/sec
2.1189 0.0353
l/m Cu ft/sec
0.0005886
Cu ft/sec l/m l/s Million gallons/day Gallons (US)/min
2.2222 28.317 0.64632 448.83
Cu ft/min Cu cm/sec Cu ft/hr Gallon (US)/min Gallon (US)/sec
471.95 60 7.48052 0.1247
Cu ft/hr Cu cm/sec Cu ft/min Gallons (US)/hr l/hr
7.8658 0.0167 7.4805 28.317
Cu ft Cu cm Cu inches Cu m Cu yards Gallon (US) dry Gallon (US) liq
28316.8 1728.0 0.02832 0.03704 6.42851 7.48052
4 OTHER INFORMATION
FINANCIAL 110 OTHER INFORMATION
71
ENERGY CONVERSIONS
Unit To Multiply By
Btu Cal, g Joules Kg Calories Kw-hours Watt seconds Hr/TR
251.996 1054.35 0.2520 0.000292875 1054.35 8.33333x10−5
Watt/m2 Joules/hr m2 Joules/sec m2 Kw/m2
3600 1.0 0.001
Joules Btu Cal, g Kw-hours Watt seconds
0.000949 0.239045 2.778x10−7 1
Horsepower Btu/hr Cal, g/sec Cal, kg/hr Joules/sec Kilowatts
2547.16 178.298 641.87 746 0.746
Kw-hours Btu Cal,g Joules Kg-cal TR
3410.1 860000 3.6x10−6 859845 0.284345136
Ton Refrigerant Btu/hr Kw-hours Joules/hour Horsepower
12000 3.5168525 12660670.23 4.781
FINANCIAL 110 OTHER INFORMATION
72
DENSITY OF COMMON CONSTRUCTION MATERIALS
Material Imperial Metric
Aluminium 171 lb/ft³ 2739 kg/m³
Cast iron 450 lb/ft³ 7208 kg/m³
Portland cement
94 lb/ft³ 1506 kg/m³
Concrete 148 lb/ft³ 2370 kg/m³
Concrete gravel 150 lb/ft³ 2400 kg/m³
Crushed stone 100 lb/ft³ 1600 kg/m³
Earth dry excavated
90 lb/ft³ 1440 kg/m3
Earth packed 95 lb/ft³ 1520 kg/m³
Glass, window 161 lb/ft³ 2580 kg/m³
½ inch Gypsum 2.08 lb/ft² 10.2 kg/m²
Limestone 171 lb/ft³ 2739 kg/m³
Marble 160 lb/ft³ 2560 kg/m³
Sand, dry 110 lb/ft³ 1600 kg/m³
Water 62.4 lb/ft³ 1000 kg/m³
8” Concrete block
55 lb/ft³ 881 kg/m³
¼” Plywood 0.710 lb/ft² 3.47 kg/m²
½” Plywood 1.42 lb/ft² 6.93 kg/m²
¾“ Plywood 2.13 lb/ft² 10.4 kg/m²
Steel 490 lb/ft³ 7850 kg/m³
Stainless steel 466 lb/ft³ 7480 kg/m³
Tin 454 lb/ft³ 7280 kg/m³
Iron 490 lb/ft³ 7850 kg/m³
Lead 707 lb/ft³ 11340 kg/m³
4 OTHER INFORMATION
FINANCIAL 110 OTHER INFORMATION
73
IDD CODES & TIME DIFFERENCE
LOCATION
IDD COUNTRY
CODE
TIME DIFFERENCE
(Hours)*
Australia: Melbourne Perth Sydney
Bahrain Brunei: China:
Beijing France Germany Hong Kong India Indonesia Jakarta Bali Jayapura Italy Japan Korea (South) Macau Malaysia Myanmar Philippines Qatar Singapore Spain Taiwan Thailand UAE United Kingdom United States Vietnam
61 61 61 3
673
86 33 49 852 91
62 62 62 39 81 82
853 60 95 63 974 65 34 886 66 971 44 1 84
+4 +1 +4 -4 +1
+1 -6 -6 +1
-1.30
0 +1 +2 -6 +2 +2 +1 +1
-0.30 +1 -4 +1 -6 +1 0 -3 -7 -12 0
FINANCIAL 110
OTHER INFORMATION 74
4 OTHER INFORMATION
RELEVANT WEBSITES
Indonesian Government
Ministry of Defence www.kemhan.go.id Ministry of Education www.kemdikbud.go.id Ministry of Finance www.kemenkeu.go.id Ministry of Foreign Affairs www.kemlu.go.id Ministry of Trade www.kemendag.go.id Ministry of Justice www.kemenkumham.go.id Ministry of Manpower www.naker.go.id Ministry of Environment & Forestry www.menlh.go.id Ministry of Transport www.dephub.go.id Ministry of Home Affairs www.kemendagri.go.id Ministry of Health www.depkes.go.id Ministry of Public Work and Public Housing www.pu.go.id Ministry of Energy and Mining www.esdm.go.id Ministry of Industry www.kemenperin.go.id Ministry of National Development Planning www.bappenas.go.id Ministry of Land and Spatial Planning www.bpn.go.id Indonesia Government Website www.indonesia.go.id Indonesia Investment Co-ordinating Board www.bkpm.go.id Statistics Indonesia www.bps.go.id Competition Watchdog Commission www.kppu.go.id National Standardisation Agency www.bsn.go.id
Construction Related Associations Association of Indonesian Architects www.iai.or.id Indonesia Green Building Council www.gbcindonesia.org Indonesian Institute of Engineers www.pii.or.id Indonesia Contractors Association www.aki.or.id Indonesia Contractors Association www.aki.or.id Indonesia Construction Expert Association www.haki.or.id Indonesia Quantity Surveyor Association www.iqsi.org National Construction Services Development Board www.lpjk.org Construction Development Information System www.jasakonstruksi.net
Others Arcadis www.arcadis.com
110 OTHER INFORMATION
75
CURRENT CONSTRUCTION REGULATIONS
Construction Services Development Board
Following the 2017 Construction Services Act, all
construction companies are required to register with the
Construction Services Development Board (LPJK).
The work of the Construction Services Development
Board also includes:
• Research and Development
• Education and Training
• Registration of workforces
• Arbitration and mediation
Contractors
Contractors require a Construction Service Business
Licence (Surat Izin Usaha Jasa Konstruksi) (SIUJK).
This requires the contractor to select classification and
sub-classification from the following categories:
• Architecture
• Civils Works
• Mechanical
• Planology
Additional Conditions for Registration:
1) ISO 9001:2015 and Quality Management
Manual. Issued in Indonesia
2) Employment of at least 2 experts with
qualification in the selected categories.
3) Membership of the Construction Association
Registry (KTA)
4) Legal Entity certificate (SBU)
FINANCIAL 110
OTHER INFORMATION 76
4 OTHER INFORMATION
Building Codes
The current Indonesian building codes were
developed by the National Standardisation Agency
which was established in 1997.
Law No.28, 2002 regarding building states that:
‘Buildings should be managed based on their
utilization, safety, balance and harmonious
principles within their environment.’ (Article 2)
All buildings over 1500m2 have to be approved by
City Planning and the TPAK (City Architectural
Advisory Team)
They are a team of experts in the field of technical
architecture and urban planning.
Seismic
Indonesia is classed as one of the most active
seismic zones in the world. Article 18 of Law No. 28,
2002 states the requirement for a stable and strong
building structure to support loads arising from
‘natural behaviours’. The current building code is
based on the American Society of Civil Engineers
code ‘ASCE7-10’, issued in Indonesia as code ‘SNI-
1726,201x.’
www.aboutgeology.com
FINANCIAL 110
OTHER INFORMATION 77
Green Building
The Green Building Council Indonesia was established
in 2009. They are involved with the certification of green
buildings and promotional educational activities.
The GBCI developed the Greenship Rating Tool which
ranks buildings in six categories:
1) Land Use
2) Energy Efficiency
3) Water Conservation
4) Source Materials
5) Air Quality
6) Environmental Management
The Greenship rating is voluntary and currently take up
is low.
Source: Green Building Council
The Governor Regulation of Jakarta 2012 states that
new buildings of a certain size and existing buildings
must meet the green building requirements:
1) Apartment buildings, office buildings, trade
buildings and buildings which have more than
one function within one building with the
entire building floor size of more than
50,000m2.
2) Business functions, hotel, social and cultural
functions and health care buildings with the
entire building floor size of more than
20,000m2.
3) Social and cultural functions, educational
service buildings with the entire building floor
size of more than 10,000m2.
FINANCIAL 110
OTHER INFORMATION 78
4 OTHER INFORMATION
The requirements for new buildings are:
a) Energy efficiency
b) Water efficiency
c) Indoor air quality
d) Land and waste management
e) Implementation of construction activities
The requirements for existing buildings are:
a) Conservation and energy efficiency
b) Conservation and water efficiency
c) Indoor air quality and thermal comfort
d) Operational management and maintenance
Health and Safety
The Indonesian Manpower Act of 2003 requires all
companies with over 100 employees to enforce
health and safety standards.
Article 86 of the act states that:
1) Every worker/labourer has the right to receive:
a) Occupational safety and health protection
b) Protection against immorality and indecency
c) Treatment that shows respect to human
dignity and religious values
2) In order to protect the safety of workers /
labourers and to realise optimal productivity, an
occupational health and safety scheme shall be
administered.
3) The protection as referred to under subsection
(1) and subsection (2) shall be given in
accordance with valid statutory legislation.
FINANCIAL 110
OTHER INFORMATION 79
Article 87 states: 1) Every enterprise is under an obligation to
apply an occupational safety and health
management system that shall be integrated
into the enterprise's management system.
2) Rulings concerning the application of the
occupational safety and health management
system as referred to under subsection (1)
shall be determined and specified with a
Government Regulation.
Environmental
Following the Government Regulation PP No. 27-2012
Article 2, any business and/or activity required to have
an Amdal or UKL-UPL shall have an Environmental
Permit.
The processess for obtaining an Environmental Permit
are:
• Preparation of Amdal and UKL-UPL
• Assessment of Amdal and UKL-UPL
• Application and publishing of Environmental
Permit
Any business and/or activity having an important impact
on the environment shall have an Amdal (Article 3).
Amdal: Environmental Impact Analysis
UKL-UPL: Environmental Management Effort –
Environmental Monitoring Effort
Although the requirement for an Amdal has been in
place for many years, only in the last two years has its
importance been emphasized more, making it a non-
negotiable pre-condition to obtaining the IMB.
FINANCIAL 110
4 OTHER INFORMATION
80 OTHER INFORMATION
Employment of Foreign Workers
Foreign managerial and expert personnel in
positions that cannot yet be filled by Indonesian
nationals are allowed. Approval of company quota
and individual work permits is given by the Ministry
of Labour.
The duration of the foreign expatriate's term to
work in Indonesia is subject to Government
regulation, currently 12 months subject to
extension year by year.
Employers are obliged to pay an annual fee of US$
1,200 for every foreign worker they employ. The
obligation to pay this fee does not apply to
government agencies, international agencies,
social and religious undertakings and certain
positions in educational institutions.
Foreigners working full time in Indonesia must
obtain a Limited Stay Permit Card (KITAS).
FINANCIAL 110
OTHER INFORMATION 81
Insurance for employee (BPJS)
It is required by the law for any company registered in
Indonesia to provide employement insurance which
placed under Worker Social Security Agency
Programme (BPJS Ketenagakerjaan).
1. Work Related Accident benefit
This program provides protection against the risks of
accidents that occur in the employment relationship,
including accidents occurring on the way from home
to work or vice versa and illness caused by the work
environment.
Contribution (for participant of wage earner) paid by
employer depends on the level of working
environment risk, whose amount is evaluated once in
no longer than two (years).
2. Provident fund benefit
Provident Fund Benefit in the form of cash which
amount represents the value of accumulated
contributions plus investment results, which are paid
in a lump sum if participants reach age of 56 years,
die or permanent total disability.
Contribution of provident fund benefit is calculated at
5.7% of wage comprising of 2% contribution from the
employee and 3.7% contribution from the employers
will be paid by monthly.
3. Pension benefit
Pension benefit is a social security which is intended
to maintain the degree of a decent life for participants
and / or their heirs by providing income after
participants entering retirement, suffering total
permanent disability, or death.
FINANCIAL 110
4 OTHER INFORMATION
82 OTHER INFORMATION
Contribution of pension benefit program is calculated
at 3% of wage, comprising of 2% contribution from
employer and 1% contribution from the participating
worker. The maximum wage used in the calculation
is Rp 7,335,300 in 2016.
4. Medical benefit
Medical benefit is provided by the Health Social
Security Agency Programme (BPJS Kesehatan). The
benefit cover medical treatment, medicine and
hospitality.
Contribution of medical benefit program is calculated
at 4% of wage, comprising of 3% contribution from
employer and 1% contribution from the participating
worker. The maximum wage used in the calculation
is Rp 8,000,000 in 2016.
General Taxes
• Current VAT rate 10%
• Corporate income tax 25%
• Withholding tax for payments to residents - 15%
for interest, royalties and dividends, 2% for
services, 10% for land and building rental
• Withholding tax for payments to non-residents -
20%
Non-residents are classed as those without a
permanent establishment in Indonesia.
Withholding tax requires that the payer is responsible
for collection of the tax and provides a tax certificate
(faktur pajak) in its place.
110 OTHER INFORMATION
83 OTHER INFORMATION
Article 22 – Applies to items such as the importation
of goods, purchase of fuel, cement or steel.
Article 4.2 - Refers to Final Income Tax where it is
required to withhold final tax from payments to
resident taxpayers;
Description
Tax Rate
Classified company
Non-classified company
Construction works
Small - medium
2% 4%
Large 3%
Supply of materials for construction works (supply only)
0%
Supply and installation of materials for construction works
4% 6%
Design and construction consultancy services
4% 6%
Rental of land or buildings
10%
Proceeds from transfers of land and building rights
5%
Article 23 is applied at a rate of 2% on the fees for:
• Rentals of assets other than land and
buildings
• Technical services
• Management services
• Consulting services
• Appraisal services
• Actuary services
• Accounting and bookkeeping services
• Design services
• Drilling services for oil and gas mining
A branch of a foreign company is taxed at the
corporate rate plus a 20% branch profits tax is
applied on net profits after income tax.
110 OTHER INFORMATION
84 OTHER INFORMATION
4 OTHER INFORMATION
Relevant Legislation
Use of Indonesian language in contracts
Government Regulation No.29 of 2000 and No.24 of
2009, stipulates that all contracts must be in Bahasa
Indonesia and subject to the applicable law in
Indonesia.
Use of Indonesian Rupiah in payments
Law 7 of 2011, The Currency Law states that the
Indonesian Rupiah must be used for payment and
settlement of all commercial transactions and
monetary obligations effected in Indonesia.
Exceptions are provided for:
• Certain transactions in relation to the
state budget
• Grants received from or made overseas
• International commercial transactions
• Bank deposits denominated in foreign
currencies and
• International financing transactions.
128 OTHER INFORMATION
FINANCIAL 40
Arcadis Values
Arcadis General Business Principles
Cost Management
Project and Programme Management
Design and Engineering
Environmental Services
Water Solutions
Health and Safety
Arcadis Offices
Arcadis Asia Leadership Team
ARCADIS
LANGDON & SEAH
ARCADIS 86
5 ARCADIS
OUR CORE VALUES
People First
We care for each other and create a safe and respectful working environment where our people can grow, perform, and succeed
Client Success
We are passionate about our client’s success and bring insights, agility, and innovation to co-create value
Integrity
We always work to the highest professional and ethical standards and establish trust by being open, honest and responsible
Sustainability
We base our actions for clients and communities on environmental responsibility and social and economic advancement
Collaboration
We value the power of diversity and our global capabilities and deliver excellence by working as One Arcadis
130 LANGDON & SEAH
87 ARCADIS
ARCADIS GENERAL BUSINESS PRINCIPLES
At Arcadis we define our mission as to create
exceptional and sustainable outcomes for our clients in
natural and built assets.
In pursuing this mission as a global company, we are
committed to four core values in everything we do:
Integrity, Client Focus, Collaboration and Sustainability.
Integrity means that we perform business in an honest
and responsible way, working to the highest
professional standards. Integrity is not one action or
belief -- it is a culmination of the ethical standards we
follow and how we will create and maintain a
relationship with one another. It is a fulfilment of our high
standards of responsibility to the client, shareholders,
business partners and employees, the public, and to
governments and the laws and culture of the countries
in which we operate.
The purpose of Arcadis General Business Principles
(AGBP) is to further develop and implement our
commitment to Integrity.
The AGBP set guidance for our business decisions and
actions throughout the world at all management levels
and apply equally to company actions and to individual
behaviour of all our employees in conducting Arcadis’
business.
131 LANGDON & SEAH
5 ARCADIS
ARCADIS 88
COST MANAGEMENT
▪ Preliminary cost advice and planning
▪ Analysis of cost/design options
▪ Advice on procurement and contractual arrangements
▪ Cash flow projections
▪ Contractor pre-qualification
▪ Preparation of tender documents
▪ Formal contract documents
▪ Progress payments
▪ Assessing the cost of proposed variations
▪ Preparation of regular financial reports
▪ Settlement of final cost with contractors, specialist
contractors and suppliers
▪ Advice on contractors' claims
▪ Value engineering
▪ Reinstatement assessments for fire insurance
▪ Asset registers and depreciation calculations
▪ Project monitoring and verification of bank loans
▪ Due diligence studies
▪ Expert witness
▪ Life cycle costing
132 LANGDON & SEAH
89 ARCADIS
PROJECT AND PROGRAMME MANAGEMENT
▪ Due diligence
▪ Scheduling
▪ Design management
▪ Tender management
▪ Construction management
▪ Post completion and close out
▪ Handover
▪ Migration
▪ Occupation
133 LANGDON & SEAH
90 ARCADIS
5 ARCADIS
DESIGN AND ENGINEERING
▪ Highway design and maintenance
▪ Infrastructure-rail and railways systems, airports,
ports and maritime assets
▪ Bridges and civil structures
▪ Caverns and tunnels
▪ Geotechnics
▪ Building structures
▪ Building facades
▪ Mechanical and electrical design
▪ Urban traffic and transport planning
▪ Sustainability design
134 LANGDON & SEAH
91 ARCADIS
ENVIRONMENTAL SERVICES
▪ Strategic environmental consulting
▪ Site evaluation and restoration
▪ Environmental planning
▪ Environmental construction services
WATER SERVICES
▪ Water supply and treatment
▪ Conveyance of water
▪ Water management
▪ Water for industry
▪ Floor control and prevention
135 LANGDON & SEAH
92 ARCADIS
5 ARCADIS
HEALTH AND SAFETY
ARCADIS HEALTH AND SAFETY VISION
Based on ARCADIS core values, we strive to achieve zero
incidents in everything we do ensuring the health, safety and
well-being of our employees and stakeholders. Based on
ARCADIS’ best in class Health & Safety (H&S) culture and
performance, we integrate health and safety standards and
best practices into our solutions to manage risk and bring the
best outcomes for our employees and clients.
ARCADIS GLOBAL HEALTH AND SAFETY POLICY
At ARCADIS, H&S is also a requirement for operational
excellence. As an organization and as individuals,
determined to achieve a zero-incident culture, ARCADIS
and its staff:
▪ Keep H&S first in all we do all of the time
▪ Proactively recognize hazards, assess risks, and control
those risks in everything we do, every day (our TRACK
philosophy)
▪ Act only when we understand the hazards and controls
and exercise our authority to stop work
▪ Demonstrate visible H&S leadership and know that active
H&S stewardship is an expectation of employment
▪ Hold our leaders and staff accountable for H&S
▪ Comply with applicable legal and other H&S requirements
wherever we work
▪ Actively care for staff and stakeholders by intervening
when we observe at-risk behavior and unsafe conditions
and address them promptly
▪ Recognize staff for proactive H&S behavior
▪ Ensure that staff is competent to do their work safely
▪ Rigorously qualify, select, and evaluate our
subcontractors for H&S performance
▪ Encourage our stakeholders to align with our H&S culture
and collaborate with them to achieve zero incidents
▪ Communicate lessons learned and best practices
93 ARCADIS
FUNDAMENTAL HEALTH AND SAFETY PRINCIPLES
1. Demonstrate H&S Stewardship daily 2. Use TRACK 3. Exercise Stop Work Authority 4. Practice If not me, then who 5. Undertake Health and Safety planning 6. Report injuries and incidents immediately
T.R.A.C.K
TRACK to 0 is a challenging objective and can only be achieved if all ARCADIS staff understand, believe in, demonstrate, and communicate these commitments and engage in the continual improvement of our H&S system and performance each and every day.
Think about the task Think through the work and how it relates to the site, project,
jobs and tasks and plan the work.
Recognise the hazard Recognize the hazards of each phase of the work.
Assess the risk Assess the risks using the various risk assessment tools for each
hazard.
Control the hazard Identify the most appropriate control mechanisms to
adequately mitigate the risks identified following the hierarchy
of controls.
Keep H&S first in all things Make sure the controls are in place before any activities are
initiated and implement Stop Work as necessary.
94 ARCADIS
5 ARCADIS
INDONESIA
JAKARTA
Level 18 Ratu Plaza Office Tower
Jalan Jendral Sudirman 9
Jakarta 10270
Indonesia
GPS : 6.2271, 106.8008
Tel : (62 21) 739 7550
Fax : (62 21) 739 7846
Email : [email protected]
Contact : Ben McGeachie / Gary Miles /
Natalia Pujiyanti
BALI
Level 2 Alamanda Office Bali
Jl. By Pass Ngurah Rai No. 67
Banjar Pengenderan, Kedonganan
Bali 80361
Indonesia
GPS : 8.7893, 115.2106
Tel : (62 361) 472 5353
Fax : (62 361) 472 5354
Email : [email protected]
Contact : Ir. Putu Arya Canti
95 ARCADIS
CHINA
BEIJING
Suite 1225 - 1242, South Wing
Central Tower, Junefield Plaza
10 Xuan Wu Men Wai Street
Beijing 100052
China
GPS : 39.896738, 116.375676
Tel : (86 10) 6310 1136
Fax : (86 10) 6310 1143
Email : [email protected]
Contact : Andrew Chan
CHANGSHA
Room 2315-2317,
HUAYUAN International Center No. 36 Section 2
Xiangjiang Middle Road
Tianxin District, Changsa
Hunan Province 410002
China
GPS : 28.195233, 112.976893
Tel : (86 731) 8277 2500
Fax : (86 731) 8971 6736
Email : [email protected]
Contact : Chen Yong
CHENGDU
Room 807, Block A Times Plaza
2 Zongfu Road, Chengdu
Sichuan Province 610016
China
GPS : 30.656666, 104.080567
Tel : (86 28) 8671 8373
Fax : (86 28) 8671 8535
Email : [email protected]
Contact : Gary Lin
5 ARCADIS
ARCADIS 96
CHONGQING
Room 3409-3410, International Trade Centre
38 Qing Nian Road Central District
Chongqing 400010
China
GPS : 29.556331, 106.574332
Tel : (86 23) 8655 1333
Fax : (86 23) 8655 1616
Email : [email protected]
Contact : Gary Lin
DALIAN
Unit 07, 32F, Xiwang Tower
136 Zhongshan Road Zhongshan District
Dalian, Liaoning Province 116001
China
GPS : 38.914864, 121.631245
Tel : (86 411) 8800 8018
Fax : (86 411) 8800 8823
Email : [email protected]
Contact : Kenn Ng
FOSHAN
10/F, Foshan Lingnan Tiandi
RM. 1002-1004, Zu Miao Road,
Foshan, Guangdong Province 528000
China
GPS : 23.031224, 113.11278
Tel : (86 757) 8203 0028
Fax : (86 757) 8203 0029
Email : [email protected]
Contact : Dickey Lee
97 ARCADIS
GUANGZHOU
3A10 - 18 Unit, 3A/F
Bank of America Plaza
555 Ren Min Zhong Road
Guangzhou
Guangdong Province 510145
China
GPS : 23.123148, 113.253628
Tel : (86 20) 8130 3813
Fax : (86 20) 8130 3812
Email : [email protected]
Contact : Xu Wei Bin
HAIKOU
Unit C, 10/F, Times Square
2 Guomao Road, Haikou
Hainan Province 570100
China
GPS : 20.029509, 110.326235
Tel : (86 898) 6652 7818
Fax : (86 898) 6652 7809
Email : [email protected]
Contact : Ricky Ho
HANGZHOU
Room 1306, WinNing International
100 Min Xin Road, Hangzhou
Zhejiang Province 310016
China
GPS : 30.251755, 120.218913
Tel : (86 571) 2829 7766
Fax : (86 571) 2829 7622
Email : [email protected]
Contact : Alex Zou
98 ARCADIS
5 ARCADIS
HENGQIN
7/F, 156 Nan Shan Ju Road
Hengqin, Zhuhai
Guangdong Province 519031
China
GPS : 22.142774, 113.544438
Tel : (86 756) 868 8986
Fax : (86 756) 868 8969
Email : [email protected]
Contact : Stanley Wan
HONG KONG
17/F, Two Harbour Square
180 Wai Yip Street,
Kwun Tong, Kowloon
Hong Kong
GPS : 22.310065, 114.221216
Tel : (852) 2911 2000
Fax : (852) 2911 2002
Email :[email protected]
Contact : Francis Au
MACAU
Avenida da Praia Grande, No. 594
Edificio BCM 12th Floor
Macau
GPS : 22.192210, 113.541252
Tel : (853) 2833 1710
Fax : (853) 2833 1532
Email : [email protected]
Contact : Katherine Chan
99 ARCADIS
NANJING
1104 South Tower Jinmao Plaza
201 Zhong Yang Road
Nanjing
Jiangsu Province 210009
China
GPS : 32.071984, 118.783443
Tel : (86 25) 5791 1860
Fax : (86 25) 6698 1860
Email : [email protected]
Contact : Taofen Chen
QINGDAO
Room 2008, 20/F, HNA Center
234 Yan An San Road
Shinan District
Qingdao
Shangdong Province 266071
China
GPS : 36.060852, 120.375351
Tel : (86 532) 8280 1818
Fax : (86 532) 8280 1881
Email : [email protected]
Contact : Andy Feng
SHANGHAI
11th Floor, Building C, The Place
No. 150 Zunyi Road
Cangning District
Shanghai 200051
China
GPS : 31.207363, 121.407984
Tel : (86 21) 6026 1300
Fax : (86 21) 6091 1800
Email : [email protected]
Contact : Joe Chan
100 ARCADIS
5 ARCADIS
SHENYANG
Room 3013 - 3015, Office Tower 1
E Tower of Fortune Plaza
Forum 66, 1-1 Qingnian Avenue
Shenhe District, Shenyang
Liaoning Province 110063
China
GPS : 41.799603, 123.433787
Tel : (86 24) 3195 8880
Fax : (86 24) 3128 6983
Email : [email protected]
Contact : Simon Chow
SHENZHEN
Room 1001, AVIC Centre
1018 Huafu Road, Shenzhen
Guangdong Province 518031
China
GPS : 22.543241, 114.082051
Tel : (86 755) 2598 1841
Fax : (86 755) 2598 1854
Email : [email protected]
Contact : Kenneth Lo / Ricky Ho
SUZHOU
Room 906 The Summit
118 Suzhou Avenue West,
Suzhou
Jiangsu Province 215021
China
GPS : 31.315966, 120.669099
Tel : (86 512) 8777 5599
Fax : (86 512) 8777 5600
Email : [email protected]
Contact : Zhang Rui
101 ARCADIS
TIANJIN
4002, 40/F
Tianjin World Financial Centre Office Tower
2 Dagubei Road
He Ping District
Tianjin 300020
China
GPS : 39.129619, 117.202758
Tel : (86 22) 2329 8611
Fax : (86 22) 2319 3186
Email : [email protected]
Contact : Kenn Ng
WUHAN
Room 1703, Citic Pacific Mansion
No. 1627 Zhongshan Avenue
Jiangan District
Wuhan, Hubei Province 430010
China
GPS : 30.616813, 114.317276
Tel : (86 27) 5920 9299
Fax : (86 27) 5920 9298
Email : [email protected]
Contact : Wong Chin Ying
XI'AN
Room 1606-1607, CapitaMall Office Building
64 South Second Ring Western
Xi’an, Shaanxi Province 710065
China
GPS : 34.230397, 108.934893
Tel : (86 29) 8866 9711
Fax : (86 29) 8866 9760
Email : [email protected]
Contact : Wang Zhu Zhu
102 ARCADIS
5 ARCADIS
INDIA
BANGALORE
135, 4th Floor, RMZ Titanium
Old Airport Road, Kodihalli
Bangalore 560017
India
GPS : 12.9591527, 77.6481456
Tel : (91 80) 4123 9141
Fax : (91 80) 4123 8922
Email : [email protected]
Contact : Sreekanth A P V
DELHI
3rd Floor, Tower B
Logix Techno Park
Sector 127
Uttar Pradesh 201304 Noida
India
GPS : 28.5359691, 77.34585591
Tel : (91 120) 436 8400
Email : [email protected]
Contact : Sreekanth A P V
MUMBAI
Unit 1001, 10th Floor,
Vishwaroop Infotech Park,
Plot No. 34, 35, 38, Sector 30A
Vashi, Navi Mumbai 400 705
India
GPS : 19.0644562, 72.9965259
Tel : (91 22) 4125 6060
Fax : (91 22) 4125 6050
Email : [email protected]
Contact : Sreekanth A P V
ARCADIS
103 ARCADIS
MALAYSIA SELANGOR
Level 5, Menara TSR
12 Jalan PJU 7/3, Mutiara Damansara
47810 Petaling Jaya
Selangor Darul Ehsan
Malaysia
GPS : 3.1616, 101.6129
Tel : (60 3) 2106 8000
Fax : (60 3) 2106 9090
Email : [email protected]
Contact : Loo Ming Chee / justin Teoh / Nur Aziz
Abu Bakar / Mohamad Faiz Awang /
Syed Mahadzir Syed Ahmad / Yap Sai
Hoe / Lim Jit Fung (Jeffrey) / Rozila
Abdul Rahman / Mohd Ali Abd Karim
JOHOR
47, Jalan Setia Tropika 1/30
Taman Setia Tropika
81200 Johor Bahru
Johor Darul Takzim
Malaysia
GPS : 1.5422, 103.7111
Tel : (60 7) 232 8300
Fax : (60 7) 232 8232
Email : [email protected]
Contact : Syed Mahadzir Syed Ahmad / Tan Pei Ling
ARCADIS
5 ARCADIS
ARCADIS 104
PENANG
Suite 3A-3, Level 3A, Wisma Great Eastern
No. 25, Lebuh Light
10200 Penang
Malaysia
GPS : 5.4201, 100.3408
Tel : (60 4) 264 2071 / 264 2072 / 264 2073
Fax : (60 4) 264 2068
Email : [email protected]
Contact : Nur Aziz Abu Bakar
SABAH
Lot No. H-06-07 & H-06-08 Level 6, Block H
Aeropod Commercial Square, Tanjung Aru
Jalan Aeropod Off Jalan Kepayan
88100 Kota Kinabalu, Sabah
Malaysia
GPS : 5.9492, 116.0596
Tel : (60 88) 215 530 / 215 531
Fax : (60 88) 215 570
Email : [email protected]
Contact : Jeffrey Lim / VK Wong
SARAWAK
No. 2 (3rd Floor), Jalan Song Thian Cheok
93100 Kuching Sarawak
Malaysia
GPS : 1.5532, 110.3532
Tel : (60 82) 232 212
Fax : (60 82) 232 198
Email : [email protected]
Contact : Nor Azman Bin Baharum
ARCADIS
105 ARCADIS
SINGAPORE
1 Magazine Road
#05-01 Central Mall
Singapore 059567
GPS : 1.288526, 103.8426085
Tel : (65) 6222 3888
Fax : (65) 6224 7089
Email : [email protected]
Contact : Tim Risbridger / Kho Sze Boon /
Lorimer A. Doig
PHILIPPINES
MANILA
25th Floor, Circuit Corporate Center 1
Circuit Makati, A.P. Reyes Street, Bgy Carmona
Makati City 1207
Philippines
GPS : 14.57333, 121.01802
Tel : (63 2) 811 2971
Fax : (63 2) 811 2071
Email : [email protected]
Contact : Ross McKenzie / Darneil Perez
CEBU
12F, 2Quad Building
Cardinal Rosales Avenue
Cebu Business Park
Cebu City 6000
Philippines
GPS : 10.3142574, 123.9053502
Tel : (63 32) 232 2200
Fax : (63 32) 260 3699
Email : [email protected]
Contact : Ross McKenzie / Darneil Perez
106 ARCADIS
5 ARCADIS
THAILAND
BANGKOK
10th Floor, Kian Gwan II Building
140/1 Wireless Road
Lumpini, Pratumwan
Bangkok 10330, Thailand
GPS : 13.734969, 100.545448
Tel : (66 2) 253 1438
Fax : (66 2) 253 4977
Email : [email protected]
Contact : Ang Yen Kooi / Wong Soon Bin
VIETNAM
HO CHI MINH CITY
L12-03, Level 12, Vincom Center B
72 Le Thanh Ton Street,
Ben Nghe ward, District 01
Ho Chi Minh City
Vietnam
GPS : 10.777936, 106.702265
Tel : (84 28) 3823 8297
Fax : (84 28) 3823 8197
Email : [email protected]
Contact : Truong Minh Tri
ARCADIS
107
ARCADIS ASIA HEAD OFFICE
HONG KONG
ARCADIS ASIA LIMITED
ARCADIS ASIA REGIONAL HEADQUARTERS LIMITED
17/F, Two Harbour Square,
180 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong
GPS : 22.310065, 114.221216
Tel : (852) 2911 2000
Fax : (852) 2911 2002
Email : [email protected]
Contact : Glenn Lutz, CEO Asia /
Daniel Blitch, CFO Asia
ARCADIS HEAD OFFICE
AMSTERDAM
ARCADIS NV
"Symphony"
Gustav Mahlerplein 97 - 103
1082 MS Amsterdam
P.O. Box 7895
1008 AB Amsterdam
The Netherlands
Tel : (31 20) 201 1011
Fax : (31 20) 201 1002
Email : [email protected]
Website : www.arcadis.com
Contact : Peter Oosterveer, CEO
ARCADIS
5 ARCADIS
108
ARCADIS ASIA LEADERSHIP TEAM
Glenn Lutz
Chief Executive Officer, Asia
Daniel Blitch Chief Financial Officer, Asia
Niek Niens
Chief Operating Officer, Asia [email protected]
Adam Sutton Regional HR and Change
Director [email protected]
Carl Watson
General Counsel, Asia [email protected]
Penny Murphy Head of Digital Transformation
Grant Sprick Head of HSEQ, Asia
ARCADIS
109
Ben McGeachie
Country Head, Indonesia
Gary P. Miles Director, Indonesia
Natalia D. Pujiyanti Director, Indonesia