1
Featured Project:
Maari Field Floating Production Storage Offloading (FPSO) facility, New Zealand
Trusted by the world’s largest projects
Conquer Interface Management,Deliver Successful Projects
2
Challenging industry landscape
• Oil price declines
• Tighter budgets
• Smaller margins
• Increased regulation
• More JVs and partnerships
• Increasing project costs
• Bigger & more complex projects
3
Big projects struggle
Effective process management can improve both cost and schedule
Percentage of projects exceeding budget and cycle time by over 10%Source: Booz Allen Hamilton
4
Interface Management relies on collaboration
EPCM
Engineer
Consultants
Owner
Identifying, creating, managing and tracking in real time, project-wide
EPC EPC Internal Departments
5
Aconex provides that collaboration
EPCM
Engineer
Consultants
Owner
Identifying, creating, managing and tracking in real time, project-wide
EPC EPC Internal Departments
Interface Management
6
Aconex: secure, project-wide collaboration Save money, increase productivity. Manage project risk.
Cloud & Mobile
Information & Process Management
Engineering & Construction
Project-Wide
Across the Project Lifecycle
Plan Design Construct OperateBid
OperatorSub-contractorsContractorConsultantsOwner EPC Design team
7
One integrated collaboration platform for project information and process
Owner EPC Designteam
Consultants Contractor Subcontractors
Client Service & Support
Web Mobile APIs
Information & Process Management
Platform
Document Management 3D Modeling Field Inspections
Correspondence Registers Bidding & Tenders
Workflows O&M / Deliverables Site Mobility
Network Integration API Reporting & Search
Infrastructure 2D & 3D Viewer Archiving
Operator
8
The world’s most widely-used collaboration platform for engineering & construction
500thousandusers worldwide
$800billionin projects
1.1billiondocuments
48thousand
companies served
70countries
around the world
40offices
globally
Vista Projects Chiyodo BG Group
Tanker Pacific Leighton Welspun Bilfinger
9
Case Study: ABADI FLNG
Tabitha PendleburyInterface Systems Engineer
Over 15 year oil and gas industry experience
10
ABADI FLNG Project Overview
• INPEX (65%) Shell (35%) Joint Venture
• 2 FLNG - Front End Engineering Design (FEED) contractors
• Single Subsea (below waterline) contractor
• Challenging information exchange between contractors for all interface information
• Probity rules created significant compliance requirements and risks
11
ABADI IM Challenges
• First FLNG designed in Indonesia
• Inexperienced local staff
• Indonesian legislative requirements and constraints
• >200 plus interfaces in total managed
• SURF Contractor started three (3) months before FLNG Contractor
12
Interface example on the ABADI FLNG
• Change - Addition of Fiber Optic readiness
• Impact - Changes to the following FLNG/ SURF interfaces;
– Cabling trays and pig tails
– Umbilicals
– Umbilical termination assembly
– Entire telecommunications strategy and design
• Resolution – Central team to ensure the Management of Change included processes to:
– Identify impacts to all interfaces
– Define impacts
– Manage impacts
– Communicate to all stakeholders
13
Interface Management emerging best practices
• Upfront process definition Pre FEED
• Process driven communication
• Cross organization coordination
• Consistent interface management processes across contracts and organizations
• Support of seamless handover through commissioning and start up
14
Overcoming Challenges
Challenge Manual process System process
Information exchange Email, FTP, error prone Secure auditable central system
IT resources Create and manage spread sheets and distribution lists
Little to no IT support
File size and compatibility issues
Inability to email or open files No file size limits and integrated viewer
Security Email is not secure and files can be forwarded
All communication is within a secure environment and all activity is tracked
Time spent transmitting documents
Manual sending of multiple versions to multiple parties
Everything needed is in one central location available from anyplace anytime
Dispute over incorrect/ undelivered documents
Searching through sent boxes and transmittal logs
Clear audit trail with accountability
15
Interface Management systems – lessons learned
Flexibility• Supports your project processes
• Accommodates process changes
• Captures informal and formal communication
Ease of set up and use• Supports industry specific processes
• Proven track record
• Local system support for ALL users
Security• Redundancy
• Backup
• Built in security measures
16
Results
• Reduced project risk – clear audit trail
• Improved communication - visibility into status of all interfaces
• Time savings – no tracking, searching or waiting
• A safe operating asset – built as designed
17 Trusted by the world’s largest projects
Thank you… and thanks to guest presenter Tabitha Pendlebury.