CVE 4070 Construction Engineering Value Engineering Prof. Ralph V. Locurcio, PE.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
-
Upload
allyssa-quimby -
Category
Documents
-
view
228 -
download
1
Transcript of CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
CON 4003 CON 4003 CVE 4073/5073CVE 4073/5073
The Estimating Process The Estimating Process
Prof. Ralph V. Locurcio, PEProf. Ralph V. Locurcio, PE
Contract DocumentsContract Documentsor or
Bid SetBid Set
Contract Documents…Contract Documents…
1.1.The Agreement or ContractThe Agreement or Contract2.2.The SpecificationsThe Specifications3.3.The DrawingsThe Drawings
Important Note: Important Note: Unless otherwise specified this list is Unless otherwise specified this list is the the ““order of precedence” of the contract order of precedence” of the contract documents documents
Where Estimates are Where Estimates are Used…Used…
Need for a projectIs recognized
Owner appointsProject Manager
Project Manager develops project
program: scope & cost parameters
Project is entered into an annual
capital program
Designer prepares concept design & preliminary cost
estimate
Owner orders bid documents
Project Manager advertises for
construction bids
Contractors assemble team,
prepare & submit bid
Bids opened & reviewed by owner
(with designer)
Builder’s credentials &
bonding approved
Owner approves program
Project Manager advertises for
designer
Owner hires designer
Owner authorizes final
design
Owner selectsbuilder
Contract Signed
Notice to
Proceed
Resident Engineeroversees
construction
Project phase(s)completed
All work completed final inspection
made
Progresspayment
Final paymentOwner accepts
facility
Designer completes plans &
specifications
EstimatingEstimating
The Estimating Process-1The Estimating Process-1 Decision to bidDecision to bid Form the estimating teamForm the estimating team Estimate work planEstimate work plan
Type of estimateType of estimate ProceduresProcedures DocumentationDocumentation
Risk & contingency analysisRisk & contingency analysis Review & check the estimateReview & check the estimate Finalize the estimateFinalize the estimate
The Estimating ProcessThe Estimating Process
KickoffMeeting
WorkPlan
EstablishStandards
UpdateDatabase
PrepareEstimate
DocumentEstimate
ReviewEstimate
Adjust Estimate?
SubmitBid
ProjectExecution
ProjectCompletion
Yes
No
Revise
Lessons Learned
Feedback to improve data base
Re
ality Ch
eck
Estimate work planEstimate work plan Type of estimate required Deliverables by subcontractors Budget for the estimate Staffing Schedule Methodology Controls & reviews Presentation format & production
Types of EstimatesTypes of Estimates Conceptual estimateConceptual estimate
Decision on unitsDecision on units Adjustments for time & locationAdjustments for time & location
Detailed estimateDetailed estimate Material take-offMaterial take-off Equipment & cycle timeEquipment & cycle time Labor & productivityLabor & productivity Admin + overhead+ Admin + overhead+
logistics+taxes+profitlogistics+taxes+profit
Basic estimating Basic estimating procedureprocedure
Read the plans, specs & contractRead the plans, specs & contract Conduct a site investigationConduct a site investigation Decide on construction methodDecide on construction method Consider the construction Consider the construction
scheduleschedule Material quantity takeoffsMaterial quantity takeoffs Plan for equipmentPlan for equipment Plan for subcontractsPlan for subcontracts Estimate costs of labor & materialsEstimate costs of labor & materials Assess risksAssess risks Determine contingencyDetermine contingency Finalize bidFinalize bid
Basic estimating Basic estimating procedureprocedure
Read the Plans, Specs & Contract
Conduct Site Visit
Decide Construction
MethodPrepare Schedule
Plan for Subcontracts
Plan for EquipmentMaterial Take-Offs
Estimate costs
Determine contingency
Analyze Risk Factors
Finalize Bid
Conduct thorough site Conduct thorough site visitvisit
Physical characteristicsPhysical characteristics Sub-surface conditionsSub-surface conditions Site logistics for construction Site logistics for construction
layoutlayout Condition of roads & bridgesCondition of roads & bridges Storage space for lay-downStorage space for lay-down Security requirementsSecurity requirements Operational requirementsOperational requirements
Read the plans, specs & Read the plans, specs & contractcontract
Contract terms & conditionsContract terms & conditions Payment & penaltiesPayment & penalties Scope and quantities Scope and quantities Complexity of constructionComplexity of construction Completeness of plansCompleteness of plans Quality of materials Quality of materials
requiredrequired
Decide construction Decide construction methodmethod
Basic approach & teamingBasic approach & teaming Work breakdown structure & Work breakdown structure &
sequencesequence Skills of work crewsSkills of work crews Decision on work to be Decision on work to be
subcontractedsubcontracted Timing of individual activitiesTiming of individual activities Phasing of crews on sitePhasing of crews on site Procurement of equipmentProcurement of equipment Flow of materials & laydownFlow of materials & laydown Cash flow projectionCash flow projection
Work scheduleWork schedule
Based on contract provisionsBased on contract provisions Sequence of workSequence of work Operational constraintsOperational constraints Site constraintsSite constraints Weather & safety factorsWeather & safety factors Lead time for materialsLead time for materials Availability of subcontractorsAvailability of subcontractors
Material quantity takeoffMaterial quantity takeoff Study plans & specsStudy plans & specs Systematic breakdown of unitsSystematic breakdown of units Bid instructions, format & Bid instructions, format &
alternatesalternates Follow sequence of constructionFollow sequence of construction CSI category of materials & laborCSI category of materials & labor Check for duplicates & Check for duplicates &
omissionsomissions Document all workDocument all work Review & check for errorsReview & check for errors
Direct costsDirect costs
Materials, labor, equipmentMaterials, labor, equipment Subcontractor bidsSubcontractor bids Contact suppliers Contact suppliers Market factors applyMarket factors apply Establish and update cost Establish and update cost
data basedata base
Indirect costsIndirect costs
MobilizationMobilization Field officeField office InsuranceInsurance BondsBonds Taxes & permitsTaxes & permits CleanupCleanup DemobilizationDemobilization
Risk analysisRisk analysis Complexity of plans & specsComplexity of plans & specs Terms of contract & penaltiesTerms of contract & penalties Experience with ownerExperience with owner Timing of projectTiming of project Market factors for labor & materialsMarket factors for labor & materials Weather & safety Weather & safety Other uncertainties effecting Other uncertainties effecting
executionexecution Probability of occurrence of eachProbability of occurrence of each
Determine contingencyDetermine contingency
Percentage of base estimatePercentage of base estimate Determine high-cost risk Determine high-cost risk
factorsfactors Expected net risk based on Expected net risk based on
probabilityprobability Aggregate total project riskAggregate total project risk Establish contingency Establish contingency
The Estimating ProcessThe Estimating Process
KickoffMeeting
WorkPlan
EstablishStandards
UpdateDatabase
PrepareEstimate
DocumentEstimate
ReviewEstimate
Adjust Estimate?
SubmitBid
ProjectExecution
ProjectCompletion
Yes
No
Revise
Lessons Learned
Feedback to improve data base
Re
ality Ch
eck
CSI Master Format-1CSI Master Format-1
CSI Master Format-2CSI Master Format-2
CSI Master Format-1CSI Master Format-1
CSI Master Format-2CSI Master Format-2
Typical Excel FormatTypical Excel Format
RSMeansRSMeans
Bid summaryBid summary One line item cost for each CSI categoryOne line item cost for each CSI category
01 – General conditions = 01 – General conditions = $3000$3000 02 – Concrete =02 – Concrete = $1000$1000 05 – Metals=05 – Metals= $ 500$ 500 06 – Wood, Plastics=06 – Wood, Plastics= $1500$1500 Total ………………………….Total …………………………. $6000$6000 Contingency…………………...Contingency…………………... $ 600$ 600 Taxes………………………….Taxes…………………………. $ 396$ 396 Profit………………………….Profit…………………………. $ 700$ 700 Your bid………………………Your bid……………………… $7696 $7696
BiddingBidding
Issuance of Bid Issuance of Bid Documents…Documents… Prepare adequate bid setsPrepare adequate bid sets
Make “reproducible” set of Mylar drawingsMake “reproducible” set of Mylar drawings
Plan bidding process carefullyPlan bidding process carefully May issue pre-bid noticeMay issue pre-bid notice May include pre-bid conference to clarify owner’s intentMay include pre-bid conference to clarify owner’s intent Issue amendments to correct errorsIssue amendments to correct errors Avoid “irregularities”Avoid “irregularities” Documents are “close hold” to ensure competitionDocuments are “close hold” to ensure competition
Issue bid documentsIssue bid documents All sets must be identicalAll sets must be identical Keep accurate log of documents issuedKeep accurate log of documents issued Addenda must be mailed to all bidding firmsAddenda must be mailed to all bidding firms Answers to questions to all biddersAnswers to questions to all bidders
Avoid bid protestAvoid bid protest Process stopped pending review Process stopped pending review May be cause for rebidMay be cause for rebid Financial problems resultFinancial problems result
Bonds…Bonds… Bid bondsBid bonds
Avoids loss if bidder cannot/does not accept contractAvoids loss if bidder cannot/does not accept contract 5%-10% of bid price5%-10% of bid price Returned when agreement signedReturned when agreement signed Common on public contractsCommon on public contracts Bonds purchased from “surety” companyBonds purchased from “surety” company
Performance & payment bondsPerformance & payment bonds Intent is to protect owner from contractor failureIntent is to protect owner from contractor failure Insurance (surety) company guarantees completionInsurance (surety) company guarantees completion Payment bond pays labor & material debts of contractorPayment bond pays labor & material debts of contractor Prime often requires bonds of subcontractorsPrime often requires bonds of subcontractors Ability to obtain bonds depends on prior performanceAbility to obtain bonds depends on prior performance
Insurance…Insurance… General liability insuranceGeneral liability insurance
OperationsOperations Personal injuryPersonal injury Liability during constructionLiability during construction Automobile medical & physical paymentsAutomobile medical & physical payments Post-project liabilityPost-project liability
Builder’s Risk InsuranceBuilder’s Risk Insurance Covers perils during constructionCovers perils during construction Fire, lightning, vandalism, windstormFire, lightning, vandalism, windstorm Additional perils: collapse, terrorism, rupture, etc…Additional perils: collapse, terrorism, rupture, etc…
Bid Opening & Bid Opening & Evaluation…Evaluation… Technical evaluation & reviewTechnical evaluation & review
Will bid achieve owner’s intentWill bid achieve owner’s intent Is bidder’s plan competent & safeIs bidder’s plan competent & safe Are subcontractors qualifiedAre subcontractors qualified
Price evaluationPrice evaluation Rank order by low to high bidRank order by low to high bid Are all bids “responsive”; i.e.. meet all requirementsAre all bids “responsive”; i.e.. meet all requirements Bids may not be “qualified” in any wayBids may not be “qualified” in any way Review of “schedule of values” or estimated payment scheduleReview of “schedule of values” or estimated payment schedule Determine “apparent” low bidderDetermine “apparent” low bidder
Bid qualificationBid qualification Is bidder disqualified for any reasonIs bidder disqualified for any reason Are bonds, insurance & certifications adequateAre bonds, insurance & certifications adequate
Recording of bids & recommend awardRecording of bids & recommend award
Questions?Questions?
That’s all for today…That’s all for today…
Slides are on my web siteSlides are on my web site My web site:My web site:
www.my.fit.edu/~locurciowww.my.fit.edu/~locurcio
Schedule of ValuesSchedule of Values