Compliance Report “Group Housing Project” By …nromoef.gov.in/SMPR/new26052014/100.docx · Web...
Transcript of Compliance Report “Group Housing Project” By …nromoef.gov.in/SMPR/new26052014/100.docx · Web...
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Six-Monthly Environmental Compliance Report of
Stipulated Conditions of Environmental Clearance
(June 2013 to Nov 2013)
For
“Group Housing Project”
SECTOR-3, Village Gwal Pahari
Gurgaon (Haryana)
For Submission to:
Ministry of Environment and Forests (MOEF)
Submitted by:
Ambawatta Buildwell Pvt. Ltd.
NOV, 2013
INDEX
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Description Page No.
Chapter 1 Compliance of Stipulated Conditions of Environmental Clearance
Part A Specific Conditions for buildings in operational phase 4
I. Construction Phase 4
II. Operation Phase 8
Part B General Conditions 12
Chapter 2 Details of Environmental Monitoring
2.2 Ambient Air Quality Monitoring 14
2.2.1 Ambient Air Quality Monitoring Stations 14
2.2.2 Ambient Air Quality Monitoring Methodology 14
2.2.3 Ambient Air Quality Monitoring Results 15
2.2.4 Discussion on Ambient Air Quality in the Study Area 16
2.3 Ambient Noise Monitoring 17
2.3.1 Ambient Noise Monitoring Locations 17
2.3.2 Methodology of Noise Monitoring 17
2.3.3 Ambient Noise Monitoring Results 17
2.3.4 Discussion on Ambient Noise Levels in the Study Area 18
2.4 Groundwater Quality Monitoring 19
2.4.1 Groundwater Quality Monitoring Locations 19
2.4.2 Methodology of Groundwater Quality Monitoring 19
2.4.3 Groundwater Quality Monitoring Results 20
2.4.4 Discussion on Groundwater Quality in the Study Area 21
2.5 Soil Monitoring 22
2.5.1 Soil Monitoring Locations 22
2.5.2 Methodology of Soil Monitoring 22
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Description Page No.
2.5.3 Soil Monitoring Results 23
2.5.4 Discussion on Soil Characteristics in the Study Area 23
Figures
2.1 Location-wise Variation of Ambient Air Quality 16
2.2 Location-wise Variation of Ambient Noise Levels 18
Annexure
1 Lab reports of Ambient Air, Ambient Noise, Water and Soil monitoring
2 Clearance from Airport Authority.
S. No. PART A:- SPECIFIC CONDITIONConstruction Phase:-
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
CONDITIONED OF EIA CLEARENCE REPLY
[i] A first aid room as proposed in the project
report shall be provided during
construction and operation phase of the
project.
Adequate first Aid facilities have been
ensured for construction labours.
[ii] Adequate drinking water and sanitary
facilities should be provided for
construction workers at the site. Provision
should be made for mobile toilets. Open
defecation by the labours is strictly
prohibited. The safe disposal of waste
water and solid waste generated during the
construction phase should be ensured.
Yes being complied. Adequate facilities
are being provided in regard to drinking
water, sanitation and solid waste
management.
[iii] All the top soil excavated during
construction activities should be stored for
use in horticulture/ landscape development
within the project site.
Complied. The same excavated earth
will be reused for horticulture
development.
[iv] Disposal of muck during construction
phase should not create any adverse effect
on the neighbouring communities and be
disposed off taking the necessary
precautions for general safety and health
aspects of people, Only in approved sites
with the approval of competent authority.
Yes, all the practicable precautions are
being adopted for the proper disposal of
excavation materials at project site and
it will not go beyond our project
premises.
[v] Construction spoils including bituminous
material and other hazardous materials,
must not be allowed to contaminate
watercourse and the dump sites for such
material must be secured so that they
should not leach into the ground water and
any hazardous waste generated during
Complied; all feasible precautions will
be undertaken to prevent water source
contamination.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
construction phase, should be disposed off
as per applicable rules and norms with
necessary approval of the Haryana State
Pollution Control Board.
[vi] The diesel generator sets to be used during
construction phase should be of low
sulphur diesel type and should conform to
Environment (Protection) Rules prescribed
for air and noise emission standards.
DG sets during construction phase are
used for running only the site office.
And they are operated only during
power failure; added that the
construction activities are during day
time only. Hence usage of D.G. sets
during construction phase is minimal.
D.G. sets being used in the construction
phase are as per Environment
(Protection) Rules for air and Noise
emission standard. Only low sulphur
diesel is used for DG sets.
[vii] The diesel required for operator DG sets
shall be stored in underground tanks and if
required, clearance from Chief controller
of Explosive shall be taken.
Will be complied.
[viii] Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during construction
phase. Adequate measures should be taken
to reduce ambient air and noise level
during construction phase, so as to conform
to the stipulated residential standards.
Available best construction practices
are followed to take care of the
Environment. The Lab Analysis Report
attach as Annexure 1.
[ix] Fly ash should be used as building material Yes, fly ash based ready mixed
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
in the construction as per the provision of
Fly Ash notification of September 1999
and amended as on 27th August 2003.
concrete material is used in building
construction.
[x] Ready mixed concrete must be used in
building construction.
Yes, ready mixed concrete is used for
building construction.
[xi] Strom water control and its re-use as per
CGWB and BIS Standards for various
applications should be ensured.
Yes, being complied. Layout of storm
water drainage network has already
submitted.
[xii] Water demand during construction should
be reduced by use of Premixed concrete,
curing agents and other best practices as
referred.
Yes, pre-mixed concrete is being used
and will be used to reduce the water
demand during the construction phase
of the project.
[xiii] Permission from component Authority for
supply of water shall be obtained prior to
operation of the project.
Yes, MOU will be signed With HUDA.
[xiv] Roof should meet perspective requirements
as per Energy conservation Building Code
by using appropriate thermal insulation
material to fulfil requirements.
All the roofs will be designed as per
ECBC norms and will be insulated to
minimize heat gain.
[xv] Opaque wall should meet prescriptive
requirements as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is aspirational for non-air-
conditioned spaces by use appropriate
thermal insulation material to fulfil
requirement
The project is being developed
according to ECBC norms.
[xvi] The approval of the competent authority
shall be obtained for structural safety of the
building on account of earthquake,
Yes, being complied. The project is
being developed as per NBC norms.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
adequacy of fire fighting equipments, etc.
as per National Building Code including
protection measures from lighting etc. If
any forest land is involved in the proposed
site, clearance under Forest Conservation
Act shall be taken from the Competent
Authority.
The said project doesn’t fall under
forest land. Copy of NOC issued from
forest department, has already been
submitted. The necessary approval will
be taken in the operation phase,
whoever safely measures are adopted
from any fire etc.
[xvii] The project proponent will use the water
for construction phase through tankers.
However, prior permission from CGWA
will be taken before using the bore well
water for construction purpose.
Yes, being complied. Agreement with
private water tanker to supply water
from safe zone has already been
submitted.
[xviii] The project proponent will construct rain
water harvesting pits@1pit per acre for
recharging the ground water within the
project premises.
Yes, being complied. Rain water
Harvesting pit details have already
submitted.
[xix] The project proponent will start
construction only after getting permission
of the Airport authority.
Yes, we have obtained clearance from
Airport Authority for the said project.
Copy of the same is enclosed as
Annexure 2.
Operation Phase:-[i] The STP shall be installed for the treatment Yes, will be complied.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
of the sewage generated to the prescribed
standards including odour and treated
effluent will be recycled to achieve zero exit
discharge. The STP should be installed at the
remotest place in the project area.
Relevant details have been already
submitted.
[ii] Separation of the gray and black water
should be done by the use of dual plumbing
line. Treatment of 100% gray water by
decentralized treatment should be done
ensuring that the re-circulated water should
be have BOD maximum 10ppm and the
recycled water will be used for flushing,
gardening and DG set cooling and running of
fountain in the water body.
Will be complied. Dual plumbing
system will be adopted to avoid the
contamination between fresh water
and the tertiary level treated water.
[iii] For disinfections of the treated wastewater
ultra violate radiation or ozonization should
be used.
Yes, ultra violet radiation system will
be adopted.
[iv] The solid waste generated should be properly
collected and segregated. Bio-degradable
waste will be decomposed at site and
dry/inert solid waste should be disposed off
to the approved sites for land filling after
recovering recyclable material.
The generated solid waste from the
project will be managed as per MSW
Rules 2000. Details are already
submitted with initial compliance
report.
[v] Diesel power generating sets proposed as
source of backup power for lifts, common
area illumination and for domestic use should
be of enclosed type and conform to rules
made under the Environment (Protection)
Act, 1986. The location of the DG sets
should be in the basements as promised by
All the DG sets provided for the
project will be acoustically treated
and will conform to rules made under
Environment (Protection) Act for air
and noise emission standard. The
provided DG sets will use low sulfur
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
the project proponent with appropriate stack
height i.e. above the roof level of the building
as per the CPCB norms. The diesel used for
DG sets should be of Low Sulphur contents
(maximum 0.25%).
content HSD.
The stack height will be kept as per
CPCB norms.
[vi] Ambient Noise level should be controlled to
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the Proposed Residential Complex.
Will be complied.
[vii] The project proponent should maintain at
least 20% as green cover for tree plantation
especially all around the periphery of the
project and on the road sides preferably with
local species so as to provide protection
against particulates and noise. The open
spaces inside the plot should be preferably
landscaped and covered with
vegetation/grass.
Yes, the green belt will be developed
as per the guidelines of SEAC
Haryana.
Please refer the landscape details
submitted with initial compliance
report.
[viii] Weep holes in the compound front wall shall
be provided to ensure natural drainage of rain
water in the catchments area during the
monsoon period.
Will be complied. Relevant plans
already submitted.
[ix] Rain water harvesting for roof run-off and
surface runoff, as per plan submitted should
be implemented. Before recharging the
surface run-off, pre-treatment must be done
to remove suspended matter, oil & grease.
The bore well for rainwater recharging
should be kept at least 5mts. Above the
highest ground water table.
Will be complied.
[x] The ground water level and its quality should
be monitored regularly in consultation with
Being complied. Sampling results are
covered under Monitoring Reports
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Central ground Water Authority. enclosed as Annexure 1
[xi] There should be no traffic congestion near
the entry and exit points from the roads
adjoining the proposed project site. Parking
should be fully internalized and no public
spaces should be utilized.
The road network for the project has
been designed as per the applicable
guidelines. Please refer the submitted
parking plan with initial compliance
report.
[xii] A report on the energy conservation
measures confirming to energy conservation
norms finalize by Bureau of Energy
Efficiency should be prepared incorporating
details about building materials and
technology, R and U factors, etc and
submitted to SEIAA, Haryana in three
months time.
Will be complied.
[xiii] Energy conservation measures like
installation of CFLs/TFLs for lighting the
area outside the building should be integral
part of the project design and should be in
place before project commissioning. Used
CFLs and TFLs should be properly collected
and disposed off/sent for recycling as per the
prevailing guidelines/rules of the regulatory
authority to avoid mercury contamination.
Use of solar panels must be adapted to the
maximum extent possible for energy
conservation.
Installation of CFLs/TFLs for
lighting the area will be integral part
of the project design. Used/damaged
CFLs will be stored separately from
domestic waste in a HDPE container
and periodically will be handed over
only to Authorized Vendor. Solar
lighting feasibility will be explored
for the project.
[xiv] The solid waste generated should be properly
collected and segregated as per the
requirements of the MSW rules, 2000 and as
amended from time to time. The bio-
degradable waste should be composted by
vermin-compositing at the site ear marked
The solid waste generated will be
properly collected and segregated as
per the requirements.
The details of solid waste
management plan proposed for the
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
within the project area and dry/inert solid
waste should be disposed off to the approved
sites for land filing after recovering
recyclable material.
project have been submitted already.
[xv] The provision of the solar water heating
system shall be as per the norms specified by
HAREDA and shall be made operational in
each building block.
Since the project is a commercial
complex development so there are no
requirements of solar hot water
system.
[xvi] The project proponent will use the water
from the tube well for domestic purposes and
commercial purpose only after getting
permission from CGWA or will use water
supply from HUDA whichever is earlier
during operation phase.
All requisite permission from the
competent authorities will be taken.
[xvii] The traffic plan and the parking plan
proposed by the project proponent should be
adhered to meticulously with further scope of
additional parking for future requirements.
There should be no traffic congestion near
the entry and exit points from the roads
adjoining the proposed site. Parking should
be fully internalized and no public space
should be used.
Yes, will be complied.
Please refer the submitted parking
plan with initial compliance report.
PART B:-GENERAL CONDITIONS
[i] The environmental safeguards contained in
the EIA/EMP Reports should be
implemented in letter and spirit.
Yes, Adequate environmental
safeguards will be implemented for
the proposed project in a time bound
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
and satisfactory manner.
[ii] Six monthly compliance reports should be
submitted to the HSPCB and Regional
Office, MoEF, GOI, Northern Region,
Chandigarh and a copy to the SEIAA,
Haryana
Being complied.
[iii] The SEIAA , Haryana reserves the right to
add additional safeguards measures
subsequently, if found necessary,
Environmental Clearance granted will be
revoked if it is found that false information
has been given for getting approval of this
project.
We will abide by the additional
safeguards time to time if suggested
by the ministry in future as applicable
and technically feasible.
[iv] The project proponent will start construction
only after getting NOC from the forest
department that the area under consideration
does not fall under section -4 and -5 PLPA-
1990.
Yes, we have obtained clearance
from forest department for the said
project. Copy already submitted.
[v] All other statutory clearances such as the
approvals for storage of diesel from Chief
Controller of Explosives, Fire Department,
Civil Aviation Department, Forest
Conservation Act, 1980 and wildlife
(Protection) Act, 1972. Forest Act, 1927,
PLPA 1900, etc. shall be obtained as
applicable by project proponent from the
respective authorities prior to construction of
the project.
We are committed to abide by the
rules applicable for the project.
Approvals of:
Chief Controller of Explosives:
will be obtained in time.
PLPA, 1900, Forest Act, 1927:
Already submitted.
Forest Conservation Act: N/A
Wildlife Act : N/A
[vi] The project proponent will not violate any
judicial orders/pronouncements issued by the
We are committed to adhere to the
said stipulations stated by SEIAA in
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Hon’ble Supreme Court/High Courts. the said EC letter.
[vii] The project proponent shall seek NOC from
the Mining Department before the start of
construction activity.
Yes, we have obtained clearance
from Mining Department for the said
project.
CHAPTER- 2
Details of Environmental Monitoring
2.1 AMBIENT AIR QUALITY MONITORING
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.1.1 Ambient Air Quality Monitoring Stations
Ambient air quality monitoring has been carried out at two locations, one being near the front gate and one location is Project site of the building to assess the ambient air quality of the project site. This will enable to have a comparative analytical understanding about air quality and the changes in the air environment in the study area with respect to the condition prevailing. The locations of the ambient air quality monitoring stations are given in Table 2.1.
Table 2.1 Details of Ambient Air Quality Monitoring StationsS. No. Location Code Location Name Environmental Setting
1. AAQ-1 Near Front Gate Residential
2. AAQ-2 Near Project Site Residential
AAQ-1: Front Gate
The sampler was placed near front gate of building and was free from any obstructions. Surroundings of the sampling site represent residential environmental setting
AAQ-2: Project Site
The sampler was placed near project site of building. Vicinity represents residential environmental setting.
2.1.2 Ambient Air Quality Monitoring Methodology
Monitoring was conducted in respect of the following parameters:
Particulate Matter 2.5 (PM 2.5)
Particulate Matter 10 (PM 10)
Sulphur Dioxide (SO2)
Oxides of Nitrogen (NOx)
Carbon Monoxide (CO)
The duration of sampling of PM2.5, PM10, SO2 and NOx was 24 hourly continuous sampling per day and CO was sampled for 8 hours continuous, thrice in 24 hour duration monitoring. The monitoring was conducted for one day at each location. This is to allow a comparison with the National Ambient Air Quality Standards.
The air samples were analyzed as per standard methods specified by Central Pollution Control Board (CPCB) and IS: 5182. The techniques used for ambient air quality monitoring and minimum detectable levels are given in Table 2.2.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Fine Particulate Sampler instruments have been used for monitoring Particulate Matter 2.5 (PM2.5 i.e. <2.5 microns), and Respirable Dust Sampler was used for sampling Respirable fraction (<10 microns), gaseous pollutants like SO2, and NOx. Bladder and Aspirator bags were used for collection Carbon monoxide samples. Gas Chromatography techniques have been used for the estimation of CO.
Table 2.2 Techniques used for Ambient Air Quality Monitoring
S. No. Parameter Technique Technical Protocol
1 Particulate Matter 2.5
Fine Particulate Sampler, Gravimetric Method
CPCB/MOEF Guideline
2 Particulate Matter 10 Respirable Dust Sampler, with cyclone separator, Gravimetric Method
IS-5182 (Part-23)
3 Sulphur dioxide Modified West and Gaeke IS-5182 (Part- II)
4 Oxides of Nitrogen Jacob & Hochheiser IS-5182 (Part-VI)
5 Carbon Monoxide Gas Chromatography IS-5182 (Part-X)
2.1.3 Ambient Air Quality Monitoring Results
The detailed on-site monitoring results of PM2.5, PM10, SO2, NOx and CO are presented in Table 2.3.
Table 2.3 Ambient Air Quality Monitoring ResultsS.No. Location
Code
Location PM10
(g/m3)
PM2.5
(g/m3)
SO2
(g/m3)
NOx
(g/m3)
CO
(mg/m3)
1. AAQ1 Near Main Gate 87.35 41.30 11.20 22.30 <0.50
2. AAQ2 Near Project Site 83.25 39.24 9.36 19.20 <0.50
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
PM10 PM2.5 SO2 Nox0
20
40
60
80
100
120
AAQ1AAQ2LIMIT
Figure 2.1 Location-wise Variation of Ambient Air Quality
AAQ1 AAQ2 LIMIT0
0.5
1
1.5
2
2.5
CO(mg/m3)
Figure 2.2 Location-wise Variation of Ambient Air Quality
2.1.4 Discussion on Ambient Air Quality in the Study Area
PM10 and PM2.5 levels at the project site are under the permissible limit of 100 μg/m3 and 60 μg/m3 respectively (for residential, rural and other areas as stipulated in the National Ambient Air Quality Standards). SO2, NOx and CO was observed within the corresponding stipulated limits (Limit for SO2 and NOx: 80 g/m3 and limit for CO: 4.0 mg/m3) at all monitoring locations. Station wise variation of ambient air quality parameters has been pictorially shown in Figure 1&2
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.2 AMBIENT NOISE MONITORING
2.2.1 Ambient Noise Monitoring Locations
The main objective of noise monitoring in the study area is to assess the present ambient noise levels in project site & project boundary due to various construction allied activities and increased vehicular movement. A preliminary reconnaissance survey has been undertaken to identify the major noise generating sources in the area. Ambient noise monitoring was conducted at locations at the boundary of the project site as given in Table 2.4
Table 2.4 Details of Ambient Noise Monitoring StationsS. No. Locn. Code Location Name/ Description Present Land use
1. N1 Near Main Gate Residential
2.2.2 Methodology of Noise Monitoring
Noise levels were measured using sound level meter. Noise level monitoring was carried out continuously for 24-hours with one hour interval starting at 06:00 hrs to 06:00 hrs next day. The noise levels were monitored on working days only. During each hour Leq were directly computed by the instrument based on the sound pressure levels. Leq day & Leq night values were computed using correspond in hourly . Monitoring was carried out at ‘A’response and fast mode.
2.2.3 Ambient Noise Monitoring Results
The location wise ambient noise monitoring results is summarized in Table 2.5. The location-wise variation of noise levels are graphically presented in Figure 2.2.
Table 2.5 Ambient Noise Monitoring Results
Day Night
Location code LocationLeq Lmin Lmax Leq Lmin Lmax
N1 Near Main Gate 56.20 52.30 62.30 50.25 47.50 54.20
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Leq Lmin Lmax0
10
20
30
40
50
60
70
DayNight
Figure 2.2 Location-wise Variation of Ambient Noise Levels
2.2.4 Discussion on Ambient Noise Levels in the Study Area
Day Time Noise Levels (Lday):
The day time noise level at all the locations were found to within limits prescribed for commercial area i.e. 65 db(A).
Night Time Noise Levels (Lnight):
The night time noise level at all the locations were found to within limit prescribed for commercial area i.e. 55 dB (A).
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.3 GROUNDWATER QUALITY MONITORING
2.3.1 Groundwater Quality Monitoring Locations
Keeping in view the importance of groundwater as an important source of drinking water to the local population, sample of ground water was collected from the project site for the assessment of impacts of the project on the ground water quality.
Water sample was collected from the project site. The sample was analyzed for various parameters to compare with the standards for drinking water as per IS: 10500 for ground water sources. The details of water sampling locations are given in Table 2.6.
Table 2.6 Details of Water Quality Monitoring StationS. No. Locn. Code Location Name/ Description
1. GW 1 Onsite
2.3.2 Methodology of Groundwater Quality Monitoring
Sampling of ground water was carried out on April 2013. Samples were collected as grab sample and sampling forms are filled in as per the sampling plan. The preservative sample were properly added to preserve as per standard operating procedures (SOP) and stored immediately in ice boxes, which were ensured for appropriate temperatures. Sample for chemical analysis was collected in polyethylene carboys. Sample collected for metal content were acidified to <2 pH with 1 ml HNO3. A sample for bacteriological analysis was collected in sterilized glass bottles.
Soon after the completion of sampling, chain of custody sheets for the samples are filled in and then they were transported by road to Vardan Enviro Lab Gurgaon for further analysis. Proper care was taken during packing and transportation of samples. After ensuring the same the samples were forwarded immediately for analysis.
The samples were analyzed as per the standard procedures specified in 'Standard Methods for the Examination of Water and Wastewater' published by American Public Health Association (APHA) and CPCB. The analytical techniques and the test methods adopted for testing of ground water are given in Table 2.7.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.3.3 Groundwater Quality Monitoring Results
The detailed groundwater quality monitoring results are presented in Table 2.7.
Table 2.7 Groundwater Quality Monitoring Results
S. No. Parameters Onsite Units Test Method
1 pH 7.11 - APHA 4500 – H+B
2 Colour <1.0 Hazen APHA 2120 B
3 Turbidity 5.0 NTU APHA 2130 B
4 Odour Unobjectionable - APHA 2150 B
5 Taste Agreeable - APHA 2160 B
6 Total Hardness (as CaCO3) 236.50 mg/L
APHA 2340 C
7 Chloride (as Cl-) 117.50 mg/L APHA 4500 –Cl B
8 Calcium (as Ca) 69.50 mg/L APHA 3500 –Ca B
9 Magnesium (as Mg) 15.33 mg/L APHA 3500 –Mg B
10 Chlorine Residual BDL mg/L APHA 4500 –Cl B
11 Total Disolve Solids 448.50 mg/L APHA 2540 D
12 Alkalinity (as CaCO3) 198.50 mg/L APHA 4500 Norg B
13 Sulphate (as SO4) 54.20 mg/L APHA 4500 NO3- B
14 Total Kjehldal Nitrogen BDL mg/L
IS: 3025-1964 (13)
15 Nitrate (as NO3-) 1.65 mg/L APHA 4500 SO4-- E
16 Fluoride (as F-) 0.56 mg/L APHA 4500 F- D,B
17 Iron Dissolve (as Fe) 0.24 mg/L APHA 3500 Fe B
18 Nickel (as Ni) BDL mg/L APHA 3111 B
19 Chromium Total
(as Cr) BDL mg/L
APHA 3111 B
20 Copper (as Cu) BDL mg/L APHA 3111 B
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
S. No. Parameters Onsite Units Test Method
21 Lead (as Pb) BDL mg/L APHA 3111 B
22 Zinc (as Zn) <0.01 mg/L APHA 3111 B
23 Mercury (as Hg) BDL mg/L APHA 5530 D
24 Phenolic Compounds BDL mg/L APHA 3112 B
25 Cyanide (as CN) BDL mg/L APHA 4500 CN- C
26 Cadmium (as Cd) BDL mg/L IS 3025 Part -59
27 Manganese (as Mn) BDL mg/L APHA 3111 B
28 Selenium (as Se) BDL mg/L IS: 3025 Part 56
29 Arsenic (as As) BDL mg/L APHA 3114 B
30 Boron (as B) 0.010 mg/L APHA 4500 B 8
31Total Coliform < 2/100ml
MPN/100 ml
IS: 1622:1981
32E. Coli Absent
MPN/100 ml
IS:1622:1981
2.3.4 Discussion on Groundwater Quality in the Study Area
The ground water quality in the project area is observed to be alkaline in nature with total alkalinity reaching up to 214.14 against desirable limit of 200 mg/L, however, alkalinity is less than the permissible limit of 600 mg/L. Total dissolved solids in the ground water is 590.25 mg/L which is higher then prescribed limit of 500 mg/L. However, remaining parameters are within the CPCB prescribed limits.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.4 SOIL MONITORING
2.4.1 Soil Monitoring Locations
The objective of the soil monitoring is to identify the impacts of ongoing project activities on soil quality and also predict impacts, which have arisen due to execution of various constructions allied activities. Accordingly, a study of assessment of the soil quality has been carried out.
To assess impacts of ongoing project activities on the soil in the area, the physico-chemical characteristics of soils were examined by obtaining soil samples from selected points and analysis of the same. single sample of soil was collected from the project site for studying soil characteristics, the location of which is listed in Table 2.8.
Table 2.8 Details of Soil Quality Monitoring LocationS. No. Locn. Code Location Name/ Description
1. S1 Onsite
2.4.2 Methodology of Soil Monitoring
The sampling has been done in line with IS: 2720 & Methods of Soil Analysis, Part-1, 2nd edition, 1986 of American Society for Agronomy and Soil Science Society of America. The homogenized samples were analyzed for physical and chemical characteristics (physical, chemical and heavy metal concentrations). The soil samples were collected in the month of Oct. 2013.
The samples have been analyzed as per the established scientific methods for physico-chemical parameters. The heavy metals have been analyzed by using Atomic Absorption Spectro-photometer .
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.4.3 Soil Monitoring Results
Single sample of soil is collected from the site to check the quality of soil of the study area .The physico-chemical characteristics of the soil, as obtained from the analysis of the soil sample, are presented in Table 2.9.
Table 2.9 Physico - Chemical Characteristics of Soil in the Study Area
S. No.
Parameters Test Method Result Unit
Onsite
1 pH TM- S/10 7.25 -
2 Moisture Content TM- S/16 1.30 %
3 Organic Matter TM- S/08 0.80 %
4 Phosphorus Available as P TM- S/11 3.36 mg/100 gm
5 Total Kjehldal Nitrogen TM- S/17 0.046 %
6 Potassium as K TM- S/13 59.68 mg/100 gm
7 Exchangable Calcium TM- S/15 2.15 %
8 Exchangable Magnesium TM- S/05 0.032 %
9 Iron as Fe TM- S/05 1.22 mg/kg
10 Zinc as Zn TM- S/25 3.20 mg/kg
11 Copper as Cu TM- S/25 1.20 mg/kg
12 Bulk Density TM- S/25 0.91 Gm/cm3
13 Lead as Pb TM- S/25 BDL mg/kg
14 Water Holding Capacity TM- S/34 101.25 ml/100 gm
15 Sodium as Na TM- S/47 27.45 mg/100 gm
2.4.4 Discussion on Soil Characteristics in the Study Area
The soil in study area is characterized by moderate organic content. The soil quality in the project area has not been affected by the project activities.