Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an...
Transcript of Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an...
![Page 1: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/1.jpg)
AABC Commissioning GroupAIA Provider Number 50111116
Completing a Global Enterprise
Building Commissioning Program in
Six MonthsCourse Number: CXENERGY1614
Michael Chimack, PE, QCxP, CEM, PMP, LEED GA
Steven Dodd, EMP, LEED GA
Siemens
April 12, 2016
![Page 2: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/2.jpg)
Credit(s) earned on completion of
this course will be reported to AIA
CES for AIA members.
Certificates of Completion for both
AIA members and non-AIA
members are available upon request.
This course is registered with AIA
CES for continuing professional
education. As such, it does not
include content that may be
deemed or construed to be an
approval or endorsement by the
AIA of any material of construction
or any method or manner of
handling, using, distributing, or
dealing in any material or product._______________________________________
Questions related to specific materials, methods and services will be addressed at the conclusion of this presentation.
![Page 3: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/3.jpg)
This presentation is protected by U.S. and International Copyright laws. Reproduction, distribution, display and use of the presentation without written
permission of the speaker is prohibited.
Restricted © Siemens Industry, Inc. 2016 All rights reserved
Copyright Materials
![Page 4: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/4.jpg)
Six months to complete an existing building
commissioning program at 12 facilities in 8
countries is daunting. This, real-world case study
with lessons learned shows how with
coordination, global resources and a proven
approach, it was completed and exceeded Cx
Objectives.
CourseDescription
![Page 5: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/5.jpg)
LearningObjectives
1. Tailor common commissioning practices and strategies to meet global market
challenges.
2. Understand how commissioning strategies can be used to enhance system
performance and increase energy efficiency.
3. Learn how to deliver maximum value to customers with a fixed budget and a
significantly compressed project timeline.
4. Understand some of the key managerial, financial and tactical challenges of
managing a global commissioning project. .
At the end of the this course, participants will be able to:
![Page 6: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/6.jpg)
Consumption
Results
Building Commissioning Market Drivers
Pilot Project
Global Project
Building
Commissioning
Market Drivers
4 Phase Commissioning
Process
Results
![Page 7: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/7.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 7
Demand and expectations for commissioning continue to grow
Global revenue projection from building commissioning
services
$50B
$20B
$10B
$3B
2014 2016 2018 2020 2022 2024
© 2013 Navigant Research
$6B
$30B
$40B
Value drivers
• Energy savings
• Improve building performance/value
• Increase tenant satisfaction/retention
• Other-specific owner/manager goals
Challenges
Financial
• Meet payback expectations
• Address RFP variances
Procedural
• M&V processes
• Ensure persistence of savings
Organizational
• Organizational challenges
• Consistent delivery
• Implementation procedures
![Page 8: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/8.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 8
This is not your standard commissioning process…
![Page 9: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/9.jpg)
Consumption
Results
Pilot Project
Building Commissioning Market Drivers
Global Project
Pilot
Project
4 Phase Commissioning
Process
Results
![Page 10: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/10.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 10
• Complete all assessment, investigation and implement
approved corrective actions by April 30, 2014.
• Support the target of reducing GHG emissions to 20 percent
below 2005 levels. (Energy use accounts for 98 percent of
the greenhouse gas (GHG) emissions generated)
• Identify corrective actions and measures through the project.
• Achieve a simple payback of 2.5 years for the overall project
through energy improvement measures executed during the
project.
• Review and document HVAC systems performance
Work Within the
Customer’s
Expedited Timeline
Support
Sustainability
Target
Find and Achieve
Energy Savings
Project Goal Challenges:
Document
Performance
Goals for the pilot project
![Page 11: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/11.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 11
Key results of the pilot EBCx project
1 Saved 940,000 kWh,17,000 therms and over $96,000 in the first year. Achieved by identifying
and executing 11 facility improvement measures.
3 New sequence of operations: Documented existing sequence of operations and created new
sequences based on current facility requirements.
2 79 sensors verified/OAT sensor replaced and relocated: Completed by using NIST traceable
calibrated devices and functional testing of major HVAC systems.
4BAS programming updates: Implemented building automation system programming updates
based on the new sequence of operations.
5Failed device replacement: Identified and replaced failed devices including sensors (28% of all
sensors), control modules, thermostats and terminal box controllers.
6Performance recommendations: Generated actions to preserve and enhance value achieved
through the existing building commissioning process.
![Page 12: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/12.jpg)
Consumption
Results
Global Project
Building Commissioning Market Drivers
Pilot ProjectGlobal
Project
4 Phase Commissioning
Process
Results
![Page 13: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/13.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 13
Global EBCx project overview
• Commission 6.3MSF of mixed use
buildings located in 8 countries (4
continents) in 6 months or less!
• Reduce energy consumption by
10-20% per site
• Save a minimum of $2.5M across the
portfolio
• Building managed by separate facility
managers
• Submit proposal (RFP) in less than one
month
![Page 14: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/14.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 14
Siemens challenges
• Minimal response time (proposal)
• Incomplete/inaccurate RFP data
• Limited resource availability internally and
externally
• Contracting
• Cost conversions with fluctuations in rate
exchange
• Site visits to 11 campuses in 8 countries
and 9 time zones
• Project paid by corporate but executed by
local site management
• Limited execution timeline
![Page 15: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/15.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 15
Walkthrough findings:
Variance from specs in RFP
• 23% more equipment than listed
• Over 30 central plants and over 70 chillers
• 1000’s of terminal units
• 100’s of miscellaneous unique pieces of HVAC equipment
Technical complexities
• Load disaggregation estimates understated total manufacturing load
• Eight different BAS systems of varying age and complexity
Organizational challenges
• Difficult to gain access to sites from local site managers
• Lack of data transparency made it difficult to communicate level of
inefficiency
![Page 16: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/16.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 16
• Two commissioning components
1. Planning, finding, quantifying, reporting
2. Implementing, verifying
• Approximately 60-65% of the budget was allocated to component #1
• The remaining 35-40% of the budget was set aside to implement low cost
corrective actions and conservation measures
Assessment and
InvestigationImplementation
Project Budget Breakdown
![Page 17: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/17.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 17
Program Process Flow
Implementation
Assessment
Investigation
Hand Off
![Page 18: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/18.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 18
A journey of one thousand miles…
Starter pistol fired, only a few started running (immediate challenges)
• Assembling and deploying our teams
• Contracting and getting POs
• Scheduling and access
• Lots of deferred maintenance items
![Page 19: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/19.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 19
The Siemens Team
Site Team (typ.)
Lead Energy Eng.
Engineering QA/QC
Tool Development
Operations Support
Project Manager
Asia
Project Manager
Europe
Global Commissioning Program Team
Program Manager
Regional PM
North American Sites
Regional PM
Europe/Asia Sites
Program Admin.
Engineering Technical
Support Mgr.
IT Manager
Finance/Business
Admin
National Ops Mgr.
Executive Sponsor
Client Relationship
Mgr
Legal
Site Scheduling
Support
Booking/Invoicing
Collections
Controller
Commissioning Eng.
Energy Engineer
Project Manager
Senior Technician
Mechanic
Site Team (typ.)
Commissioning Eng.
Energy Engineer
Project Manager
Senior Technician
Mechanic
Site Team (typ.)
Commissioning Eng.
Energy Engineer
Project Manager
Senior Technician
Mechanic
Subcontracted
Commissioning
Team
Customer
Deliverables
Report
Reviewers
QA/QC
Contracting
![Page 20: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/20.jpg)
Consumption
Results
4 Phase Commissioning
Process
Building Commissioning Market Drivers
Pilot Project
4 Phase
Commissioning Process
Results
Global Project
![Page 21: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/21.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 21
Tasks:• Kick-off of projects/schedule weekly meetings
• Align teams
• ID Current Facility Requirements
• Develop and execute commissioning plans
• ID corrective actions
Challenges:• ID Current Facility Requirements
• Goal misalignment between
corporate and field management
• Scheduling building occupant interviews
• Vetting corrective actions and implementation
Implementation
Hand-off
Assessment
Investigation
Assessment Phase
![Page 22: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/22.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 22
Tasks:• Manage teams (weekly updates)
• Internal
• External site team
• Corporate
• ID conservation measures
• Update commissioning plans
• Prioritize and present
conservation measures
Challenges:• Managing timeline
• Quality of analysis (master CM
tool)
• Implementation Plan
Implementation
Hand-off
Assessment
Investigation
Investigation Phase
![Page 23: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/23.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 23
Global project initial improvements
Corrective Actions
• Sensor verification/replacement
• AHU maintenance
• Damper seals
• Damper actuation
• Air filters
• Leaking valves
• VAV box functionality
• Minor programming modifications
Conservation Measures
• Temperature setpoint and over-
ventilating
• V in VFD means variable
• Night setback
• OA, MA, RA damper modulation
• Air and water balancing
• Major sequence of operation
modifications
![Page 24: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/24.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 24
Tasks:• Implementing corrective actions
and conservation measures
• Verifying savings and
performance
• Updating commissioning plans
• Create Persistence Phase plan
Challenges:• Managing timeline
• Spending all the budget in
the allotted timeframe
• Coordinating with
subcontractors and site teams
Project Development and Multi-
facility planning
Implementation
Hand-off
Assessment
Investigation
Implementation Phase
![Page 25: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/25.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 25
Informed Advisors:
• VP Energy (portfolio)
• Portfolio Program Manager
• Regional Project Managers
ImplementDecisionIssue
Identified
Siemens Team
Site Manager
Engineer
Engineer
Sr. Controls Technician
“Other Staff”Project
Manager
Project Team and
Meeting Structure
created to support a
Fast Track Workflow
Global project initial improvements
![Page 26: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/26.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 26
Implementation
Issue Identified
Recommend Corrective
Action
Decision Made
Remediation Executed
Corrective Action Verified
Weekly Status
Meeting
Assessment
Investigation
Hand Off
Global project initial improvements
![Page 27: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/27.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 27
Tasks:• Preparing final reports
• Preparing site trainings
• Preparing corporate PowerPoint presentation
Challenges:• Running out of TIME
• QA/QC of final reports
• Sharing implementation dollars
Implementation
Hand-off
Assessment
Investigation
Project Development and Multi-
facility planning
Hand-off Phase
![Page 28: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/28.jpg)
Consumption
Results
Building Commissioning Market Drivers
Pilot Project
Results
Global Project
5 Phase Commissioning
Process
4 Phase Commissioning Process
![Page 29: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/29.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 29
Energy Savings Results
![Page 30: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/30.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 30
Environmental Metrics
Key Performance Metric Result
Emissions Reduction 20,103 Mt CO2e
Criteria Pollutant Reduction MT NOx
Area preserved from Deforestation 161 acres
Cars taken off of the road 4,384 cars
![Page 31: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/31.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 31
Lessons learned (Internal)
1 Are your teams ready? Is management ready?
2 Contracting globally – many issues
3 Make sure all internal stakeholders are identified early
4 Weekly meetings with PM and site decision maker
5 Intangibles
![Page 32: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/32.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 32
Lessons learned (External-site and corporate)
1Corporations and their internal teams must be aligned
prior to the start
2 Full transparency of savings / cost data
3 Weekly meetings with PM and site decision maker
4 Building commissioning is a great investment
![Page 33: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/33.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 33
• Post project pull-through implementations
• CAPEX Planning
• Leverage Technology
• Commissioning of additional sites
![Page 34: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/34.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 34
Thank you!
Mike Chimack
Director, Energy Services, Building Technologies Division,
Siemens Industry, Inc.
Phone: (847) 941-6191
Email: [email protected]
Steven Dodd, Senior National Sales Manager, EMP, LEED
Green, Building Technologies Division, Siemens Industry, Inc.
Phone: (804) 925-7656
Email: [email protected]
![Page 35: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/35.jpg)
CxEnergy 2016 Conference Course Number: CXENERGY1614
Restricted © Siemens Industry, Inc. 2016 All rights reserved.
Page 35
Questions & additional resources
Learn more about Commissioning
http://usa.siemens.com/commissioning
Additional resources
Commissioning: An essential
Part of a Comprehensive Energy
Strategy
Three Big Myths about Big DataConsulting-Specifying Engineer Magazine,
March 2016
http://www.csemag.com/magazine.html
![Page 36: Completing a Global Enterprise Building Commissioning ...€¦ · Six months to complete an existing building commissioning program at 12 facilities in 8 countries is daunting. This,](https://reader035.fdocuments.us/reader035/viewer/2022071105/5fdf72f350c2d5525636a687/html5/thumbnails/36.jpg)
This concludes The American Institute of Architects Continuing Education Systems Course