Comparing Parallel ERD and Oxidation Pilot Tests in a Low ...
Transcript of Comparing Parallel ERD and Oxidation Pilot Tests in a Low ...
LAKE
B-190
B-189
B-1
95
B-191
"
INACTIVE POND
(COVERED)
B-1OX-1
OX-2OX-2'
B-2
OX-3
OX-5OX-4
OX-8OX-7
OX-7'OX-8' OX-6
MW45
RW03MW19
RW02
MW18R
MW54
LEGEND
INJECTION BORING
RESPONSE ACTION MONITOR WELL LOCATION & NUMBER
FENCELINE
FIGURE 2 - WESTERN INJECTION BORING LOCATIONS CORPUS CHRISTI TECHNICAL CENTERCELANESE, LTD.Project No.: 60339332
Issue Status: DRAFT
Fourth International Symposium on Bioremediation and Sustainable Environmental TechnologiesMay 22-25, 2017 | Miami, Florida
Groundwater impacts have been identified at a closed chemical research facility in the gulf coast of Texas. Two distinct plumes are present without comingling
Comparing Parallel ERD and Oxidation Pilot Tests in a Low Permeability AreaBryon Dahlgren P. E. (AECOM, Atlanta, GA) | Jing Zhou, PhD (AECOM Atlanta, GA)
www.aecom.com
Introduction Activities Results
• 22,400 pounds of persulfate activated ferric oxide compound was injected with 7,000 gallons of water
Direct push activities for chlorobenzene
• Targeted injections were completed in January 2016• Chemical oxidation was selected for treatment for chlorobenzene• Enhanced Reductive Dechlorination (ERD) was selected as treatment for
carbon tetrachloride• Direct push technology was used for each injection• Both activities were completed in a single mobilization• These activities allow direct comparison of reductive and oxidation processes
under otherwise identical field conditions
• Pre-remediation carbon tetrachloride
• Off-site concentrations recently identified above the standard of 0.5 mg/L
• Remediation was planned
• Pre-remediation chlorobenzene
• Off-site concentrations are below the standard of 10 mg/L
• Concentrations near boundary are close to limit and remediation was planned
The site geology is primarily silty sands with low hydraulic conductivity. The groundwater flow velocity is estimated to be less than one-half foot per year. Therefore, injection activities present a particular challenge. Two remediation pilot studies were completed to address separate plumes. Chemical oxidation was applied to a chlorobenzene plume and Enhanced Reductive Dechlorination (ERD) was applied to a carbon tetrachloride plume. The objectives of the pilot studies were:• Determine effectiveness of remedial
technologies under site conditions• Inform design of further remediation and/or
migration control measures• Eliminate highest concentrations
• 8,100 pounds of reductive agent was injected with approximately 3,000 gallons of water
• Reductive agent included primarily carbon source with zero valent iron, and proprietary enhancements
Direct push activities for carbon tetrachloride
Conclusions
• Consistent site conditions appear to have produced mirrored results for oxidative and reductive processes in this study
• Despite rapid increase in ORP, the chlorobenzene concentration did not change initially following injection. After a delay, concentrations improved significantly
• Carbon tetrachloride concentrations dropped immediately but rebounded quickly
• Contact is the key• Oxidation effectiveness was delayed by transport to
the right location• Reduction was immediately effective, but carbon
source did not persist long enough to address porespace diffusion
0
5
10
15
20
25
30
35
40
Oct‐12 May‐13 Nov‐13 Jun‐14 Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17
Concen
tration (m
g/L)
Date
Chlorobenzene at Target Well
Pre‐injectionInitial
post injection
recent results
0
0.5
1
1.5
2
2.5
Nov‐13 Jun‐14 Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17
Concen
tration (m
g/L)
Date
Carbon Tetrachloride at Target Well
Pre‐injection
Initial post injection
recent results
• Chlorobenzene results showed no change in target concentrations for several quarters
• Results fluctuated between 30 and 37 mg/L
• Then concentrations dropped significantly, meeting criteria
• Current concentrations are approximately 5 mg/L
• Carbon tetrachloride concentrations immediately dropped more than 75%.Rebound occurred shortly thereafter with a recovery to approximately 50% of initial concentrations
• Total organic carbon has dropped to approximately pre-injection levels
• Further remediation is not expected based on work completed
From Darcy's Law: average linear velocity =
Assumed parameter values:Minimum Maximum
gradient (ft/ft) 1.17E-03 1.70E-03hydraulic conductivity (cm/s) 5.35E-05 5.35E-05effective porosity 3.00E-01 2.50E-01
Minimum velocity:v = ( 1.17E-03 ) x ( 5.35E-05 ) = 2.09E-07 cm/s
7.09E-03 inches/day2.16E-01 ft/year
Maximum velocity:v = ( 1.70E-03 ) x ( 5.35E-05 ) = 3.64E-07 cm/s
1.24E-02 inches/day3.76E-01 ft/year
Notes:cm/s = centimeters per secondinches/day = inches per dayft/year = feet per yearHydraulic conductivity values based on October 2015 slug test on MW-64.Gradient values from November 2016 potentiometric surfaces.Porosity values from TWC-CME report 1986.
Table 6
0.30
0.25
Flow Velocity Calculations – November 2016Celanese Ltd. Corpus Christi Technical Center
gradient x hydraulic conductivityeffective porosity
1 of 1
S-29
STORES WAREHOUSEB-216
RAMP
HOUSEGUARDB-220
B-2
05
B-212
B-204
B-203B-180
B-133B-129 B-107
B-163
B-132
LAYDOWN YARD
Avenue "E"
(COVERED)
(COVERED)
B-150
B-215
POND #10INACTIVE
CONTROL BLDG.B-206
B-1
83
B-211
BLDG
B-217
B-190
B-189
B-1
59
B-1
68
B-2
01
BLDGSTAGING
TOTE
B-225
B-207B-161
B-200
B-148 B-112
B-2
02
B-111
B-1
85
B-1
13
B-199
B-182
B-147
B-1
87 B-160
B-188
B-156
B-157
B-198 B-194
B-1
95
B-213
B-149
B-114
B-210
B-1
58
B-223
B-166
BLDGANALYZER
B-214
B-1
45
B-167
TOWERCOOLING
B-130
B-191
"90"
STR
EE
T
Avenue "S"
(COVERED)CLOSED
BURN PIT
"100
" STR
EE
T
Avenue "P"
Avenue "M"
Avenue "U"
"70"
STR
EE
T
"50"
STR
EE
T
"60"
STR
EE
T
"50"
STR
EE
T
Avenue "S"
Avenue "W"
B-184
B-144
"80"
STR
EE
T
(COVERED)
POND #6INACTIVE
B-155
B-146
LAKE
Bld
g.S
tora
geTe
mpo
rary
Bldg.Storage
Temporary
FLARE
SUMP
drainstorm
Sto
rage
Tem
pora
ry
Temporary Storage
Bldg.Storage
Temporary
Bldg.Storage
Temporary
Bldg.Storage
Temporary
S-28
1.0
10.0
1.0
1.0
CELANESE, LTD.CORPUS CHRISTI TECHNICAL CENTER
FIGURE 13CHLOROBENZENE
JUNE 2016CONCENTRATIONS IN GROUNDWATER
LEGEND
MONITORING WELL
CHLOROBENZENE CONCENTRATION IN GROUNDWATER (mg/L)
CHLOROBENZENE ISOCONTOUR (mg/L) (DASHED WHERE INFERRED)
NOT DETECTED AT OR ABOVE THE LABORATORY REPORTING LIMIT
PROTECTIVE CONCENTRATION LEVEL = 10 mg/L
MW-61
0.4
1.0
<
S-29
STORES WAREHOUSEB-216
RAMP
HOUSEGUARDB-220
B-2
05
B-212
B-204
B-203B-180
B-133B-129 B-107
B-163
B-132
LAYDOWN YARD
Avenue "E"
(COVERED)
(COVERED)
B-150
B-215
POND #10INACTIVE
CONTROL BLDG.B-206
B-1
83
B-211
BLDG
B-217
B-190
B-189
B-1
59
B-1
68
B-2
01
BLDGSTAGING
TOTE
B-225
B-207B-161
B-200
B-148 B-112
B-2
02
B-111
B-1
85
B-1
13
B-199
B-182
B-147
B-1
87 B-160
B-188
B-156
B-157
B-198 B-194
B-1
95
B-213
B-149
B-114
B-210
B-1
58
B-223
B-166
BLDGANALYZER
B-214
B-1
45
B-167
TOWERCOOLING
B-130
B-191
"90"
STR
EE
T
Avenue "S"
(COVERED)CLOSED
BURN PIT
"100
" STR
EE
T
Avenue "P"
Avenue "M"
Avenue "U"
"70"
STR
EE
T
"50"
STR
EE
T
"60"
STR
EE
T
"50"
STR
EE
T
Avenue "S"
B-184
B-144
"80"
STR
EE
T
(COVERED)
POND #6INACTIVE
B-155
B-146
LAKE
Bld
g.S
tora
geTe
mpo
rary
Bldg.Storage
Temporary
FLARE
SUMP
drainstorm
Sto
rage
Tem
pora
ry
Temporary Storage
Bldg.Storage
Temporary
Bldg.Storage
Temporary
Bldg.Storage
Temporary
S-28
0.5
0.05
0.05
0.5
0.5
5.0
5.00.5
0.05
0.05
CELANESE, LTD.CORPUS CHRISTI TECHNICAL CENTER
FIGURE 10CARBON TETRACHLORIDE
NOVEMBER 2016CONCENTRATIONS IN GROUNDWATER
LEGEND
MONITORING WELL
CARBON TETRACHLORIDE CONCENTRATION IN GROUNDWATER (mg/L)
CARBON TETRACHLORIDE ISOCONTOUR (mg/L) (DASHED WHERE INFERRED)
NOT DETECTED AT OR ABOVE THE LABORATORY REPORTING LIMIT
PROTECTIVE CONCENTRATION LEVEL = 0.50 mg/L
MW-61
0.16
0.05
<
Carbon TetrachlorideNovember 2016
ChlorobenzeneNovember 2016
Avenue "W"
MW57
IR-1IR-1'IR-2
IR-3IR-4
IR-2'
MW46MW56
LEGEND
INJECTION BORING
RESPONSE ACTION MONITOR WELL LOCATION & NUMBER
FENCELINE
FIGURE 1 - EASTERN INJECTION BORING LOCATIONS CORPUS CHRISTI TECHNICAL CENTERCELANESE, LTD.Project No.: 60339332
Issue Status: DRAFT