ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid...

12
ColumbiaGrid Update WECC PPC June 11, 2010 1

Transcript of ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid...

Page 1: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

ColumbiaGrid Update

WECC PPCJune 11, 2010

1

Page 2: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

2

Page 3: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Biennial Plan Update Approved by the

ColumbiaGrid Board of Directors on

February 17, 2010

Page 4: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.
Page 5: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Updated Information

on Major

Regional Projects

Page 6: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Historical Usage Information

Northwest to British Columbia

Page 7: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

2010 Transmission System Assessment

• Assessments are completed each year• The 2010 Assessment will be complete in July

– Summer and winter conditions– 5 and 10 years into the future– Problems identified can be addressed by the

transmission owners or through ColumbiaGrid Study Teams

• Transmission owners are also using the assessment to help demonstrate compliance with NERC Reliability Standards

Page 8: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Northwest Area Coordinator

• ColumbiaGrid officially began performing this function for the Northwest area on March 5, 2010– Previously performed by BPA

Page 9: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

9

• Mid Columbia Area– Transmission expansion plan complete– Working out cost allocation

• Puget Sound Area– Transmission expansion plan nearing completion– Five projects

• Wind Integration Study Team– Joint with NTTG– Two Efforts

• Dynamic scheduling technical limits• Remote versus local generation

• Cross Cascades Area– New study team formed

Other Planning Activities

Page 10: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Middle Columbia Area Preferred Plan

Page 11: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Puget Sound Area Preliminary Plan

Page 12: ColumbiaGrid Update WECC PPC June 11, 2010 1. 2 Biennial Plan Update Approved by the ColumbiaGrid Board of Directors on February 17, 2010.

Cross Cascades Study Team