Columbia RiverColumbia RiverWater Management ProgramWater Management Program
(CRWMP)(CRWMP)
Review of Year OneReview of Year One
Upper Crab Creek Planning Unit MeetingUpper Crab Creek Planning Unit MeetingApril 17, 2007April 17, 2007
What’s the Problem?What’s the Problem?
• 360 existing water rights subject to interruption during summer low flows of drought years
• 465 applications for new water rights on file
• Future growth of municipalities and agricultural industry in peril
• Fish needs of tribes, commercial fishermen, and recreational fishermen in jeopardy
Columbia River Bill—Columbia River Bill—What Does Legislation What Does Legislation
Do?Do?
• Aggressively pursue new water supplies for both instream and out-of-stream uses
• New water supplies from both conservation and storage
• Formula for allocation of new water –1/3 for instream flows; 2/3 for out-of-stream uses
• Establishes mechanism for Voluntary Regional Agreements
• Future water supply and demand forecast
How Are We Going To Pay For It?How Are We Going To Pay For It?And Who’s Going To Do The Work?And Who’s Going To Do The Work?
Legislation established a water supply development account with authorization for bonds up to $200 million
– Capital Budget: $20 million FY 05-07; projected investment of $50 million for FY 07-09
– Operating Budget: $2 million and 15 new FTEs
CRWMP Program Goals & CRWMP Program Goals & ObjectivesObjectives
Conservation MeasuresPromote water conservation by providing grants for water conservation projects, and by encouraging development of “voluntary regional agreements”.
Optimize Existing InfrastructureOptimize management of existing Columbia Basin Project infrastructure such as Banks Lake, Pinto Dam, Potholes Reservoir, and associated water delivery systems (canals & ditches).
Construct New StorageConstruct off-channel reservoirs to store a portion of Columbia River winter flows for release in the summer months, to meet the needs of both instream and out-of-stream water users.
Contents - An assessment of potential programmatic impacts - Identification & assessment of a few “early actions”
EIS evaluated: - Programmatic elements include storage, conservation,
voluntary regional agreements, account administration, etc.
- Evaluation of policy alternatives - Early actions (Lake Roosevelt drawdown, Potholes
alternative feed route, CSRIA VRA) Schedule: - Draft EIS issued October 5, 2006 - Final EIS issued February 15, 2007
Environmental Impact StatementEnvironmental Impact Statement
How To…
- Evaluate and fund proposed storage and conservation projects?
- Calculate net water savings from conservation?
- Define “acquisition” and “transfer”?
- Initiate and process Voluntary Regional Agreements?
- Define “no negative impact” to instream flows?
- Define main channel and one-mile zone?
- Coordinate VRA mitigation and processing of new water rights?
- Coordinate VRA and non-VRA processing of new water rights?
- Fund projects associated with VRAs?
Policy AlternativesPolicy Alternatives
Information ManagementInformation ManagementEnormous effort initiated to construct a comprehensive Columbia River water resources information database
Voluntary Regional Voluntary Regional AgreementsAgreements
A VRA is a voluntary agreement between Ecology and a group of water users
Consultation Requirements - 60-day consultation with selected groups:
County governmentsWatershed planning unitsWDFWFederal agenciesTribes
- Post-consultation negotiation with proponent - 30-day public comment period
Ecology recently completed negotiations for a VRA with the Columbia-Snake River Irrigators Association. The public comment period will start soon.
Purpose: Replace withdrawals of groundwater from declining Odessa aquifer with Columbia Basin Project surface water (Columbia River water)
Schedule:
- Appraisal-level report completed in spring 2007
- EIS to be completed by summer 2010
Odessa Subarea Special StudyOdessa Subarea Special Study
Lake Roosevelt Lake Roosevelt DrawdownDrawdown
Purpose: Withdraw up to 102K acre-feet of water stored in FDR Lake to provide water for:- Odessa Subarea- Municipal and industrial needs- Interruptible water rights during drought years- Instream flow augmentation
Actions: - Colville Tribe environmental assessment - Supplemental EIS required - Water right permitting decisions by Ecology
Lake Roosevelt Water ElevationsWet - Dry - Average Water Years
1200
1210
1220
1230
1240
1250
1260
1270
1280
1290
1300
1-Jan 31-Jan 2-Mar 1-Apr 1-May 31-May 30-Jun 30-Jul 29-Aug 28-Sep 28-Oct 27-Nov 27-Dec
Date
Ele
vatio
n
1997 (Wet) 2003 (Dry) 2002 (Average)
Lake Roosevelt Water ElevationsWet - Dry - Average Water Years
1200
1210
1220
1230
1240
1250
1260
1270
1280
1290
1300
1-Jan 31-Jan 2-Mar 1-Apr 1-May 31-May 30-Jun 30-Jul 29-Aug 28-Sep 28-Oct 27-Nov 27-Dec
Date
Ele
vatio
n
1997 (Wet) 2003 (Dry) 2002 (Average)
Purpose: Increase operational flexibility and reliability of Columbia Basin Project by providing an additional route for conveying project water to Potholes Reservoir
Schedule:
- Design/NEPA Environmental Assessment completed July 2007
- Construction initiated during fall 2007 or spring 2008?
Potholes Supplemental Feed Potholes Supplemental Feed RouteRoute
Purpose:Evaluate potential for large, off-channel storage site or sites to store between 1.1 and 2.3M acre-feet of water.
Schedule:- Appraisal-level study underway.
- Feasibility-level study will be initiated in 2009, if funded.
Columbia Off-Channel StorageColumbia Off-Channel Storage
Purpose: Evaluate alternatives to store water to improve anadromous fish habitat, reliability of irrigation supplies, and availability of water for municipal needs. Several alternatives being evaluated.
Schedule: - Appraisal-level study completed in October 2006 - Yakima Basin Storage EIS Scoping in January 2007 - Feasibility study and Environmental Impact Statement to be completed by November 2008
Yakima Basin StorageYakima Basin Storage(Black Rock Reservoir)(Black Rock Reservoir)
2006 Report to Legislature
Columbia River Water Supply Inventory First report in November 2006 Annual inventory updates (RCW 90.90.040)
Long-Term Water Supply and Demand Forecast
First report in November 2006
Updates every 5 years
2006 Reports2006 Reports
KConsultation with a wide variety of stakeholders
KConsultation with other states with Columbia River interests
KConsultation with Canada
KSelection and implementation of initial projects
Year Two and BeyondYear Two and Beyond
Project selection and implementation process:
KEstablish & refine funding criteria
KScreen and rank proposed projects, with review and recommendations by CRWMP Technical Advisory Group
KSelection of projects to be funded, with decisions made by Ecology in consultation with CRWMP Policy Advisory Group and watershed planning units
KApproval from Legislature to spend funds in account
Project Selection—Project Selection—““Harmonization” with Watershed Harmonization” with Watershed