Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County...
Transcript of Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County...
![Page 1: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/1.jpg)
Columbia CountyHighway “V”
Public Involvement Meeting
August 9, 2018
![Page 2: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/2.jpg)
Project Team
• Columbia County– Chris Hardy, Highway and Transportation Commissioner
• Design Team– Dan Schrum, Ayres Associates– Eric Sorensen, Ayres Associates
• Wisconsin Department of Transportation’s Management Consultant Representatives– Bill Biesmann, KL Engineering– Mark Westerveld, WisDOT
![Page 3: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/3.jpg)
Topics
• Project History • Current Project Limits• Purpose and Need• Project Overview• Project Elements• Real Estate• Construction• Schedule
![Page 4: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/4.jpg)
Project History
![Page 5: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/5.jpg)
Current Project Limits
• STH 113 to Rapp Road
• Pavement Reconstruction
• Intersection Realignment
• Re-deck of the Bridge on the Causeway
![Page 6: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/6.jpg)
Project Purpose and Need
• Address deteriorating pavement, roadside drainage and deteriorating bridge deck on the Spring Creek Inlet bridge
• The need is defined by the physical, structural and geometric deficiencies along with social demands
![Page 7: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/7.jpg)
Project Purpose and Need
![Page 8: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/8.jpg)
Project Overview
![Page 9: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/9.jpg)
Project Elements - Intersections
• STH 113 Intersection
• RR Crossing
• Old Sauk and Shamrock Roads Intersection Realignment
![Page 10: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/10.jpg)
Project Elements – CTH V
• On-street parking• Bike and pedestrian accommodations• Curb and gutter
![Page 11: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/11.jpg)
Project Elements - Causeway
![Page 12: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/12.jpg)
Real Estate
• Right of way acquisition• What is a Temporary
Limited Easement (TLE)?• Who will I talk to? • When will the process
start?
![Page 13: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/13.jpg)
Project Construction - 2019
• Construction schedule start after July 4th weekend, completed by mid-October 2019. • Removals – pavement• Underground work
storm sewer• Concrete curb and gutter,
sidewalk and driveways• Railroad crossing• Bridge work• Asphalt paving• Signing and Marking
• Note: Activities such as utility relocations and tree removal will most likely occur prior to the contractor start date
![Page 14: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/14.jpg)
Project Construction - 2019
• CTH V – closed to through traffic with a signed detour in place• Locals and businesses will still have
access• 2 complete closures
• Structure work – after Labor Day for several weeks
• Railroad crossing work ~ 3 weeks• Old Sauk and/or Shamrock
would be required to remain open to STH 113
![Page 15: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/15.jpg)
Project Construction - 2019
• Concerns during construction• Who do I talk to?• Accessing driveways• Parking • Mail• Fire Numbers
![Page 16: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/16.jpg)
Design Schedule
• Preliminary Design (30%) Spring 2017• Public Meeting Fall 2017• Environmental Document Winter 2017/18• Preliminary Design (60%) Winter 2017/18• Public Meeting Summer 2018• Begin Acquisition of Easements Summer 2018• Final Design Plans Fall 2018• Construction Summer 2019
to Fall 2019
![Page 17: Columbia County Highway “V” - Lodi Bridge... · 8/9/2018 · Project Team • Columbia County – Chris Hardy, Highway and Transportation Commissioner • Design Team – Dan](https://reader036.fdocuments.us/reader036/viewer/2022063009/5fc1606b5f66fc622061edc7/html5/thumbnails/17.jpg)
Thank You!
Please fill out a comment form
Your input, participation and comments are appreciated
Project ContactEmail address:[email protected]