Coburg (Handing Over)

8
Handing Over Checklist (Authorities) Setia Eco Park Authority Status Issue to Fo 1 TNB Approved SL Approved No iss TMB Approved No iss 2 TNB By PJL TNB KM Ap SL Submitted To follow up TMB (External) Submitted To follow up 3 TNB By Others TNB KM Ap SL Submitted To follow up TMB (External) Pending To sub 4 Street Lighting Phase 3 (Done) Setia Eco Glades Authority Status Issue to Fo 1 TNB Approved SL (MPS) Approved No iss Fiber at Home Approved To submit amen 2 TNB Approved SL (MPS) Approved No iss Fiber at Home Approved To submit amen 3 TNB BY LMC To sub SL (MPS) Pending To subm Fiber at Home Pending To sub 4 TNB Approved SL (MPS) Submitted No Iss Fiber at Home Approved To submit amen 5 TNB By LMC To sub SL (MPS) Pending To sub Fiber at Home Pending To sub 6 TNB Pending To submit TNB Inf SL (MPS) KIV KIV Fiber at Home KIV KIV 7 TNB Approved SL (MPS) Approved No Iss Fiber at Home Approved To submit amen 8 TNB Pending To resubmit. Par SL Pending To sub Fiber at Home Pending To sub TNB By LMC To sub Phase 8E (43 Units) To follow TNB Charge Phase 12 (139 Units) Phase 16 (90 Units) Overall SL Handing Over To conduct final remaining phases Parcel A1 (104 Units) To follow TNB Charge Parcel A2 (115 Units) To follow TNB Charge Parcel B1 (82 Units)- New Project (2015) Parcel B2 (110 Units) To follow up w supply connecti Parcel C3- New Project (2015) Parcel G1 (25 Units)- Tan Seri Liew Parcel G2 (75 Units) To follow TNB Charge Parcel G3 (83 Units) Parcel G5 (240

description

electrical

Transcript of Coburg (Handing Over)

Page 1: Coburg (Handing Over)

Handing Over Checklist (Authorities)

Setia Eco Park Authority Status Issue to Follow Up

1 Phase 8E (43 Units)

TNB Approved To follow TNB Connection Charges.

SL Approved No issue

TMB Approved No issue

2 Phase 12 (139 Units)TNB By PJL TNB KM Approved

SL Submitted To follow up approvalTMB (External) Submitted To follow up approval

3 Phase 16 (90 Units)TNB By Others TNB KM Approved

SL Submitted To follow up approvalTMB (External) Pending To submit

4 Street Lighting Phase 3 (Done)

Setia Eco Glades Authority Status Issue to Follow Up

1 Parcel A1 (104 Units)

TNB Approved To follow TNB Connection Charges.

SL (MPS) Approved No issues

Fiber at Home Approved To submit amendment plan

2 Parcel A2 (115 Units)TNB Approved To follow TNB Connection Charges.

SL (MPS) Approved No issuesFiber at Home Approved To submit amendment plan

3TNB BY LMC To submit

SL (MPS) Pending To submit Fiber at Home Pending To submit

4 Parcel B2 (110 Units)TNB Approved

SL (MPS) Submitted No IssuesFiber at Home Approved To submit amendment plan

5TNB By LMC To submit

SL (MPS) Pending To submitFiber at Home Pending To submit

6TNB Pending To submit TNB Infra Application

SL (MPS) KIV KIVFiber at Home KIV KIV

7 Parcel G2 (75 Units)TNB Approved To follow TNB Connection Charges.

SL (MPS) Approved No IssuesFiber at Home Approved To submit amendment plan

8 Parcel G3 (83 Units)TNB Pending To resubmit. Partial approved

SL Pending To submitFiber at Home Pending To submit

9 Parcel G5 (240 Units)TNB By LMC To submit

Overall SL Handing Over

To conduct final inspection for remaining phases & handing over

Parcel B1 (82 Units)- New Project (2015)

To follow up with TNB for supply connection. (Urgent)

Parcel C3- New Project (2015)

Parcel G1 (25 Units)- Tan Seri Liew

Page 2: Coburg (Handing Over)

9 Parcel G5 (240 Units) SL Pending To submit Fiber at Home Pending To submit

10 RING RoadTNB Approved To submit bridge crossing detail.

SL Approved To submit Fiber at Home Approved To submit gantry crossing detail

11 SEG Interchange

TNB Approved Obtained TNB Acceptance LetterSL (LLM/PLUS) Pending Pending LMR.

SL (MPS) Approved No issueTime Dot Com Approved Obtained TIME Acceptance Letter

Setia Eco Hill Authority Status Issue to Follow Up

1

TNB (33kV,11kV) Approved Obtained TNB Acceptance Letter

SL (JKR) Approved Final Inspection & Sokongan SL (LLM/LEKAS) Approved Final Inspection & Sokongan

Telekom Approved Obtained Telekom Acceptance Letter

2 SEH Intchg (Eco Link)

TNB Approved Meter Installation (Pending)

SL (JKR) Approved Final Inspection & Sokongan SL (MPKJ) Approved To follow up Approval Letter Telekom Approved Obtained Telekom Acceptance Letter

SEH Intchg (Relocation)

Page 3: Coburg (Handing Over)

Issue to Follow Up

To follow TNB Connection Charges.

No issue

No issueTNB KM Approved

To follow up approvalTo follow up approval

TNB KM ApprovedTo follow up approval

To submit

Issue to Follow Up

To follow TNB Connection Charges.

No issues

To submit amendment plan

To follow TNB Connection Charges. VP on April 2016

No issuesTo submit amendment plan

To submitTo submit To submit

No IssuesTo submit amendment plan

To submitTo submitTo submit

To submit TNB Infra Application

KIVKIV

To follow TNB Connection Charges.

No IssuesTo submit amendment plan

To resubmit. Partial approvedTo submitTo submitTo submit

To conduct final inspection for remaining phases & handing over

VP on Dec 2015 (Urgent)

To follow up with TNB for supply connection. (Urgent)

Page 4: Coburg (Handing Over)

To submit To submit

To submit bridge crossing detail.To submit

To submit gantry crossing detailObtained TNB Acceptance Letter

Pending LMR. No issue

Obtained TIME Acceptance Letter

Issue to Follow Up

Obtained TNB Acceptance Letter

Final Inspection & Sokongan Final Inspection & Sokongan

Obtained Telekom Acceptance Letter

Meter Installation (Pending)

Final Inspection & Sokongan To follow up Approval Letter

Obtained Telekom Acceptance Letter

Page 5: Coburg (Handing Over)

Project Status

Setia Eco Park Issue to Follow Up

1

1. To issue EI to TNH for additional special lot (upon confirmation from BES)2. To issue EI to CSB for revised landscape lighting position

3. To issue EI to CSB for additional meter panel for SL & LD FP

4. To follow up with the rectification works for collapsed SL pole.

5. EOT accessment for Phase 8E (Infa)

6. To issue EI for omission of CCTV breaker (PABX)

2 To prepare infra tender

Setia Eco Glades Issue to Follow Up

11. To issue EI for clubhouse air con point

2. To follow with CICET for rectification works for genset room

2 1. To issue EI for special lots upon confirmation from client.

3 Infra (PKG A- KJ)1. TNB handing over (Rodding Test and etc) to TNB for Parcel B2- URGENT !!2. To issue EI for omission of ducting for security CCTV cable.3. To issue EI for revised landscape lighting (tapping from SL)

4 Infra (PKG B- KEMJ)1. To issue EI for omission of ducting for security CCTV cable.2. To issue EI for revised landscape lighting (tapping from SL)3. EOT accessment

51. To follow up with MME for rectification works for gantry structure2. To follow up with MME/TNB for handing over acceptance. 3. To follow up with MME for as built drawing & O&M manual

61. To follow up with MME/PLUS for SL acceptance letter (Realignment Works)2. To follow up with MME for as built drawing & O&M manual

7 Infra (A1-Landscape) 1. To follow up GW Bersekutu for shop drawing & sample submission

7 Infra (Water Fountain) 1. Testing & Commissioning with Sri Lantai (Fountain 1,2,3,4)

10 SEG Interchange

1. To re-submit after confirmation of final LMR or other approach method.2. To issue EI to Juang Antara for jointing of sub main cable under MME3. To issue EI to Juang Antara for Temporary power cable under MME4. To prepare letter for material approval.

7 Infra (A2-Landscape) To prepare BQ,drawing for tender.

7 To prepare BQ,drawing for tender.

7 Infra (B1,C3,G3,G5) To prepare BQ,drawing for tender.

Setia Eco Hill Issue to Follow Up

1 SEH Intchg (Relocation)

2 SEH Intchg (Eco Link)

Phase 8E (43 Units)- Building & Infra

Infra Tender (Phase 12 & 16)

Buidling -Parcel A1 (104 Units)

Building- Parcel A2 (115 Units)

Infra (B2 Gallery-Mega Mayang)

Infra (Realignment-Mega Mayang)

Infra (Main Road- Waterway)

Refer to the site minutes for remaining outstanding works for Cablecon & Mega Mayang

Page 6: Coburg (Handing Over)

2 SEH Intchg (Eco Link)

Setia Alam Issue to Follow Up

1 Baiduri1. SMATV Issue and review new proposal submitted by SEP

2. To follow up with SEP for revised schematic diagram for PE endorsement.2. To follow up with SEP for O&M Manual

Refer to the site minutes for remaining outstanding works for Cablecon & Mega Mayang

Page 7: Coburg (Handing Over)

Issue to Follow Up1. To issue EI to TNH for additional special lot (upon confirmation from BES)2. To issue EI to CSB for revised landscape lighting position

3. To issue EI to CSB for additional meter panel for SL & LD FP

4. To follow up with the rectification works for collapsed SL pole.

5. EOT accessment for Phase 8E (Infa)

6. To issue EI for omission of CCTV breaker (PABX)

To prepare infra tender

Issue to Follow Up

1. To issue EI for clubhouse air con point

2. To follow with CICET for rectification works for genset room

1. To issue EI for special lots upon confirmation from client.

1. TNB handing over (Rodding Test and etc) to TNB for Parcel B2- URGENT !!2. To issue EI for omission of ducting for security CCTV cable.3. To issue EI for revised landscape lighting (tapping from SL)

1. To issue EI for omission of ducting for security CCTV cable.2. To issue EI for revised landscape lighting (tapping from SL)3. EOT accessment1. To follow up with MME for rectification works for gantry structure2. To follow up with MME/TNB for handing over acceptance. 3. To follow up with MME for as built drawing & O&M manual1. To follow up with MME/PLUS for SL acceptance letter (Realignment Works)2. To follow up with MME for as built drawing & O&M manual

1. To follow up GW Bersekutu for shop drawing & sample submission

1. Testing & Commissioning with Sri Lantai (Fountain 1,2,3,4)1. To re-submit after confirmation of final LMR or other approach method.2. To issue EI to Juang Antara for jointing of sub main cable under MME3. To issue EI to Juang Antara for Temporary power cable under MME4. To prepare letter for material approval.

To prepare BQ,drawing for tender.

To prepare BQ,drawing for tender.

To prepare BQ,drawing for tender.

Issue to Follow Up

Refer to the site minutes for remaining outstanding works for Cablecon & Mega

Page 8: Coburg (Handing Over)

Issue to Follow Up

1. SMATV Issue and review new proposal submitted by SEP

2. To follow up with SEP for revised schematic diagram for PE endorsement.2. To follow up with SEP for O&M Manual

Refer to the site minutes for remaining outstanding works for Cablecon & Mega