Handing Over Checklist (Authorities)
Setia Eco Park Authority Status Issue to Follow Up
1 Phase 8E (43 Units)
TNB Approved To follow TNB Connection Charges.
SL Approved No issue
TMB Approved No issue
2 Phase 12 (139 Units)TNB By PJL TNB KM Approved
SL Submitted To follow up approvalTMB (External) Submitted To follow up approval
3 Phase 16 (90 Units)TNB By Others TNB KM Approved
SL Submitted To follow up approvalTMB (External) Pending To submit
4 Street Lighting Phase 3 (Done)
Setia Eco Glades Authority Status Issue to Follow Up
1 Parcel A1 (104 Units)
TNB Approved To follow TNB Connection Charges.
SL (MPS) Approved No issues
Fiber at Home Approved To submit amendment plan
2 Parcel A2 (115 Units)TNB Approved To follow TNB Connection Charges.
SL (MPS) Approved No issuesFiber at Home Approved To submit amendment plan
3TNB BY LMC To submit
SL (MPS) Pending To submit Fiber at Home Pending To submit
4 Parcel B2 (110 Units)TNB Approved
SL (MPS) Submitted No IssuesFiber at Home Approved To submit amendment plan
5TNB By LMC To submit
SL (MPS) Pending To submitFiber at Home Pending To submit
6TNB Pending To submit TNB Infra Application
SL (MPS) KIV KIVFiber at Home KIV KIV
7 Parcel G2 (75 Units)TNB Approved To follow TNB Connection Charges.
SL (MPS) Approved No IssuesFiber at Home Approved To submit amendment plan
8 Parcel G3 (83 Units)TNB Pending To resubmit. Partial approved
SL Pending To submitFiber at Home Pending To submit
9 Parcel G5 (240 Units)TNB By LMC To submit
Overall SL Handing Over
To conduct final inspection for remaining phases & handing over
Parcel B1 (82 Units)- New Project (2015)
To follow up with TNB for supply connection. (Urgent)
Parcel C3- New Project (2015)
Parcel G1 (25 Units)- Tan Seri Liew
9 Parcel G5 (240 Units) SL Pending To submit Fiber at Home Pending To submit
10 RING RoadTNB Approved To submit bridge crossing detail.
SL Approved To submit Fiber at Home Approved To submit gantry crossing detail
11 SEG Interchange
TNB Approved Obtained TNB Acceptance LetterSL (LLM/PLUS) Pending Pending LMR.
SL (MPS) Approved No issueTime Dot Com Approved Obtained TIME Acceptance Letter
Setia Eco Hill Authority Status Issue to Follow Up
1
TNB (33kV,11kV) Approved Obtained TNB Acceptance Letter
SL (JKR) Approved Final Inspection & Sokongan SL (LLM/LEKAS) Approved Final Inspection & Sokongan
Telekom Approved Obtained Telekom Acceptance Letter
2 SEH Intchg (Eco Link)
TNB Approved Meter Installation (Pending)
SL (JKR) Approved Final Inspection & Sokongan SL (MPKJ) Approved To follow up Approval Letter Telekom Approved Obtained Telekom Acceptance Letter
SEH Intchg (Relocation)
Issue to Follow Up
To follow TNB Connection Charges.
No issue
No issueTNB KM Approved
To follow up approvalTo follow up approval
TNB KM ApprovedTo follow up approval
To submit
Issue to Follow Up
To follow TNB Connection Charges.
No issues
To submit amendment plan
To follow TNB Connection Charges. VP on April 2016
No issuesTo submit amendment plan
To submitTo submit To submit
No IssuesTo submit amendment plan
To submitTo submitTo submit
To submit TNB Infra Application
KIVKIV
To follow TNB Connection Charges.
No IssuesTo submit amendment plan
To resubmit. Partial approvedTo submitTo submitTo submit
To conduct final inspection for remaining phases & handing over
VP on Dec 2015 (Urgent)
To follow up with TNB for supply connection. (Urgent)
To submit To submit
To submit bridge crossing detail.To submit
To submit gantry crossing detailObtained TNB Acceptance Letter
Pending LMR. No issue
Obtained TIME Acceptance Letter
Issue to Follow Up
Obtained TNB Acceptance Letter
Final Inspection & Sokongan Final Inspection & Sokongan
Obtained Telekom Acceptance Letter
Meter Installation (Pending)
Final Inspection & Sokongan To follow up Approval Letter
Obtained Telekom Acceptance Letter
Project Status
Setia Eco Park Issue to Follow Up
1
1. To issue EI to TNH for additional special lot (upon confirmation from BES)2. To issue EI to CSB for revised landscape lighting position
3. To issue EI to CSB for additional meter panel for SL & LD FP
4. To follow up with the rectification works for collapsed SL pole.
5. EOT accessment for Phase 8E (Infa)
6. To issue EI for omission of CCTV breaker (PABX)
2 To prepare infra tender
Setia Eco Glades Issue to Follow Up
11. To issue EI for clubhouse air con point
2. To follow with CICET for rectification works for genset room
2 1. To issue EI for special lots upon confirmation from client.
3 Infra (PKG A- KJ)1. TNB handing over (Rodding Test and etc) to TNB for Parcel B2- URGENT !!2. To issue EI for omission of ducting for security CCTV cable.3. To issue EI for revised landscape lighting (tapping from SL)
4 Infra (PKG B- KEMJ)1. To issue EI for omission of ducting for security CCTV cable.2. To issue EI for revised landscape lighting (tapping from SL)3. EOT accessment
51. To follow up with MME for rectification works for gantry structure2. To follow up with MME/TNB for handing over acceptance. 3. To follow up with MME for as built drawing & O&M manual
61. To follow up with MME/PLUS for SL acceptance letter (Realignment Works)2. To follow up with MME for as built drawing & O&M manual
7 Infra (A1-Landscape) 1. To follow up GW Bersekutu for shop drawing & sample submission
7 Infra (Water Fountain) 1. Testing & Commissioning with Sri Lantai (Fountain 1,2,3,4)
10 SEG Interchange
1. To re-submit after confirmation of final LMR or other approach method.2. To issue EI to Juang Antara for jointing of sub main cable under MME3. To issue EI to Juang Antara for Temporary power cable under MME4. To prepare letter for material approval.
7 Infra (A2-Landscape) To prepare BQ,drawing for tender.
7 To prepare BQ,drawing for tender.
7 Infra (B1,C3,G3,G5) To prepare BQ,drawing for tender.
Setia Eco Hill Issue to Follow Up
1 SEH Intchg (Relocation)
2 SEH Intchg (Eco Link)
Phase 8E (43 Units)- Building & Infra
Infra Tender (Phase 12 & 16)
Buidling -Parcel A1 (104 Units)
Building- Parcel A2 (115 Units)
Infra (B2 Gallery-Mega Mayang)
Infra (Realignment-Mega Mayang)
Infra (Main Road- Waterway)
Refer to the site minutes for remaining outstanding works for Cablecon & Mega Mayang
2 SEH Intchg (Eco Link)
Setia Alam Issue to Follow Up
1 Baiduri1. SMATV Issue and review new proposal submitted by SEP
2. To follow up with SEP for revised schematic diagram for PE endorsement.2. To follow up with SEP for O&M Manual
Refer to the site minutes for remaining outstanding works for Cablecon & Mega Mayang
Issue to Follow Up1. To issue EI to TNH for additional special lot (upon confirmation from BES)2. To issue EI to CSB for revised landscape lighting position
3. To issue EI to CSB for additional meter panel for SL & LD FP
4. To follow up with the rectification works for collapsed SL pole.
5. EOT accessment for Phase 8E (Infa)
6. To issue EI for omission of CCTV breaker (PABX)
To prepare infra tender
Issue to Follow Up
1. To issue EI for clubhouse air con point
2. To follow with CICET for rectification works for genset room
1. To issue EI for special lots upon confirmation from client.
1. TNB handing over (Rodding Test and etc) to TNB for Parcel B2- URGENT !!2. To issue EI for omission of ducting for security CCTV cable.3. To issue EI for revised landscape lighting (tapping from SL)
1. To issue EI for omission of ducting for security CCTV cable.2. To issue EI for revised landscape lighting (tapping from SL)3. EOT accessment1. To follow up with MME for rectification works for gantry structure2. To follow up with MME/TNB for handing over acceptance. 3. To follow up with MME for as built drawing & O&M manual1. To follow up with MME/PLUS for SL acceptance letter (Realignment Works)2. To follow up with MME for as built drawing & O&M manual
1. To follow up GW Bersekutu for shop drawing & sample submission
1. Testing & Commissioning with Sri Lantai (Fountain 1,2,3,4)1. To re-submit after confirmation of final LMR or other approach method.2. To issue EI to Juang Antara for jointing of sub main cable under MME3. To issue EI to Juang Antara for Temporary power cable under MME4. To prepare letter for material approval.
To prepare BQ,drawing for tender.
To prepare BQ,drawing for tender.
To prepare BQ,drawing for tender.
Issue to Follow Up
Refer to the site minutes for remaining outstanding works for Cablecon & Mega
Issue to Follow Up
1. SMATV Issue and review new proposal submitted by SEP
2. To follow up with SEP for revised schematic diagram for PE endorsement.2. To follow up with SEP for O&M Manual
Refer to the site minutes for remaining outstanding works for Cablecon & Mega