Suitability of depleted gas reservoirs for geological CO2 ...
CO2 capture, transport and geological storage programmes
-
Upload
global-ccs-institute -
Category
Environment
-
view
374 -
download
0
description
Transcript of CO2 capture, transport and geological storage programmes
CO2 capture, transport and
geological storage programmes
KS CCS Network
8th May, 2014
CIUDEN es.CO2 Centre for technological development
KS CCS Network 8th May, 2014
es.CO2 - Schematic diagram
15-30 MWthCFB
BOILER
FUEL
PREPARATION
SYSTEM
SCR
GAS
CLEANING
SYSTEM
Compression
and Separation
Unit
MIX AND
PREHEATING
SYSTEM
20 MWthPC
BOILER
Air
FGR1
O2 Storage
and
Vaporisation
FGR2
FGDBag Filter
STACK
CO2
ExpanderBiomass
Cyclon
TorchGASIFIER
PC
SILO
MIXERS
Gas Clean up
Preheating
train
CO2 TRANSPORT
TEST RIG
CO2
Final Review Meeting Brussels 13/02/2014
KS CCS Network 8th May, 2014
FUEL PREPARATION
BIOMASS
GASIFIER
PC BOILER
20 MWth
CFB BOILER
30 MWth
TECHNICAL BUILDINGS
AND CONTROL ROOM
FLUEGAS
CLEANING
FLUE GAS
RECIRCULATION AND
MIXING
CO2
COMPRESSION &
PURIFICATION
UNIT
CO2 EXPERIMENTAL
TRANSPORT RIG
INDUSTRIAL SITE
65.000 m2
BUILDINGS
• Technical: 3.500 m2
• Industrial: 1.300 m2
es.CO2 – Aerial view
Final Review Meeting Brussels 13/02/2014
KS CCS Network 8th May, 2014
July 2011 First gas fire CFB boiler
November 2011 1st phase completed: CO2 capture in oxycombustion
October 2012 Completed CO2 capture in oxycombustion
June 2011 Works completed for: •Balance of the plant •Auxiliary power •Cyclone and bag filter •Ash evacuation system
August 2011 First coal fire CFB boiler
September 2011 First oxycombustion CFB boiler
September 2012 CPU ready for testing
4
Milestones
KS CCS Network 8th May, 2014
MORE THAN 2,600 OPERATING HOURS IN
OXYCOMBUSTION!
MORE THAN 3,700 OPERATING
HOURS IN TOTAL!
2011 2012 2013
Lessons learned
Oxycombustion in CFB demonstrated at this scale
Integration of oxycombustion and CO2 capture demonstrated
Complete automation of air to oxy mode and vv. transitions achieved
Adequate operational conditions identified
Dramatic reduction of specific emissions
Important design data for scale-up collected
KS CCS Network 8th May, 2014
Technology maturity at low cost
Less risks Public perception
FGD Development: a good case study for CCS technologies at utility scale?
Ref: Rubin, et al. GHGT-8 proceedings, 2006
Lessons learned
KS CCS Network 8th May, 2014
• European Energy Programme for Recovery EEPR
• Allocation of
CCS and RES emissions allowances NER-300
• CCS European Industrial Initiative CCS EII
• Horizon 2020 Relevant funding mechanism (EC)
CCS support initiatives
Fundación Ciudad de la Energía
CO2 Geological Storage Programme
J. Carlos de Dios
Director of CO2 Geological Storage Programme
KS Event CCS Network May 8th, 2014
9
WP3 CO2 Storage
Identification, characterization and operation of a Technology Development Plant for CO2 Geological Storage
Activities committed in the project include:
• Site Selection
• Site Characterization
• Design and construction of the TDP
• Modelling of CO2 injection strategies and their behaviour
• CO2 Monitoring Strategies
• Long term Risk Assessment
• Cost reduction actions identification
TDP in operation : December 2013 Final Conclusions Study : October 2014
KS CCS Network 8th May, 2014
Transfer of liabilities
Site Selection & Characterization
Injection in the storage rock
Storage Engineering Injection Monitoring
Monitoring
Commercial CO2 Storage
Pre-operational Operational Post-
operational Transfer to the state
CIUDEN´S OBJECTIVES RELATED TO GEOLOGICAL STORAGE OF CO2
To demonstrate its feasibility and security.
To develop methodologies and technologies.
To facilitate technical criteria for the Regulating
Authority.
To promote education.
Real-scale Technological
Development Plant is required
11
CIUDEN´S TECHNOLOGICAL DEVELOPMENT PLANT FOR CO2 GEOLOGICAL STORAGE
Site selection, since 2008
The process involved
the study of data at
national level. The
screening works led to the
election of Hontomin,
based on its structure,
properties, availability of
previous data, being also
compared with other
options in the same basin
on a risk assessment basis.
12
Baseline, characterization & monitoring at Hontomín TDP
CIUDEN´S TECHNOLOGICAL DEVELOPMENT PLANT FOR CO2 GEOLOGICAL STORAGE
Micro-seismic network of 30 stations
446400 446500 446600 446700 446800 446900 447000 447100
47
14
50
04
71
46
00
47
14
70
04
71
48
00
47
14
90
0
Este
No
rte
2
4
4
4
4
4
6
6
6
6
6
8 8
8
8
8
8 8
8
10
10
10
10
10
10
10
10
12 12
12
12
12
12
12
12
12
14
14 14
14
14
14
14
16
16
Gas Flow
Displacement measurement from satellite
High resolution 3D Seismics
13
Baseline, characterization & monitoring at Hontomín TDP
This installation is
highly instrumented with
a wide range of
monitoring technologies,
which will allow to track
the changes once in
operation.
These data is also
essential to validate risk
assessment activities,
increasing knowledge in
safe CO2 storage.
CIUDEN´S TECHNOLOGICAL DEVELOPMENT PLANT FOR CO2 GEOLOGICAL STORAGE
14
Knowledge of the groundwater state before the CO2 injection. Hydrogeological characterization of the aquifer and seal formations.
Identification of geological structures which allow the CO2 to migrate upwards.
Hydrogeological and hydrochemical monitoring of the CO2 migration.
HYDROGEOLOGICAL CHARACTERIZATION
KS CCS Network 8th May, 2014
TECHNOLOGICAL DEVELOPMENT PLANT OF HONTOMÍN
H-A Well
H-I Well
Gas Plant
Water Plant
Pools
16
PROCESS DIAGRAM OF THE TDP OF HONTOMÍN
17
WELL DRILLING
0
50
100
150
200
250
300
350
400
450
500
550
600
650
700
750
800
850
900
950
1000
1050
1100
1150
1200
1250
1300
1350
1400
1450
1500
1550
1600
1650
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140
H-A: Curva Profundidad vs. Tiempo
Días
Pro
fun
did
ad
(m
)
PrognosisActual
216,60 m Casing 13 3/8"
20 m Casing 20"
593,92 m Casing 9 5/8"
Perforación 12 1/4" a Rotación C.I.
Perforación 8 1/2" a Rotación C.D.
Registro CBL/VDL Casing 9 5/8"
1281 - 489,6 m 7" LinerTestigo-1: 1313 - 1320 m
Testigo-2: 1320 - 1323,8 m
Testigo-3: 1343 - 1350 m
Testigo-10: 1515 - 1522 m
Testigo-11: 1522 - 1528,8 mTestigo-12: 1528,8 - 1531 m
16/08/2013
Perforación 6" a Rotación C.D.
Perforación 17 1/2" a Percusión
Perforación 17 1/2" a Rotación C. I.
Testigo-4: 1401 - 1405 mTestigo-5: 1405 - 1412 m
Testigo-6: 1442 - 1449 m
Testigo-7: 1449 - 1450,26 mTestigo-8: 1457 - 1463 m (Rec.0%)
Testigo-9: 1464 - 1464,12 m
TD: 1580 m MD
WO logging: 4 díasLogging: 3 díasDesplazar lodo: 1 díaProducción agua: 5 díasTests inyección: 6 díasTP&A and rig down: 3 días
23/03/2013
18
PETROLOGICAL AND PETROPHYSICAL CHARACTERIZATION OF RESERVOIR AND SEAL FORMATIONS
Composition
Mechanical properties
Porosity and pore size distribution
0,000
0,500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
K
1/Pm
Permeability
19
COMPLETION AND INSTRUMENTATION OF HI & HA WELLS
20
INJECTIVITY AND CONNECTIVITY TESTS
Determination of hydraulic parameters (permeability, injectivity, etc.).
Determination of connectivity between HI and HA wells.
Well Tests Summary - Hontomin H-A
Test Bottom Packer Bottom Packer Total H Total net H P @ depth P/hydr T Formation
mMD mMD m m bar mMD °C
Production #1 296 111,7 1281 0,872163 37,8 All
Injection #1 1530 unset - TD = 1580 50 ? - 1530 - 46,5
Dolomias de sopeña +
anhidritas
Injection #2 1501 1529,8 28,8 8 141,2 1501 0,941 45,8 Dolomias de sopeña
Injection #3 1472 1500,8 28,8 5 138,6 1472 0,942 44,8 calizas inf sopeña
Injection #4 1439,1 1467,9 28,8 15 135,4 1439,1 0,941 43,9 calizas sup sopeña
Injection #5 1414,2 unset - TD = 1580 165,8 28 132,7 1414,2 0,938 43,3 All
Injection #5B 1414,2 unset - TD = 1580 165,8 28 132,5 1414,2 0,937 43,3 All
In red: doubtful values
Test Model Remarks DP WH Rate Dt K.h K S K outside zone
l/hr hr mD.m mD for radial comp model
Production #1
Rate drops down to 1/4
within 24hr 50 ? 200 > 24
Injection #1 unconclusive tests 23 - - - - -
Injection #2 Possible Double F (weak) Inj with N2 at WH 53 17,34 0,52 0,18 0,0225 -1
Injection #3 Possible Double F (weak) Inj with N2 at WH 48 47,8 1,03 1,43 0,286 -0,4
Injection #4 Possible Double F (weak) Inj with N2 at WH 41,6 9,42 1,09 0,95 0,063192 9,8
Injection #5 Radial comp
Inj with Solexpert small
pump 12,5 90 4,00 8,83 0,316 2,11 # 3 mD @ 12m ?
Injection #5B Radial comp Inj with Rig pump 42 600 2,00 24,23042 0,866 1 # 3-5mD @ 20m ?
no packer / whole OH section = 1284 - 1580
1E-4 1E-3 0.01 0.1 1 10
Time [hr]
1
10
100
Pre
ssure
[psi]
119
119.5
Pre
ssure
[bara
]
0 20 40
Time [hr]
-250
-125
Liq
uid
rate
[m
3/D
]
RISK ASSESSMENT
To develop a risk probabilistic assessment model related to deep geological CO2 Storage in saline carbonate aquifers, proved with results from experimental activities at real scale in Hontomin TDP
Resultado Riesgo de fuga en el primario
Resultado Riesgo de fuga en el secundario
Resultado Riesgo de fuga
Resultado Capacidad de dispersión edáfica
Análisis de Sensibilidad
Falla del primario
Tectónica
Alcance de la pluma de CO2 en el primario
Formación sello del primario
Escape estructural en el primario
Pozo del primario
Función matemática
Falla del secundario
Formación sello del secundario
Alcance de la pluma de CO2 en el secundario
Escape estructural en el secundario
Pozo del secundario
Función matemática
Capacidad de dispersión edáfica
Función matemática
( ) ( )
( )( )
i i
i
P B A P AP A B
P B
( ) ( )
( )( )
i i
i
P B A P AP A B
P B ( ) ( )
( )( )
i i
i
P B A P AP A B
P B
22
The works developed in this project have allowed to create a trustworthy relationship with key stakeholders as with the local community.
PUBLIC ENGAGEMENT
23
Drilling phase finished, operative last quarter 2013
This installation will be devoted to real scale experiments in deep porous rock formations to test and develop new technologies in storage engineering, CO2 injection strategies and safe operation.
• Current site capacity threshold by Law: 100,000 t. • On-shore deep saline aquifer storage. (administrative requirement Spanish Law 40/2010 CO2 Geological Storage) • Cost reduction Action with the use of Light Drilling Equipment (up to 60%). • Safe operation including well integrity and leakage prediction techniques. • CO2 injection strategies: liquid, supercritical and gas.
CURRENT STATUS OF THE TDP OF HONTOMÍN
KS CCS Network 8th May, 2014
HONTOMÍN TDP
KS CCS Network 8th May, 2014
Thanks for the attention
J. Carlos de Dios CO2 Geological Storage Programme
Tel.+34 987 456 323 Mobile +34-639 110 760
[email protected] Technological Development Plant for CO2 Storage
www.ciuden.es