Reengineering of Primary
water dosing system in
Thermal Power Plant.
SSTPS
1
Click to edit Master title style
Copyright © 2016 NTPC PMI All Rights Reserved. 2 Learning @ the speed of business
The future is now !
OUR TEAM
D.K. Saraswat
AGM(C&I)
Narendra Swarnkar
DGM (C&I)
Abhishek Joshi
Mgr(C&I)
2
NTPC Ltd SSTPS
NO. OF PLANTS CAPACITY (MW)
NTPC Owned
Coal 21 40,355
Gas/Liquid Fuel 7 4,017
Hydro 1 800
Renewable energy projects (Solar PV)
12 878
Wind 1 50
Total 42 46,100
Owned By JVs/Subsidiaries
Coal & Gas 9 7,551
Total 51 53,651
3
Singrauli Super Thermal Power Station
THERMAL
SOLAR
HYDRO
2000 MW
15 MW
8 MW
TOTAL 2023 MW
4
3
OUR VISION OUR MISSION
OUR CORE VALUES
To be the World's Leading Power Company, Energizing India's Growth.
Provide Reliable Power and Related Solutions in an Economical, Efficient and Environment friendly manner, driven by
Innovation and Agility.
5
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 6
Section-1 Project Background & Purpose
In this section, we will cover how NTPC ‘does’ project planning,
project identification, and project prioritization.
We will then cover specifics of why this project was picked along
with Goals, Benefits, and Success Measures
4
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 7
1.01 Organizational approach to project planning
Identify project that support the strategy
Evaluate and prioritize the project
Select, approve and initiate the project
Review project regularly
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 8
1.02 Project identification process.
1 Customer feedback
2 No of problems reported online (SAP)
3 Through Suggestion scheme
4 Various audit
5 Professional meet
6 Current problems in work area
7 Given by management
5
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 9
Customer feedback
1.02 Project identification process.
No of problems reported online (SAP)
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 10
1.02 Project identification process.
Through Suggestion scheme
6
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 11
1.03 Project selection process.
1. All projects are characterized into : A,B,C,D,E category.
2. Based on the plant area, projects are assigned in that category.
A 01 Main Plant Boiler
B 02 Main Plant Turbine
C 03 Main Plant Generator
D 04 Off site area
E 05 CHP area
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 12
1.03 Project selection process.
S.
NO
`
PROBLEM
CRITERIA
MAX
NO.
A
B
C
D
E
1 Safety 10 7 5 8 4 6
2 Quality 10 6 6 7 8 7
3 Productivity 10 6 7 6 7 5
4 Ease of use 10 6 5 7 6 5
5 Effectiveness 10 7 6 5 5 6
6 Maintenance 10 7 5 7 6 6
Total 60 39 34 40 36 35
Priority 2 5 1 3 4
After assigning projects in A,B,C,D,E category , evaluation and prioritization of the problems are done based on following matrix.
7
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 13
1.04 Project selection specific.
Sl.
NO.
Projects
Jury Proj-1 Proj-2 Proj-3 Proj-4 Proj-5
1 Member-1 5 3 2 4 1
2 Member-1 1 3 2 5 4
3 Member-1 5 2 1 3 4
4 Member-1 3 1 5 4 2
Marks 14 9 10 16 11
PRIORITY NO. 2 5 4 1 3
After selection of projects, a committee was formed to evaluate each project on the basis of following matrix : 1) Risk 2) Safety 3) Cost benefit. 4) Customer satisfaction. 5) Quality 6) Gap
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 14
1.05 Project goals and benefits.
Project goals Specific measures Additional Benefits
Customer satisfaction
Reliability and safety
Cost
Zero notification from customer about failures
100% information and control in remote for
customer
Equipment down time reduction up to 0% .
Cost saving up to 18 lakhs.
Intangible Cost saving up to 560 Cr.
Brand image Customer loyalty
Learning Mutual respect and
trust
Total quality Plant outage
reduction
Inventory reduction.
Obsolescence handling.
8
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 15
1.06 Success measures and criteria identified.
0
20
40
60
Before Executionof project
After completionof project
Gap analysis
breakdownsyearly
Analysis of PSW dosing system found the gap of 50 breakdowns per year which needs to be reduced up to 0 .
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 16
1.06 Success measures and criteria identified.
Analysis of PSW dosing system found the variation of the parameter beyond set
limits, resulting in increase in maintenance time.
0102030
BeforeExecution of
project
After completionof project
Gap analysis
Maintenancetime
20
0.67
Specific goal of the project reduced the down time from 20 hr/Month to .67
Hr/Month.
9
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 17
2.0 Project Framework/Charter
PROJECT STATEMENT The current system appears to be confusing to customers and it is considered to be a difficult and time-consuming process for maintenance of system. No control and information was available to customers . The re-
engineered system will be simplified and improved for a better value proposition for both the customers and maintenance engineers. It will result in customer loyalty , inventory reduction and huge intangible cost benefits.
PROJECT TYPE This project is a process improvement and redesign effort
ASSUMPTIONS/EXPECTATIONS
PROJECT
SCOPE The following assumptions were taken into consideration while undertaking the project:
1) Thorough knowledge of existing system.
2) Thorough knowledge of Digital control system.
3) Possibility of design and interfacing with new control system.
4) Trained team member on Design and Re-engineering.
5) Availability of drawing ,documents and spares.
IN Scope
Out of scope
1) Change in design. 1) Change in the alarm set values.
2) Change in control system. 2) Change in the Protection set values.
3) Incorporation of additional features 3) Change in existing equipment.
4) Provision for remote operation. 4) Change in power requirement.
5) Provision for auto operation. 5) Change the physical location.
6) Reduction in repetitive failures.
BUDGET (Financial and/or Resource Constraints) 7) Reduction in Maintenance Time .
The project budget was considered on the basis of following :
1. Material Requirement.
2. Man power Requirement.
3. Training Requirement.
4. Stakeholder Requirement.
The above mentioned needs were so far below the actual limits that these were not considered to be
constraints.
8) Use of existing resources.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 18
2.0 Project Framework/Charter (Contd.)
Sr. no
Probable Risk
Solution
1 Whether new changes, will be permitted or not ? We will convince the head of the department through logical drawings.
2 How will we do it ? We will take the help of our existing team and stakeholders.
3 Can it be done in running Unit ? No, We got the opportunity during overhauling of units.
4 Will there be any resistance from Operation ? No.
5 How will we arrange the material ? It will be arranged from internal resources.
6 Will new system interface with existing system ? Yes, The checking of new system will be done offline in simulator.
RISK MANAGEMENT
PROJECT SCHEDULE Start – 01/06/2018 Complete- 02/09/2018
10
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
19
05 Control and information available to customer with reduction in maintenance time
04
Design and Re-engineering of PSW Alkalizer system
No control and information available to customer
03
Maintenance is considered to be a difficult and time-consuming process
02
01 Variation in Generator cooling water conductivity
2.01 Project statement
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 20
2.02 Type of Project
This project is a process improvement and redesign effort. The current system was the starting point and will form the basis for the revised system.
Current measuring and control process
process improvement
and redesign effort
Refine and informative
control system
11
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 21
2.03 Project Scope
IN Scope Out of scope
1) Change in design. 1) Change in the alarm set values.
2) Change in control system. 2) Change in the Protection set values.
3) Incorporation of additional features
3) Change in existing equipment
4) Provision for remote operation. 4) Change in power requirement.
5) Provision for auto operation.
5) Change the physical location.
6) Reduction in repetitive failures.
7) Reduction in Maintenance Time .
8) Use of existing resources.
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
22
05
Availability of drawing ,documents and spares.
04
Trained team member on Design and Re-engineering
Possibility of design and interfacing with new control system.
03
Thorough knowledge of Digital control system.
02
01 Thorough knowledge of existing system.
2.04 Project Assumptions
12
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 23
2.05 Project Schedule
1 2 3 4 5 6 7 8 9 10 11 12 13
1
2
3
4
5
6
7
8
9
10
Start – 01/06/2018 Complete- 02/09/2018
Time Scale in week SL NO.
Activities
Define the problem
Analysis of problem
Identification of causes
Finding out the root causes
Data Analysis
Developing solutions
Foreseeing probable resistance
Trial implementation Regular implementation
Follow up/Review
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 24
2.06 Project Budget (Financial or Resources)
Material requirement 95% materials were used from existing resources. Balance 5% materials which were used are as follows:-
1) Relay (2 no’s) 2) Cables (50 meters)
Man power requirement Trained team members
Training requirement Training on Honeywell Digital control system.
Stakeholder requirement Knowledge of the process and impact of parameter variation on process.
The above mentioned needs were so far below the actual limits that these were not
considered to be constraints
13
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 25
2.07 Project Risk management
Sr. no Probable Risk
Solution
1 Whether new changes, will be permitted or not ?
We will convince the head of the department through logical drawings.
2 How will we do it ?
We will take the help of our existing team and
stakeholders.
3 Can it be done in running Unit ?
No, We got the opportunity during overhauling of
units.
4 Will there be any resistance from Operation ? No.
5 How will we arrange the material ? It will be arranged from internal resources.
6 Will new system interface with existing system ?
Yes, The checking of new system will be done
offline in simulator.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 26
3.01 Project Stakeholders
Stakeholders group Who
Approver
Steering committee
Sponsor
Champion
Project Leader
Project Team
Interested party
CGM
Head of maintenance
Head of Business excellence
Group Head
Section head
Functional process experts
1) Maintenance manager.
2) DCS expert .
3) Quality manager
Head of Operation
GM (O&M)
Head of Total quality management
Key customer
1) Operation engineer.
2) Planning Manager.
3) Chemical expert
Head of Chemistry Head of Business
excellence
14
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 27
3.02 Project Stakeholders(How are they identified)
Stakeholders I P C POWER IMPACT TYPE IMPACT DEGREE
SUPPORT STRATEGY
have need
CGM X 1 help or derail goal high 4 1 weekly status update
GM (O&M) X x 1 help or derail goal high 4 1 weekly PERSONAL update
Head of Maint. X x 2 help or derail goal moderate 3 2 weekly PERSONAL update
Head of TQM X 2
Head of BE X 3
Group Head X x x 2 help or derail goal moderate 3 2 Daily status update
Section head X x x 3 help goal Daily personal update
Functional process experts X x x 3 help or derail goal moderate 1 4
Key customer X x x 4 Help goal moderate 2 3 Keep informed and get feedback
Head of Operation x 4
Head of Chemistry X 5
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 28
CGM & GM
HEAD OF MAINT
GR
OU
P H
EAD
HEA
D O
F TQ
M
HEAD OF BE
FUN
CTIO
NA
L PR
OC
ESS EX
PER
TS
SEC
TIO
N H
EAD
HEAD OF CHEMISTRY
HEA
D O
F OP
ERA
TION
KEY CUSTOMER
3.02 Project Stakeholders(How are they identified)
15
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 29
3.02 Project Champion
Key stakeholder Head of plant
Project Champion Head of Business excellence
Head of plant requires periodic updates on progress including copies of working documents for review.
Brand image, Customer Loyalty, Total Quality and Plant outage Reduction is the key for stakeholders.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 30
3.03 Project Team selection
What knowledge or skill sets were determined to be necessary for successful completion of the project? To what extent did the existing stakeholder groups have the required knowledge or skills?
Knowledge/Skill set Project Steering Committee
Execution Team Project Management Group
Process Owner
Domain Knowledge YES YES YES YES
Basic quality tool YES YES YES YES
Leadership skill NA YES YES YES
Communication YES YES YES YES
Project management NA NA YES YES
Decision making YES YES YES YES
Conflict management YES NA YES YES
Team building NA YES YES NA
16
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 31
3.04 Project Team preparation
What additional knowledge and skills were brought in to make the project successful?
Knowledge/Skill set Project Steering Committee
Execution Team Project Management Group
Process Owner
Operation. NA NO NA NO
Control system interfacing NA NO NA NA
Before the project started, what specific training was done?
Execution Team Process Owner
Operation. Operation.
Control system interfacing
Control system basics
1) Honeywell DCS system training. 2) Internal workshop on PSW dozing system.
DCS training
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 32
3.04 Project Team preparation
Before the project started, what was done to prepare the team to work together as a team?
Activities Details
Set clear purpose and goals which related to the project
1) All the team members were called inside a VC room 2) Briefing was done by Head of plant to all the team members about the goal & expectation related to projects.
Empowering Team Member Team Member were encouraged by Group head to reach out to him over mail incase of any bottle neck in execution.
Role clarification Roles of different team members were clearly set out by the project leader at the start
Expected Reward & Recognition Scheme
Brief details of internal Reward & Recognition scheme was shared with all team members.
Basic Team Building Training Mandatory completion of Team Building Class room training of all the team members
17
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 33
3.04 Project Team preparation
What roles and expectations were determined ahead of the project?
Role D M A D V
Sponsor I I I A I
Leader R R R A R
Team Member R R R R R
Process Owners I I I I I
Resource Resource to the team, one whose expertise, skills, are needed
Member Member of team, within the authorities and boundaries of the charter
Informed Interested party, one who will need to be kept informed on direction, findings
Approver Approval of team decisions
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 34
3.04 Project Team preparation
Project Steering Committee
1) Set objective & purpose 2) Ensure availability of adequate resources 3) Monitor progress 4) Resolves escalated matter/bottleneck 5) Organize team
Project Leader 1) Chair team meeting and maintain focus on the goal 2) Ensure progress towards the goal 3) Act as a communication hub and as a liaison with management 4) Ensure execution of action items assigned for individual team members 5) Ensure right set of tools & techniques are used
Execution Group 1) Complete all action items assigned on time . 2) Participate in team meetings 3) Communicates ideas and expertise
Process Owners 1) Support team members with resources and information. 2) Participate in project review 3) Share required information with team.
18
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 35
3.05 Project Team Routines
Before the project started, what team routines, including communication, were established?
Report Type
Frequency
Day of Publishing
Who will publish
Recipients
Daily Status Report
Daily
Daily Project Leader
Execution group, Project Management group & process owners
Weekly Status Report
Once in a week
Saturday All Stakeholder group
Milestone Reporting
As per agreed milestone date
As per agreed
All Stakeholder group
Co
mm
un
icat
ion
pla
n
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 36
3.05 Project Team Routines
Before the project started, what team routines, including communication, were established?
Review Name
Frequency
Location Day/Time of Review
Participants
Weekly Review
Weekly
Conference hall
Friday 11 AM-12PM IST
Execution group, Project Management group
Monthly Review
Monthly
1st of Every Month 11AM-1 PM IST
All Stakeholder group
Milestone Review
As per agreed milestone date
As per agreed date 11AM-2 PM IST
All Stakeholder group
Go
vern
ance
p
lan
19
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 37
3.05 Project Team Routines
Before the project started, what team routines, including communication, were established?
* Recurring meeting invites to be accepted * Be on time for meetings * Provide advance notice of being absent for a meeting * Action points should be closed before the next scheduled meeting * Agenda of the meeting to be shared 2 days before the meeting date
Me
eti
ng
No
rms
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 38
4.01 Project Approach
20
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 39
4.01 Project Approach
Define
Measure and Analyze
combined
Design Verify.
1) What is the process ? 2) Where is Primary water used ? 3) What is the role of dosing ? 4) How dosing is done ?
1) Types of Problems faced.
2) Quantify the problems.
3) Issues in current method
4) Steps of problem solving
1) Finalization of Phases of design . 2) Implementation of the design.
1) Verify the output before implementation .
TYPE OF PROJECT: Process Improvement/Redesign Effort DESCRIPTION OF PROJECT APPROACH: The project used a typical DMADV process: Define, Measure/Analyze, Design, Verify with Measure and Analyze combined into a single phase.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 40
4.02 Tools used
Define
Measure and Analyze
combined
Design Verify.
1) In frame / Out frame to fully understand the scope.
1) Brainstorming to obtain the suggestion.
Successive draft to refine and verify the design.
1) Draft review to finalize results.
2) Stakeholder Analysis to prioritize stakeholders.
2) Pareto chart.
2) Pilot trial run done to verify the design.
3) Stakeholders Prioritization 3) Cause and effect diagram/ Fishbone diagram.
TYPE OF PROJECT: Process Improvement/Redesign Effort DESCRIPTION OF PROJECT APPROACH:
The project used a typical DMADV process: Define, Measure/Analyze, Design, Verify with Measure and Analyze combined into a single phase.
21
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 41
4.03 Tools output
Define
Measure and Analyze
combined
Design Verify.
1) In frame /Out frame / fully understand the scope.
1) Data collection / Measurement to understand the impact of problem
1) Successive draft / refine and verify the design.
1) Draft review/ finalize results.
2) Stakeholder analysis/ prioritize stakeholder.
2) Brainstorming and cause and effect diagram / obtain the suggestion and root causes.
2) PDCA to meet the requirements.
2) Pilot trial run / to verify the design.
4) Stakeholder analysis to prioritization / visuals for above
3) Pareto chart/ For prioritization of the requirement.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 42
4.04 Preparation of team to use tool
Project Champion: An extensive experienced person lead the team through the exercises as part of on-the-job-training for some of the more technical tools and Took care of the following:- 1) removed roadblocks. 2) assigned, defined and aligned roles. 3) developed the core structure of the team. 4) owns the process, guarantees implementation.
Project Member : 1) Workshop for six sigma tools was organized by project champion and hands on knowledge was given. 2) No training was needed for Design and Verify as all members are having more than 8 Years of experience in the field.
22
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 43
4.05 Dealing with Project risk
Potential Risk Impact Steps to deal with risk
Experienced staff will leave the project before it is finished
Project Delayed Standby staff was also given training taking into consideration the mentioned risk
Change of organisational management with different priorities.
Project Delayed/suspended
1) Project champion was in continual touch with management to make them aware of importance and results of the project.
2) Cost benefit analysis and project progress with respect to planned activity was made ready .
Hardware that is essential for the project will not be delivered on schedule.
Project Delayed Increase in the cost of the Project
Availability of hardware is Ensured in nearby plants of NTPC
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 44
4.05 Dealing with project risk
Potential Risk Impact Steps to deal with risk
There will be a larger number of changes to the requirements than anticipated.
Project Delayed
1) Stand by team will be taken in to consideration.
Results of the project do not perform as anticipated
Project failure.
1) Projects were executed in phased manner and in each phase there is two possible solution and based on PDCA if one didn’t work other will be taken in to consideration.
2) Original design is also kept intact in case of failure of all possible solutions so the system will not get affected.
23
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 45
4.06 Encountering and Handling resistance
Possible Resistance Mitigation
Understanding the internal and external resistance Survey was taken and resistance was addressed through dialogue, presentations.
Permissions for modification and redesign. All legal and official permissions were taken.
Drawing and manuals Requirement of old system. Ensuring the availability of old systems drawing and manual.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 46
4.07 Stakeholder involvement
Stakeholders
CGM
Head of maintenance
Head of Business excellence
Group Head
Section head
Functional process experts
1) Maintenance manager.
2) DCS expert .
3) Quality manager
Head of Operation
GM (O&M)
Head of Total quality management
Key customer
1) Operation engineer.
2) Planning Manager.
3) Chemical expert
Head of Chemistry Head of Business
excellence
Involvement
DECISION MAKING
ADMINISTRATIVE
QUALITY / TECHNICAL
TECHNICAL /
IMPLEMENTATION
TECHNICAL / CUSTOMER
24
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 47
5.00 Project walkthrough
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 48
5.00 Project walkthrough
Define
1. Scope 2. Stakeholders 3. Process
25
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 49
5.00 Project walkthrough (Define)
BFP
LPT
BOILER
MILL
HPT
IPT
PLANT OVER VIEW 500MW
OSU 1
OSU 2
MILLS
DRUM
ECONOMISER
REHEATER
ECONOMISER
HPT IPT LPT GENERATOR
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 50
5.00 Project walkthrough (Define)
GENERATOR
PRIMARY WATER IN LET
PRIMARY WATER OUT LET
NAOH TANK
DOSING P/P
DOSING
MEASURE
LOCAL CONTROL
PANEL
26
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
51
PSW Alkalizer System: Importance
Low Conductivity of cooling water may cause corrosion in Copper tubes, thereby damaging them.
High Conductivity of water may cause flashover in generator.
Therefore ,PSW System Conductivity should be maintained at optimum value.
5.00 Project walkthrough (Define)
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
52
In St-II (2x500 MW), PSW Conductivity measurement, monitoring
and control system was available through local control
panel.
There was control, Alarm and information available
for operation People at local only. Desk engineer
has to come to local for start and stop of dosing
pump and changing conductivity requirement,
annunciation etc.
5.00 Project walkthrough (Define)
LOCAL CONTROL PANEL
52
27
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
53
5.00 Project walkthrough (Define)
LOCAL CONTROL PANEL
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
54
5.00 Project walkthrough (In frame/Out Frame)
Change in the alarm set values.
1) Provision of remote operation. 2) Provision for auto operation. 3) Reduction in repetitive failures. 4) Use of existing resources.
Change in control system.
Change in design.
Inco
rpo
ration
of
add
ition
al featu
res
.
Ch
ange
in m
easu
ring
Instru
me
nt
Change in the Protection set values
Ch
ange
in p
ow
er re
qu
irem
en
t .
Ch
ange
the
ph
ysical locatio
n
Change in the alarm set values.
Out Of frame
Up for discussion
In frame
28
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 55
CGM & GM
HEAD OF MAINT
GR
OU
P H
EAD
HEA
D O
F TQ
M
HEAD OF BE
FUN
CTIO
NA
L PR
OC
ESS EX
PER
TS
SEC
TIO
N H
EAD
HEAD OF CHEMISTRY
HEA
D O
F OP
ERA
TION
KEY CUSTOMER
5.00 Project walkthrough (Define Stakeholder Prioritization)
To the right is the stakeholder prioritization
graphic we introduced earlier.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 56
5.00 Project walkthrough (Measure)
Measure
29
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 57
5.00 Project walkthrough (Measure)
REPITITIVE PROBLEM REPORTED (SAP)
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 58
5.00 Project walkthrough (Measure)
PERAMETER NOT MAINTAIN IN RANGE
30
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 59
5.00 Project walkthrough (Measure)
NO REMOTE ACCESS
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 60
5.00 Project walkthrough (Measure)
SYSTEM: OBSOLESCENCE
31
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 61
5.00 Project walkthrough (Measure)
Problem No.
Pump Trip 60 nos
Hooter blows 120 nos
Conductivity not in range 30 times
Material not available due to obsolescence
10
Total 220 Nos
Datasheet ( 01/04/2017 to 01/04/2018) Data source: Logbook and notifications
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 62
5.00 Project walkthrough (Analyze)
Analyze
32
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
63
POWER SUPPLY 230V AC
RECORDER (LOCAL)
RELAY
CONDUCTIVITY MEASUREMENT
(LOCAL) PROCESS
DULCOMETER (LOCAL)
RESET SWITCH
ACKNOWLEDGE
SWITCH
LOCAL START
SWITCH
TANK
LOCAL
PID CONTROLLER
P/P
DOSING PUMP
PROTECTION LOGIC IN RECORDER
P/P TRIP
HIHI CONTACT FOR PUMP TRIP
TO CONTROL ROOM FOR DISPLAY
VARIABLE PULSE O/P
5.00 Project walkthrough (Analyze)
Alkalizer System: Detailed Analysis
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
64
5.00 Project walkthrough (Analyze)
33
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
65
Malfunction of measurment
USER EQUIPMENT
DESIGN MATERIAL
Improper training
Lack Of Awareness
Design Factor
Confined Space
Improper Purging
Pump Damage
Low Transport Water
Pump Run Without Water
lube Water Using For Other Work
Obsolesence
Pump Run Dry Pump Break Down
Poor Pipe Quality
Mounting Problem
Pump Suction Chocked
P/P piston Jam
System Design
Unavailability of spare
Movement
Design Criteria Confined Space
Foreign Material Obstructed
Less Skill
Improper Approach
Fluid stuck in pipe
Frequent damage Pipe
Pump Got Break Down Pump Not Take Start
Transport fluid Inadequate
MudDeposit
Cable loosness
Defective Diaphragm
Card problem Pump Discharge Chocked
Different Kind Of Use
Pipe Rapture
PipeStuck-up
No Start provision in control room
Pump not available
Pump Break Down
Maintenance Problem
Design Criteria
Lack Of Awareness Lack Of Awareness
Electrical Problem
Pump Chocked Due to foreign material
Problem in PSW dosing system
No auto start provision
Hooter problem
CAUSE & EFFECT DIAGRAM
5.00 Project walkthrough (Analyze)
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
66
Sl. No. Reason No of problems %
A USER
11 5%
B EQUIPMENT
33 15%
C MATERIAL
44 20%
D DESIGN
132 60%
TOTAL 220 100%
5.00 Project walkthrough (Analyze)
PARETO CHART
34
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
67
Y - Axis
MATERIAL DESIGN USER
100%
90%
80%
70%
60%
50%
30%
20%
10%
40% 9
3
6
0
20
60%
EQUIPMENT
No
. of
Pro
ble
ms
20% 15%
5%
80%
2
90%
Cause and Effect
PARETO ANALYSIS
PARETO CHART
5.00 Project walkthrough (Analyze)
Click to edit Master title style
Copyright © 2016 NTPC PMI All Rights Reserved. 68 Learning @ the speed of business
The future is now !
Obsolescence
Regular Failure
Unsafe
Local Access
Non Availability of Spares in market
Regular Retuning required in
maintaining Conductivity
Non Availability of Pump related
Annunciation
No Remote access to Retuning as
well as Pump Operation
RELEVANT CAUSES
5.00 Project walkthrough (Analyze)
35
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 69
5.00 Project walkthrough (Design)
Design
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
70
Phases of Design
Detail Analysis of Old Hardwire System
Compatibility of old system with existing DCS studied.
Interfacing issues were resolved
Logic was prepared to take care of all sub controller functions: 1.PID Controller 2.A/D converter 3.Frequency generator 4.Interfacing with Field devices
Remote Access given in UCB:
1.Remote Start/Stop
2.Protection Trip
3. Annunciation
Phase-I Phase-II Phase-III
5.00 Project walkthrough (Design)
36
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
71
DCS
PROCESS
TANK
P/P
CONDUCTIVITY MEASUREMENT
(LOCAL)
PSW Alkalizer System: DDCMIS Logic
5.00 Project walkthrough (Design)
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 72
GENERATOR
PRIMARY WATER IN LET
PRIMARY WATER OUT LET
NAOH TANK
DOSING P/P
DOSING
MEASURE DCS
ALL CONTROL AND INFORMATION
AVAILIABLE TO REMOTE OPERATOR
5.00 Project walkthrough (Design)
37
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 73
5.00 Project walkthrough (Design)
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 74
5.00 Project walkthrough (Verify)
Verify
38
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 75
After Implementation results are verified by trends.
5.00 Project walkthrough (Verify)
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 76
5.00 Project walkthrough (Verify)
Continuous monitoring of device
failure for 07 days
Found Zero failure
39
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 77
5.02 Project solution validation
Sap notification reduced to zero in last three months. Fit and forget concept.
Before After
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 78
5.02 Project solution validation
Parameter are with in range
Before After
40
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 79
5.02 Project solution validation
Interfaced with latest control system to cater to obsolescence
No inventory required for control system.
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 80
5.03 Project Solution justification
Cost required to procure latest Primary stator water dosing system:-
Refer :- Budgetary offer
Installation and Material Cost
Cost of Dulcometer Rs.50,000
Cost of Controller Rs.30,000
Cost of Up gradation quoted by BHEL-Haridwar in 2017
Rs.8.1 Lakhs
Total Cost for 1 Unit Rs.9 Lakhs approx.
41
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 81
5.03 Project Solution justification
COST BENFIT ANALYSIS
Cost required to implement proposed project solution:-
Two 24Vdc Relays Cable Cost Total Cost Approximately Rs.10,000/-
In terms of cost benefit analysis, implementation of proposed project cost 10 thousand over installation of new system, which
would have cost us 9 Lakhs. Hence, project is justified.
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
82
5.04 Project Results(Tangible benefits)
This give us net tangible benefit of 8.9 Lack ( implementation of proposed project cost 10 thousand over installation of new
system cost 9Lack)
We have achieved Our GOAL 100% in 1 Unit
implementation.
42
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
83
The Intangible Benefits in terms of Cost may seem improbable but if proper care is not taken then it may cause huge financial loss in the long run. Some Examples are mentioned below:
1.Wonogiri hydro power plant- Indonesia
2 Roxburgh hydro power plant- NewZealand
These Hydro power plants suffered stator winding failure in generator because of improper cooling due to deposit of oil , dirt and dust blocking the cooling passage.
5.04 Project Results(Intangible benefits)
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
84
Other examples where Unit had to be shut down for major overhaul because of copper corrosion in generator include:
1. San Onofre Nuclear Generating station – California.
2. Sundance-3 thermal power plant – Canada.
5.04 Project Results(Intangible benefits)
The Alkali shock, which occurs inside copper tubes and generator because of improper conductivity, is not visible immediately but it reduces the plant life drastically in the long run as we have seen in
the examples mentioned in the slide.
43
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
85
5.04 Project Results
Generator windings repair cost Rs. 113 crores
Unit outage for approx. 6 months
Rs. 135 crores
Generator copper tubes repair cost
Rs. 12 crores
Total Cost per unit of 500MW Rs. 260 crores ( approx)
In terms of intangible results if proper care is not taken to maintain conductivity either by running older system which ultimately affect the generator parameter
and resulting to huge financial loss in the long run
Copyright © 2016 Your Company All Rights Reserved.
Click to edit Master title style
86
5.04 Project Results
Other intangible results are :-
: Increased safety of working person during the maintenance .
: Increased self confidence & moral of team members .
: Improvement in team work .
: Improvement in knowledge sharing .
44
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 87
5.05 Maintaining the Gains
SL NO ACTIVITY RAW P/P REMARKS
1 Checking of Pump Trip
OK/NOT OK
2 Checking of Hooter blows
OK/NOT OK
3 Conductivity not in range
OK/NOT OK
5 Survey data is collected bimonthly from customer to determine if new changes are needed
DONE
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 88
5.04 Project Communication
DETAILED SAVED TO MAINTENANCE
FOLDER
SOP OF MAINTENANCE AND CHECKLIST
PREPARED
INFORMATION CIRCULATED TO ALL
45
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 89
5.06 Project Communication
DESIGN REVIEW +
TECHNICAL REVIEW +
QUALITY REVIEW
REWARDS AND RECOGNITION
+ INCLUSION OTHER UNITS OF
PLANT
WHO HOW RESULTED IN
CGM
Head of maintenance
GM (O&M)
Head of Total quality mgmt
Head of Business excellence
Head of Operation
Head of Chemistry
Group Head
Click to edit Master title style
Copyright © 2016 Your Company All Rights Reserved. 90
5.04 REWARDS AND RECOGNITION