Cleco Transmission Planning Summit 2011

40
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, 2011 10:00 – 11:00am

description

Cleco Transmission Planning Summit 2011. Coughlin Transmission Operations Center. April 15, 2011. 10:00 – 11:00am. Introduction. Welcome. Terry Whitmore, Mgr- Trans Planning & Operation Support James Simms, Lead Engineer- Transmission Planning - PowerPoint PPT Presentation

Transcript of Cleco Transmission Planning Summit 2011

Page 1: Cleco Transmission Planning Summit 2011

Cleco Transmission Planning Summit 2011

Coughlin Transmission Operations CenterApril 15, 2011

10:00 – 11:00am

Page 2: Cleco Transmission Planning Summit 2011

Welcome

Terry Whitmore, Mgr- Trans Planning & Operation Support

James Simms, Lead Engineer- Transmission Planning

Chris Thibodeaux, Sr. Engineer- Transmission Planning

Robby Michiels, Sr. Engineer- Transmission Planning

Introduction

Page 3: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 4: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 5: Cleco Transmission Planning Summit 2011

Economic Planning Studies

None were requested for 2011

Page 6: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 7: Cleco Transmission Planning Summit 2011

Acadiana Load Pocket ProjectUpdate

Page 8: Cleco Transmission Planning Summit 2011

Acadiana Load Pocket

Page 9: Cleco Transmission Planning Summit 2011

Acadiana Load Pocket ProjectYear 2010 Progress Report

• Flanders – Hopkins 138KV Transmission line tapped for new Segura substation.

• New Segura 230/138KV Cleco substation Phase I completed– 138KV facilities are presently energized– 230KV facility commission is scheduled for the end of second quarter

2011

• New Segura – Moril 138KV Transmission line completed & connected to Segura 138KV bus

Page 10: Cleco Transmission Planning Summit 2011

ALP Project Update – Summer 2010

•Cleco- 230KV Segura Substation

•Cleco- Segura to Moril 138KV Trans. Line (0.2 mi)

Note: Hopkins – Flanders 138KV line is tapped for new Segura substation. Just 138KV bus is energized at this point.

Page 11: Cleco Transmission Planning Summit 2011

ALP Project Update – Summer 2011

Page 12: Cleco Transmission Planning Summit 2011

ALP Project Update – Summer 2012

Page 13: Cleco Transmission Planning Summit 2011

ALP Project Update

Questions ?

Page 14: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 15: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Page 16: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Budgeted Projects

• Near term projects deal with Cleco’s obligations to the Acadiana Load Pocket Project and the Reliable operation of the Bulk Electric System.

Page 17: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Cleco 2011 Transmission ConstructionConstruction PlanPlanBudgeted

Projects

• Build a new 230KV Transmission line from Wells to the LUS Labbe Substation• Reconductor existing Segura – Hopkins 138KV transmission line (This will complete Cleco’s participation in the ALP project.)• Second 230/138KV Autotransformer at Cocodrie Substation

2012

• Construction of a new Rork 230KV Substation adjacent to the one at Richard• Build a new 230KV Transmission line from Rork to the Sellers Road Substation• Construction of a new 230KV Sellers Road Substation• Build a new 230KV Transmission line from Sellers Road to the Segura Substation• Construction of a new Mansfield Compressor 230KV Substation tapping Dolet Hills – Fisher 230KV line• Construction of a new Clarence – Maurice 69KV transmission line• Transmission element replacements on Plaisance – Coughlin 138KV transmission line

2011

Page 18: Cleco Transmission Planning Summit 2011

ALP Project Timeline (All participants)2011

• Cleco- 230KV Sellers Road Substation

• Cleco- 230KV Rork Substation

• Cleco- 230KV Rork - Sellers Road Trans. Line (30.1 mi)

• Cleco- 230KV Sellers Road- Segura Trans. Line (17 mi)

• Entergy- 230KV Sellers Road- Meaux Trans. Line (8.3 mi)

• Cleco- 230KV Wells - Labbe Trans. Line (17 mi)

• Entergy- 230KV Sellers Road - Labbe Trans. Line (14 mi)

• LUS- 230KV Labbe - Bonin Trans. Line (3 mi)

2012

• Cleco- Reconductor 138KV Segura- Hopkins Trans. Line (3 mi)[Serves to enhance the ALP project objectives]

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Page 19: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Long Range Planning- 5 years or greater

• System models used in the analysis go out 5 years and beyond •Inputs are extrapolated from short term planning estimates•Accuracy is therefore limited•Results are given leeway in terms of interpretation

•Long Term Planning does allow the identification of potential areas of concern•Attention is given to those problems that remain consistent over model runs especially those that get closer to the present•Typically, there is enough time to develop mitigation plans and fund projects

•Long Range Planning Analysis has identified some areas of concern•These occur at the end of the planning horizon•At this time, these areas don’t warrant the outlay of capital but will be noted

Page 20: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Regions in purple indicate potential planning criteria violations

Bus Under Voltage

Page 21: Cleco Transmission Planning Summit 2011

Cleco 2011 Construction PlanCleco 2011 Construction Plan2022 Study

CasesBus under voltage Violations

Mitigation: Investigate installation of capacitor banks at Pine Prairie.

Pine Prairie 138KV Bus Voltage 0.8907 P.U.

Most limiting Contingency: Coughlin – Pine Prairie 138KV Line

Oakdale 138KV Bus Voltage 0.8979 P.U.

Mitigation: Investigate installation of capacitor banks at Plaisance.

Most limiting Contingency: Coughlin – Plaisance 138KV Line

Plaisance 138KV Bus Voltage 0.885 P.U.

Page 22: Cleco Transmission Planning Summit 2011

Cleco 2011 Transmission Construction PlanCleco 2011 Transmission Construction Plan

Questions ?

Page 23: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 24: Cleco Transmission Planning Summit 2011

• New NERC standards mandated Cleco to re-evaluate all 100KV and above Transmission Line Ratings including the following elements:– Breakers– Switches– Conductor– Jumpers– Bus– CT Ratios– Wave Traps– Relay Setting Limits

Page 25: Cleco Transmission Planning Summit 2011

Results of Analysis

• Upgrade of multiple lines whose limiting element created base case overloads

• Since 2010– Changed Normal Rating temperature basis from 85° to 93°C

• Increased Normal Ratings

– Changed Normal and Emergency Rating procedures for jumpers

• Increased Normal and Emergency Ratings

Page 26: Cleco Transmission Planning Summit 2011

• Comparison of 2010 to 2011 SPP series of models:

– Cleco Transmission lines 100KV or greater• 51% had their A rating increase

– 8% had their A rating decrease

• 13% had their B rating increase– 1% had their B rating decease

– Cleco Tie Lines• 11% had their A rating increase

– 49% had their A rating decrease

• 19% had their B rating increase– 28% had their B rating decrease

• Refer to the SPP models for specific line ratings

Page 27: Cleco Transmission Planning Summit 2011

Facility Rating Changes

Questions ?

Page 28: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 29: Cleco Transmission Planning Summit 2011

Model Review• New Substations in Regional

models

• New 69KV Transmission Line

• N-1 ACCC Results

Page 30: Cleco Transmission Planning Summit 2011

Model Review New Transmission Line and

Substations in 2011 Regional models

Barker’s Corner

Youngsville

Mansfield Compressor

Clarence – Maurice 69KV Line

Page 31: Cleco Transmission Planning Summit 2011

LAGN : (2011)Barkers Corner 230KV Substation(moving load from other subs)

Model Review

New Substations in Regional models

Page 32: Cleco Transmission Planning Summit 2011

Model Review

New Substations in Regional models

CLECO : (2011)Mansfield Compressor 230KV Substation(Serving projected area load growth )

Page 33: Cleco Transmission Planning Summit 2011

ENTERGY : (2011)Youngsville 138KV Substation(Moves load off of 69KV System)

Model Review

New Substations in Regional models

Page 34: Cleco Transmission Planning Summit 2011

Model Review

New 69KV Transmission

Line in Regional models

Cleco : (2011)Clarence – Maurice 69KV Line

Page 35: Cleco Transmission Planning Summit 2011

SPP 2011 Series Model ACCC Results

Unmitigated Thermal Overloads

Champagne – Plaisance 138KV: 120% Contingency: Cocodrie – Ville Platte 230KV

Models: Summer/Winter 2013, 2017 & 2022 Limiting element resides outside of the Cleco Control Area Will be monitored in subsequent years

Page 36: Cleco Transmission Planning Summit 2011

SPP 2011 Series Model ACCC Results

Unmitigated Long Range Low Bus Voltages

Oakdale & Pine Prairie 138KV : 0.89PU Contingency: Coughlin – Pine Prairie 138KV

Model: Summer 2022 Long Range Mitigation Plan considers adding capacitor banks at

Pine Prairie

Plaisance 138KV : 0.885PU Contingency: Coughlin – Plaisance 138KV

Model: Summer 2022 Will monitor this voltage in future years

Page 37: Cleco Transmission Planning Summit 2011

Model Review

Questions ?

Page 38: Cleco Transmission Planning Summit 2011

Agenda

• Introduction

• Economic Planning Studies

• Acadiana Load Pocket Project Update

• 2011 Transmission Construction Plan

• Facility Ratings Changes

• Model Review

• Stakeholder Business

• Final Questions

• Adjourn

Page 39: Cleco Transmission Planning Summit 2011

Stakeholder Business

• Chance for Stakeholders to bring issues up for discussion

Page 40: Cleco Transmission Planning Summit 2011

Final Questions?