cien-166-1-009.pdf

download cien-166-1-009.pdf

of 1

Transcript of cien-166-1-009.pdf

  • 7/27/2019 cien-166-1-009.pdf

    1/19

    Civil Engineeringvolume 166 Issue CE1 February 2013

    ttp://dx.doi.org/10.1680/cien.2013.166.1.9

    Using building information modellingon a highway projectSibert

    ICE Publising: All rigts resered

    For further information contact: Ben Sibert Tel: +44 29 2047 3727 Email: [email protected] Web: www.a465brynmawr2tredegar.co.uk

    Using building information modellingon a highway project

    BRIEFING:INNOvATION

    Building information modelling (BIM) is to be implemented on all UK government construction projects

    by 2016 to help cut costs. Ben Sibert of Arup explains how BIM is being used on a section of the A465

    highway dualling in south Wales and the lessons being learned on the way.

    Te Wels goernments 150 million A465

    Brynmawr to Tredegar project inolesdualling 78 km of te eads of te alleysroad in sout Wales. Work started onsite at te end of 2012 and te project is

    due for completion by 2015. ContractorCarillion, engineering consultancy Arupand enironment consultancy TACP are

    deeloping teir approac to buildinginformation modelling (BIM) on te projectto elp cut costs.

    Te BIM plan coered work stages,model elements, file system and designreiew. For work stages, te Royal

    Institute of Britis Arcitects (RIBA) stages

    were adopted. Model elements wereplanned across te Specification for

    higway Works eadings, and te filesystem is Bentleys Projectwise. 4Projectsis used as te static data store for

    completed design data.

    Improed understanding

    During work stage D design

    deelopment te project team

    deeloped a complete model of all of te

    aboe-ground features. It was deelopedinto a drie-troug ideo, wic elpedcommunicate wit te public during tedraft orders stage.

    Te ideo added real alue for te clientbecause it communicated te scemeclearly and sowed people exactly wat

    tey could expect in a way two-dimensionaldrawings could not. Only tree objectionsto te draft orders remained at te public

    inquiry in Marc 2012.At te end of 2012, te team ad

    completed its stage E design tecnical

    design. Te wole of te igway and

    all its features were ten assembled intoa reiew enironment using Autodesks

    Naisworks, resoling conflicts to stageF production information wit acoordinated design.

    Bot te client and contractorbenefited from being able to detectproblems in a tree-dimensional

    enironment before construction started.

    Issues and lessons

    Certainly, te project teams ability and

    willingness to take on new tings asbeen important to BIMs success on tissceme so far.

    An important callenge for softwareproiders as been to facilitate inter-compatibility and flexibility of coice.

    Eac discipline uses a different softwarepackage and different reiew platformsae different merits. It is adisable to

    retain flexibility on te coice of softwareas firm decisions now may exclude

    partners of te future.

    Wit regard to programme, projectteams sould also consider allocatingmore time to stage E in adance ofstage F. Furter suggestions include

    supplementing te original RIBA workstage plan wit Te American Instituteof Arcitects leel of deelopment

    requirements to proide a better interfacewit te wider market.

    Object-based modelling sould also

    be increased. Eac part of te constructionis modelled as an object wit embeddedmaterials and property information. Tese

    attributes can be taken forward into

    different reiew platforms to aid witconstruction planning and ultimately wit

    asset management.

    Conclusions so far

    Te A465 Brynmawr to Tredegar

    project as demonstrated tat BIM canproide a structured approac to designdata storage and saring for design

    teams, constructors and operators. It asimproed coordination and olistic designfor multidisciplinary teams, and been

    elpful in communicating constructionsequences and programme.

    howeer, it is important to get te

    best out of different software packagesand not to restrict ariety. Differentplatforms ae different merits and

    proide flexibility for collaboration witdifferent partners. Te design alsoneeds to be modelled at object leelto aid construction planning and asset

    management.

    A complete building information model of te

    A465 dualling sceme in sout Wales as sofar significantly facilitated planning, designcoordination and construction planning

    Bot te client and contractor benefited from beingable to detect problems in a tree-dimensionalenironment before construction started