CHINA POWER TRANSFORMER EFFICIENCY PROGRAM · Web viewS7, S8, S11 and S15 are the model numbers of...
Transcript of CHINA POWER TRANSFORMER EFFICIENCY PROGRAM · Web viewS7, S8, S11 and S15 are the model numbers of...
CHINA POWER TRANSFORMER EFFICIENCY PROGRAM
Environmental Management Plan
The State Grid Corporation of ChinaJune 10, 2010
1
E2653
Table of Contents
1. Introduction......................................................................................................................3
2. Project Description.......................................................................................................3
2.1 Project Scope.........................................................................................................3
2.2 Project Locations...................................................................................................4
2.3 Major Project Activities and Institutional Arrangements.....................................5
3. Major Chinese Laws and Regulations Applicable to the Project.................................8
4. Major Impacts and Mitigation Plan..............................................................................9
5. Implementation Arrangements for Environmental Management and Monitoring and Reporting Procedures…...…………………………………………..15
6. Public Consultation………………………………………………………………....15
Annex 1. Names of the participants in the public consultation.........................................18
2
1. Introduction
In order to reduce power distribution losses, improve energy efficiency and reduce CO2
emissions, the State Grid Corporation of China (hereinafter referred to as SGCC) intend to implement the SGCC Transformer Efficiency Program. This Program is to replace low efficiency in-service 10 kV distribution transformers (Type S7 or Type S8 transformers1) with high efficiency 10 kV distribution transformers (whose no-load losses are compliant with or better than Type S11 transformers) to reduce the losses of transformers of the power distribution system of SGCC. Currently there are around 120,000 inefficient S7/S8transformers serving the distribution network of SGCC. Most of these S7/S8 transformers were installed in late 80s and 90s and still have remaining lifetime of at least 5 years.
The purpose of this Environmental Management Plan (EMP) is to be used to provide guidance to related SGCC departments and subsidiaries which will implement the proposed program for the environmental management and monitoring process to be followed in implementing individual sub-projects under the Program. This EMP defines the contents, procedures and institutional responsibilities for environmental management of the sub-projects. The purpose of the EMP is to ensure the transformer replacement program will be carried out in compliance with both Chinese environmental laws and regulations SGCCs’ policies and procedures for environment, health and safety and/or best international practice in accordance with World Bank/IFC Environment, Health and Safety Guidelines.
2. Project Description
2.1 Project Scope
The proposed project is to replace low efficiency in-service 10 kV distribution transformers (Type S7 or Type S8 transformers) with high efficiency 10 kV distribution transformers (whose no-load losses are compliant with or better than Type S11 transformers) to reduce the losses of transformers of the power distribution system of SGCC. It will replace around 120,000 inefficient S7/S8 distribution transformers with S11 transformers or transformers of higher efficiency than S11 from 2010 to 2012 in power grids in 26 provincial subsidiary grid companies (GCs) owned by SGCC. The program will be implemented from mid 2010 to end of 2012.
All the transformers to be eligible for replacement will be:
10 kV (or 6 kV) distribution transformers; Type 7 or type 8
1 S7, S8, S11 and S15 are the model numbers of distribution transformers in China, the higher number of the series, the more advanced the technology and the higher the efficiency.
3
Manufactured after 1985 (including 1985) and before January 31, 1999; Free of any current oil leaks or other insulation problems; Located at a site which currently meets environmental, health and safety
requirements of the People’s Republic of China and related SGCC environment, health and safety provisions as determined by SGCCs’ due diligence review and;
Free of any oils containing polychlorinated biphenyls (PCBs)
All the new transformers to be installed to replace the existing inefficient transformers will be:
Dry types, modern oil immersed, and/or other modern types of transformers manufactured to meet current related Chinese and related international industrial standards, as well as related environment, health and safety regulations in China
S11 efficiency of better Free of PCBs.
As the trustee of the Danish Carbon Fund (DCF) and Spanish Carbon Fund (SCF), the World Bank intends to purchase Certified Emission Reductions (CERs) to be generated by the China Transformer Efficiency Project. ERPA payments will be made annually based on actual CERs verified by a Designated Operational Entity (DOE), an independent auditing company, and issued by the CDM Executive Board which supervises the CDM for UNFCCC Parties.
2.2 Project Locations
The geographical boundary of the program is the 25 provinces within China as listed below.
Table 1: Project LocationsRegional grid Dominant provinces Sub-total
Northeast China Region
Liaoning Province, Jilin Province, Heilongjiang Province, Inner Mongolia Autonomous Region, 4
North China Region
Beijing Municipality, Tianjin Municipality, Hebei Province, Shanxi Province, Shandong Province
5
East China Region
Shanghai Municipality, Jiangsu Province, Zhejiang Province, Anhui Province, Fujian Province
5
Central China Region
Henan Province, Hubei Province, Hunan Province, Jiangxi Province, Sichuan Province, Chongqing Municipality
6
Northwest China Region
Shaanxi Province, Gansu Province, Qinghai Province, Ningxia Hui Autonomous Region, Xinjiang Uygur Autonomous Region
5
Total - 25
The project will be implemented along selected 10 kV distribution lines owned and operated by the SGCC where eligible inefficient 10 kV distribution transformers are installed, and places where the replaced transformers will be storage, and dismantled
4
These places are owned by SGCC or by licensed contractors. No land acquisitions, either permanent or temporarily, are required.
2.3 Major Project Activities and Institutional Arrangements
Replacement of old transformers with new transformers
The replacement includes disassembling existing low efficiency transformers and installing of new highly efficient transformers in the distribution lines within designated areas. As the proposed project will only replace existing distribution transformers with more efficient transformers in SGCC's 10 kV distribution systems and there are no civil works required for the proposed project.
The typical sizes of 10 kV distribution transformers are in the range of one (1) to two (2) cubic meters. The replacement of these transformers is very simple and straight forward. Usually, an estimated two to four-hour power shutoff of nearby districts is required. Because the replacement activities will take place in the existing 10 kV power distribution systems, it does not require temporary occupation or permanent acquisition of additional land. Therefore, no involuntary resettlement is required. In addition, no significant noise is anticipated to occur, or dust to be produced in the replacement process.
5
Fig. 1. Replacement of 10 kV Distribution Transformers
Storage and Disposal
The replaced the old transformers will be transported to special storages either owned by SGCC directly or owned and operated by qualified and licensed transformer disposers. Again, in either case, related regulations/procedures of the Government and SGCC will be followed.
The disposal of the old transformers will be carried out by licensed special waste recycling companies. Usually, the replaced old transformers will be sold by the SGCC’s provincial subsidiary companies to licensed recycling companies where old transformers will be dismantled: some materials will be recovered and recycled (e.g. metals, oils etc.) and the remaining materials (porcelain, glass etc.) will be disposed.
Since all the transformers involved were made in China after mid 1980s, there are no issues of disposal of polychlorinated biphenyls (PCBs). Experience also indicated that the possibility of oil leakages of the distribution transformers to be replaced is extremely low. In fact, transformers with oil leakage will not be qualified for the project2. The
2 Transformers with at least a five year remaining life under normal operation conditions will be qualified for the CDM project. Transformers that are currently leaking oil will not qualify for the project.
6
transformer oils are basically petroleum products. It can be recycled and re-used. No significant secondary pollution is expected.
Fig 2. Dismantling of Old 10 kV Distribution Transformers
Implementation Institutional Arrangements
SGCC is the implementation agency. SGCC headquarters will play a leading and coordinating role in the project implementation. It will be responsible for planning, subproject approval and be the focus point of the company in dealing with the World Bank and related government agencies. SGCC has prepared <<The SGCC Distribution Transformer Program Management Measures>> in order to ensure the effective implementation.
The 25 provincial grid companies (GCs) of SGCC will be responsible for identifying and implementing the subprojects in their own service areas. Within each province, the various municipal and county-level operation divisions of the provincial GC will be responsible for replacing the transformers identified eligible under this program.
The old transformers will be dismantled and disposed by licensed contractors. The contractors will be recruited by each provincial company through a competitive bidding process in according to SGCC’s policy. All the contractors will be regulated by relevant local authorities, especially in the areas of waste treatment, recycling and disposal. These
7
contractors should also have special licenses which allow them to dismantle and disposal electric power supply equipment, such as power transformers.
SGCC has well established institutional arrangements internally to deal with environmental, health, safety and social issues related to its operation and development. At each level of the company (headquarter, provincial and municipal), there are departments or divisions responsible for environmental, health and safety management and monitoring. These business units are staffed with fully or partially specialized environmental protection personnel who will directly provide technical supports to the project implementation.
3. Major Chinese Laws and Regulations Applicable to the Project
Laws, regulations and SGCC Provisions applicable to the project are listed below.
Table 2: Environment, Health, Safety and Emergency SpecificationsArea Level Project Related Regulations
Safe
ty a
nd G
ener
al E
HS State Safe Production Act of the Peoples Republic of China (PRC)
SGCC
SGCC Power Construction Safety, Health and Environmental Management Regulation [2003] No.168
SGCC Environmental Assessment for Power Construction Safety and Health Management Practices (Pilot) [2004] No. 488
SGCC Operational Safety Supervision Provisions [2003] No. 408
Emer
genc
y Pr
epar
edne
ss a
nd R
espo
nse State
Emergency Preparedness Act of PRC [Presidential Order, No. 69, 2007]
Guidelines for Enterprises to Develop Emergency Response Plan for Work Place Accidents [2006]
Sector
SGCC
SGCC Emergency Response Plan [2007] No. 98
SGCC Emergency Management Regulations 〔2007 〕 No. 110
Construction Hazard Prevention and Emergency Response [2004] No. 264
Envi
ronm
enta
l State Environmental Protection Law of PRC
SGCC– General
SGCC Environmental Management Approach
SGCC Environmental Protection Requirements
SGC Environmental Protection Evaluation Methods
8
Area Level Project Related Regulations
SGCC– Construction
SGCC Provisions for Energy-Saving and Environmental Protection Technical Supervision
SGCC Interim Measures for Power Grid Project Construction Environmental Impact Assessment
SGCC Interim Measures for Power Grid Project Construction Completion Environmental Protection Approval
SGCC Power Grid Construction Project Management Guideline for Soil and Water Conservation
Dis
man
tling
and
Dis
posa
l
State
Solid Waste Treatment and Pollution Prevention Law of the People’s Republic of China, Dec. 29, 2004
Resource Recycling and Reuse Management Regulation. The Ministry of Commerce, the National Development and Reform Commission; the
Ministry of Public Security, the Ministry of Construction, the National Administration of Industrial and Trade, the Environment Protection
Administration, May 1, 2007
SGCCSGCC Equipment and Material Transportation and Storage Management
Policy;
SGCC Old Equipment Disposal Management Policy.Local
governmentsResource Recycling and Reuse Management Regulations stipulated by
various local governments.
9
4. Major Impacts, Mitigation and Monitoring Plans
A. MITIGATION PLAN
Issue Mitigating Measure
Cost of Mitigation
(If Substantial)
Responsibility Start End
Replacement of the Transformers
Dust The construction normally doesn’t result in dust pollution and doesn’t require special
preventive measures. If necessary, the construction site will be sprinkled with water, especially during hot, dry and/or
windy conditions..
MinorMunicipal or county-level ( Grid Companies) GCs
At beginning of replacement
At end of replacement
Audible Noise Construction activities will be performed only during working hours (8 AM to 6
PM). If construction activities is close to residential areas and have to be performed before or after the specified time limits, the local society must be notified at least one
week in advance.
MinorMunicipal or county-level
GCs
At beginning of replacement
At end of replacement
Traffic Disruption
Conduct work during periods of light traffic (after rush hour) and to avoid peak
time of electricity consumption
Identify alternate traffic route(s) and place clearly marked signs
MinorMunicipal or county-level
GCs
At beginning of replacement
At end of replacement
Soil Contamination caused by oil
leaks.
Given the small sizes of the transformers, soil contamination from oil leaks, if any,
will be light.In accordance with SGCC standard
MinorMunicipal or county-level
GCs
At beginning of replacement
At end of replacement
10
Issue Mitigating Measure
Cost of Mitigation
(If Substantial)
Responsibility Start End
procedures, if there is light contamination, soil will be removed by Grid Company placed in plastic bags and transported to
sites approved by environmental authorities.
Non-toxic solid wastes (metal,
packing and used equipment, etc.)
To be removed to places specially allocated for landfills or recycle, approved by local
authorities
MinorMunicipal or county-level
GCs
In the beginning of construction
After completion of construction
Occupational Health and Safety(OHS)
&Emergency
Preparedness and Response (EPR)
SGCC has well established OHS procedures and emergency response system (see Table 2).This system is
consistent with IFC Guidelines (General EHS and Electric Power Transmission and Distribution). This system will be in effect
during removal of old transformers. No additional OHS and EPR requirements are
needed
MinorMunicipal or county-level
GCs
At beginning of replacement
At end of replacement
Storage and Disposal of the Old Transformers
Solid Waste and liquid
Management for old transformer
Old transformers will be transported to special storage facilities either owned by SGCC directly or owned and operated by
qualified and licensed transformer disposers. The storage facilities will have a concrete base or heavy plastic sheet as the base and designed to contain and collect
any oil leaks. The facilities will be locked. Eventually, the old transformers will be
collected by a licensed contractor for disposal for scrap recycling.
Bidding documents will specify that the contractor should have valid business
license for dismantling and disposal of old
Minor and part of the operation
budget.
Medium, and part of the operation
costs of the
Provincial, Municipal or county-level GCs
Qualified and licensed contractors.
At beginning of Storage
After the replaced
transformers are handed over to
the licensed contractor for
disposalAt the end of the
disposal.
11
Issue Mitigating Measure
Cost of Mitigation
(If Substantial)
Responsibility Start End
transformer and that the waste materials would be transported to sites officially
approved by the local municipal authorities or delivered to companies that are licensed
to recycle any recovered oils or scrap materials. All the disposal and recycling
activities will follow “Solid Waste Treatment and Pollution Prevention Law of the People’s Republic of China” and related Resource Recycling and Reuse Management Regulations stipulated by
various government agencies.
contractors.
At beginning of dismantling.
Operation of the New Transformers
Occupational Health and Safety(OHS)
&Emergency
Preparedness and Response (EPR)
SGCC has well established environment and OHS procedures and emergency
response system. This system is consistent with IFC Guidelines (General EHS and
Electric Power Transmission and Distribution).The SGCC system will be in effect during installation and operation of the new transformers. No additional OHS
and EPR requirements are needed
Minor Provincial, Municipal or county-level GCs
At beginning of operation
Continuous
12
B. MONITORING PLAN
What parameter is to be monitored?
Whereis the parameter
to be monitored?
Howis the parameter to be
monitored/ type of monitoring equipment?
Whenis the parameter to
be monitored-frequency of
measurement or continuous?
Monitoring Cost
What is the cost of equipment or
contractor charges to perform
monitoring
Responsibility Start End
Replacement of Old Transformers
Dust At project site, along
equipment/materials delivery
routes
Visual Daily SmallMunicipal or county-
level GCs
At beginning of replacement
At end of replacement
Audible Noise Construction site
Observation that specified construction
times are obeyed
During replacement
SmallMunicipal or county-
level GCs
At beginning of replacement
At end of replacement
Traffic flow conditions
At site of detour Visual When detour is established
Small Municipal or county-level GCs
At beginning of replacement
At end of replacement
Non-toxic solid wastes (metal,
packing and used equipment, etc.)
At construction site
Visual Prior to removal of scrap transformer
Small Municipal or county-level GCs
At beginning of dismantling
At end of dismantling
Soil contamination At equipment storage location
and/or construction
site
Visual Weekly Small Municipal or county-level GCs
At beginning of dismantling
At end of dismantling
Occupational Health and Safety(OHS)
& Emergency
At construction site
Visual Daily Small Municipal or county-level GCs
At beginning of replacement
At end of replacement
13
Preparedness and Response (EPR)
Storage and Disposal of the Old Transformers
Condition of SGCC used
transformer storage site
Checking contractors qualifications, including
license validation.
Checking the dismantling and
disposal processes of the contractors on the
spot
SGCC used transformer storage site
In SGCC’s Office, but may
require site visits to the
facilities of the potential
contractors.
In the contractors’
facilities
Visual -Used transformers placed on concrete
base. Site locked. Oil leaks properly contained and
collected
Visual
Visual
Weekly
During the bidding evaluation.
At least once
Small
Small
small
Provincial, Municipal or county-
level GCs
Provincial, Municipal or county-
level GCs
Provincial, Municipal or county-
level GCs
At beginning of storage
At the beginning of
the bid evaluation
At the beginning of
the dismantling and disposal
At end of storage
At the end of the bid evaluation
At the end of the dismantling and
disposal
Operation of Replacement Transformer
Occupational Health and Safety(OHS)
&EmergencyPreparedness and Response (EPR)
At transformer site
Visual During maintenance SmallProvincial,
Municipal or county-level GCs
During maintenance
During maintenance
14
5. Implementation Arrangements for Environmental Management And Monitoring and Reporting Procedures
Table 3: Institutional Arrangements for Implementation
15
Action Institutional ResponsibilityMonitoring Data Collection
(From Monitoring Plan)Replacement of Old Transformers
Storage and Disposal of Old Transformers
Operation of Replaced Transformers
Municipal Operation division of provincial GC /installation contractor
Municipal Operation division of provincial GC /qualified contractor
Municipal Operation division of provincial GC
Data AnalysisReplacement of Old Transformers
Storage and Disposal of Old Transformers
Operation of Replaced Transformers
Municipal Operation division of provincial GC /installation contractor
Municipal Operation division of provincial GC /qualified contractor
Municipal Operation division of provincial GCEnvironmental Report PreparationReplacement of Old Transformers
Storage and Disposal of Old Transformers
Operation of Replaced Transformers
Municipal Operation division of provincial GC /installation contractor
Municipal Operation division of provincial GC /qualified contractor
Municipal Operation division of provincial GC
Environmental Report Receipt/Frequency (Who receives report/how often)Replacement of Old Transformers
Environment reports are to be prepared annually and sent to the project team in the HQ of SGCC
Storage and Disposal of Old TransformersEnvironment reports are to be prepared semi-annually and sent to the project team in the HQ of SGCC
Operation of Replaced TransformersEnvironment reports are to be prepared annually and sent to the project team in the HQ of SGCC
Management ActionReplacement of Old Transformers
Storage and Disposal of Old Transformers
Operation of Replaced Transformers
Municipal Operation division of provincial GC /installation contractor
Municipal Operation division of provincial GC /qualified contractor
Municipal Operation division of provincial GC
16
6. Public Consultation
Public consultation was conducted on July 8, 2009 in Beijing and on July 9 and 10, 2009 in Shenyang City of the Liaoning Province where subprojects have been identified. Before the public consultation, an announcement was posted in the State Grid News, on June 25, 2009. The State Grid News is an accredited newspaper publicly issued both paper and internet editions in China and the covers all the project areas.
Representatives of the SGCC (implementing agency), government (the Ministry of Environment), affected communities, manufacturers and academics participated in the public consultation.
During the public consultation, the representatives of SGCC introduced the project design and the draft environmental management plan and SGCC’s relevant environment, health and safety regulations and policies to the participants. All of participants believed that the negative environmental and social impacts of the proposed project, by nature, are very limited and manageable. No significant issues were raised.
17
Annex 1. Names of the participants in the public consultation
Institutions Name and Title Invitation by Date of Invitation
State Grid Corporation of China
ZHOU, XinfengVice-Division Chief of the
Department of Production and Technology
Telephone 2009.07.03
State Grid Corporation of China
LIN, XujunEngineer of the Department of
Production and Technology
Telephone2009.07.03
International Equipment and Technology Co. of SGCC
SUN, MengDeputy Director, Dept.of
Development and Planning
Telephone2009.07.03
International Equipment and Technology Co. of SGCC
DUAN, XiaohuaDeputy Director, Dept. of
Technical Support
Telephone2009.07.03
International Equipment and Technology Co. of SGCC
XU, ShengtingInternational Dept.
Telephone 2009.07.03
International Equipment and Technology Co. of SGCC
GUO, XuejianDept. of Technical Support
Telephone 2009.07.03
International Equipment and Technology Co. of SGCC
MENG, ZhongweiDept.of Development and
Planning
Telephone2009.07.03
International Equipment and Technology Co. of SGCC
XIE, ShaofenDept.of Development and
Planning
Telephone2009.07.03
International Equipment and Technology Co. of SGCC GUO, Xin Telephone 2009.07.03
Municipal Power Grid Company of Beijing
ZHU, MinEngineer for Distribution
System
Telephone2009.07.06
Consultant JIANG Shan Telephone 2009.07.03Consultant PAN, Tao Telephone 2009.07.03
Energy Research Institution of the National
Development and Reform Commission
MI, ChuanDeputy Division Chief
Letter of Invitation 2009.07.06
The Ministry of Environment
XIAO, XuezhiInternational Cooperation
Center
Letter of Invitation 2009.07.06
Community Representative WU, Xuequn Public Announcement 2009.07.06
Community RepresentativeLI, Hongqing
Public Announcement 2009.07.06
18
Institutions Name and Title Invitation by Date of Invitation
Community RepresentativeWANG, Hongsong
Public Announcement 2009.07.06
Community RepresentativeSONG, Jinkao
Public Announcement 2009.07.06
Xinjiang Transformer Plant ZHANG, Yinzhong Letter of Invitation 2009.07.03
Huapeng Transformer Company of Jiansu Province
DI, JingxiangDeputy General manager
Letter of Invitation 2009.07.03
Tian Wei Shun Da Transformer Company of
Baoding
SHANG, HuikaiTechnical Specialist
Letter of Invitation 2009.07.03
Da Chi Electrical Equipment Company of
Shandong Province
JIA, XiangheBeijing Chief Representative
Letter of Invitation 2009.07.03
China Electric Power Research Institute
CHENG, HuachaoDistribution Transformer
Specialist
Letter of Invitation 2009.07.03
19