Chiller Checklist
-
Upload
mohammed-sayeeduddin -
Category
Documents
-
view
14 -
download
0
description
Transcript of Chiller Checklist
!"#$%&'#()*+',+%&#-.,/%0#1%2%*&%#345# 6478#
!"#9/%*&#:;)#"*<;)#=>.,?@%A'#BC?%&#
It should be noted that this cost savings calculation does not account for an electric peak demand reduction. If the facility has a peak demand charge, and the chiller operates everyday with on operational schedule that is coincident with the facilities peak demand, then this estimate slightly underestimates the cost savings.
Condenser Temperature Reset Energy Savings and Economics Example
Example Synopsis: A water cooled centrifugal chiller currently has an entering condenser temperature of 55°F. After inspection it was determined that the temperature controls can allow modulation down to 52°F during low load periods. The operators estimate that the chiller can operate at 52°F for 3,000 hrs per year, and the chiller has an electrical load of 300 kW when operating at these low load conditions. The average electric rate is $0.10/kWh.
The annual energy savings can be estimated as:
The annual cost savings can be estimated as:
!"! !#$%&'(()*$+,-)*./0)$1)0-$2*,3-'3)0$
The predominant impact chillers have on water use relates to proper function. An inef#cient chiller will require longer hours of operation to satisfy the load. It is these additional hours that result in greater water use though evaporation at the cooling tower and any leaks in the system. Any inef#ciency results in a less-than-optimal operation leading to increased resource use – water is one of those resources.
!"!#4$ %&'(()*0$%&)35('0-$
Description Comments Maintenance Frequency
Daily Weekly Semi-
Annually
Annually
Chiller use/sequencing Turn off/sequence unnecessary chillers X
Overall visual inspection Complete overall visual inspection to be sure all equipment is operating and safety systems are in place
X
Check setpoints Check all setpoints for proper setting and function
X
Evaporator and condenser Assess evaporator and condenser coil fouling as required
X
Compressor motor temperature
Check temperature per manufacturer’s speci#cations
X
647D# !"#$%&'#()*+',+%&#-.,/%0#1%2%*&%#345#
!"#9/%*&#:;)#"*<;)#=>.,?@%A'#BC?%&#
Description Comments Maintenance Frequency
Daily Weekly Semi-
Annually
Annually
Perform water quality test Check water quality for proper chemical balance
X
Leak testing Conduct leak testing on all compressor #ttings, oil pump joints and #ttings, and relief valves
X
Check all insulation Check insulation for condition and appropriateness
X
Control operation Verify proper control function including: • Hot gas bypass • Liquid injection
X
Check vane control settings
Check settings per manufacturer’s speci#cation
X
Verify motor load limit control
Check settings per manufacturer’s speci#cation
X
Verify load balance operation
Check settings per manufacturer’s speci#cation
X
Check chilled water reset settings and function
Check settings per manufacturer’s speci#cation
X
Check chiller lockout setpoint
Check settings per manufacturer’s speci#cation
X
Clean condenser tubes Clean tubes at least annually as part of shutdown procedure
X
Eddy current test condenser tubes
As required, conduct eddy current test to assess tube wall thickness
X
Clean evaporator tubes Clean tubes at least annually as part of shutdown procedure
X
Eddy current test evaporator tubes
As required, conduct eddy current test to assess tube wall thickness
X
Compressor motor and assembly
• Check all alignments to speci#cation • Check all seals, provide lubrication
where necessary
X
Compressor oil system • Conduct analysis on oil and #lter • Change as required • Check oil pump and seals • Check oil heater and thermostat • Check all strainers, valves, etc.
X
Electrical connections Check all electrical connections/ terminals for contact and tightness
X
Water %ows Assess proper water %ow in evaporator and condenser
X
Check refrigerant level and condition
Add refrigerant as required. Record amounts and address leakage issues.
X
Chiller Checklist (contd)
!"#9/%*&#:;)#"*<;)#=>.,?@%A'#BC?%&#
!"!##$$6,78()$%&'(()*$98)*,-':;$<:=$
Job Name Date
Unit Tag
Model # Time
Serial #
Full Load Design
__________degF
__________Volts
__________Hertz
__________RLA
_____PSID_____gpm
__________degF
__________degF
__________degF
_____PSID_____gpm
__________degF
__________degF
__________degF
Operating Condition
Operating Code
Last Diagnostic
LCHW Setpoint
Current Limit Setpoint
Start #
Run Hours
Volts – AB
Volts – AC
Volts – BC
Amps L1
Amps L2
Amps L3
Amps AVG
% of RLA
Oil Sump Temperature
Oil Temperature to Bearings
Oil Level
Low Oil Pressure
High Oil Pressure
Net Oil Pressure
Operating Purge Pressure
Operating Purge Oil Level
Purge Starts
Purge Run Hours
CHW PSID
CHW Temperature in
CHW Temperature out
CHW Temperature Differential
CHW Makeup Water
Evaporator Temperature
Evaporator Pressure
CW PSI Differential
CW Temperature in
CW Temperature out
CW Temperature Differential
Condenser Temperature
Condenser Pressure
Cooling Tower Makeup Water
CHW Makeup Water
Operator Initials
!"#$%&'#()*+',+%&#-.,/%0#1%2%*&%#345# 6476#