ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS MULTI CABLE TRANSIT Project Name : WORTEL FIELD DEVELOPMENT PROJECT Customer : SANTOS (Sampang) Pty. Ltd. E03 Drawing Reff. / Rev : System / Sub No. : 9820-U-009 Single Line No. / R : System Desc. : Control Room Building S Location / Area : E/I Building Sub System Desc. : 9820-U-009-1 No. Inspection Check List Tag No. 1 Check frame material have correct specifiction and size 2 Check frame design accordance with design drawing 3 4 Check that frame have completed fabrication work 5 Check that MCT frame location refer to layout 6 Check that support have completed finishing work 7 8 Check that MCT installed at correct location refer to layout 9 10 Check that MCT accessories are installed correctly 11 12 Notes : Description Performed by Witnessed / Approved by Witnessed / Approved Company Signature Print Name Check frame have correct dimension accordance to design drawing Check MCT specification refer to MTO and company specification Check that MCT installation arrangement refer to installation detail SANTOS (SAMPANG ) PTY LTD

description

xf

Transcript of Check List MCT

Page 1: Check List MCT

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

MULTI CABLE TRANSIT

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd. E03MC

Drawing Reff. / Rev : System / Sub No. : 9820-U-009

Single Line No. / Rev : System Desc. : Control Room Building System

Location / Area : E/I Building Sub System Desc. : 9820-U-009-1

No. Inspection Check List

Tag No.

1 Check frame material have correct specifiction and size

2 Check frame design accordance with design drawing

3 Check frame have correct dimension accordance to design drawing

4 Check that frame have completed fabrication work

5 Check that MCT frame location refer to layout

6 Check that support have completed finishing work

7 Check MCT specification refer to MTO and company specification

8 Check that MCT installed at correct location refer to layout

9 Check that MCT installation arrangement refer to installation detail

10 Check that MCT accessories are installed correctly

11

12

Notes :

Description Performed by Witnessed / Approved by Witnessed / Approved by

Company

Signature

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 2: Check List MCT

Date

Page 3: Check List MCT

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

MULTI CABLE TRANSIT

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd. E03MC

Drawing Reff. / Rev : 9820-64-352-2 System / Sub No. : 9820-U-009

Single Line No. / Rev : System Desc. : Control Room Building System

Location / Area : E/I Building Sub System Desc. : 9820-U-009-1

No. Inspection Check List

Tag No.

9820-MCT-E01

IND

OK

OM

AS

PA

L

SA

NT

OS

1 Check frame material have correct specifiction and size

2 Check frame design accordance with design drawing

3 Check frame have correct dimension accordance to design drawing

4 Check that frame have completed fabrication work

5 Check that MCT frame location refer to layout

6 Check that support have completed finishing work

7 Check MCT specification refer to MTO and company specification

8 Check that MCT installed at correct location refer to layout

9 Check that MCT installation arrangement refer to installation detail

10 Check that MCT accessories are installed correctly

Notes :

Description Performed by Witnessed / Approved by Witnessed / Approved by

Company

Signature

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 4: Check List MCT

Date

Page 5: Check List MCT

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

MULTI CABLE TRANSIT

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd. E03MC

Drawing Reff. / Rev : 9820-64-352-2 System / Sub No. : 9820-U-009

Single Line No. / Rev : System Desc. : Control Room Building System

Location / Area : E/I Building Sub System Desc. : 9820-U-009-1

No. Inspection Check List

Tag No.

9820-MCT-E02

SA

NT

OS

1 Check frame material have correct specifiction and size

2 Check frame design accordance with design drawing

3 Check frame have correct dimension accordance to design drawing

4 Check that frame have completed fabrication work

5 Check that MCT frame location refer to layout

6 Check that support have completed finishing work

7 Check MCT specification refer to MTO and company specification

8 Check that MCT installed at correct location refer to layout

9 Check that MCT installation arrangement refer to installation detail

10 Check that MCT accessories are installed correctly

Notes :

Description Performed by Witnessed / Approved by Witnessed / Approved by

Company

Signature

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 6: Check List MCT

Date

Page 7: Check List MCT

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

MULTI CABLE TRANSIT

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd. E03MC

Drawing Reff. / Rev : System / Sub No. :

Single Line No. / Rev : System Desc. :

Location / Area : Sub System Desc. :

No. Inspection Check List

Tag No.

9820-MCT-E03

IND

OK

OM

AS

PA

L

SA

NT

OS

1 Check frame material have correct specifiction and size

2 Check frame design accordance with design drawing

3 Check frame have correct dimension accordance to design drawing

4 Check that frame have completed fabrication work

5 Check that MCT frame location refer to layout

6 Check that support have completed finishing work

7 Check MCT specification refer to MTO and company specification

8 Check that MCT installed at correct location refer to layout

9 Check that MCT installation arrangement refer to installation detail

10 Check that MCT accessories are installed correctly

Notes :

Description Performed by Witnessed / Approved by Witnessed / Approved by

Company

Signature

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 8: Check List MCT

Date

Page 9: Check List MCT

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

MULTI CABLE TRANSIT

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd. E03MC

Drawing Reff. / Rev : System / Sub No. : 9820-U-009

Single Line No. / Rev : System Desc. : Control Room Building System

Location / Area : E/I Building Sub System Desc. : 9820-U-009-1

No. Inspection Check List

Tag No.9820-M

CT

-E06

9820-MC

T-101

9820-MC

T-102

9820-MC

T-103

1 Check frame material have correct specification and size

2 Check frame design accordance with design drawing

3 Check frame have correct dimension accordance to design drawing

4 Check that frame have completed fabrication work

5 Check that MCT frame location refer to layout

6 Check that support have completed finishing work

7 Check MCT specification refer to MTO and company specification

8 Check that MCT installed at correct location refer to layout

9 Check that MCT installation arrangement refer to installation detail

10 Check that MCT accessories are installed correctly

11

12

Notes :

Description Performed by Witnessed / Approved by Witnessed / Approved by

Company

Signature

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 10: Check List MCT

Date