C&G 2395-01 - William Campbell. Test instruments and the... · 2015-06-02 · describe the...
Transcript of C&G 2395-01 - William Campbell. Test instruments and the... · 2015-06-02 · describe the...
Test instruments and recommended
testing sequence
1
C&G 2395-01
Level 3 Award in the
Periodic Inspection, Testing and
Certification of Electrical Installations
describe the different types of test instrument required
explain the requirements regarding periodic testing sequence
describe the importance of comparing test results with relevant
criteria
explain the requirements for safety when testing
state the requirements for circuits in prescribed special
installations and locations, in terms of identifying the installations
and locations to which special requirements apply, demonstrating
the ability to make reference to the appropriate requirements in
each case and, from given information, be able to identify the
requirements in relation to specific areas and installations.
02/06/2015 2
Outcomes of this Session
The person carrying out inspection and testing must be
competent.
The inspector must therefore be, skilled, experienced,
and have sufficient knowledge of the type of installation
to be inspected and tested to ensure that no danger
arises to any person, livestock or property.
02/06/2015 3
Requirements of testing
Know the instrument, its uses and limitations
Follow all the safety procedures
Check that the equipment meets current standards
Check that the test leads meet with the requirements of GS 38
Check that the test equipment is calibrated correctly.
02/06/2015 4
Test Instruments
Testing should be carried out in such a manner that
`no danger to person livestock or property arises’
There are certain tests that can cause damage to equipment
Before testing can take place, the correct instruments must be selected.
The type of instrument chosen depends on the test being done.
You should be aware of certain criteria that need to be considered.
When using test instruments, the precautions to take are:
BS 7671 lays out the minimum requirements for
the test instruments used to test in accordance
with BS EN 61557
All the differing test instruments are listed and
although two of them are the most common, it is
necessary for you to know the requirements of
all of each.
02/06/2015 5
Requirements of Test Instruments
A low resistance ohmmeter or
continuity scale on a combined
insulation/continuity tester.
Four characteristics:
1. The measuring range should have a
resolution of at least 0.01 Ω.
2. A test current derived from a source
with no-load voltage between 4 V-24 V.
3. A short-circuit test current of not less
than 200 mA.
Instruments to BS EN 61557-4 will meet
these requirements.
02/06/2015 6
Low-resistance ohmmeter
(continuity test instrument) 4.3 p.82
Zero reading on the display shows that the
resistance of the leads have been nulled.
Calibration label
showing date
Leads
connected
together
The person carrying out the tests, should also be aware that the accuracy of
any results will depend on the way in which a particular test instrument is used.
02/06/2015 7
Accuracy of results
You should check that:
you know how to ‘null’ or ‘zero’,
where necessary, the test
instrument
where applicable, the crocodile
clips are connected the right way
round
you are aware of the limits of the
test instrument
02/06/2015 8
Insulation Resistance Tester (High resistance ohmmeter)
An Insulation Resistance Tester is a small d.c. generator.
(This instrument is often, incorrectly, called a `megger’!)
The instrument should comply with BS EN
61557-2.
02/06/2015 9
Insulation Resistance Tester/Ohmmeter O.S.G. 10.3.3 p.95 (GN3 4.4 p.83)
1. 250V d.c. for SELV and PELV
circuits/SPDs (O.S.G Table 10.3.3 p.96)
2. 500V d.c. for all circuits ≤ 500V a.c.
3. 1000V d.c. for circuits > 500V < 1000V
The test voltages required are:
02/06/2015 10
Insulation Resistance Test
The insulation resistance test
is the electrician’s ‘pressure
test’.
We ‘pressurise’ the system
by applying a voltage, and
we can see where the
current ‘leaks’ .
We are testing for current
‘leakage’ between conductors.
We are making sure that the
current passes through the
load and not between the live
conductors, or between live
conductors to earth.
02/06/2015 11
Earth Fault Loop Impedance Tester
This should operate in less than 40
ms (about 2 cycles of alternating
current), with a test current of
between 20-25 A.
The resolution on the scale is
adequate at 0.01 Ω.
This instrument should comply
with BS EN 61557-3.
02/06/2015 12
Earth Electrode Test Instrument O.S.G 10.3.5.2 p.101 (GN3 2.7.12 p.46-47)
There are two types of instrument that can be
used for carrying out an earth electrode
resistance test.
Test method 1 (DEAD testing)
Earth electrode test instrument which has three or
four terminals (C1,P1/P2,T2/C2,T1),
Test method 2 (LIVE testing)
An earth fault loop impedance test instrument
when there is an RCD protecting the TT
installation.
Instruments should comply with BS EN 61557-5.
02/06/2015 13
RCD Test Instrument
The RCD test instrument needs three scales. These are ×½; ×1 and ×5.
In each of the tests required for the RCD, the
test voltage must not rise above 50 V a.c. rms.
The accuracy of the instrument must be ± 10%
to allow for voltage variations and have a timing
accuracy of ± 5%.
Additionally, they should allow for positive and
negative half-cycles to be tested, as well as
allowing for time delayed RCDs.
fit for use
used properly
appropriate for the task
02/06/2015 14
Checking of Test Instruments
Test instruments require regular testing and calibration where required. The
instrument should have a current test certificate!
The normal time span between calibration checks should not be more than 1
year.
As far as the EAWR is concerned, test instruments should be:
The accuracy of a test instrument can be judged in one of two ways:
1. regular accuracy checks using resistors/calibration check unit, etc.
2. regular (at least annual) calibration of the test instrument.
15
Visual Inspection
Check for any obvious mechanical damage
or deterioration of materials and equipment,
exposed cables and live parts, missing
covers, fixings, labels and notices etc.
Inspection and Testing Procedure
16
Visual Inspection
The main switchgear and all distribution boards. These
should be inspected for the following:
Fuses and MCBs are correctly rated for over-current and
fault current
Fuse and switch contacts are clean and have not been
over-heating
Conductor terminations are tight and correctly lugged (if
possible)
Busbar connections are properly made and clamps are
tight.
Inspection and Testing Procedure
17
Cables - whenever possible cables should be
inspected to ascertain:
The suitability for the load and operating
environment
The condition of the insulation and protection
Adequacy of fixings and mechanical protection
Suitability of glands and shrouds
Proper use of earthing clamps and earth
connections
Any signs of over-heating and damage
Inspection and Testing Procedure
18
Equipment, accessories and lighting fittings should be
inspected for:
Deterioration due to the atmosphere
Mechanical damage
Over-heating and adequate fixings
Connections of conductors and condition of flexes -
This should include removing light fitting covers, switch
plates, socket outlets and covers of equipment.
A sample of approximately 10% of all parts and areas of
the installation should be inspected.
Inspection and Testing Procedure
Inspection and Testing Procedure
19
Testing
Continuity of circuit protective conductors (CPCs) at all
metal accessories and equipment within a height of 3.5
metres from floor level, and at 10% of all lighting fittings.
Continuity of all bonding conductors and earth clamps.
Continuity of all ring circuit conductors, including CPCs.
R1 + R2 continuity test or R2 test on every final circuit.
Inspection and Testing Procedure
20
Testing
Insulation resistance between live conductors and earth of
all circuits collectively, excepting any circuits supplying
electronic equipment which may be damaged by the test.
These shall be listed separately as not having been
tested.
An electrical separation test on all electrically separated
circuits.
Polarity at the board and at a 10% sample of all lighting
switches and equipment to ensure that switches interrupt
only phase conductors.
Inspection and Testing Procedure
21
Testing
Earth fault loop impedance (Ze) at the main intake position.
Earth fault loop impedance (Zs) at each distribution board.
Earth fault loop impedance (Zs) test on every final circuit and every
socket outlet.
Test all Residual Current Devices.
The resistance of every earth electrode.
Prospective fault current at the main intake position and at every
distribution board.
A manual operation test on all MCBs, RCDs, switch fuses and
isolators.
Exhibitions, shows and stands - Regulation 711.6 requires inspection
and testing to be carried out each time the installation is assembled. No
additional tests are called for.
Electrical installations in caravans and motor caravans - Fig 721 requires
that a periodic inspection is to be carried out not less than once every
three years and annually if the caravan is used frequently.
Temporary electrical installations for structures, amusement devices and
booths at fairgrounds, amusement parks and circuses - Regulation 740.6
requires the electrical installation between its origin and any electrical
equipment to be inspected and tested after each assembly on site. No
additional tests are called for.
02/06/2015 22
Inspection and testing of special
installations and locations
Part 7 of BS 7671 details the particular requirements for special installations
and locations, such as swimming pools, saunas, caravan parks etc. There
are occasional instances where a special location makes mention of
inspection and testing.
End