CE 806.1 Introduction

download CE 806.1 Introduction

of 38

Transcript of CE 806.1 Introduction

  • 8/3/2019 CE 806.1 Introduction

    1/38

    1

  • 8/3/2019 CE 806.1 Introduction

    2/38

    GEOMETRIC DESIGN OFGEOMETRIC DESIGN OF

    HIGHWAYS/FREEWAYSHIGHWAYS/FREEWAYS(CE(CE -- 806)806)

    OVERVIEW OF THE HIGHWAYPLANNING

    Spring 2012

    Dr. Muhammad Babar Khan

    National Institute of Transportation (NIT)

    School of Civil & Environmental Engineering (SCEE)

    National University of Sciences & Technology (NUST)2

  • 8/3/2019 CE 806.1 Introduction

    3/38

    OVERVIEW OF THE HIGHWAYOVERVIEW OF THE HIGHWAY

    PLANNINGPLANNING

    y Highway design is only one element in theoverall highway development process.

    y It is during the first three stages:

    planning project development

    design

    yDesigners and communities, working

    together, can have the greatest impacton the final design features of theproject.

    3

  • 8/3/2019 CE 806.1 Introduction

    4/38

    THE STAGES OF HIGHWAYTHE STAGES OF HIGHWAY

    DEVELOPMENTDEVELOPMENT

    y The five basic stages in the highway:

    Planning

    Project development (preliminary design)

    Final design

    Right of way

    Construction

    y

    Although these activities are distinct, there isconsiderable overlap between all phases of

    highway planning and development.

    4

  • 8/3/2019 CE 806.1 Introduction

    5/38

    THE STAGES OF HIGHWAYDEVELOPMENTTHE STAGES OF HIGHWAYDEVELOPMENT

    5

  • 8/3/2019 CE 806.1 Introduction

    6/38

    PlanningPlanning

    y The initial definition of the need for any highway

    or bridge improvement project takes place

    during the planning stage.

    y It occurs at the State, regional, or local level,depending on the scale of the proposed

    improvement.

    y This is the key time to get the public involved

    and provide input into the decision makingprocess.

    6

  • 8/3/2019 CE 806.1 Introduction

    7/38

    PlanningPlanning

    y The problems identified usually fall into one or

    more of the following four categories:

    1.The existing physical structure needs major

    repair/replacement (structure repair).2.Existing or projected future travel demands exceed

    available capacity, and access to transportation and

    mobility need to be increased (capacity).

    3.The route is experiencing an inordinate number of

    safety and accident problems that can only be

    resolved through physical, geometric changes (safety).

    4.Developmental pressures along the route make a

    reexamination of the number, location, and physical

    design of access points necessary (access). 7

  • 8/3/2019 CE 806.1 Introduction

    8/38

    PlanningPlanning

    y It is important that all parties agree that the

    problem exists, pinpoint what the problem is,

    and decide whether or not they want it fixed.

    y For example, some communities do not want toimprove the roadway for fear that such action

    will encourage more growth along the corridor.

    y Road access may be a problem, but a

    community may decide it is better not toincrease access.

    8

  • 8/3/2019 CE 806.1 Introduction

    9/38

    y If a consensus cannot be reached on the

    definition of the problem at the beginning, it will

    be difficult to move ahead in the process and

    expect consensus on the final design.

    9

  • 8/3/2019 CE 806.1 Introduction

    10/38

    Planning Government LevelsPlanning Government Levels

    y State Planning.

    State DOTS are required to develop and

    maintain a statewide, multimodal

    transportation planning process. 20year projections of traffic demands.

    Every few years, the State selects

    improvement projects based on the long

    range plan and includes them in the Statewide

    Transportation Improvement Program, or

    STIP.

    10

  • 8/3/2019 CE 806.1 Introduction

    11/38

    y Regional Planning.

    Metropolitan planning organizations (MPOs)

    develop their own regional plans, which must

    rely on the State planning process. The plan not only defines a region's

    multimodal transportation needs, but also

    identifies the local funding sources that will be

    needed to implement the identified projects.

    11

  • 8/3/2019 CE 806.1 Introduction

    12/38

    y Local Planning.

    Most cities and counties follow a similar

    process of project identification, conceptual

    costing, and prioritization of the roadways forwhich they are responsible.

    These are roads that are not the

    responsibility of the State DOT.

    The State must work with localities to get

    their input into the long range plan and

    Statewide Transportation Improvement

    Program (STIP)12

  • 8/3/2019 CE 806.1 Introduction

    13/38

    Factors To Consider DuringFactors To Consider During

    PlanningPlanning

    y During planning, key decisions are made that

    will affect and limit the design options in

    subsequent phases.

    y Some questions to be asked at the planningstage include:

    How will the proposed transportation improvement

    affect the general physical character of the area

    surrounding the project? Does the area to be affected have unique historic or

    scenic characteristics?

    What are the safety, capacity, and cost concerns of

    the community? 13

  • 8/3/2019 CE 806.1 Introduction

    14/38

    Factors to consider in PlanningFactors to consider in Planning

    y Answers for such questions are found in

    planning level analysis, as well as in public

    involvement during planning

    14

  • 8/3/2019 CE 806.1 Introduction

    15/38

    Project DevelopmentProject Development

    y At this stage, the environmental analysis

    intensifies.

    y The level of environmental review varies widely,

    depending on the scale and impact of theproject.

    y It can be a comprehensive document that

    analyzes the potential impact of proposed

    alternatives.

    y Or a modest environmental review completed

    in a matter of weeks.

    15

  • 8/3/2019 CE 806.1 Introduction

    16/38

    y The basic steps in this stage include the

    following:

    Refinement of purpose and need

    Development of a range of alternatives (including the"nobuild" and traffic management system [TMS]

    options)

    Evaluation of alternatives and their impact on the

    natural and built environments

    Development of appropriate mitigation

    y Project development level helps to define major

    features of project through the remainder of

    the design and construction process. 16

  • 8/3/2019 CE 806.1 Introduction

    17/38

    Scoping brings all participants into theScoping brings all participants into the

    process.process.

    17

  • 8/3/2019 CE 806.1 Introduction

    18/38

    y Scoping

    many decisions made during the scoping

    phase of project development

    It is important that the various stakeholdersin the project be identified and provided with

    the opportunity to get involved.

    y Assessing the Character of an Area

    physical location carefully during this stage of

    project planning.

    18

  • 8/3/2019 CE 806.1 Introduction

    19/38

    The physical character of an area can vary,The physical character of an area can vary,

    from a peaceful countryside...from a peaceful countryside...

    . . . to an urban corridor.

    19

  • 8/3/2019 CE 806.1 Introduction

    20/38

    Character of an AreaCharacter of an Area

    y Some of the questions to ask at this stage

    include: What are the physical characteristics of the corridor? Is it in an

    urban, suburban, or rural setting?

    How is the corridor being used (other than for vehicular traffic)?

    Are there destination spots along the traveled way that require

    safe access for pedestrians to cross? Do bicycles and other

    nonmotorized vehicles or pedestrians travel along the road?

    What is the vegetation along the corridor? Is it sparse or dense;

    are there many trees or special plants?

    Are there important viewsheds from the road?

    What is the size of the existing roadway and how does it fit into

    its surroundings?

    20

  • 8/3/2019 CE 806.1 Introduction

    21/38

    y Are there historic or especially sensitive environmental features

    (such as wetlands or endangered species habitats) along the

    roadway?

    y How does the road compare to other roads in the area?

    y Are there particular features or characteristics of the area that thecommunity wants to preserve (e.g., a rural character, a

    neighborhood atmosphere, or a main street) or change (e.g., busy

    electrical wires)?

    y Is there more than one community or social group in the area?Are

    different groups interested in different features/characteristics?Are

    different groups affected differently by possible solutions?

    y Are there concentrations of children, the elderly, or disabled

    individuals with special design and access needs (e.g.,pedestrian

    crosswalks, curb cuts, audible traffic signals, median refuge areas)?

    21

  • 8/3/2019 CE 806.1 Introduction

    22/38

    Final DesignFinal Design

    y The product of this stage is a complete set of

    plans, specifications, and estimates (PS&Es) of

    required quantities of materials ready for the

    solicitation of construction bids and subsequentconstruction.

    y The following are some important

    considerations of design, including:

    Developing a concept Considering scale

    Detailing the design.

    22

  • 8/3/2019 CE 806.1 Introduction

    23/38

    y Developing a Concept

    A design concept gives the project a focus and

    helps to move it toward a specific direction.

    All elements of highway design

    need to be part of an overall

    concept.

    23

  • 8/3/2019 CE 806.1 Introduction

    24/38

    y A multidisciplinary design team consists of some of

    these professionals.

    24

  • 8/3/2019 CE 806.1 Introduction

    25/38

    y For this overpass, an artist and structural engineers

    worked together to achieve a design that represents

    the unique characteristics of the area

    (Thomas Road Overpass, Phoenix, AZ) 25

  • 8/3/2019 CE 806.1 Introduction

    26/38

    y Piers were designed and decorated with art forms

    from the Hohokam tribe, whose ancient burial

    ground is near the overpass.

    (Thomas Road Overpass, Phoenix, AZ) 26

  • 8/3/2019 CE 806.1 Introduction

    27/38

    y Considering Scale

    People driving in a car see the world at a

    much different scale than people walking on

    the street. For example, it has become common in many

    suburban commercial areas that a shopper

    must get in the car and drive from one store

    to the next.

    27

  • 8/3/2019 CE 806.1 Introduction

    28/38

    y Main streets are much more pedestrian friendly,

    partly because of their design scale, than the typical

    modern commercial strip

    A typical "modern" commercial strip. 28

  • 8/3/2019 CE 806.1 Introduction

    29/38

    A "main street. (Bellevue Avenue, Newport, RI)

    29

  • 8/3/2019 CE 806.1 Introduction

    30/38

    y Considering Scale

    The design element with the greatest effect

    on the scale of the roadway is its width, or

    cross section. The cross section can include a clear zone,

    shoulder, parking lanes, travel lanes, and/or

    median.

    30

  • 8/3/2019 CE 806.1 Introduction

    31/38

    y Elements (or a lack of elements) along the

    roadside also contribute to the perceived width

    of the road and can even affect the speed at

    which motorists travel.

    Relatively minor differences in

    roadway cross section and the

    treatment of the roadway edge can

    have major effects on perceived width 31

  • 8/3/2019 CE 806.1 Introduction

    32/38

    y Detailing the Design

    Particularly during the final design phase, it is

    the details associated with the project that

    are important. Often it is the details of the project that are

    most recognizable to the public.

    A special type of tree that was used as part of

    the landscape plan, antique lighting, bricksidewalks, and ornamental traffic barriers are

    all elements of a roadway that are easily

    recognizable and leave an impression.32

  • 8/3/2019 CE 806.1 Introduction

    33/38

    y A multidisciplinary design team can produce an aesthetic

    and functional product when the members work together

    and are flexible in applying guidelines. (BaltimoreWashington

    Parkway,MD)

    33

  • 8/3/2019 CE 806.1 Introduction

    34/38

    y An innovative barrier design was used on the Baltimore

    Washington Parkway.(MD)

    34

  • 8/3/2019 CE 806.1 Introduction

    35/38

    Right of way, Construction, andRight of way, Construction, and

    MaintenanceMaintenancey Right of way is purchased, construction bid

    packages are made available, a contractor is

    selected, and construction is initiated.

    y

    During the rightofway acquisition andconstruction stages, minor adjustments in the

    design may be necessary.

    y There should be continuous involvement of the

    design team throughout these stages.y Once construction has been completed, the

    facility is ready to begin its normal sequence of

    operations and maintenance.35

  • 8/3/2019 CE 806.1 Introduction

    36/38

    Elements of a Successful ProcessElements of a Successful Process

    y In other words, a successful highway design process

    includes the following:

    y Early and continuous public involvement throughout the

    project

    y The use of visualization techniques to aid the public

    y Early and continuous use of a multidisciplinary design

    team

    y The application of flexible and creative design criteria

    36

  • 8/3/2019 CE 806.1 Introduction

    37/38

    y Visualization tools were used to generate these images showing the

    public a proposed highway improvement. (State Highway 38,MN)

    37

  • 8/3/2019 CE 806.1 Introduction

    38/38

    Source:Source:y US Department ofTransportation (DOT): Federal

    HighwayAdministration (FHWA) website.

    y http://www.fhwa.dot.gov/

    38