THE POST-CLASSICAL WORLD 600 CE – 1450 CE Introduction to Unit 3.
CE 806.1 Introduction
-
Upload
hadia-jahangir -
Category
Documents
-
view
225 -
download
0
Transcript of CE 806.1 Introduction
-
8/3/2019 CE 806.1 Introduction
1/38
1
-
8/3/2019 CE 806.1 Introduction
2/38
GEOMETRIC DESIGN OFGEOMETRIC DESIGN OF
HIGHWAYS/FREEWAYSHIGHWAYS/FREEWAYS(CE(CE -- 806)806)
OVERVIEW OF THE HIGHWAYPLANNING
Spring 2012
Dr. Muhammad Babar Khan
National Institute of Transportation (NIT)
School of Civil & Environmental Engineering (SCEE)
National University of Sciences & Technology (NUST)2
-
8/3/2019 CE 806.1 Introduction
3/38
OVERVIEW OF THE HIGHWAYOVERVIEW OF THE HIGHWAY
PLANNINGPLANNING
y Highway design is only one element in theoverall highway development process.
y It is during the first three stages:
planning project development
design
yDesigners and communities, working
together, can have the greatest impacton the final design features of theproject.
3
-
8/3/2019 CE 806.1 Introduction
4/38
THE STAGES OF HIGHWAYTHE STAGES OF HIGHWAY
DEVELOPMENTDEVELOPMENT
y The five basic stages in the highway:
Planning
Project development (preliminary design)
Final design
Right of way
Construction
y
Although these activities are distinct, there isconsiderable overlap between all phases of
highway planning and development.
4
-
8/3/2019 CE 806.1 Introduction
5/38
THE STAGES OF HIGHWAYDEVELOPMENTTHE STAGES OF HIGHWAYDEVELOPMENT
5
-
8/3/2019 CE 806.1 Introduction
6/38
PlanningPlanning
y The initial definition of the need for any highway
or bridge improvement project takes place
during the planning stage.
y It occurs at the State, regional, or local level,depending on the scale of the proposed
improvement.
y This is the key time to get the public involved
and provide input into the decision makingprocess.
6
-
8/3/2019 CE 806.1 Introduction
7/38
PlanningPlanning
y The problems identified usually fall into one or
more of the following four categories:
1.The existing physical structure needs major
repair/replacement (structure repair).2.Existing or projected future travel demands exceed
available capacity, and access to transportation and
mobility need to be increased (capacity).
3.The route is experiencing an inordinate number of
safety and accident problems that can only be
resolved through physical, geometric changes (safety).
4.Developmental pressures along the route make a
reexamination of the number, location, and physical
design of access points necessary (access). 7
-
8/3/2019 CE 806.1 Introduction
8/38
PlanningPlanning
y It is important that all parties agree that the
problem exists, pinpoint what the problem is,
and decide whether or not they want it fixed.
y For example, some communities do not want toimprove the roadway for fear that such action
will encourage more growth along the corridor.
y Road access may be a problem, but a
community may decide it is better not toincrease access.
8
-
8/3/2019 CE 806.1 Introduction
9/38
y If a consensus cannot be reached on the
definition of the problem at the beginning, it will
be difficult to move ahead in the process and
expect consensus on the final design.
9
-
8/3/2019 CE 806.1 Introduction
10/38
Planning Government LevelsPlanning Government Levels
y State Planning.
State DOTS are required to develop and
maintain a statewide, multimodal
transportation planning process. 20year projections of traffic demands.
Every few years, the State selects
improvement projects based on the long
range plan and includes them in the Statewide
Transportation Improvement Program, or
STIP.
10
-
8/3/2019 CE 806.1 Introduction
11/38
y Regional Planning.
Metropolitan planning organizations (MPOs)
develop their own regional plans, which must
rely on the State planning process. The plan not only defines a region's
multimodal transportation needs, but also
identifies the local funding sources that will be
needed to implement the identified projects.
11
-
8/3/2019 CE 806.1 Introduction
12/38
y Local Planning.
Most cities and counties follow a similar
process of project identification, conceptual
costing, and prioritization of the roadways forwhich they are responsible.
These are roads that are not the
responsibility of the State DOT.
The State must work with localities to get
their input into the long range plan and
Statewide Transportation Improvement
Program (STIP)12
-
8/3/2019 CE 806.1 Introduction
13/38
Factors To Consider DuringFactors To Consider During
PlanningPlanning
y During planning, key decisions are made that
will affect and limit the design options in
subsequent phases.
y Some questions to be asked at the planningstage include:
How will the proposed transportation improvement
affect the general physical character of the area
surrounding the project? Does the area to be affected have unique historic or
scenic characteristics?
What are the safety, capacity, and cost concerns of
the community? 13
-
8/3/2019 CE 806.1 Introduction
14/38
Factors to consider in PlanningFactors to consider in Planning
y Answers for such questions are found in
planning level analysis, as well as in public
involvement during planning
14
-
8/3/2019 CE 806.1 Introduction
15/38
Project DevelopmentProject Development
y At this stage, the environmental analysis
intensifies.
y The level of environmental review varies widely,
depending on the scale and impact of theproject.
y It can be a comprehensive document that
analyzes the potential impact of proposed
alternatives.
y Or a modest environmental review completed
in a matter of weeks.
15
-
8/3/2019 CE 806.1 Introduction
16/38
y The basic steps in this stage include the
following:
Refinement of purpose and need
Development of a range of alternatives (including the"nobuild" and traffic management system [TMS]
options)
Evaluation of alternatives and their impact on the
natural and built environments
Development of appropriate mitigation
y Project development level helps to define major
features of project through the remainder of
the design and construction process. 16
-
8/3/2019 CE 806.1 Introduction
17/38
Scoping brings all participants into theScoping brings all participants into the
process.process.
17
-
8/3/2019 CE 806.1 Introduction
18/38
y Scoping
many decisions made during the scoping
phase of project development
It is important that the various stakeholdersin the project be identified and provided with
the opportunity to get involved.
y Assessing the Character of an Area
physical location carefully during this stage of
project planning.
18
-
8/3/2019 CE 806.1 Introduction
19/38
The physical character of an area can vary,The physical character of an area can vary,
from a peaceful countryside...from a peaceful countryside...
. . . to an urban corridor.
19
-
8/3/2019 CE 806.1 Introduction
20/38
Character of an AreaCharacter of an Area
y Some of the questions to ask at this stage
include: What are the physical characteristics of the corridor? Is it in an
urban, suburban, or rural setting?
How is the corridor being used (other than for vehicular traffic)?
Are there destination spots along the traveled way that require
safe access for pedestrians to cross? Do bicycles and other
nonmotorized vehicles or pedestrians travel along the road?
What is the vegetation along the corridor? Is it sparse or dense;
are there many trees or special plants?
Are there important viewsheds from the road?
What is the size of the existing roadway and how does it fit into
its surroundings?
20
-
8/3/2019 CE 806.1 Introduction
21/38
y Are there historic or especially sensitive environmental features
(such as wetlands or endangered species habitats) along the
roadway?
y How does the road compare to other roads in the area?
y Are there particular features or characteristics of the area that thecommunity wants to preserve (e.g., a rural character, a
neighborhood atmosphere, or a main street) or change (e.g., busy
electrical wires)?
y Is there more than one community or social group in the area?Are
different groups interested in different features/characteristics?Are
different groups affected differently by possible solutions?
y Are there concentrations of children, the elderly, or disabled
individuals with special design and access needs (e.g.,pedestrian
crosswalks, curb cuts, audible traffic signals, median refuge areas)?
21
-
8/3/2019 CE 806.1 Introduction
22/38
Final DesignFinal Design
y The product of this stage is a complete set of
plans, specifications, and estimates (PS&Es) of
required quantities of materials ready for the
solicitation of construction bids and subsequentconstruction.
y The following are some important
considerations of design, including:
Developing a concept Considering scale
Detailing the design.
22
-
8/3/2019 CE 806.1 Introduction
23/38
y Developing a Concept
A design concept gives the project a focus and
helps to move it toward a specific direction.
All elements of highway design
need to be part of an overall
concept.
23
-
8/3/2019 CE 806.1 Introduction
24/38
y A multidisciplinary design team consists of some of
these professionals.
24
-
8/3/2019 CE 806.1 Introduction
25/38
y For this overpass, an artist and structural engineers
worked together to achieve a design that represents
the unique characteristics of the area
(Thomas Road Overpass, Phoenix, AZ) 25
-
8/3/2019 CE 806.1 Introduction
26/38
y Piers were designed and decorated with art forms
from the Hohokam tribe, whose ancient burial
ground is near the overpass.
(Thomas Road Overpass, Phoenix, AZ) 26
-
8/3/2019 CE 806.1 Introduction
27/38
y Considering Scale
People driving in a car see the world at a
much different scale than people walking on
the street. For example, it has become common in many
suburban commercial areas that a shopper
must get in the car and drive from one store
to the next.
27
-
8/3/2019 CE 806.1 Introduction
28/38
y Main streets are much more pedestrian friendly,
partly because of their design scale, than the typical
modern commercial strip
A typical "modern" commercial strip. 28
-
8/3/2019 CE 806.1 Introduction
29/38
A "main street. (Bellevue Avenue, Newport, RI)
29
-
8/3/2019 CE 806.1 Introduction
30/38
y Considering Scale
The design element with the greatest effect
on the scale of the roadway is its width, or
cross section. The cross section can include a clear zone,
shoulder, parking lanes, travel lanes, and/or
median.
30
-
8/3/2019 CE 806.1 Introduction
31/38
y Elements (or a lack of elements) along the
roadside also contribute to the perceived width
of the road and can even affect the speed at
which motorists travel.
Relatively minor differences in
roadway cross section and the
treatment of the roadway edge can
have major effects on perceived width 31
-
8/3/2019 CE 806.1 Introduction
32/38
y Detailing the Design
Particularly during the final design phase, it is
the details associated with the project that
are important. Often it is the details of the project that are
most recognizable to the public.
A special type of tree that was used as part of
the landscape plan, antique lighting, bricksidewalks, and ornamental traffic barriers are
all elements of a roadway that are easily
recognizable and leave an impression.32
-
8/3/2019 CE 806.1 Introduction
33/38
y A multidisciplinary design team can produce an aesthetic
and functional product when the members work together
and are flexible in applying guidelines. (BaltimoreWashington
Parkway,MD)
33
-
8/3/2019 CE 806.1 Introduction
34/38
y An innovative barrier design was used on the Baltimore
Washington Parkway.(MD)
34
-
8/3/2019 CE 806.1 Introduction
35/38
Right of way, Construction, andRight of way, Construction, and
MaintenanceMaintenancey Right of way is purchased, construction bid
packages are made available, a contractor is
selected, and construction is initiated.
y
During the rightofway acquisition andconstruction stages, minor adjustments in the
design may be necessary.
y There should be continuous involvement of the
design team throughout these stages.y Once construction has been completed, the
facility is ready to begin its normal sequence of
operations and maintenance.35
-
8/3/2019 CE 806.1 Introduction
36/38
Elements of a Successful ProcessElements of a Successful Process
y In other words, a successful highway design process
includes the following:
y Early and continuous public involvement throughout the
project
y The use of visualization techniques to aid the public
y Early and continuous use of a multidisciplinary design
team
y The application of flexible and creative design criteria
36
-
8/3/2019 CE 806.1 Introduction
37/38
y Visualization tools were used to generate these images showing the
public a proposed highway improvement. (State Highway 38,MN)
37
-
8/3/2019 CE 806.1 Introduction
38/38
Source:Source:y US Department ofTransportation (DOT): Federal
HighwayAdministration (FHWA) website.
y http://www.fhwa.dot.gov/
38