Wind Turbine Project2011-2012
Harry McGrathProduction DirectorFeb 2012
![Page 2: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/2.jpg)
Global Performer
years50
million£110
employees800
![Page 3: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/3.jpg)
Global Performer
Continents5 Countries74Export sales50%
![Page 4: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/4.jpg)
![Page 5: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/5.jpg)
![Page 6: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/6.jpg)
![Page 7: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/7.jpg)
![Page 8: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/8.jpg)
![Page 9: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/9.jpg)
Multi Site Operations
Coventry Staveley Luton & ScotlandBurscoughMallusk
![Page 10: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/10.jpg)
www.youtube.com/w
Feasibility study………..2005 Planning Application…..Jul 2006EIS Submitted ………...July 2007Planning Decision… …Sept 2008Resubmission ……. ….May 2009Planning Approval …….Feb 2010Order Placed………….Aug 2010Installation…Sept 2010/May 2011
![Page 11: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/11.jpg)
ENERCON E-70 Technical Data• Max Output 2.3 MW• Height 99.5m• Rotor Diameter 71m• Hub height 64m• Cut-in wind speed 2.5m/s• Cut-out wind speed 28-34m/s• Rated wind speed 14m/s• Weights..blade 6T, gen 50T tower 139T• Foundation 30m diameter
![Page 12: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/12.jpg)
Costs• Planning/Project management £50k+• Anemometer hire £20k• Foundations £50K• Turbine £2mill • Cabling/Ducting £40k
![Page 13: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/13.jpg)
Issues to Consider
• Planning/Local Knowledge/PPS 18
• Grid Connectivity/NIE Grid Connection Code• Height, wildlife, bats, shadow flicker, noise
![Page 14: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/14.jpg)
Performance Expectations• Site demand >25 Gwhr
• 15% contribution from wind
• 20% contribution to cost
• All generated units used/no spillage
• Carbon Reduction
![Page 15: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/15.jpg)
Operation of E-70
• SCADA Remote performance monitoring
• 15 year maintenance contract
![Page 16: CBI NI energy conference: Harry McGrath](https://reader034.fdocuments.us/reader034/viewer/2022051818/54bf3da14a795905248b4577/html5/thumbnails/16.jpg)
Performance to date• Operational since late June
2011• July/Aug low wind speeds!• Sept to date above average• Generated 2.5mill units to
Jan 2012• Forecast >3 mill
units/annum