Carbon Capture, Utilization and Storage (CCUS) Roadmap for Mexico
4
Road Map (Incubation)
Framework agreement
Carbon marketanalysis
Link with International Institutions in CCUS Scienceand Technology
National and International Funding mechanism fortehcnology implementation
Regulatory framework analysis
INCUBATION
World Bank grant in progress
Consultancy contractingprocess ongoing
5
Creation of Mexican CCUS Center Capacity Building
Regulatory framework adjustments
Permanent monitoringbinding
National financing mechanism and incentives for technolgy development and programs compliance
Aditional International Financing and Funding mechanism and Carbon Markets
Disemination of theTechnology Implentation Plan
Entailment with stakeholder
Policies to Encourage the Private Sector
Implementation Plan for National CO2 Transport Network
National Policy of CCUS READY
PUBLIC POLICY
Road Map (Public Policy)
Consultancy contractingprocess ongoing
Actually planning
A graduate program in planning withUNAM and Berkeley University
6
Estimation of storage capacity
Potential Fields Analysis, Selection and Priorization
CO2 –EOR strategies
CO2 –EOR Plans
Capture and storage plan fromPower Plants
CO2 Use and Supply Strategy
Use and Supplyreview
Use and Supplyreview
Use and Supplyreview
Road Map (Planning)PLANNING
7
Road MapPilot and demonstration project Power Plants
Site selection for NGCC power plants
Selection of capture technology (Consultancy contracting process ongoing)
Feasibility and design studies
Tender
Construction and commissioning
Operation
Closure and decommissioning
Feasibility and design studies
Tender
PILOT PROJECT-POWER PLANT
DEMONSTRATION PROJECT-POWER PLANT
Environmental studies and authorizations
Builiding of Plant and CO2transport network
Public comunication
Commissioning
Injection tests and base line studiesand monitoring Injection and monitoring
Injection site caracterization
and social involvement
8
Site Selection for first pilot test
Lab Analysis /first pilot
Pilot Testing Design/firt pilot
First pilotimplementation
Monitoring, reporting and verification (MRV)/First pilot Evaluation
Follow up
CCS-EOR Scaling Plant
CCS-EOR Research
Field scale design
Execution
Operations from comercial scaleprojects according to theimplementation plan
Operation and MRV
PILOT PROJECT-EOR
DEMONSTRATION PROJECT-EOR
Road MapPilot and demonstration project EOR
10
Road Map (Commercial Scale)
Identification of priority capture plants
CO2 –pipelines feasability analysis
CO2 transport network construction
Construction and commercial operation of CCS and CCS-EOR
CO2 commercialization
MRV
COMMERCIAL SCALE
12
Works on CCS at IIEPOST-COMBUSTION PROGRAM AT IIE(ElectricalResearch Institute)
• A bench scale absorption unit to test different amine solvents to knowthe behaviour of these and study the different variables and parametersinvolved in the process of CO2 capture
• Absorber with 1.7 m highand 4 inches diameter
• Stripper with 2.15 m highand 5 inches diameter
• Both columns made withborosilicate glass Schott® Duran 3.3
• Packing polypropilene pallring 5/8 inches
13
Works on CCS at IIEOXYCOMBUSTION FURNACE AT IIE
• Purposes:– Hands on experience with
oxycombustion– Characterize the
combustion process– Assess applicability to
Mexico
• Part of IIE’s strategic program for CCS• 30 KW thermal• Oxygen delivered by oxygen bottles• Originally CO2 and steam were also externally produced to
simulate recirculation. Now recirculation is beingimplemented
14
• A small gas turbine to investigate the behaviour in operationalconditions using biofuels, CO2 capture, CO2 recirculation and the use in cogeneration.
Works on CCS at IIE gas turbine
15
CCS Pilot Plant
ObjectiveTo develop a conceptual design for a capture pilot plant, to test three different technologies, this pilot plant will be located at the 160 MW Poza Rica NGCC (retrofitted plant)
PRE-FEASIBILITY STUDY by Nexant