This leaflet contains information on the proposed Capitalworks to be carried out in the 2009/2010 financial year.This years programme will again concentrate mainly onworks that will help us to achieve the Decent HomesStandard by 2010.
The table below illustrates the number of properties planned foreach of the main elements of work in the two housing areas. Allthese works are subject to survey.
2 Capital Programme 2009/10
Introduction
Work Done
Kitchen and BathroomReplacements
HeatingReplacements
Roofing
Lift Replacement
Rewires
Sustainability Works
Concierge
Property Conversion’s
Overcladding androofing to NonTraditional Properties
DDA and FRAS Works
Fees and Additional/ Misc. Works
Carecall Upgrade
Non Decent Homeswork
PropertiesPlanned
2,801
812
242
400
1,019
N/A
N/A
132
N/A
N/A
N/A
N/A
EastArea
Brinnington, Marple,Mottram St. and Offerton
High Lane, Marple, MarpleBridge, Offerton and Romiley
Great Moor and Hazel Grove
Hillgate
High Lane, Marple, MarpleBridge, Offerton and Romiley
Borough Wide
Borough Wide
Birch Court
Offerton
Borough Wide
N/A
Borough Wide
Brinnington andVictoria Park
WestArea
Adswood, Cale Green, Gatley,Edgeley, Reddish andShaw Heath
Cale Green, Cheadle, CheadleHeath and Heaviley
Cheadle, Cheadle Hulme,Cheadle Heath and Davenport
Heaton Norris and Edgeley
Cheadle, Cheadle Heath,Edgeley and Lancashire Hill
Borough Wide
Borough Wide
Cheadle Heath, Edgeley
Borough Wide
N/A
Borough Wide
Edgeley, Heaton Norris andLancashire Hill
Area Locations Covered
East Brinnington, Marple,Mottram Street and Offerton
West Adswood, Cale Green, Gatley,Edgeley, Reddish and Shaw Heath
3Capital Programme 2009/10
Kitchen and bathroom replacements
The kitchen and bathroom installation programme is now into itsfourth year and will continue to be rolled out across the Borough in2009/10.
A survey of all the properties in this years programme will beundertaken to find out the condition of the existing kitchen andbathroom. Kitchens and bathrooms that already meet the DecentHomes standard will not be included in the replacementprogramme. Properties that are included in this years programmewill receive confirmation by letter.
Customers will be invited to attend a choice event at a locationclose to their homes, to see and choose from the kitchen andbathroom samples on display. It will also provide an opportunity tomeet staff from Stockport Homes and also the Contractor who willbe involved with the installations. Kitchen and bathroom surveysand replacements will take place in the following areas this year:
Seven contractors have been appointed through GM Procure tocarry out the kitchen and bathroom replacements this year. Thecontractors are as follows:
Casey’sEmanuel WhittakersFT Finley’sMears
Hughes BrothersJackson & JacksonPMS
In addition to the above schemes planned maintenance andsustainability works will also be undertaken. The plannedmaintenance works will include projects such as external painting,upgrade works to balconies, railings and gates and DisabilityDiscrimination Act (DDA) and fire safety works.
4 Capital Programme 2009/10
Heating Replacements
Following a concentration on this area, this year will see a smallprogramme of heating replacements, referred to as a ‘Mop-Up’which will aim to complete those properties that have not beendone in previous years.
These works will be carried out in the following areas:
Rewires
Rewires will be carried out across the Borough. A large proportionof this work will be undertaken in conjunction with the kitchen andbathroom replacements. The rewires will be carried out to therelevant properties in the areas identified below.
Area Locations Covered
East
West
High Lane, Marple, Marple Bridge, Offerton and Romiley.
Cheadle, Cheadle Heath, Edgeley and Lancashire Hill.
Area Locations covered
East
West
High Lane, Marple, Marple Bridge, Offerton and Romiley.
Cale Green, Cheadle, Cheadle Heath, and Heaviley.
The contractor that has been appointed for heating replacement isDodds.
5Capital Programme 2009/10
Overcladding and Roofing to non-traditional properties
The overcladding and roofing works to non-traditional propertiesimprove the aesthetics of the area as well as delivering aconsiderable saving on customers’ fuel bills.
Roofing
Area Locations Covered
East Great Moor and Hazel Grove
West Cheadle, Cheadle Hulme, CheadleHeath and Davenport.
Miscellaneous Projects
Pitched roofing works will be carried out in the following areas:
Various works will be done across the Borough including lift replacements, paintingworks, and health and safety works which we are required to carry out due toregulatory and legislative requirements.
6 Capital Programme 2009/10
Works in Progress
We understand that nobody likes upheaval in their home. However,some of the works to be carried out are extensive and it isinevitable that disruption will be encountered.
For our part we will do our best to keep any mess and generalinconvenience to a minimum.
For any further information, please telephone the InvestmentProgramme Advice line on 0161 474 4407 or visit StockportHomes’ website at www.stockporthomes.org
7Capital Programme 2009/10
Notes
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
.................................................................................................................
Accessing our services
This leaflet gives you information on the proposedCapital works to be carried out in 2009/10financial year. If you would like a copy in largeprint, Braille, on audio tape or CD, please contactthe Social Inclusion Team on 0161 474 2860 oremail: [email protected]
Ref:385/July2009