    BUDGET PREPARATION W ORKSHOP:

    C APITAL IMPROVEMENTS PROGRAM 

     – P ART II

    City Council May 17, 2016

  • 8/17/2019 Capital Improvements Program – Part II

    2/50

    PRESENTATION OBJECTIVES 

    Overview of Past Capital Planning & Funding

    Proposed Capital Planning & Funding Approach

    Preliminary CIP Needs

    Highlight Representative Projects Next Steps

    “…long-term plan to manage our infrastructure

    including maintenance, expansion and funding.” 

  • 8/17/2019 Capital Improvements Program – Part II

    3/50

    EXISTING INFRASTRUCTURE 

    Current Infrastructure represents well over $1 Billioninvested over 100 years by tax and rate payers

    1000+ miles of streets

    600+ miles of alleys

    130+ miles of storm sewers

    1200+ miles of water lines

    1000+ miles of wastewater lines

    3000+ acres of parkland

    2+ M square feet of facilities

    Water/wastewater treatments plants

     Airport

    2000+ computers and servers

    Landfill

    1,600+ vehicles/pieces of equipment

  • 8/17/2019 Capital Improvements Program – Part II

    4/50

    C APITAL PLANNING & FUNDING 

    Comprehensive Plan

    Master Plans

     Assessments & Evaluations

  • 8/17/2019 Capital Improvements Program – Part II

    5/50

    C APITAL PLANNING & FUNDING 

     Annual CIP as part of Annual Budget

    Funded through debt (GO/CO/RevBonds), cash,

    tax revenue, rates, fees, state loans, grants, etc

    FY 15/16 $80 Million

  • 8/17/2019 Capital Improvements Program – Part II

    6/50

    C APITAL PLANNING & FUNDING 

    Traditionally most General Fund Projects (Fire

    Stations, New Equipment, Streets, New

    Facilities, IT, etc) funded through cash realized

    through preceding budget year savings

    Traditionally most Utility projects (water,

    wastewater, drainage, etc) funded through a

    combination of cash realized through increased

    sales and through debt backed by rate increases

  • 8/17/2019 Capital Improvements Program – Part II

    7/50

    C APITAL PLANNING & FUNDING 

    Needs are outpacing resources at an increasing

    rate. This means…. 

    Not able to maintain pavement preservation program

    within life cycle goals

    Not able to address drainage needs of both growthand existing problem areas

    Not able to address utility needs of both growth and

    existing problem areas

    Not able to meet community level of serviceexpectations in parks and recreation, transit, etc.

    Not able to meet internal service demands for IT,

    communications, fleet, facilities, etc.

  • 8/17/2019 Capital Improvements Program – Part II

    8/50

  • 8/17/2019 Capital Improvements Program – Part II

    9/50

    PROPOSED CAPITAL PLANNING & FUNDING 

    Strategic Approach to planning to address capital

    needs –  Enhanced Process

    Citizen Engagement

    Council Priorities

    Comprehensive/StrategicPlans

    Master Plans

    Neighborhood, District,Corridor Plans

     Assessments &Evaluations

    Multi-Year Funded CIP

    Enhanced Project Administration and

    Management

  • 8/17/2019 Capital Improvements Program – Part II

    10/50

    PROPOSED C APITAL PLANNING &

    FUNDING 

    Full accounting of current needs

    Multi-year CIP –  fiscally viable

     Annually Updated/On-Going –  Enhanced Product

     Additional Revenues Required

  • 8/17/2019 Capital Improvements Program – Part II

    11/50

    PROPOSED CAPITAL PLANNING & FUNDING 

    Staff –  Identified Needs

    $900+ Million

    Facilities Maintenance

    F1 410214 Reroof Various City Buildings 1,000,000

    F2 410640 City Hall Cooling Tower Replacement 52,000

    F3 410782 Interior Lighting Upgrades 750,000F4 410818 R22 HVAC Systems Replacement 250,000

    F5 410822 Upgrade Police & Municipal Court Entrances 108,500

    F6 411102 City Hall Architectural and Engineering Design 488,250

    F7 411104 Central Library Streetscape 505,610

    F8 411105 Concrete Wash Bay 488,250

    F9 411106 Service Center Lighting Upgrade 379,750

    F10 411107 Service Center Loading Dock Replacement 352,625

    F11 411108 Service Center Space Study 80,000

    F12 411119 Bucket Truck 125,000

    F13 411126 Vital Statistics Remodel 103,750

    F14 411132 Legal Dept Remodel 300,000F15 411133 IT Department Remodel 300,000

    F16 411134 Parks Department Remodel 450,000

    F17 411135 Risk Mgmt & Benefits Department Remodel 150,000

    F18 411136 City Hall Restroom Remodel 850,000

    F19 411178 Coke Recreation Area Next to MPEV 4,958,800

    F20 411179 Liberty Theater and Park 4,860,000

    F21 411180 Santa Fe Depot Rehab 7,290,000

    F22 411181 Transit Hub 3,888,000

     Total 27,730,535

  • 8/17/2019 Capital Improvements Program – Part II

    12/50

    NEEDS IN SUMMARY  

    $276M in Street and Drainage Projects

    $124M in Parks and Recreation Projects

    $27M in Facilities

    $169M in Utilities

    $21M in Airport

    $16M in Solid Waste

    $20M In IT

    $23M in Public Safety

    $166M in Civic Center

    $4M in Traffic

    Projects across all program areas

    Projects across entire City

    Projects take care of what we have and respond to newgrowth

  • 8/17/2019 Capital Improvements Program – Part II

    13/50

    PROPOSED CAPITAL PLANNING & FUNDING 

  • 8/17/2019 Capital Improvements Program – Part II

    14/50

    PRIORITIZATION OF PROJECTS 

    Staff Preliminary Prioritization will be based on:

     Alignment with Blueprint

     Assessment of Public Benefit

     Assessment of Economic Benefit

     Alignment with Plan/Study/Assessment

     Assessment of Project Urgency

     Assessment of Ability to Deliver Project

     Alignment with Regulatory Mandates

    Complimentary to Previous Expenditures

    Further Refinement through Community

    Engagement and Council Direction

  • 8/17/2019 Capital Improvements Program – Part II

    15/50

    HIGHLIGHTS OF REPRESENTATIVE 

    PROJECTS 

    Public Works

    Utilities

    Facilities

    Parks & Recreation Civic Center

  • 8/17/2019 Capital Improvements Program – Part II

    16/50

  • 8/17/2019 Capital Improvements Program – Part II

    17/50

    Ridgemere Blvd

    from NE 3rd to

     Amarillo Blvd –  

    Concrete Paving:

    $2,675,000

    Microsurfacing of Various Streets:

    $293,950

    Streets 

  • 8/17/2019 Capital Improvements Program – Part II

    18/50

    SE 10th Ave. Railroad Underpass:

    $2,910,000

    Olsen Blvd. and S. Western Storm

    Sewer Extension to Lawrence Lake:

    $500,000

    Drainage 

  • 8/17/2019 Capital Improvements Program – Part II

    19/50

    Gas Collection &

    Control System:

    $5,541,000

    Solid Waste/Landfill 

  • 8/17/2019 Capital Improvements Program – Part II

    20/50

    UTILITIES 

    REPRESENTATIVE PROJECTS 

  • 8/17/2019 Capital Improvements Program – Part II

    21/50

    LIFT STATION 32

    Lift Station # 32 was Identified in the 2013 WW Master

    Study as being overloaded and it was determined that the

    wet well was undersized

    The study also identified that the wet well was in need of

    repairs as soon as probable from deterioration from high

    levels of H2S.

    The City of Amarillo conducted a feasibility study with

    Kimley-Horn to determine rehabilitation or replacement

    options. The engineer and city staff determined that if LS

    32 was moved north just under ½ mile, we would gain

    approximately 15’ of depth and the ability to serve another

    5 sections of land south and east of the proposed new

    location of Lift Station 32.

  • 8/17/2019 Capital Improvements Program – Part II

    22/50

    Current Service Area for LS #32

  • 8/17/2019 Capital Improvements Program – Part II

    23/50

    New Service Area for LS #32

  • 8/17/2019 Capital Improvements Program – Part II

    24/50

    NORTHEAST OUTFALL LINE 

     Address the preliminary design of a new 3-MGD facility.

    Consider two treatment processes: one using an oxidation

    ditch and the other a conventional activated sludge plant.

     Address the Northeast Interceptor as the proposed means of

    conveying wastewater to either RR or in combination with a

    scalping plant.

    Determine a preliminary pipeline route allowing operation of

    the interceptor main without pumping.

    Identified in the 2013 WW Mater study in Task M section 5.2

    under option #1.

    In the WW Master study proposed CIP schedule as project #

    37.

    Identified in the WW Master Study the first option to relieve

    the load from LS # 29 and expand the north east corridor

  • 8/17/2019 Capital Improvements Program – Part II

    25/50

  • 8/17/2019 Capital Improvements Program – Part II

    26/50

    NORTHWEST OUTFALL LINE 

    The Northwest Wastewater Outfall Line was originally identified

    in the 1995 City of Amarillo Wastewater Collection Master Plan

    Further developed in the 2007 Northwest Amarillo Wastewater

    Serviceability Study

    Will consists of mains ranging from 10 to 30-inch beginning just

    north of Lift Station 48 and extending north to Lift Station 40

    The outfall line will eliminate/decommission the need for Lift

    Stations 39, 44 and 45

     Lift Stations 44 and 45 are small package lift stations that currently serve

    very small areas along Citadel Dr

    Lift Station 39 (a small wet well/dry well station) has a small service area

    that flows into the station where it is pumped to the east parallel to

    Fairway Dr. The wet well will continue to be used as a manhole.

    Increase capacity for future growth and development of the

    medical centers and surrounding basins.

  • 8/17/2019 Capital Improvements Program – Part II

    27/50

  • 8/17/2019 Capital Improvements Program – Part II

    28/50

    F ACILITIES 

    REPRESENTATIVE PROJECTS 

  • 8/17/2019 Capital Improvements Program – Part II

    29/50

    FIRE STATION 3

    •  6009 Estacado Ln.

    •  Constructed in 1975•  41 Years Old

    •  4,800 SF

  • 8/17/2019 Capital Improvements Program – Part II

    30/50

    FIRE STATION 3

      Oxford & Coulter Drive•  City Owns The Property

    •  New Station Will Match F/S 8

    and 12 - 9,650 SF

    •  Improved Response Time &

    Service

  • 8/17/2019 Capital Improvements Program – Part II

    31/50

    SERVICE CENTER SPACE STUDY  

    • Space Study $80,000•  Constructed in 1966•  Reorganization Needed To Improve Efficiency

    •  Operations

    •  Utilities

    •  Public Works

    •  Parks•  Transit

    •  Fire Garage

    •  Radio Shop

    •  Warehouse

      Solid Waste•  Municipal Garage

    •  Welding Shop

    •  Traffic

  • 8/17/2019 Capital Improvements Program – Part II

    32/50

     A NIMAL M ANAGEMENT & WELFARE 

    • Site Preparation• $268,707

    •  Covered Dog Runs

    •  $256,653

    •  Drive Through Barn

    •  $68,672

    •  Employee Training Area•  $457,185

    •  Medical Treatment Barn

    •  $384,230

    •  Sally Port

    •  $230,218 

  • 8/17/2019 Capital Improvements Program – Part II

    33/50

    LIBERTY  SQUARE 

     Development of a Useful Space

    •  Enhance Green Space Downtown

    •  Rehabilitate Historical Value of Property

    •  $4,860,000

  • 8/17/2019 Capital Improvements Program – Part II

    34/50

    P ARKS & RECREATION 

    REPRESENTATIVE PROJECTS 

  • 8/17/2019 Capital Improvements Program – Part II

    35/50

     

  • 8/17/2019 Capital Improvements Program – Part II

    36/50

    Existing Softball Complex

    Renovations $4,210,000

    Southwest Complex (5) $1,460,000

    Southeast Complex $1,375,000

    Martin Road Complex $1,375,000

    Complete field lighting replacement.

    Demolish and replace restroom and concessionwith ADA accessible building.

    Fence repair and replacement.

    Entry walkway asphalt to concrete.

    Electrical service upgrade to facility.

    Re-grade and replace infield material.

  • 8/17/2019 Capital Improvements Program – Part II

    37/50

    Rick Klein Baseball

    Complex Expansion$11,606,0006 field conversion to syn.

    3 new lighted syn. Fields

    1 new lighted field of dreams

    400 parking

     Youth SoftballBaseball Complex

    $12,443,6338 lighted 225” lighted syn. fields 

    Restroom/concession

    550 parking

     Access Roads/Widening of Grand

    Rick Klein

    Soccer Complex

    $13,800,00010 lighted syn. fields

    Restroom/Concession

    Stadium Field/Seating

    750 parking

     Youth Sport Field Expansion

  • 8/17/2019 Capital Improvements Program – Part II

    38/50

  • 8/17/2019 Capital Improvements Program – Part II

    39/50

    Park Renovation Projects

    • Gene Howe $550,000

    • Hilltop/Hines $1,925,000

    • Pleasant Valley $825,000

    • Mary Hazelrigg $660,000

    New Park Projects

    • Colonies $940,000

    • Pinnacle (design only) $125,000

  • 8/17/2019 Capital Improvements Program – Part II

    40/50

    John Stiff Park Development• Skate Park Expansion $400,000

    • Restroom Replacement $170,000

    • Hike Bike Trail Expansion $340,000

    • Dog Park Improvements $35,000

    • Parking Expansion (625) $687,000

    • Roadway Improvements $2,751,000

    • Multi-Use Field Conversion (3) $2,975,000

  • 8/17/2019 Capital Improvements Program – Part II

    41/50

     Amarillo ZooMaster Plan Completion

    • $135,000

    Zoo Improvements & Renovations

     $1,000,000

  • 8/17/2019 Capital Improvements Program – Part II

    42/50

    CIVIC CENTER 

    REPRESENTATIVE PROJECTS 

  • 8/17/2019 Capital Improvements Program – Part II

    43/50

    Facility Needs Assessment Study

    Dekker/Perich/Sabatini

     Volume I –  May 2012

    Existing Feasibility Assessment& Market Study

     Volume II –  Summer 2016

    Master Plan

    Financial Analysis

  • 8/17/2019 Capital Improvements Program – Part II

    44/50

    Civic Center Complex Rehabilitation and Expansion - $81

    Million

    New Arena - $66 Million

    New Parking Garage - $11 Million

    75,000 ft2 contiguous, column-free exhibit hall (divisible)

    30,000 ft2 ballroom (divisible)

    20,000 ft2 breakout meeting space

    Scope and scale of a convention center with main entrance and

    true back of house areas

    Up to 7,500 fixed seats, yielding up to 9,000 seats for an end stageconcert

    Up to 300 premium seats

    Improved guest and user experience

    Industry standard specifications and amenities (regulation ice floor;

    correcting 38’ clearance; quality and quantity of concessions, dressing

    rooms, storage, service access, loading areas and meeting accessibilitycodes)

    Replace parking lost to proposed expansion and new arena

  • 8/17/2019 Capital Improvements Program – Part II

    45/50

  • 8/17/2019 Capital Improvements Program – Part II

    46/50

  • 8/17/2019 Capital Improvements Program – Part II

    47/50

  • 8/17/2019 Capital Improvements Program – Part II

    48/50

  • 8/17/2019 Capital Improvements Program – Part II

    49/50

    NEXT STEPS 

    Continue to Refine Projects and Priorities

    Community Engagement –  May, June, July

    Council Budget Workshops - August

    Public Hearings, Tax Rates, Utility Rates, FeeSchedules, Election Issues –  August/September

    Budget Approval –  September

    Budget In Effect –  October

    Election (if scheduled) –  November CIP Implementation –  November –  On-Going

  • 8/17/2019 Capital Improvements Program – Part II

    50/50

    QUESTIONS?