Capital Improvements Program – Part II
Transcript of Capital Improvements Program – Part II
-
8/17/2019 Capital Improvements Program – Part II
1/50
BUDGET PREPARATION W ORKSHOP:
C APITAL IMPROVEMENTS PROGRAM
– P ART II
City Council May 17, 2016
-
8/17/2019 Capital Improvements Program – Part II
2/50
PRESENTATION OBJECTIVES
Overview of Past Capital Planning & Funding
Proposed Capital Planning & Funding Approach
Preliminary CIP Needs
Highlight Representative Projects Next Steps
“…long-term plan to manage our infrastructure
including maintenance, expansion and funding.”
-
8/17/2019 Capital Improvements Program – Part II
3/50
EXISTING INFRASTRUCTURE
Current Infrastructure represents well over $1 Billioninvested over 100 years by tax and rate payers
1000+ miles of streets
600+ miles of alleys
130+ miles of storm sewers
1200+ miles of water lines
1000+ miles of wastewater lines
3000+ acres of parkland
2+ M square feet of facilities
Water/wastewater treatments plants
Airport
2000+ computers and servers
Landfill
1,600+ vehicles/pieces of equipment
-
8/17/2019 Capital Improvements Program – Part II
4/50
C APITAL PLANNING & FUNDING
Comprehensive Plan
Master Plans
Assessments & Evaluations
-
8/17/2019 Capital Improvements Program – Part II
5/50
C APITAL PLANNING & FUNDING
Annual CIP as part of Annual Budget
Funded through debt (GO/CO/RevBonds), cash,
tax revenue, rates, fees, state loans, grants, etc
FY 15/16 $80 Million
-
8/17/2019 Capital Improvements Program – Part II
6/50
C APITAL PLANNING & FUNDING
Traditionally most General Fund Projects (Fire
Stations, New Equipment, Streets, New
Facilities, IT, etc) funded through cash realized
through preceding budget year savings
Traditionally most Utility projects (water,
wastewater, drainage, etc) funded through a
combination of cash realized through increased
sales and through debt backed by rate increases
-
8/17/2019 Capital Improvements Program – Part II
7/50
C APITAL PLANNING & FUNDING
Needs are outpacing resources at an increasing
rate. This means….
Not able to maintain pavement preservation program
within life cycle goals
Not able to address drainage needs of both growthand existing problem areas
Not able to address utility needs of both growth and
existing problem areas
Not able to meet community level of serviceexpectations in parks and recreation, transit, etc.
Not able to meet internal service demands for IT,
communications, fleet, facilities, etc.
-
8/17/2019 Capital Improvements Program – Part II
8/50
-
8/17/2019 Capital Improvements Program – Part II
9/50
PROPOSED CAPITAL PLANNING & FUNDING
Strategic Approach to planning to address capital
needs – Enhanced Process
Citizen Engagement
Council Priorities
Comprehensive/StrategicPlans
Master Plans
Neighborhood, District,Corridor Plans
Assessments &Evaluations
Multi-Year Funded CIP
Enhanced Project Administration and
Management
-
8/17/2019 Capital Improvements Program – Part II
10/50
PROPOSED C APITAL PLANNING &
FUNDING
Full accounting of current needs
Multi-year CIP – fiscally viable
Annually Updated/On-Going – Enhanced Product
Additional Revenues Required
-
8/17/2019 Capital Improvements Program – Part II
11/50
PROPOSED CAPITAL PLANNING & FUNDING
Staff – Identified Needs
$900+ Million
Facilities Maintenance
F1 410214 Reroof Various City Buildings 1,000,000
F2 410640 City Hall Cooling Tower Replacement 52,000
F3 410782 Interior Lighting Upgrades 750,000F4 410818 R22 HVAC Systems Replacement 250,000
F5 410822 Upgrade Police & Municipal Court Entrances 108,500
F6 411102 City Hall Architectural and Engineering Design 488,250
F7 411104 Central Library Streetscape 505,610
F8 411105 Concrete Wash Bay 488,250
F9 411106 Service Center Lighting Upgrade 379,750
F10 411107 Service Center Loading Dock Replacement 352,625
F11 411108 Service Center Space Study 80,000
F12 411119 Bucket Truck 125,000
F13 411126 Vital Statistics Remodel 103,750
F14 411132 Legal Dept Remodel 300,000F15 411133 IT Department Remodel 300,000
F16 411134 Parks Department Remodel 450,000
F17 411135 Risk Mgmt & Benefits Department Remodel 150,000
F18 411136 City Hall Restroom Remodel 850,000
F19 411178 Coke Recreation Area Next to MPEV 4,958,800
F20 411179 Liberty Theater and Park 4,860,000
F21 411180 Santa Fe Depot Rehab 7,290,000
F22 411181 Transit Hub 3,888,000
Total 27,730,535
-
8/17/2019 Capital Improvements Program – Part II
12/50
NEEDS IN SUMMARY
$276M in Street and Drainage Projects
$124M in Parks and Recreation Projects
$27M in Facilities
$169M in Utilities
$21M in Airport
$16M in Solid Waste
$20M In IT
$23M in Public Safety
$166M in Civic Center
$4M in Traffic
Projects across all program areas
Projects across entire City
Projects take care of what we have and respond to newgrowth
-
8/17/2019 Capital Improvements Program – Part II
13/50
PROPOSED CAPITAL PLANNING & FUNDING
-
8/17/2019 Capital Improvements Program – Part II
14/50
PRIORITIZATION OF PROJECTS
Staff Preliminary Prioritization will be based on:
Alignment with Blueprint
Assessment of Public Benefit
Assessment of Economic Benefit
Alignment with Plan/Study/Assessment
Assessment of Project Urgency
Assessment of Ability to Deliver Project
Alignment with Regulatory Mandates
Complimentary to Previous Expenditures
Further Refinement through Community
Engagement and Council Direction
-
8/17/2019 Capital Improvements Program – Part II
15/50
HIGHLIGHTS OF REPRESENTATIVE
PROJECTS
Public Works
Utilities
Facilities
Parks & Recreation Civic Center
-
8/17/2019 Capital Improvements Program – Part II
16/50
-
8/17/2019 Capital Improvements Program – Part II
17/50
Ridgemere Blvd
from NE 3rd to
Amarillo Blvd –
Concrete Paving:
$2,675,000
Microsurfacing of Various Streets:
$293,950
Streets
-
8/17/2019 Capital Improvements Program – Part II
18/50
SE 10th Ave. Railroad Underpass:
$2,910,000
Olsen Blvd. and S. Western Storm
Sewer Extension to Lawrence Lake:
$500,000
Drainage
-
8/17/2019 Capital Improvements Program – Part II
19/50
Gas Collection &
Control System:
$5,541,000
Solid Waste/Landfill
-
8/17/2019 Capital Improvements Program – Part II
20/50
UTILITIES
REPRESENTATIVE PROJECTS
-
8/17/2019 Capital Improvements Program – Part II
21/50
LIFT STATION 32
Lift Station # 32 was Identified in the 2013 WW Master
Study as being overloaded and it was determined that the
wet well was undersized
The study also identified that the wet well was in need of
repairs as soon as probable from deterioration from high
levels of H2S.
The City of Amarillo conducted a feasibility study with
Kimley-Horn to determine rehabilitation or replacement
options. The engineer and city staff determined that if LS
32 was moved north just under ½ mile, we would gain
approximately 15’ of depth and the ability to serve another
5 sections of land south and east of the proposed new
location of Lift Station 32.
-
8/17/2019 Capital Improvements Program – Part II
22/50
Current Service Area for LS #32
-
8/17/2019 Capital Improvements Program – Part II
23/50
New Service Area for LS #32
-
8/17/2019 Capital Improvements Program – Part II
24/50
NORTHEAST OUTFALL LINE
Address the preliminary design of a new 3-MGD facility.
Consider two treatment processes: one using an oxidation
ditch and the other a conventional activated sludge plant.
Address the Northeast Interceptor as the proposed means of
conveying wastewater to either RR or in combination with a
scalping plant.
Determine a preliminary pipeline route allowing operation of
the interceptor main without pumping.
Identified in the 2013 WW Mater study in Task M section 5.2
under option #1.
In the WW Master study proposed CIP schedule as project #
37.
Identified in the WW Master Study the first option to relieve
the load from LS # 29 and expand the north east corridor
-
8/17/2019 Capital Improvements Program – Part II
25/50
-
8/17/2019 Capital Improvements Program – Part II
26/50
NORTHWEST OUTFALL LINE
The Northwest Wastewater Outfall Line was originally identified
in the 1995 City of Amarillo Wastewater Collection Master Plan
Further developed in the 2007 Northwest Amarillo Wastewater
Serviceability Study
Will consists of mains ranging from 10 to 30-inch beginning just
north of Lift Station 48 and extending north to Lift Station 40
The outfall line will eliminate/decommission the need for Lift
Stations 39, 44 and 45
Lift Stations 44 and 45 are small package lift stations that currently serve
very small areas along Citadel Dr
Lift Station 39 (a small wet well/dry well station) has a small service area
that flows into the station where it is pumped to the east parallel to
Fairway Dr. The wet well will continue to be used as a manhole.
Increase capacity for future growth and development of the
medical centers and surrounding basins.
-
8/17/2019 Capital Improvements Program – Part II
27/50
-
8/17/2019 Capital Improvements Program – Part II
28/50
F ACILITIES
REPRESENTATIVE PROJECTS
-
8/17/2019 Capital Improvements Program – Part II
29/50
FIRE STATION 3
• 6009 Estacado Ln.
• Constructed in 1975• 41 Years Old
• 4,800 SF
-
8/17/2019 Capital Improvements Program – Part II
30/50
FIRE STATION 3
•
Oxford & Coulter Drive• City Owns The Property
• New Station Will Match F/S 8
and 12 - 9,650 SF
• Improved Response Time &
Service
-
8/17/2019 Capital Improvements Program – Part II
31/50
SERVICE CENTER SPACE STUDY
• Space Study $80,000• Constructed in 1966• Reorganization Needed To Improve Efficiency
• Operations
• Utilities
• Public Works
• Parks• Transit
• Fire Garage
• Radio Shop
• Warehouse
•
Solid Waste• Municipal Garage
• Welding Shop
• Traffic
-
8/17/2019 Capital Improvements Program – Part II
32/50
A NIMAL M ANAGEMENT & WELFARE
• Site Preparation• $268,707
• Covered Dog Runs
• $256,653
• Drive Through Barn
• $68,672
• Employee Training Area• $457,185
• Medical Treatment Barn
• $384,230
• Sally Port
• $230,218
-
8/17/2019 Capital Improvements Program – Part II
33/50
LIBERTY SQUARE
•
Development of a Useful Space
• Enhance Green Space Downtown
• Rehabilitate Historical Value of Property
• $4,860,000
-
8/17/2019 Capital Improvements Program – Part II
34/50
P ARKS & RECREATION
REPRESENTATIVE PROJECTS
-
8/17/2019 Capital Improvements Program – Part II
35/50
-
8/17/2019 Capital Improvements Program – Part II
36/50
Existing Softball Complex
Renovations $4,210,000
Southwest Complex (5) $1,460,000
Southeast Complex $1,375,000
Martin Road Complex $1,375,000
Complete field lighting replacement.
Demolish and replace restroom and concessionwith ADA accessible building.
Fence repair and replacement.
Entry walkway asphalt to concrete.
Electrical service upgrade to facility.
Re-grade and replace infield material.
-
8/17/2019 Capital Improvements Program – Part II
37/50
Rick Klein Baseball
Complex Expansion$11,606,0006 field conversion to syn.
3 new lighted syn. Fields
1 new lighted field of dreams
400 parking
Youth SoftballBaseball Complex
$12,443,6338 lighted 225” lighted syn. fields
Restroom/concession
550 parking
Access Roads/Widening of Grand
Rick Klein
Soccer Complex
$13,800,00010 lighted syn. fields
Restroom/Concession
Stadium Field/Seating
750 parking
Youth Sport Field Expansion
-
8/17/2019 Capital Improvements Program – Part II
38/50
-
8/17/2019 Capital Improvements Program – Part II
39/50
Park Renovation Projects
• Gene Howe $550,000
• Hilltop/Hines $1,925,000
• Pleasant Valley $825,000
• Mary Hazelrigg $660,000
New Park Projects
• Colonies $940,000
• Pinnacle (design only) $125,000
-
8/17/2019 Capital Improvements Program – Part II
40/50
John Stiff Park Development• Skate Park Expansion $400,000
• Restroom Replacement $170,000
• Hike Bike Trail Expansion $340,000
• Dog Park Improvements $35,000
• Parking Expansion (625) $687,000
• Roadway Improvements $2,751,000
• Multi-Use Field Conversion (3) $2,975,000
-
8/17/2019 Capital Improvements Program – Part II
41/50
Amarillo ZooMaster Plan Completion
• $135,000
Zoo Improvements & Renovations
•
$1,000,000
-
8/17/2019 Capital Improvements Program – Part II
42/50
CIVIC CENTER
REPRESENTATIVE PROJECTS
-
8/17/2019 Capital Improvements Program – Part II
43/50
Facility Needs Assessment Study
Dekker/Perich/Sabatini
Volume I – May 2012
Existing Feasibility Assessment& Market Study
Volume II – Summer 2016
Master Plan
Financial Analysis
-
8/17/2019 Capital Improvements Program – Part II
44/50
Civic Center Complex Rehabilitation and Expansion - $81
Million
New Arena - $66 Million
New Parking Garage - $11 Million
75,000 ft2 contiguous, column-free exhibit hall (divisible)
30,000 ft2 ballroom (divisible)
20,000 ft2 breakout meeting space
Scope and scale of a convention center with main entrance and
true back of house areas
Up to 7,500 fixed seats, yielding up to 9,000 seats for an end stageconcert
Up to 300 premium seats
Improved guest and user experience
Industry standard specifications and amenities (regulation ice floor;
correcting 38’ clearance; quality and quantity of concessions, dressing
rooms, storage, service access, loading areas and meeting accessibilitycodes)
Replace parking lost to proposed expansion and new arena
-
8/17/2019 Capital Improvements Program – Part II
45/50
-
8/17/2019 Capital Improvements Program – Part II
46/50
-
8/17/2019 Capital Improvements Program – Part II
47/50
-
8/17/2019 Capital Improvements Program – Part II
48/50
-
8/17/2019 Capital Improvements Program – Part II
49/50
NEXT STEPS
Continue to Refine Projects and Priorities
Community Engagement – May, June, July
Council Budget Workshops - August
Public Hearings, Tax Rates, Utility Rates, FeeSchedules, Election Issues – August/September
Budget Approval – September
Budget In Effect – October
Election (if scheduled) – November CIP Implementation – November – On-Going
-
8/17/2019 Capital Improvements Program – Part II
50/50
QUESTIONS?