CANAVERAL HARBOR, FLORIDA Integrated Section 203 Navigation Study Report & Final Environmental Assessment Economics Appendix (sub-part of Volume 3) October 2012 (last revised February 2012)

Transcript of CANAVERAL HARBOR, FLORIDA Integrated Section 203 ... · PDF fileCANAVERAL HARBOR, FLORIDA ....

  • CANAVERAL HARBOR, FLORIDA

    Integrated Section 203 Navigation Study Report

    &

    Final Environmental Assessment

    Economics Appendix(sub-part of Volume 3)

    October 2012 (last revised February 2012)

  • ECONOMICS APPENDIX

    Canaveral Harbor, Florida Integrated Section 203 Navigation Study Report &

    Draft Environmental Assessment

    February 2012

  • Canaveral Harbor, FL, Section 203 Study

    Table of Contents 1 Introduction............................................................................................................................. 1

    1.1 Project Location .............................................................................................................. 1

    1.2 Port Description .............................................................................................................. 3

    2 Existing Conditions................................................................................................................. 6

    2.1 Federal Project Dimensions ............................................................................................ 6

    2.2 Existing Conditions: Terminal Facilities ........................................................................ 7

    2.2.1 Existing South Side Cargo Terminal Facilities ........................................................... 8

    2.2.2 Existing North Side Cargo Terminal Facilities ........................................................... 9

    2.2.3 Cruise Terminal Facilities ......................................................................................... 12

    2.3 Socio-Economics .......................................................................................................... 13

    2.4 Port Hinterland.............................................................................................................. 14

    2.5 Port Canaveral Historical and Current Cruise Ship Operations .................................... 14

    2.5.1 Floridas Cruise Ship Industry .................................................................................. 16

    2.5.2 Port Canaverals Cruise Ship Industry...................................................................... 19

    2.5.3 Port Canaveral Cruise Ship Operations .................................................................... 23

    2.6 Port Canaveral Historical and Current Cargo ............................................................... 27

    2.6.1 Existing Cargo Traffic Characterization................................................................... 29

    2.6.2 Existing Cargo Fleet ................................................................................................. 32

    2.6.3 Existing Cargo Fleet Operations and Tidal Advantage ............................................ 36

    3 Without-Project Conditions .................................................................................................. 40

    3.1 Navigation Features ...................................................................................................... 40

    3.1.1 Canaveral Ocean Dredged Material Disposal Site (ODMDS) ................................. 40

    3.1.2 Channel Conditions................................................................................................... 41

    3.2 Terminal Facilities ........................................................................................................ 41

    3.2.1 Cargo Terminals........................................................................................................ 41

    3.2.2 Cruise Terminals ....................................................................................................... 42

    3.3 Economic Conditions in the Project Hinterland ........................................................... 42

    3.4 Port Canaveral Operations ............................................................................................ 44

    3.4.1 Commodity Projections ............................................................................................ 44

    3.4.2 Cargo Fleet Forecast ................................................................................................. 50

    3.4.3 Projected Cruise Ship Operations ............................................................................. 51

    Economics Appendix February 2012 Page i

  • Canaveral Harbor, FL, Section 203 Study

    4 Problems Addressed by the Economic Analysis .................................................................. 53

    4.1 Cruise Ship Size Limitations ........................................................................................ 53

    4.1.1 Channel Widths ......................................................................................................... 53

    4.1.2 Turning Basins .......................................................................................................... 54

    4.2 Cargo Vessel Size Limitations ...................................................................................... 55

    4.3 Surge Effects................................................................................................................. 58

    4.4 Future Berth Congestion ............................................................................................... 59

    4.5 Limitations on New Cargo and Cruise Terminals ........................................................ 59

    5 Alternative Plan Evaluation .................................................................................................. 59

    5.1 Detailed Alternative Plan Description .......................................................................... 60

    5.1.1 Without-Project Condition Channel Description ...................................................... 60

    5.1.2 Alternative With-Project Condition Channel Descriptions ...................................... 60

    5.1.3 Identification of Alternative Plan Increments ........................................................... 60

    5.2 Alternative Plan Costs................................................................................................... 68

    5.2.1 Construction and Investment Costs .......................................................................... 68

    5.2.2 Operations and Maintenance Costs........................................................................... 72

    5.2.3 Total Average Annual Equivalent Costs................................................................... 73

    5.3 With-Project Condition Benefits ................................................................................... 75

    5.3.1 Channel Widening Benefits ...................................................................................... 76

    5.3.2 Channel Deepening Benefits..................................................................................... 86

    5.4 Net Benefits of Alternative Plans ................................................................................. 94

    5.5 Summary of Accounts ................................................................................................... 96

    5.6 Risk and Uncertainty..................................................................................................... 96

    5.6.1 Commodity Forecast Uncertainty Ranking .............................................................. 97

    5.6.2 Reduced Cargo Forecast and Cruise Schedule ......................................................... 98

    5.6.3 Increased Cargo Forecast .......................................................................................... 98

    5.6.4 Increased Seaport Canaveral Forecast ...................................................................... 99

    5.6.5 Alternative Seaport Canaveral Vessel Origins ....................................................... 100

    5.6.6 Alternative Cement Forecasts ................................................................................. 102

    5.6.7 Alternative Slag Forecasts ...................................................................................... 105

    5.6.8 Alternative Aggregate Materials Forecast .............................................................. 108

    Economics Appendix February 2012 Page ii

  • Canaveral Harbor, FL, Section 203 Study

    List of Tables Table 2-1 Port Canaveral Channel Dimensions .............................................................................. 6

    Table 2-2 Port Canaveral Cargo Category by Berth ....................................................................... 8

    Table 2-3 Port Canaveral Existing South Side Cargo Terminal Facilities Summary ..................... 9

    Table 2-4 Seaport Canaveral (Vitol, S.A., Inc) Terminal Storage Capability .............................. 10

    Table 2-5 Seaport Canaveral Vessel Type Summary February 2010 through July 2011 ............. 11

    Table 2-6 Port Canaveral Existing North Side Cargo Terminal Facilities Summary ................... 11

    Table 2-7 Port Canaveral Cruise Terminal Summary ................................................................... 13

    Table 2-8 Projected Growth for City of Orlando 2004 - 2030 ..................................................... 14

    Table 2-9 RCI Voyager, Freedom, and Oasis Class Vessel Deployment Schedules ................... 16

    Table 2-10 North American Multi-Day Cruise Passengers by Selected Departure Ports (000s) 17

    Table 2-11 North American Cruise Passengers By Destination (000s) ...................................... 18

    Table 2-12 Port C