CADRe Update for 2017 Cost and Schedule Symposium Eric … · 2018-05-04 · Office of the Chief...
Transcript of CADRe Update for 2017 Cost and Schedule Symposium Eric … · 2018-05-04 · Office of the Chief...
Office of the Chief Financial Officer
1
CADRe Update for2017 Cost and Schedule Symposium
Eric PlumerAUGUST 29, 2017
For Internal Use Only
Office of the Chief Financial Officer
For Internal Use Only 2
Briefing Outline
• CADRe Document
• CADRe Requirements, Thresholds, & Uses
• 2017 CADRe Focus Group highlights
• 2016-2017 New Accomplishments
• 2018 Planned Work
Office of the Chief Financial Officer
For Internal Use Only 3
Overview of CADRe
• What is CADRe:– The CADRe is a means to collect and track, by milestone, a project’s historical
programmatic, technical, and cost information
– CADRe consists of three parts: Part A is general descriptive information, Part B provides technical data, and Part C contains project cost data
– The CADRe’s are stored in the One NASA Cost Engineering (ONCE) database to facilitate broader NASA cost, schedule, and technical communities Note, CADRes are not released to broader community until after project launch date
• Why is CADRe important:– CADRe serves as key source documentation for the NASA Strategic Investment
Division (SID) as well as the broader NASA cost, schedule, and technical communities. It provides a historical record of cost, schedule, and technical project attributes so that analysts can better estimate future similar projects.
– CADRes describes project mission and approach that facilitates understanding of what is driving costs. CADRe contains objective technical data that tend to drive costs.
– Facilitates consistent Agency data retrieval for a given project
Office of the Chief Financial Officer
For Internal Use Only 4
CADRe Overview
• CADRe is a Requirement in 7120.5E
• The collection of CADRe documents has already proven
successful in providing a mechanism to:•Perform data driven analysis
•Track and explain changes from milestone to milestone
•Provides historical data to help perform JCL Analysis
•Estimate cost and schedule of new projects
•Build data driven products to help answer difficult programmatic
questions.
•Calibrate NASA’s cost models which will help improve cost estimates for
future projects.
Office of the Chief Financial Officer
For Internal Use Only
Cost Analysis Data Requirement (CADRe)
• A three-part document:– Part A: Describes a NASA project at each milestone (SRR, PDR, CDR, SIR, Launch and End of Mission),
and describes significant changes that have occurred.
– Part B: Contains standardized templates to capture key technical parameters that are considered to drive cost (Mass, Power, Data Rates).
– Part C: Captures the NASA project’s Cost Estimate and actual life cycle costs within the project’s and a NASA Cost Estimating Work Breakdown Structures (WBS).
– Note: THE “LAUNCH” CADRes for a mission captures the final costs and as-built mass, and power data. The SRR, PDR, CDR CADRes contain Current Best Estimates.
Part A:
Descriptive
Information
Part B:
Technical
Data
Part C:
Life Cycle
Cost Estimate
Management
Agreement
UFE managed
above the project
KDP-C
Project Reserves/UFE
SRRPDR
UFE managed
above the project
Project Reserves/UFE
UFE managed
above the project
Project Reserves/ UFE
CDRUFE managed
above the project
Project Reserves/UFE
SIRUFE managed
above the project
LRD
CADRe CADReCADRe
CADRe
CADRe
Project LCCE
Project LCCE
Project LCCE Project LCCE Project LCCEProject LCCE
Any Remaining
UFE back to MD
PI Cost + Project Oversight + LV = MA
CADRe Part CCapture LCC from the Project’s View
Agency Baseline Commitment (ABC)• 70% JCL
• External Commitments
6
7
Program
Phases
Formulation Implementation
KDP-A KDP-B KDP-C KDP-D KDP-E
Flight Projects
Life Cycle
Phases
Pre-Phase A:
Concept
Studies
Phase A:
Concept
Development
Phase B:
Preliminary Design
Phase C:
Detailed Design
Phase D:
Fabrication,
Assembly & Test
Phase E:
Operations &
Sustainment
Phase F:
Disposal
SRR/MDR PDR CDR SIR Launch EOM
Traditional
Waterfall
Development
or Directed
Missions1
CR2 3 4 5 6
Down
AO-Driven
Projects
Select
Step 1Select Step 2
CR
1 2 3 4 5 6
Mission Decision Review3 Update as necessary CADRe, All Parts
30-45 days after CDR 5All parts of CADRe due 30-45 days 90 days after launch,
1 using CDR material after KDP B as built or as deployed
configuration
CADRe delivered; based on Update as necessary 30-45 1 4Concept Study Report (CSR) days after KDP-D using 6 CADRe, update Part C only
and winning proposal SIR material at the End of Planned
MissionAll parts of CADRe due 30-45 days 2
after KDP-C using PDR material
Temporal Aspects CADRe
8
Project Requirements for a CADRe
• The Project Needs to have a Beginning Point and End Point • Projects that have finish dates have milestone reviews which is where
CADRe works best. Having a completion date is important• Level of effort research projects don’t make good CADRe material
• Research on properties of propellants or making jet engines quieter won’t lend itself to a CADRe.
• The Project Needs to have a “measurable” product• Requires some hardware or software that can be touched, weighed,
measured in someway. Can be flight and ground articles includes HW and SW. This is necessary to complete a Part B
• The Project Needs to be a Complete and Whole End Product• Piece parts of hardware such as instruments can be done but it is more
challenging.
• The Project Needs to have a Life Cycle Cost Estimate • Needed for completion of Part C. • Updating the LCCE allows for capturing changes over time• Temporal aspect
Office of the Chief Financial Officer
For Internal Use Only 9
CADRe Scope and Dollar Thresholds
There are no stated $ thresholds for CADRe in our policy documents• Positive-- Gives us flexibility for doing CADRes on lower dollar threshold projects • Negative—Projects can attempt to get a CADRe waiver since they feel the dollar
amount is low enough to justify not having a CADRe, and nothing is written in policy to object.
IN GENERALCADRe covers nearly all 7120.5E (Cat I, II, III) for missions over $150M dollars. (flight and significant ground projects)
CADRe funding; Will complete CADRes for smaller missions as funding permits.• Instrument only projects in SMD• larger STMD Missions-cover all projects over $150M in 7120.8 • Unique ISS Projects• Larger CubeSat projects such as iSAT
Provide CADRe funding for large projects that are not strictly space flight projects within 7120.8. Here is where it gets real confusing –
• CADRe is NOT a requirement for projects solely under 7120.8
Office of the Chief Financial Officer
For Internal Use Only
CADRe Requirements, Thresholds, & Uses
Office of the Chief Financial Officer
For Internal Use Only 11
CADRe is centralized in SID
• Recognition that historical “Data Capture” is not high on a project’s list of
priorities. Delivering flight hardware, and delivering science is priority
• STANDARDIZATION: Configuration Control of all CADRe templates are
maintained within SID
• FOCUS: SID being the champion for CADRe helps ensure
homogeneous product for database purposes.
• CONSITENCY: SID is the voice to communicate, Coordinate,
Disseminate Templates, Structure and Policy.
• UNIFORMITY: SID being the single point for CADRe administration is
efficient
• Current CADRe experience has proven effective, which is a contrast with
other data capture experiences at NASA
Office of the Chief Financial Officer
For Internal Use Only
Who’s Who in CADRe-ville
12
The mayor of Whoville
SID funds, directs and manages day to day activities of all CADRe development using several support contractors
• AEROSPACE--SMD Missions• SAIC -- HEO Missions• TECOLOTE— STMD and ISS Missions• JPL-- JPL Missions• APL- Data Support, CADRe Support
AEROSPACE-- SMD Missions. full compliment of Science Mission Directorate flight projects including JPSS-2, WFIRST, GOES-S, JWST, Solar Probe Plus, GOLD, TESS, Landsat-9, DART, TESS, GPIM, Lucy
JPL-- SMD Missions. JPL team engages with the JPL Projects to build the CADRes including kickoff meetings and data collection with JPL projects.
SAIC--HEOMD & SMD. Primary projects are MPCV, SLS, GSDO, ICESAT-2.
TECOLOTE -- STMD, ISS Tier 2 Projects, ARMD. Unique and innovative CADRes that require special CADRe techniques.
APL--Data support for CADRe and NICM and review/signature coordination with APL
Office of the Chief Financial Officer
For Internal Use Only 13
2016-17- CADRe Accomplishments
CADRes Completed iSAT PDR
GPIM PostSIR
GEDI PDR
eCryo 2nd Annual Review
TESS CDR
Radiation Budget Instrument (RBI) PDR
Jason-3 SIR
Space Network Ground Segment (SGSS) Post-CDR
LDSD Launch CADRe (Tech Demo)
Moon Mineralogy Mapper (M3) EoM
JPSS-2 SRR
Mars2020 PDR
The Low Density Supersonic Decelerators (LDSD) #3
GOES-R SIR
ICESAT-2 (SIR)
Surface Water Ocean Topography (SWOT) PDR
GOES-S (SIR)
Ground System Development Office (GSDO CDR)
Total and Spectral Solar Irradiance Sensor TSIS CDR
OSIRIS-REX Launch
Solar Probe Plus SIR
GEDI CDR
Restore-L SRR
RBI dSRR
RBI CDR
CADRes Kicked Off LANDSAT-9 SRR
GEDI PDR
Solar Probe Plus (SIR)
GEDI CDR
ICON SIR
Restore-L SRR
PACE SRR
OSIRIS-Rex Launch CADRe
DART (SRR)
JPSS-2 PDR
ICON SIR
Low Boom Flight Demonstration Quiet Supersonic
Transport (QueSST) X-plane
SAGE III Launch
Lucy SRR
Psyche SRR
eCryo Annual Review #3
DART SRB Review at APL
JPSS CGS Operation Readiness Review
EO-1 satellite Phase F KDP
GOLD PSR Solar Orbiter Collaboration (SOC) Heavy Ion
Sensor (HIS) and SoloHI Instruments
GeoCarb mission
Office of the Chief Financial Officer
For Internal Use Only14
CADRe Accomplishments
Cumulative CADRe Completions across NASA
Year by Year CADRe Completions across NASA
0
10
20
30
40
50
60
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Completed & Signed CADRes
In Process CADRes
Office of the Chief Financial Officer
For Internal Use Only 15
CADRe Metrics
Number of Completed CADRes by Center- Nearly all CADRes are unmanned missions which is currently most represented at GSFC and JPL
Office of the Chief Financial Officer
For Internal Use Only 16
CADRe Accomplishments
Number of Completed CADRes by Milestone. LRD, EOM, CADRe Plus will contain actual parameters.
Office of the Chief Financial Officer
For Internal Use Only
2017 CADRe Focus Group highlights
Office of the Chief Financial Officer
For Internal Use Only
2017 CADRe/ONCE Focus Group
CADRe Developers Workshop held on 4 May 2017. First year that it was virtual• In Attendance
• NASA SID · Aerospace
• TECOLOTE · SAIC
• JPL
• ~30 Attendees
– Topic focus included:
Part A New Executive Summary, Change Log.
Part B template revisions, Power Parameters, Full Review/Design of Summary Table, SW Logical vs Physical. New Mission Types.
Part C, Both Fiscal Year and by Phase.
– Action Item Listing Developed during the Workshop
Divided into General Actions, CADRe Template Actions, and ONCE Actions
• ONCE Action Items
– New Template updates will be integrated into ONCE
ONCE updates, CADRe upload
Office of the Chief Financial Officer
For Internal Use Only
Hello CADRe superstar users,
In late spring I’m holding a focus group with my
CADRe authors to go over good CADRe
development practices. The CADRe has improved
over the years because of input from our users such
as yourself.
Please let me know if you have any suggestions for
specific CADRe improvements that you would find
useful in your particular line of work. This also
includes any improvements to the ONCE database
itself. Simply send me a sentence or two for your
suggestion by April 15th.
As a reminder CADRe has three key parts:
Part A: Detailed Descriptions, to help analysts
understand the overall level of complexity and
technology used for the project.
Part B: Technical Data Sheets, where the key
technical parameters are captured that can support
cost/schedule analysis at different stages and levels.
(The Launch and EOM CADRes contain final mass,
power, and other tech parameters)
Part C: Programmatic Capture, showing the project’s
LCCE, Schedule, and Risk posture. (The Launch
and EOM CADRes contain actual costs while earlier
milestone CADRes are the project’s estimates)
Thanks again for all your continued support and
input!
Appreciatively,
Eric
19
CADRe User Input
• Actively petitioned user input using ONCE database to query super users across Part A, B, C
• Received ~1 Dozen responses and discussed them at the Focus Group
• Common Themes: • Notification of when CADRes get posted• Access to full up source packages and
documentation• Provide more cost detail on instruments• Conduct data collection for Balloon missions• More data on Cubesat missions• Expansion of other types of projects• More detail on Integration and Test• Better explanation of Power• More detail on Section A.5• ONCE Related: Build a Percent Factors Capability• Include a Summary Report across all Milestones
Office of the Chief Financial Officer
For Internal Use Only
20
Workshop Action Item List
Successful Focus Group: 33 Separate Actions
• Re-engineered Power Parameters to allow selectable menu of power modes.
• Disconnect average and peak power calculations in template so a sum is not forced on data. Make CADRes more consistent with NICM type data.
• Re-engineered the Summary Table for clarity • Section A.5. Now an Executive Summary for LRD, EOM • Change Log has now been formalized in Part A. • Provide update on SW physical and logical definitions
without using the actual physical and logical terms within the definition.
• Adapted solar array menu . There is never a time that an array is single or dual axis and not be deployed
• Rename A.1.2.1 to Launch and Launch Vehicle Description
• Improve instrument delivery mechanism.• Add in Lagrange; Primitive Body (Comets, Asteroids) to
Mission Type drop down • Mission System Parameter Tab - link mass and power
values to summary table • Adjustments to GDS template
Action\Request\Comment Application Status Requestor Assigned To
When using a mass or power allocation - make sure it's noted as an allocation rather than a true breakdown. Need to know if it's manipulated. CADRe Completed Chris Chromik N/A
John wasn't sure about including data from prior milestones (e.g. MEL/PEL to back up allocations) - thought it would introduce confusion. Mike pointed out that it's always best to have actual values rather than derived values in ONCE. CADRe Completed John Spagnuolo N/A
Vahe provided explanation and examples to explain power value differences between NICM and CADRe many times in past with projects and users of these products. FYI Completed Vahe Mazmanian N/A
The way CADRe template is set up with formulas for power section is causing trouble. Should break down so each instrument is independently reflecting power values and a separate area for SC power that doesn't require a roll-up. CADRe Completed Vahe Mazmanian N/A
When pulling data for CER purposes she assumes that data is pure on instrument tab - would not assume some arbitrary mode that is related to SC and it's predominant operation mode is being used down at the instrument level.
CADRe Completed Sara Lang N/A
Disconnect average and peak power calculations in template so a sum is not forced on data. Make CADRes more consistent with NICM type data. Notate in CADRe that values aren't related to total system values. CADRe Completed Eric Plumer Eric
Add pull down menus to CADRe (including on summary table) that allows selection of power mode (e.g. insert after column F in SC HW Parms tab) CADRe Completed Greg Henning Eric
Got 533s in past that would be summed up so much that wasn't usable (e.g. total-total FTEs). Can CADRe developer's get access to 533 data? CADRe Completed Chris Chromik N/A
Risk data applicable if it's little bit before and after (1 to 2 month delta) as long as in general time frame - is that true? CADRe Completed John Spagnuolo N/A
Correct note in Column P in Risk Register so that Column O is identified rather than Column N. CADRe Completed John Spagnuolo Eric
What does Description/Example mean in column A of the Risk Register if you don't want input? Perhaps remove title and change title to "Risk #" or something that doesn't lead the developer to hunt down a description. CADRe Completed John Spagnuolo Eric
Add in visual indicator when ONCE is searching or "thinking". ONCE Open User Feedback Mike
Devise listing of most useful documents for CADRe development to aid in direction for the project office and utilize time most efficiently. CADRe Completed User Feedback Eric
A.1.2.1 Launch description is concerning - includes flyby and destination maneuvers data requests which is non-sensical. CADRe Completed John Spagnuolo Eric
Combine A.1.3 to A.1.2.1 because A.1.3. ends up being redundant. CADRe Completed Rudy Firpo Eric
Capitalize "b" in Test beds in Part A TOC CADRe Completed Rudy Firpo Eric
Suggest adding change log to be inserted after signature page in template. CADRe Completed Mike Blandford Eric
Requirements should always be plural in "Cost Analysis Data Requirements" FYI Completed John Spagnuolo N/A
Add some text to the A.4 Project Level Description in Part A CADRe Completed John Spagnuolo Eric
Suggest eliminating "History" section from Part A CADRe Completed Rudy Firpo N/A
Relabel Program/Project History table to indicate to be completed only for CADRe Plus CADRe Completed Eric Plumer Eric
Provide tweak on physical and logical definitions without using the actual physical and logical terms within the definition. CADRe Completed Eric/Vera/John Aerospace/JPL
Add in GDS WBS Element for estimated/actual section in CADRe Plus template CADRe Completed Eric Plumer Eric
Part B Payload Parms- Improve A34 Instrument Delivery Mechanism definition CADRe Completed Eric Plumer Eric
All Parts A, B, C--Make sure tab names are correct in headers in print mode CADRe Completed Eric Plumer Eric
Add two drop down columns (deployable/not deployable; axis) for solar array type CADRe Completed Eric Plumer Eric
Suggest adding TBD to fields where N/A is a choice in CADRe template. CADRe Completed John Spagnuolo N/A
Suggest removing Deployed from options as it seems redundant (axis means deployed and anything else would be body mounted). Perhaps pinging a Solar Array expert is in order. CADRe Completed Eric Plumer Eric
Add in Lagrange; Primitive Body (Comets, Asteroids) to Mission Type drop down CADRe Completed Eric Plumer Eric
Edit Summary table interface so that the labels and format are easier to follow CADRe Completed John Spagnuolo John Spagnuolo
Mission System Parameter Tab - link mass and power values to summary table CADRe Completed Eric Plumer Eric
Gravity Probe B CADRe Plus stalled because no new data. Part A is complete - is it possible to publish Part A alone? CADRe Open Rudy Firpo Eric
Office of the Chief Financial Officer
For Internal Use Only
21
Version 7.5 CADRe Template
• Now have selectable Power Modes
• Menu of Power Modes, most commonly used
• Flows to other Spacecraft and Instrument Sheets
Office of the Chief Financial Officer
For Internal Use Only 22
Version 7.5 Template (Previous)
Spacecraft Mass and Power similar to previous template versions with addition of Numerical Entry, Option Selection, Auto-Sum Values
• Previous Part B (Spacecraft and Payload) did not allow for varying Power Modes
Office of the Chief Financial Officer
For Internal Use Only 23
Note: It is permissible to overwrite a cell equation if only the total exits. If there is a total but the children don't add up--then use the unallocated mass line for the difference
Spacecraft HW Mass and Power Totals: Structures & Mechanisms
Average Power Average Power (CBE+ Peak Power Peak Power (CBE+
Assembly Name Mass (CBE) Mass (CBE+ Cont) Average Power Mode (CBE) Cont) Peak Power Mode (CBE) Cont) Dimensions
Structures & Mechanisms Total 0.00 kg 0.00 kg
Primary Structures 0.00 kg 0.00 kg
Load Carrying Shell/Truss
Equipment Compartments
Booms
Adapters
Secondary Structures 0.00 kg 0.00 kg
Equipment (Instrument) Mountings
Ballast Mass
Mechanisms 0.00 kg 0.00 kg
Positioning
Deployment and Storage Equipment
Docking Mechanisms
Other
Pyrotechnics
Other
Unallocated
Thermal Control
Average Power Average Power (CBE+ Peak Power Peak Power (CBE+
Assembly Name Mass (CBE) Mass (CBE+ Cont) Average Power Mode (CBE) Cont) Peak Power Mode (CBE) Cont) Dimensions
Thermal Control Total 0.00 kg 0.00 kg
Active Devices 0.00 kg 0.00 kg
Cryogenic Devices
Liquid Loops
Electric Cooling (Thermoelectric)
Electric Heaters Thermistors &
Thermostats
Shutters and Louvers
Passive Devices 0.00 kg 0.00 kg
Radiator Panel/Fins
Coatings
Heat Pipes
Insulation
Conductive Structures
Heat Activated Structures
Sun Shields
Second Surface Mirrors
Other
Unallocated
Version 7.5 Template (New)
• New Part B (Spacecraft and Payload) allows for Power Modes• Automatically pulled from System Parameter Sheet• Pull Down Menu
Office of the Chief Financial Officer
For Internal Use Only 24
Version 7.0 Template (Previous)
• Previous Summary Menu-• Created challenges because of new selectable Power Modes-
Office of the Chief Financial Officer
For Internal Use Only
Version 7.5 Template (New) WARNING:
SYSTEM SUMMARY TABLE
CBE Mass
CBE Mass
w/Contingency Average Power Mode Avg Power Avg Power w/ Cont Peak Power Mode CBE Peak Power
CBE Peak Power
w/Contingency
Payload Total 0.00 kg 0.00 kg Payload
Instrument 1 Instrument 1
Instrument 2 Instrument 2
Rover Total (Dry) 0.00 kg 0.00 kg Rover
Structures & Mechanisms 0.00 kg 0.00 kg Structures & Mechanisms 0.00 W 0.00 W 0.00 W 0.00 W
Thermal 0.00 kg 0.00 kg Thermal 0.00 W 0.00 W 0.00 W 0.00 W
Electrical Power Subsystem 0.00 kg 0.00 kg Electrical Power Subsystem 0.00 W 0.00 W 0.00 W 0.00 W
Guidance, Navigation & Control 0.00 kg 0.00 kg Guidance, Navigation & Control 0.00 W 0.00 W 0.00 W 0.00 W
Telecommunications 0.00 kg 0.00 kg Telecommunications 0.00 W 0.00 W 0.00 W 0.00 W
Command and Data Handling 0.00 kg 0.00 kg Command and Data Handling 0.00 W 0.00 W 0.00 W 0.00 W
EDL Total (Dry) 0.00 kg 0.00 kg EDL
Structures & Mechanisms 0.00 kg 0.00 kg Structures & Mechanisms 0.00 W 0.00 W 0.00 W 0.00 W
Thermal 0.00 kg 0.00 kg Thermal 0.00 W 0.00 W 0.00 W 0.00 W
Electrical Power Subsystem 0.00 kg 0.00 kg Electrical Power Subsystem 0.00 W 0.00 W 0.00 W 0.00 W
Guidance, Navigation & Control 0.00 kg 0.00 kg Guidance, Navigation & Control 0.00 W 0.00 W 0.00 W 0.00 W
Propulsion (not incl. Propellant & Pressurant) 0.00 kg 0.00 kg
Telecommunications 0.00 kg 0.00 kg Telecommunications 0.00 W 0.00 W 0.00 W 0.00 W
Command and Data Handling 0.00 kg 0.00 kg Command and Data Handling 0.00 W 0.00 W 0.00 W 0.00 W
Carrier/Orbiter Total (Dry) 0.00 kg 0.00 kg Carrier/Orbiter
Structures & Mechanisms 0.00 kg 0.00 kg Structures & Mechanisms 0.00 W 0.00 W 0.00 W 0.00 W
Thermal 0.00 kg 0.00 kg Thermal 0.00 W 0.00 W 0.00 W 0.00 W
Electrical Power Subsystem 0.00 kg 0.00 kg Electrical Power Subsystem 0.00 W 0.00 W 0.00 W 0.00 W
Guidance, Navigation & Control 0.00 kg 0.00 kg Guidance, Navigation & Control 0.00 W 0.00 W 0.00 W 0.00 W
Propulsion (not incl. Propellant & Pressurant) 0.00 kg 0.00 kg
Telecommunications 0.00 kg 0.00 kg Telecommunications 0.00 W 0.00 W 0.00 W 0.00 W
Command and Data Handling 0.00 kg 0.00 kg Command and Data Handling 0.00 W 0.00 W 0.00 W 0.00 W
Propellant & Pressurant 0.00 kg 0.00 kg
EDL Propellant & Pressurant 0.00 kg 0.00 kg
Carrier/Orbiter Propellant & Pressurant 0.00 kg 0.00 kg
Total Mass (Dry) 0.00 kg 0.00 kg
Total Mass (Wet) 0.00 kg 0.00 kg
LV Capability 0.00 kg 0.00 kg
Launch Mass Margin 0.00 kg 0.00 kg
% Launch Mass Margin #DIV/0! #DIV/0!
Individual Instrument Power: (These values represent peak and average in isolation and independent from any mission power modes )
Instrument Name Avg Power Avg Power w/ Cont CBE Peak Power
CBE Peak Power
w/Contingency
Enter Instrument Name
Enter Instrument Name
Total Power
Do not sum power values to calculate a mission total power as there could be different power modes utilized. Refer to BOL and
EOL in Spacecraft Tab (Rows 22 and 23).
• Now clear Separation between Mass and Power sections• Now includes separate Individual Instrument Power- True Avg and Peak power• Warning not to simply sum power values to get a mission total
Office of the Chief Financial Officer
For Internal Use Only
261/29/
2018
CADRe Improvement Process
Requested update verified by SID
CADRe Master Sheet Updated
CADRe Sheet provided to
CADRe Developer
Developer Makes Update in Source
CADRe
Updated CDs prepared and
loaded to ONCE
For Internal Use Only
• ® . . .
. .
I l J
Creating a Change Log Office of the
Chief Financial Officer
Sample Change Log Example
DATE REVISION BY SECTION(S) CHANGED REASON FOR CHANGE REVISION
09/03/2013 Daniel Belter Initial Release -
02/27/2014 Daniel Belter C Amended cost with Univ Texas contributions. A
07/20/2015 Daniel Belter B Changed Sys Lvl Parms tab ‘Number of
Instruments’ from 4 to 5.
B
• Create a change log to show significant changes
• What section (Part A, B, C) and what was updated
Office of the Chief Financial Officer
For Internal Use Only
Release of CADRes outside NASA Community is discouraged.
Discussions with General Counsel provided Clarification
• Although CADRes are not ITAR they do contain Proprietary Cost Data (Boeing, Lockheed,
Ball, Orbital). That is why release outside of NASA is not allowed.
• Release of CADRes to Universities is not permitted since they are primes themselves and
don’t have non-disclosure agreements in place.
• Release of CADRes to other Federal Gov’t Agencies is generally OK, although SID
discourages release of Pre-Launch CADRes because of their inherent sensitivity.
• Release of CADRes to other National Entities such as ESA and JAXA is not allowed.
• CADRes are not considered ITAR since CADRes don’t describe how to “make something”
or “how to operate” something.
NOTE: Sharing of CADRe Files not allowed. If someone wants a CADRe file, they need to get a ONCE
account.
28
Release of CADRes outside NASA
Office of the Chief Financial Officer
For Internal Use Only
2016-2017 New Accomplishments
Office of the Chief Financial Officer
For Internal Use Only
New Areas of Data Collection
30
Human Space Flight- EFT-1 Data Collection
Human Space Flight- Tier 2 International Space Station Projects
Balloons - Completed 2 missions from Applied Physics Laboratory
Aircraft- In process building CADRe for QueSST (Low Boom Aircraft Development)
Software Metrics- Continual work across all the projects worked
Office of the Chief Financial Officer
For Internal Use Only 31
Completed a CADRe for the Exploration Flight Test (EFT-1) vehicle which was launched Dec 5, 2014. There is detailed non-recurring and recurring costs from Lockheed which will provide a wealth of information to help estimate follow-on systems.
Systems included on EFT-1 included • Parachute Recovery Systems• CM Structure integrity and performance• Heat Shield Performance • Electrical power storage and distribution;• Thermal control; cabin pressure control; • Command and data handling;• Communications and tracking;• Guidance, navigation and control; • Reaction control system propulsion• Flight software and computers
Systems Not included in EFT-1 (mass simulators)• Environmental control and life support system (ECLSS)• Crew support systems• Crew Displays• Crew seats and crew-operable hatches.
EFT-1 CADRe
Office of the Chief Financial Officer
For Internal Use Only
CADRes on ISS Projects (Tier 2)
Common Communications for Visiting Vehicles (C2V2).The C2V2 provides both critical and non-critical RF communications withthe Visiting Vehicle (VV) during rendezvous, proximity, departure, and docking operations for crewed and uncrewed VVs
Nitrogen Oxygen Recharge System (NORS)• NORS is the new ISS Environmental Control and Life Support System
(ECLSS) subsystem to provide gaseous nitrogen (N2) and oxygen (O2) recharge to the ISS. Airlock N2 High Pressure Gas Tank (HPGT) re-pressurization Airlock O2 HPGT re-
pressurization
Gas ContentsOxygen: 6,000 PSINitrogen: 6,100 PSI
Office of the Chief Financial Officer
For Internal Use Only
CADRes on Balloon Missions
• BOPPS Balloon. (Balloon Observation Platform for Planetary Science) SEPTEMBER 15, 2014
• Stabilized pointing platform mounting an 80-cm telescope on a gondola capable of operating at 110,000 to 140,000 feet, above most of the atmosphere's water and carbon dioxide.
– BOPPS can see wavelengths of light which are blocked by the atmosphere from reaching the ground.
– Designed to measure water and carbon dioxide from comets at infrared wavelengths in the 2.5 to 5 micron range, which cannot be seen from the ground because of atmospheric absorption.
Mass: 1856 kg
Completed 2 Balloon Mission CADRes Parts B and Part C. Focus was on collecting key Technical and Cost/Schedule information. • Development Cost Ranges $5M-$10M Development cost. • Launch & Operations $500K-$1.5M
Office of the
Chief Financial Officer
• CADRes on Balloon Missions
BRRISON Balloon The Balloon Rapid Response for ISON Studied the Comet ISON. Launched SEPTEMBER 29, 2013
• A helium-filled balloon with a gondola
• Includes telescope other equipment to near space, soaring up to 120,000 feet (36,576 meters) altitude
• BRRISON balloon's gondola carried infrared and near ultraviolet/visible imaging gear, along with fine steering mirror technology to obtain high pointing stability.
• Contains high technology infrared and visible light cameras. It demonstrated new developments in image stabilization.
• Launched from Fort Sumner, New Mexico and stayed aloft for only one day, just enough time to reveal information from comet ISON.
Mass: 1864 kg
For Internal Use Only
Office of the Chief Financial Officer
For Internal Use Only
Successful CADRe kickoff the QueSST Low Boom Flight Demonstration Quiet Supersonic Transport• Demonstrate that noise from sonic booms can be reduced to a level acceptable to
the population residing under future supersonic flight paths.• Create a community response database that supports an International effort to
develop a noise based rule for supersonic overflight
CADRe on Supersonic Aircraft
Calculated loudness level (PLdB) of the predicted sonic boom
ground signature Less than 75
Office of the Chief Financial Officer
For Internal Use Only
Initial Data collected by Space Vehicle(s) Collector's NameFull Name (of the
project mission)
Launch Date
(Date
Launch or
Launch Vehicle -
(Launch Vehicle
Type - DOD,
Mission Type
(Com, Sci, Tech,
Edu) --
Mission Objective
Procuring
Agency Type
- Civil,
Procuring AgencyDeveloper
TypeDeveloper COTS/In-House - HW; (BUS ONLY) COTS/In-House - FLIGHT SW
Developer
Country
Partners
(Commerial,
Universities,
Earth Orbiting
or "Planetary"
Development Time (mo) -
Phase B/C/D (From ATP
to Pre-Ship Review)
Mission
Duration:
Design
Mission
Successful
(Y/N), If
Source - Reference: website, document, etc… Additional Comments
% of labor
performed
by
Aerospace CINEMA (1) Mary Covert
CubeSat for Ions,
Neutrals, Electrons,
and Magnetic Field
9/13/2012
Atlas V
Part of NASA’s
ELaNa VI
initiative
Science Space Environment Civil NSF UniversityUC Berkeley Space Sciences Laboratory
(UCB/SSL)
USA
UK for
magnetometer
instrument
Imperial
College,
London,
provided the
EO
44
Start of Phase B through
PSR
12
Science
mission
began
about a
Unless otherwise noted, most info taken from
documents found in CINEMA knowledge tree available
at ftp://apollo.ssl.berkeley.edu/pub/cinema/. Key files
have been downloaded and archived.
50%
Aerospace Firefly (1)Eric Wendoloski /
Mary Covert11/20/13 Minotaur-1 Science Examine terrestrial gamma ray flashes from lightning Civil NSF Civil
NASA GSFC, with Siena College and
Hawk Institute for Space SciencesAlmost all-COTS bus United States
NASA/GSFC,
USRA, Siena
College, U. of
Maryland,
Hawk Institute
EO
During the time between
project start and launch,
we had about 36 months
of solid effort, with the
rest of the 60 month pre-
3 Y
Doug Rowland (NASA GSFC), http://firefly.siena-
space.org/,
https://directory.eoportal.org/web/eoportal/satellite-
missions/f/firefly,
http://firefly.gsfc.nasa.gov/Spacecraft/fireflymissionde.
“spacecraft still
communicating regularly with
ground station as of April 2016,
after more than 29 months on
orbit”
Aerospace KickSat (1) 4/18/14 Falcon-9 v1.1(R) Tech Demo ChipSat Deployment University Cornell University United States 4 24 Partial KickSat 1
KickSat worked on orbit, but a
faulty counter reset prevented
it from deploying the 104
"Sprites" prior to reentry.
Aerospace M-Cubed/COVE (1) 10/28/11 Tech Demo
Demonstrate a new FPGA-based image processing system intended for a
future NASA mission, Aerosol-Cloud-Ecosystem, recommended by the
Earth Science Decadal Survey
Civil NASA's Earth Science Technology Office UniversityUniversity of Michigan spacecraft, JPL
FPGA payloadUnited States 30 Partial
http://phys.org/news/2011-10-student-built-satellite-
nasa-instrument.html,
https://directory.eoportal.org/web/eoportal/satellite-
missions/m/m3-mcubed, http://umcubed.org/, "M-
Cubed: University of Michigan Multipurpose
MiniSatellite with Optical Imager Payload"
Spacecraft is alive and
transmitting, but can't be
commanded because it's
magnetically stuck to HRBE.
Aerospace NanoSail-D (2) 11/20/10 Tech Demo Demonstrate deployable sail Civil
Collaborative partnership between NASA; the
Department of Defense Space Test Program at
Kirtland Air Force Base, N.M.; and the Space and
Missile Defense Command, the Von Braun Center
for Science and Innovation, and Nexolve Corp.,
all in Huntsville; and NASA.
CivilNASA Marshall design and built; NASA
Ames did I&TUnited States 4 Y
http://en.wikipedia.org/wiki/NanoSail-D2,
http://www.nasa.gov/centers/marshall/news/news/rel
eases/2011/11-055.html,
http://www.nasa.gov/mission_pages/smallsats/nanosai
ld.html,
http://www.nasa.gov/centers/marshall/pdf/484314mai
n_NASAfactsNanoSail-D.pdf,
http://www.thevettebarn.com/forums/251718-
post1.html
Aerospace PharmaSat (1) 5/19/09 Science Study drug action in space Civil
The Exploration Technology Development
Program in NASA’s Exploration Systems Mission
Directorate at NASA Headquarters in Washington
funded the PharmaSat project
CivilSmall Spacecraft Division at NASA’s
Ames Research Center, Moffett FieldUnited States Y
http://www.nasa.gov/mission_pages/smallsats/pharma
sat/main/index.html,
http://www.nasa.gov/centers/ames/news/features/200
9/pharmasat-update_0612.html,
http://www.nasa.gov/pdf/331108main_pharmasat_Fac
t%20Sheet_FINAL.pdf
Aerospace PolySat (CP8) "IPEX" Mary CovertIntelligent Payload
Experiment12/5/13
Atlas V
ELaNa-2Tech Demo
JPL Autonomous Image Processing - validate onboard instrument
processing and autonomous payload operations for the proposed NASA
HYperSPectral Infra-Red Instrument
CivilFunded by NASA’s Earth Science Technology
Office (ESTO); managed by JPLUniversity
California Polytechnic University at San
Luis Obispo designed the spacecraft bus
(PolySat), cameras, attitude control,
flight avionics software, and
integrated/built the flight unit. Goddard
developed the Space Cube Mini payload
USAJPL (SW), GSFC
(PL processor)Earth Orbiting 24
Actual
mission
life was
14
months.
Last
Y
http://polysat.calpoly.edu/launched-missions/cp8-ipex/
and
http://mustangnews.net/polysat-testing-nasa-
technology/ and
http://www.jpl.nasa.gov/cubesat/ipex.php and
https://directory.eoportal.org/web/eoportal/satellite-
SpaceCube Mini PL processor
was replaced late in the
development process with
"Gumstix" COTS processor
Aerospace PSSC-2 7/10/11 STS-135 Tech Demo
Two demos: Miniature Tracking Vehicle (MTV) will test the satellite's
ability to function as a reference body for tracking stations; and the
Compact Total Electron Content Sensor (CTECS) will observe the signals
from occulting Global Positioning System satellites in order to study the
density of the ionosphere. The latter is risk reduction for the upcoming
SMC Space Environmental Monitoring Nanosat Experiment (SENSE).
MilitarySpace and Missile Systems Center's Development
Planning Directorate (SMC/XR), Civil Aerospace United States 6
Partial - all
three
onboard
experiment
s provided
some data,
David Hinkely, Aerospace;
http://en.wikipedia.org/wiki/PSSC-2,
http://www.nasa.gov/pdf/626635main_inspace-4-3-
hinkley.pdf,
http://www.spacedaily.com/reports/Final_Nanosatellit
e_Launched_from_Space_Shuttle_Atlantis_999.html
Aerospace RAX 1 (USA 218)David Mayo / Mary
CovertRadio Aurora eXplorer 11/20/10
Minotaur-
IV/HAPS
Science
Used for true
science but also
pathfinder for
Space Weather
The primary scientific objective is to understand the microphysics of
plasma instabilities that lead to field-aligned irregularities (FAI) of
electron density in the polar lower ionosphere.
Civil NSF University University of Michigan United States
Collaboration
between a
space science
Principal
EO 12
Partial -
The RAX I
mission
was
http://nssdc.gsfc.nasa.gov/spacewarn/spx685.html,
https://directory.eoportal.org/web/eoportal/satellite-
missions/r/rax,
https://www.nsf.gov/awardsearch/showAward?AWD_I
First National Science
Foundation sponsored CubeSat
mission
Aerospace SkyCubeDavid Mayo / Mary
CovertNanoRacks-SkyCube 1/9/14 Cygnus CRS-1 Educational
Educational mission that demonstrates the capabilities of small, low-
budget satellites in a manner that engages the public. The small satellite
takes images of the Earth from space by request, sends "tweets" in the
form of radio pings, and inflates a balloon to de-orbit itself in a
Crowdsourced Commercial Southern Stars Group LLC United States
Naval
Postgraduate
School -
ground
EO 24 3
Partial -
Initial
signals
were
https://www.kickstarter.com/projects/880837561/skyc
ube-the-first-satellite-launched-by-you/posts/985395,
https://www.kickstarter.com/projects/880837561/skyc
ube-the-first-satellite-launched-by-you/posts/824992,
SkyCube contains no onboard
guidance or active attitude
control system. Instead, the
satellite has a passive
0
ARC O/OREOS
Organism/Organic
Exposure to Orbital
Stresses
5/19/09Minotaur 4 (HAPS
stage 5)Science Plant cell gravity senseing; Study drag action in space Civil NASA HQ (SMD) and ARC Civil SSTP - NASA ARC 100% IH 100% IH United States
Santa Clara
University -
Mission Ops
Earth Orbiting 12~18-24
months
Yes -
Nominal
PM: Elwood Agasid
http://www.nasa.gov/mission_pages/smallsats/pharma
sat/main/index.html,
http://www.nasa.gov/centers/ames/news/features/200
None 0
SporeSat-1 SporeSat-1 4/18/14 Space X- CRS 3 Tech Demo Variable-g centrifuge Civil NASA ARC Civil SSTP - NASA ARC 50% COTS; 50% IH 100% IH United States
Santa Clara
University -
Mission Ops;
Purdue
Earth Orbiting 36 2 months
Yes-Partial
(centrifuge
success)
SE: Brittany; PM: Dan Launch Delay ~1 month5% from
SCU (Radio)
ARC EDSN EDSN 11/3/15DOD Launch
Vehicle
Communication,
Technology
Demonstration,
Networking,
Swarm Mission, Enable Cross-Link Communication and Multipoint
PhysicsCivil NASA ARC Civil SSTP - NASA ARC 75% IH; 25%COTS 100% IH United States
Montana Sate
University -
Payloads;
Santa Clara
Earth Orbiting 10
2 months;
design to
last 24
months.
No -
Launch
Vehicle
Failed
PM, Publications None ~5%
JPL GRIFEX Mrozinski
GEO-CAPE Readout
Integrated Circuit In-
Flight Performance
Experiment
1/31/15 Delta II Tech
The GEO-CAPE ROIC In-Flight Performance Experiment (GRIFEX) is a 3U
CubeSat that will perform engineering assessment of a JPL-developed all
digital in-pixel high frame rate Read-Out Integrated Circuit (ROIC). Its
high throughput capacity will enable the proposed Geostationary
Civil NASA
JPL/Universti
y of
Michigan
JPL/Universtiy of Michigan USA Earth Orbiting LV
JPL MarCO Michael DiNicola Mars Cube One May-18 Atlas V-401 Tech/Com
The twin communications-relay CubeSats, being built by NASA's Jet
Propulsion Laboratory, Pasadena, California, constitute a technology
demonstration called Mars Cube One (MarCO). CubeSats are a class of
spacecraft based on a standardized small size and modular use of off-
the-shelf technologies. Many have been made by university students,
and dozens have been launched into Earth orbit using extra payload
Civil NASA JPL
JPL; Project Mgmt, SE, SMA, Mission
Design, Spacecraft Structure, MGA, LGA,
X-band Transponder, SSPA & LNA, High
Gain Reflectarray, UHF Antenna and
Thermal and Harness.
USA
AstroDev, LLC
(C&DH board,
Electrical
Power
System), MMA,
LLC (solar
Planetary 21 6.5 0
marco_de_exp type dec 2015_Miked.xlsx (initial cost
data from the JPL financial system); MarCO_ CubeSats
to Mars in 2016.pdf (for technical data)
3/2/2016, M. DiNicola:
- Costs shown are for Phases
B/C/D only; operations' costs
not included.
- MarCO costs were funded by
internal JPL B&P money. If
JPL LMRST MrozinskiLow Mass Radio
Science Transponder10/8/15 Atlas V Tech/Com
CubeSats leaving the vicinity of Earth would not have access to GPS or
other forms of terrestrial navigation. The Low Mass Radio Science
Transponder (LMRST) is a bare-bones, two-way Doppler and ranging
transponder, based on well established navigation techniques in use by
Civil NASA JPL JPL USA Stanford Earth Orbiting Outlier NMass: http://www.space.com/30768-spy-satellite-
cubesat-launch-thursday-webcast.html
Had to build their own ground
station.
JPL M-Cubed/COVE 2 Mrozinski 6-Dec-13
JPL RACE
Radoimeter
Atmospheric CubeSat
Experiment
10/28/2014
Orbital Sciences
Corp. Antares
rocket
Tech
The primary scientific expedition of RACE is to measure the liquid water
path and precipitable water vapor that is pertinent to the water cycle
and Earth energy budget. The RACE payload is a microwave radiometer
that primarily observes the 183 GHz water vapor line.
Civil NASA JPL JPL USA LV
CubeSat Data Collection
2016-2017 Completed First Round of CubeSat Data Collection- Data Collection only
COMPACT Research Projects with JPL, ARC, and Aerospace. CubeSat Research Task (COMPACT) coordinated to get a team updates from JPL, ARC, and Aerospace to assess progress of data collection.
• Focused the team on the identification of various CubeSat missions and transitioned into full data collection which is the primary focus for this task.
• Reached out to APL to include CubeSat Preliminary with a dozen CubeSat projects having data.
2018 Small Amount of Research Funds targeted for second round of CubeSat Data and earlyModel Development
Office of the Chief Financial Officer
For Internal Use Only
• FSW data collection continues to be challenging– Completeness metrics for CADRe’s are comparable across
Centers
• HQ is leading Joint effort to improve & refine– Including GSFC with JPL, APL, and ARC team
• Updated CADRe template is focused on key sizing data– Software sizing parameters highest priority for data collection
• Working with GSFC to help implement capture of SW metrics– Provide feedback on model prototype and data analysis
Flight Software Data Collection
Office of the Chief Financial Officer
For Internal Use Only 38
New Initiatives
Office of the Chief Financial Officer
For Internal Use Only 39
CADRe Forward Work 2018
• SMD Mars2020, Europa, Juno, JWST, LANDSAT-9, WFIRST, RBI, TESS, SPP, SWOT, INSIGHT, OCO-III, PSYCHE
MAIA, ECOSTRESS, GOLD, JPSS-2, GOES-S, TSIS, ICON, GPIM
• ARMD– QueSST PDR CADRe in process, CDR CADRe planned after competition results
• STMD– iSAT (CubeSat Project)
– Restore-L
– DSOC
– GPIM
• ESMD– ORION (Orion Actuals)
– SLS BLK1-B
– GSDO
• ISS SPECIFIC – Lithium Ion Battery
– NASA Docking System
Office of the Chief Financial Officer
For Internal Use Only 40
CADRe Forward Work
Part A: For LAUNCH CADRE addition of an Executive Summary
• An idea has been floated by SID Management to have a CADRe executive summary after the project is completed. Suggestion submitted by SMD as well.
• A summary of all the Section A.5 sections. Add new material as necessary, inputs collected from many sources inside/outside SID.
• Focus on capturing in a summary write-up the technical changes, schedule adjustments and cost adjustments over the life of the project.
Part C: Focus on collecting PRIME WYEs
• While NASA is doing a better job capturing Project Civil Servants (FTEs) and project Support Contractors (WYEs) FTEs.
• NASA has difficulty capturing the PRIME WYEs.
• NASA CIPT: Working though ideas from the group, including Primes, who can help NASA better capture WYEs.
Office of the Chief Financial Officer
For Internal Use Only
Questions
Office of the
Chief Financial Officer
For Internal Use Only 42
How are CADRes Prepared?
Source Documents for CADRe
Part A. Descriptive Information -Project Plan
-Architecture Description Document -Acquisition Plan -Project Implementation Plan -System Engineering Plan -Risk Mitigation Plan -Integrated Design Definition Documents (Constellation) -Milestone Review Briefing Packages (SDR, PDR, CDR etc) -Concept Study Report/Proposal (if applicable)
-Concept of Operations -Integrated Master Schedule -Integrated Test Plan -Monthly Status Reports -Any Instrument specific MDR, CDR, PDR packages -ATLO Plan (used later in the project) -Mission Readiness Review (used later in the project) -Pre Environmental Readiness Review (used later in the project) -Launch Readiness Review (used later in the project)
Part B. Technical Data -Master Equipment Lists -Project Schedules -Mass Property Reports -Power Budget Summary Report -Software Design Reports -Milestone Briefing Packages/Documentation (MD
Part C. Cost and Schedule Info
-Project Cost Estimate by WBS
-WBS Dictionary
-533 or EVM reports
-Schedules
-Risk lists
Amount of documentation varies with
Size, Class, Category Project